CN213170501U - Sludge storage device integrating crushing and crushing - Google Patents

Sludge storage device integrating crushing and crushing Download PDF

Info

Publication number
CN213170501U
CN213170501U CN202022067342.9U CN202022067342U CN213170501U CN 213170501 U CN213170501 U CN 213170501U CN 202022067342 U CN202022067342 U CN 202022067342U CN 213170501 U CN213170501 U CN 213170501U
Authority
CN
China
Prior art keywords
fixed
sludge
control switch
crushing
bin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022067342.9U
Other languages
Chinese (zh)
Inventor
王兴福
刘文镔
蔡亮
霍文志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Jiasheng Environmental Protection Engineering Co ltd
Original Assignee
Chongqing Jiasheng Environmental Protection Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Jiasheng Environmental Protection Engineering Co ltd filed Critical Chongqing Jiasheng Environmental Protection Engineering Co ltd
Priority to CN202022067342.9U priority Critical patent/CN213170501U/en
Application granted granted Critical
Publication of CN213170501U publication Critical patent/CN213170501U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Treatment Of Sludge (AREA)

Abstract

The utility model relates to an environment-friendly treatment device, in particular to a sludge storage device integrating crushing into a whole, which comprises a support frame fixed on the ground and a sludge finished product bin fixed on the support frame, wherein the sludge finished product bin is positioned at the top of the support frame, and a passage space for a truck to pass in and out is arranged below the sludge finished product bin; a chute communicated with an inner cavity of the finished sludge bin is arranged on the side wall or the bottom of the finished sludge bin, an electric knife gate valve is arranged at a discharge port of the chute, and a crusher is arranged below the discharge port of the chute and fixed on a support; the electric knife gate valve and the crusher are respectively and electrically connected with the control switch a and the control switch b through leads, and when the electric knife gate valve is used, the control switch a and the control switch b are both electrically connected with an external power supply through leads; the control switch is fixed on the support frame. The utility model discloses reduce sludge treatment system equipment area, reduced the energy consumption and reduced the later maintenance cost.

Description

Sludge storage device integrating crushing and crushing
Technical Field
The utility model relates to an environmental protection treatment facility, especially a collect broken integrative mud storage device who reduces sludge treatment system equipment area, reduces the energy consumption and reduce the later maintenance cost.
Background
In the sludge treatment technology, sludge is generally used as a building filling raw material, and the sludge is treated into the building filling raw material with different particle diameters by a granulator and then conveyed into a finished product bin for storage. And conveying the building filling raw materials stored in the finished product bin to a client demand place after loading. Current finished product feed bin generally includes the support frame, fixes the feed bin on the support frame, and this feed bin is located the top of support frame, is provided with the passageway space that supplies the freight train business turn over in the below of feed bin, is provided with the sieving mechanism in the bottom of feed bin, is provided with recovery storehouse and second grade feed bin at two discharge gates of sieving mechanism.
As the diameter of the sludge particles needs to be controlled within 15 mm as building filler, but the diameter of the sludge particles is different when the sludge particles are loaded in a finished product bin, the sludge particles need to be screened before filling, and the large particles need to be crushed again after being screened out, so that the time and the fund are wasted. The existing finished product bin has the defects of large occupied area, high energy consumption and high later maintenance cost of the whole sludge treatment system due to the self structure.
Chinese patent 2018209642869 discloses a mud storage device, mud storehouse fixed mounting is in the frame, and the top and the bottom in this mud storehouse are the form of opening the both ends of baffle in pairs are provided with the connecting plate respectively, and the baffle in pairs is rotationally movable mounting in the uncovered department of mud storehouse bottom through its connecting plate respectively, pneumatic cylinder movable mounting is on the connecting plate of one of them baffle tip, and the piston rod movable mounting of pneumatic cylinder is on the connecting plate of another baffle tip, mated sector fixed mounting is respectively on the connecting plate, and intermeshing between the mated sector of homonymy, the advantage of this structure is: the space that it took is reduced, has reduced the manufacturing cost of equipment, and it is stable to open and shut, effectively prolongs its life. But the energy consumption is large, the later maintenance cost is high, and a later screening device is required to be matched with the later screening device for use.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a reduce sludge treatment system equipment area, reduce the energy consumption and reduce the broken integrative sludge storage device of collection of later maintenance cost.
The technical scheme adopted for achieving the purpose is that the sludge storage device integrating crushing and integration comprises a support frame fixed on the ground and a finished sludge storage bin fixed on the support frame, wherein the finished sludge storage bin is positioned at the top of the support frame, and a passage space for a truck to enter and exit is arranged below the finished sludge storage bin; the method is characterized in that: a chute communicated with an inner cavity of the finished sludge bin is arranged on the side wall or the bottom of the finished sludge bin, an electric knife gate valve is arranged at a discharge port of the chute, a crusher is arranged below the discharge port of the chute and fixed on a support, and the support is fixed on a support frame or the ground;
the electric knife gate valve and the crusher are respectively and electrically connected with the control switch a and the control switch b through leads, and when the electric knife gate valve is used, the control switch a and the control switch b are both electrically connected with an external power supply through leads; the control switch is fixed on the support frame.
The structure of the utility model has the advantages that: the occupied area of sludge treatment system equipment is reduced, the energy consumption is reduced, and the later maintenance cost is reduced.
Drawings
The invention can be further illustrated by means of non-limiting examples given in the figures.
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic structural diagram of the crusher of the present invention.
In the figure, 1, a supporting frame; 2. a finished sludge product bin; 3. a channel space; 4. a chute; 5. an electric knife gate valve; 6. a crusher; 7. a support; 8. a base support; 9. a motor; 10. a crushing roller; 11. and a chain.
Detailed Description
The invention will be further explained with reference to the following figures and examples:
referring to attached drawings 1 and 2, the sludge storage device integrating crushing and integration in the drawings comprises a support frame 1 fixed on the ground, and a finished sludge bin 2 fixed on the support frame 1, wherein the finished sludge bin 2 is positioned at the top of the support frame 1, and a passage space 3 for a truck to enter and exit is arranged below the finished sludge bin 2; the method is characterized in that: a chute 4 communicated with an inner cavity of the finished sludge bin 2 is arranged on the side wall or the bottom of the finished sludge bin 2, an electric knife gate valve 5 is arranged at a discharge port of the chute 4, a crusher 6 is arranged below the discharge port of the chute 4, the crusher 6 is fixed on a support 7, and the support 7 is fixed on the support frame 1 or the ground;
the electric knife gate valve 5 and the crusher 6 are respectively electrically connected with the control switch a and the control switch b through leads, and when the electric knife gate valve is used, the control switch a and the control switch b are both electrically connected with an external power supply through leads; the control switch is fixed on the support frame 1. In this embodiment, the finished sludge is crushed to within 15 mm by the crusher 6, and the screening and secondary processing are not performed in the later period, so that the floor area of the sludge treatment system is reduced, and the screening device is not needed, so that the energy consumption is reduced, and the later maintenance cost is reduced. Simultaneously, the blanking granule of mud finished product feed bin 2 falls into the 6 broken backs of breaker via chute 4 on next door, can satisfy the requirement as the filler completely, and the user only need the loading directly pull away just can, and do not need to sieve once more before the loading and the breakage, this has greatly improved work efficiency to can save time and equipment later maintenance fund.
In order to facilitate blanking, in the above embodiment, preferably: the sludge finished product bin 2 is funnel-shaped.
For the convenience of later maintenance, in the above embodiment, preferably: the crusher 6 also comprises a base bracket 8, and the base bracket 8 is fixed at the top of the bracket 7;
two sets of crushing mechanisms are symmetrically fixed on the base support 8, and each crushing mechanism comprises a motor 9 and a crushing roller 10; a driving chain wheel is arranged on an output shaft of the motor 9, the motor 9 is electrically connected with the control switch b through a lead, and a base of the motor 9 is fixed on the base support 8; the crushing roller 10 is fixed on a rotating shaft, the rotating shaft is fixed on the base bracket 8 through a bearing seat, a driving chain wheel is fixed on the rotating shaft, and the driving chain wheel is connected with a driving chain wheel through a chain 11;
the gap between the two crushing drums 10 is less than 15 mm.
All components in the above embodiments are commercially available products.
It is obvious that all the embodiments described above are some, not all embodiments of the present invention. Based on the embodiment of the present invention, all other embodiments obtained by the skilled in the art without creative work belong to the scope of the protection of the present invention.
In conclusion, due to the structure, the utility model discloses reduce sludge treatment system equipment area, reduced the energy consumption and reduced the later maintenance cost.

Claims (3)

1. A sludge storage device integrating crushing and integration comprises a support frame (1) fixed on the ground and a finished sludge storage bin (2) fixed on the support frame (1), wherein the finished sludge storage bin (2) is positioned at the top of the support frame (1), and a passage space (3) for a truck to enter and exit is arranged below the finished sludge storage bin (2); the method is characterized in that: a chute (4) communicated with an inner cavity of the finished sludge bin (2) is arranged on the side wall or the bottom of the finished sludge bin (2), an electric knife gate valve (5) is arranged at a discharge port of the chute (4), a crusher (6) is arranged below the discharge port of the chute (4), the crusher (6) is fixed on a support (7), and the support (7) is fixed on the support (1) or on the ground;
the electric knife gate valve (5) and the crusher (6) are respectively electrically connected with the control switch a and the control switch b through leads, and when the electric knife gate valve is used, the control switch a and the control switch b are both electrically connected with an external power supply through leads; the control switch is fixed on the support frame (1).
2. The sludge storage device integrating crushing and integration as claimed in claim 1, wherein: the sludge finished product bin (2) is funnel-shaped.
3. The sludge storage device integrating crushing and integration as claimed in claim 1, wherein: the crusher (6) also comprises a base support (8), and the base support (8) is fixed at the top of the support (7);
two sets of crushing mechanisms are symmetrically fixed on the base support (8), and each crushing mechanism comprises a motor (9) and a crushing roller (10); a driving chain wheel is arranged on an output shaft of the motor (9), the motor (9) is electrically connected with the control switch b through a lead, and a base of the motor (9) is fixed on the base support (8); the crushing roller (10) is fixed on a rotating shaft, the rotating shaft is fixed on a base support (8) through a bearing seat, a driving chain wheel is fixed on the rotating shaft, and the driving chain wheel is connected with a driving chain wheel through a chain (11);
the gap between the two crushing drums (10) is less than 15 mm.
CN202022067342.9U 2020-09-21 2020-09-21 Sludge storage device integrating crushing and crushing Active CN213170501U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022067342.9U CN213170501U (en) 2020-09-21 2020-09-21 Sludge storage device integrating crushing and crushing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022067342.9U CN213170501U (en) 2020-09-21 2020-09-21 Sludge storage device integrating crushing and crushing

Publications (1)

Publication Number Publication Date
CN213170501U true CN213170501U (en) 2021-05-11

Family

ID=75774739

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022067342.9U Active CN213170501U (en) 2020-09-21 2020-09-21 Sludge storage device integrating crushing and crushing

Country Status (1)

Country Link
CN (1) CN213170501U (en)

Similar Documents

Publication Publication Date Title
CN209917962U (en) Two-stage crushing device for steel waste
CN102872958A (en) Grinding process of ceramic raw material and ceramic raw material grinding production line
CN210496584U (en) Feed processing reducing mechanism
CN215277654U (en) Environment-friendly building concrete reducing mechanism with categorised waste material function of retrieving
CN213170501U (en) Sludge storage device integrating crushing and crushing
CN111167564A (en) A raw ore crushing apparatus for coal mining
CN204017970U (en) Spallar
CN107413496A (en) A kind of environment-friendly powder coating process equipment and its operating method
CN114471924B (en) Automatic coal dust sampling and screening device and control method for gap adjustment of crusher
CN111215186A (en) Horizontal gyratory crusher and intelligent control method thereof
CN107913897B (en) Smart sorting system of domestic waste
CN104002398B (en) A kind of reclaimed rubber rubber powder process units
CN103977874B (en) A kind of production equipment of rubber rubber powder
CN202983828U (en) Crushing sand-making complete plant
CN206716421U (en) Coal material screening breaker
CN210846628U (en) Battery plate smashing and recycling system
CN213254972U (en) Combined crushing device for concentrated feed
CN219424492U (en) Floor tile production raw material crushing device
CN203018169U (en) Special production device for pulverizing electrolyte
CN111054471B (en) Coal gangue crushing device
CN220277522U (en) Automatic steel forging screening machine
CN203874874U (en) Rubber powder production equipment
CN203876085U (en) Regenerated rubber powder production device
CN218459808U (en) Discharging chute
CN108686746A (en) A kind of industrial machinery pulverizer

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant