CN213169705U - House cover sliding open type garbage station - Google Patents

House cover sliding open type garbage station Download PDF

Info

Publication number
CN213169705U
CN213169705U CN202022030537.6U CN202022030537U CN213169705U CN 213169705 U CN213169705 U CN 213169705U CN 202022030537 U CN202022030537 U CN 202022030537U CN 213169705 U CN213169705 U CN 213169705U
Authority
CN
China
Prior art keywords
roof
pulley
slide
sliding
garbage station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022030537.6U
Other languages
Chinese (zh)
Inventor
窦红鑫
宋岳
贾越冬
侯文科
张振永
孙国伟
孙书伟
曹祥云
杨哲
姜昆
曹宁
王军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Co Ltd
Beijing Engineering Co Ltd of China Railway Construction Group Co Ltd
Original Assignee
China Railway Construction Group Co Ltd
Beijing Engineering Co Ltd of China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Co Ltd, Beijing Engineering Co Ltd of China Railway Construction Group Co Ltd filed Critical China Railway Construction Group Co Ltd
Priority to CN202022030537.6U priority Critical patent/CN213169705U/en
Application granted granted Critical
Publication of CN213169705U publication Critical patent/CN213169705U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The utility model discloses a house cover slip open-type rubbish station, including concrete foundation plate, square steel skeleton, house cover stand, the fixed frame of house cover, slide main frame, slide subassembly, slide mounting, slide angle bar, angle bar track, fixed house cover, slip house cover, various steel sheet, house cover girder, house cover secondary beam, pulley A, pulley B, pulley C, open rope, closed rope, concrete brick brickwork. The utility model has the advantages that: the tower crane lifting hopper directly dumps the construction waste into the waste pond, the wall body at the bottom of the waste station is a concrete structure wall with the height of 1.5 meters, and the structure of the waste station cannot be damaged in the lifting process of the tower crane; the tower crane hoists the construction waste to be directly connected into the pool, the problems of waste covering, dust control and the like are not involved, the environment is protected, and the field civilized construction is facilitated; the labor force is saved, the garbage is shoveled out of the station, the resources are saved, and the garbage dumping efficiency is improved.

Description

House cover sliding open type garbage station
Technical Field
The utility model relates to a rubbish station specifically is a room lid slides open-type rubbish station, belongs to rubbish collection depot technical field.
Background
The traditional garbage station is used for storing garbage, constructors need to use a tower crane lifting hopper to dump the building garbage at the garbage station door, and then use manpower to shovel the building garbage into the garbage station; the following inconveniences exist for a conventional garbage station:
firstly, building garbage is dumped at the door of the garbage station by a tower crane lifting hopper, so that a garbage station door or a rolling door is easy to be damaged;
secondly, the construction waste dumped at the door of the waste station can not be covered or put into the pool in time, so that the environmental pollution is caused and the environment is not protected;
and thirdly, construction waste is shoveled into the waste station by manpower, which wastes time, labor and is uneconomical.
Based on this, this application proposes a room lid slip open-type rubbish station.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a house lid slip open-type rubbish station just lies in providing for the solution problem, uses the house lid slip open-type rubbish station, only needs an operating personnel to pull open the house lid, and the pond is directly gone into with building rubbish to tower crane handling hopper, closes the main entrance, and closed house lid, building rubbish are poured into rubbish station and are easily worked out.
The utility model discloses a following technical scheme realizes above-mentioned purpose: a roof sliding open type garbage station comprises a concrete foundation plate, a concrete brick masonry and a garbage station main body; the concrete foundation plate is poured in a foundation dug on the ground, a concrete brick masonry is laid on the upper surface of the concrete foundation plate, and a garbage station main body is arranged above the concrete foundation plate;
the garbage station main body comprises a square steel framework, a slide way main frame, a fixed roof, a sliding roof, pulleys, ropes and steel plates, wherein the steel plates are fixedly connected outside the square steel framework through rivets, the bottom end of the square steel framework is fixedly connected onto a concrete foundation plate, the slide way main frame is installed at the top end of the square steel framework, the square steel framework comprises a roof upright post and a roof fixing frame, the roof fixing frame is fixedly installed above the roof upright post through rivets, the fixed roof and the sliding roof are arranged above the square steel framework, the fixed roof is fixedly connected with the square steel framework through rivets and is positioned below the slide way main frame, the sliding roof is arranged above the slide way main frame, the pulleys comprise pulleys A, B and C, and the pulleys A are connected to two sides of the lower surface of the sliding roof, and pulley A card is put in the slide main frame, pulley B installs on the roof secondary beam of slip roof, pulley C installs on one side roof stand of square steel skeleton, the rope is including opening rope and closed rope, the tail end of opening the one end fixed connection of rope at slip roof, the other end of opening the rope is walked around pulley C and is located the outside of rubbish station main part, the one end fixed connection of closed rope is at the front end of slip roof, the other end of closed rope is walked around the outside that lies in rubbish station main part behind pulley B and the pulley C in proper order.
The improved slideway comprises a slideway main frame, and is characterized in that slideway components are arranged in two side edges of the slideway main frame and comprise a slideway fixing piece, slideway angle iron and angle iron tracks, the slideway fixing piece is fixedly welded on the inner side edge of the slideway main frame, the slideway angle iron is welded on the slideway fixing piece, and the angle iron tracks are welded on the slideway angle iron.
The sliding roof comprises a color steel plate, a roof main beam and a roof secondary beam, wherein the roof main beam and the roof secondary beam are connected through rivets to form a frame structure, the roof secondary beam is located on the inner side of the roof main beam, and the color steel plate is fixedly arranged on a frame formed by the roof main beam and the roof secondary beam through rivets.
The pulley A is arranged below two side edges of the sliding roof, and the pulley A arranged on each side edge is respectively positioned at two ends and the middle position.
The pulley C is provided with two pulleys in an up-down distribution manner, the opening rope bypasses the pulley C positioned above, and the closing rope bypasses the pulley C positioned below.
The concrete brick masonry is a 1500mm high and 200mm wide partition wall body built by mortar bricks, and the concrete brick masonry divides a concrete foundation plate into three areas, namely a recyclable garbage storage chamber, a non-recyclable garbage storage chamber and a toxic and harmful garbage storage chamber.
The thickness of the concrete foundation plate is 200mm, the size is 4400mm 6800mm, and anchor bolts are buried in four outer corner parts and partition wall parts of the concrete foundation plate.
The utility model has the advantages that: the roof sliding open type garbage station is reasonable in design, the construction garbage is directly dumped into the garbage pool by the tower crane lifting hopper, the wall body at the bottom of the garbage station is a 1.5-meter high concrete structure wall, and the garbage station structure cannot be damaged in the tower crane lifting process; the tower crane hoists the construction waste to be directly connected into the pool, the problems of waste covering, dust control and the like are not involved, the environment is protected, and the field civilized construction is facilitated; the labor force is saved, the garbage is shoveled out of the station, the resources are saved, and the garbage dumping efficiency is improved.
Drawings
FIG. 1 is a schematic front view of the present invention;
FIG. 2 is a schematic top view of the present invention;
FIG. 3 is a schematic structural view of the sliding assembly of the present invention;
FIG. 4 is a schematic view of the structure of the garbage bucket of the present invention;
FIG. 5 is a schematic view of the garbage dumping structure of the garbage bucket of the present invention;
fig. 6 is the structure schematic diagram of the garbage bucket discharging from the tank.
In the figure: 1. concrete foundation slab, 2, square steel skeleton, 21, roof stand, 22, roof fixed frame, 3, slide main frame, 31, slide subassembly, 311, slide mounting, 312, slide angle bar, 313, angle bar track, 4, fixed roof, 5, slip roof, 51, color steel plate, 52, roof girder, 53, roof secondary beam, 6, pulley A, 7, pulley B, 8, pulley C, 9, opening rope, 10, closing rope and 11, concrete brickwork.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 to 6, a sliding open type garbage station for roof comprises a concrete foundation plate 1, a concrete brick masonry 11 and a garbage station main body; the concrete foundation plate 1 is poured in a foundation dug on the ground, a concrete brick masonry 11 is laid on the upper surface of the concrete foundation plate 1, and a garbage station main body is installed above the concrete foundation plate 1;
the garbage station main body comprises a square steel framework 2, a slide way main frame 3, a fixed roof 4, a sliding roof 5, a pulley, a rope and a steel plate, wherein the steel plate is fixedly connected to the outer side of the square steel framework 2 through rivets, the bottom end of the square steel framework 2 is fixedly connected to a concrete foundation plate 1, the slide way main frame 3 is installed at the top end of the square steel framework 2, the square steel framework 2 comprises a roof upright post 21 and a roof fixing frame 22, the roof fixing frame 22 is fixedly installed above the roof upright post 21 through rivets, the fixed roof 4 and the sliding roof 5 are arranged above the square steel framework 2, the fixed roof 4 is fixedly connected with the square steel framework 2 through rivets, the fixed roof 4 is located below the slide way main frame 3, the sliding roof 5 is installed above the slide way main frame 3, and the pulley comprises a pulley A6, Pulley B7 and pulley C8, pulley A6 is connected in the lower surface both sides of slip roof 5, just pulley A6 card is put in slide main frame 3, pulley B7 installs on the roof secondary beam 53 of slip roof 5, pulley C8 installs on one side roof stand 21 of square steel framework 2, the rope is including opening rope 9 and closed rope 10, the one end fixed connection who opens rope 9 is at the tail end of slip roof 5, the other end of opening rope 9 is walked around pulley C8 and is located the outside of rubbish station main part, the one end fixed connection of closed rope 10 is at the front end of slip roof 5, the other end of closed rope 10 is walked around in proper order behind pulley B7 and pulley C8 and is located the outside of rubbish station main part.
Further, in the embodiment of the utility model provides an in, be provided with slide subassembly 31 in slide main frame 3's the both sides limit, slide subassembly 31 includes slide mounting 311, slide angle bar 312 and angle bar track 313, the fixed welding of slide mounting 311 is at the inboard side of slide main frame 3, the welding has slide angle bar 312 on slide mounting 311, the welding has angle bar track 313 on the slide angle bar 312, makes pulley A6 can block and put on angle bar track 313, realizes rolling connection, and then can be convenient for remove the slip roof.
Further, in the embodiment of the present invention, the sliding roof 5 includes a color steel plate 51, a roof main beam 52 and a roof secondary beam 53, the roof main beam 52 and the roof secondary beam 53 are connected by rivet to form a frame structure, and the roof secondary beam 53 is located inside the roof main beam 52, the color steel plate 51 is mounted on the frame formed by the roof main beam 52 and the roof secondary beam 53 by rivet fixing.
Further, in the embodiment of the present invention, the pulleys a6 are provided three under the two side edges of the sliding roof 5, and the pulley a6 provided at each side edge is located at each of the two ends and the middle position, so that when the sliding roof 5 is pulled to move, the sliding roof can be opened or closed stably.
Further, in the embodiment of the utility model provides an in, pulley C8 is provided with two for the upper and lower distribution form, and opens rope 9 and walks around the pulley C8 that is located the top, and closed rope 10 walks around the pulley C8 that is located the below, selects the rope of pulling difference according to the demand in order to realize opening or closing of slip roof 5, facilitates the operation and uses.
Further, in the embodiment of the utility model provides an in, concrete brick brickwork 11 is for adopting the 1500mm height that the lime-sand brick was built by laying bricks or stones, the wide partition wall body of 200mm, and concrete brick brickwork 11 separates into recoverable rubbish apotheca, unrecoverable rubbish apotheca and the three region of poisonous and harmful rubbish apotheca with concrete foundation plate 1, sets up concrete brick brickwork 11 in order to prevent that the forklift from destroying the main part at this rubbish station, and divide into three different regions, can separate rubbish and place.
Further, in the embodiment of the present invention, the thickness of the concrete foundation plate 1 is 200mm, the size is 4400mm 6800mm, and anchor bolts are buried in four outer corner portions and the partition wall portion of the concrete foundation plate 1, so as to be used for fixing the steel column in the third portion.
The working principle is as follows: when using this roof slip open-type rubbish station, start rope 9 through personnel's pulling, slip roof 5 slides to the top right, the rubbish station opens, wait for the hopper to go into the pond, wait for slip roof 5 whole back of opening, the pond is gone into perpendicularly to tower crane handling hopper, the hopper rope is untied in personnel's operation, rubbish is poured into in the rubbish station, rubbish is emptyd the back that finishes, personnel's fixed hopper rope, the pond is gone up perpendicularly to the empty hopper of tower crane handling, personnel's pulling closed rope 10, slip roof 5 is to doing and remove to the starting position, the rubbish station seals.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (7)

1. A house cover sliding open type garbage station comprises a concrete foundation plate (1), a concrete brick masonry (11) and a garbage station main body; the method is characterized in that: the garbage station is characterized in that the concrete foundation plate (1) is poured into a foundation dug on the ground, a concrete brick masonry body (11) is built on the upper surface of the concrete foundation plate (1), and a garbage station main body is installed above the concrete foundation plate (1);
the garbage station main body is composed of a square steel framework (2), a slide way main frame (3), a fixed roof (4), a sliding roof (5), pulleys, ropes and steel plates, wherein the steel plates are fixedly connected to the outer side of the square steel framework (2) through rivets, the bottom end of the square steel framework (2) is fixedly connected to a concrete foundation plate (1), the slide way main frame (3) is installed at the top end of the square steel framework (2), the square steel framework (2) comprises a roof upright post (21) and a roof fixing frame (22), the roof fixing frame (22) is fixedly installed above the roof upright post (21) through rivets, the fixed roof (4) and the sliding roof (5) are arranged above the square steel framework (2), the fixed roof (4) is fixedly connected with the square steel framework (2) through rivets, and the fixed roof (4) is located below the slide way main frame (3), the sliding roof (5) is placed above the sliding way main frame (3), the pulley comprises a pulley A (6), a pulley B (7) and a pulley C (8), the pulley A (6) is connected to two sides of the lower surface of the sliding roof (5), the pulley A (6) is clamped in the sliding way main frame (3), the pulley B (7) is installed on a roof secondary beam (53) of the sliding roof (5), the pulley C (8) is installed on a roof upright column (21) on one side of the square steel framework (2), the rope comprises an opening rope (9) and a closing rope (10), one end of the opening rope (9) is fixedly connected to the tail end of the sliding roof (5), the other end of the opening rope (9) bypasses the pulley C (8) and is located on the outer side of the garbage station main body, one end of the closing rope (10) is fixedly connected to the front end of the sliding roof (5), the other end of the closed rope (10) sequentially rounds the pulley B (7) and the pulley C (8) and then is positioned on the outer side of the garbage station main body.
2. A roof sliding open garbage station according to claim 1, wherein: be provided with slide subassembly (31) in the both sides limit of slide main frame (3), slide subassembly (31) include slide mounting (311), slide angle bar (312) and angle bar track (313), the fixed welding of slide mounting (311) is at the inboard side of slide main frame (3), the welding has slide angle bar (312) on slide mounting (311), the welding has angle bar track (313) on slide angle bar (312).
3. A roof sliding open garbage station according to claim 1, wherein: the sliding roof (5) comprises a color steel plate (51), a roof main beam (52) and a roof secondary beam (53), the roof main beam (52) and the roof secondary beam (53) are connected through rivets to form a frame structure, the roof secondary beam (53) is located on the inner side of the roof main beam (52), and the color steel plate (51) is fixedly installed on a frame formed by the roof main beam (52) and the roof secondary beam (53) through rivets.
4. A roof sliding open garbage station according to claim 1, wherein: the pulleys A (6) are arranged below two side edges of the sliding roof (5), and the pulleys A (6) arranged on each side edge are respectively positioned at two ends and the middle position.
5. A roof sliding open garbage station according to claim 1, wherein: the pulley C (8) is provided with two pulleys in an up-down distribution manner, the opening rope (9) bypasses the pulley C (8) positioned above, and the closing rope (10) bypasses the pulley C (8) positioned below.
6. A roof sliding open garbage station according to claim 1, wherein: the concrete brick masonry (11) is a 1500 mm-high and 200 mm-wide partition wall body built by mortar bricks, and the concrete brick masonry (11) divides the concrete foundation plate (1) into three areas, namely a recyclable garbage storage chamber, a non-recyclable garbage storage chamber and a toxic and harmful garbage storage chamber.
7. A roof sliding open garbage station according to claim 1 or 6, characterized in that: the thickness of the concrete foundation plate (1) is 200mm, the size is 4400mm 6800mm, and anchor bolts are buried in four outer corner parts and partition wall parts of the concrete foundation plate (1).
CN202022030537.6U 2020-09-16 2020-09-16 House cover sliding open type garbage station Expired - Fee Related CN213169705U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022030537.6U CN213169705U (en) 2020-09-16 2020-09-16 House cover sliding open type garbage station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022030537.6U CN213169705U (en) 2020-09-16 2020-09-16 House cover sliding open type garbage station

Publications (1)

Publication Number Publication Date
CN213169705U true CN213169705U (en) 2021-05-11

Family

ID=75774076

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022030537.6U Expired - Fee Related CN213169705U (en) 2020-09-16 2020-09-16 House cover sliding open type garbage station

Country Status (1)

Country Link
CN (1) CN213169705U (en)

Similar Documents

Publication Publication Date Title
US5375944A (en) Waste disposing ground or facility
CN213169705U (en) House cover sliding open type garbage station
CN208777343U (en) A kind of dead load test on pile foundation preloading device
CN110106867A (en) Manual digging pile construction method between railcar station track
CN106638610B (en) Height difference misconnection structure and its construction method
CN201432842Y (en) Non-drainage undisturbed soil transfer device
CN208347245U (en) A kind of construction site floor refuse collection channel
CN210737607U (en) A hang braced system for reverse construction method beam slab construction
CN111979935A (en) Dismantling construction method for bridge superstructure
CN216341267U (en) Underground mine trackless equipment maintenance trench
CN210194691U (en) Protective structure for post-cast strip of settlement of basic raft
RU97111616A (en) UNDERGROUND CONSTRUCTION ESTABLISHED IN PITCH, AND METHOD OF CONCRETING
CN210597280U (en) Cast-in-situ anti-floating protective plate for hole digging pile
CN113023562A (en) Soil body taking and transporting device and method for existing building underground space development
JP3078805B1 (en) Construction method of nuclear power facilities
JP2638725B2 (en) Construction method of refuse incinerator facilities
KR102510544B1 (en) Method for inserting large disposal container and closing temporary opening in radioactive waste surface disposal facility using a construction lift
CN218563142U (en) Construction system for removing concrete plugging wall of ultra-deep foundation pit
CN109083155A (en) A kind of internal support of foundation pit structure and its blasting demolishing method
CN212224639U (en) Reinforcing bar garbage collection device
CN217226114U (en) Cement mixing pile can have enough to meet need stirring protection integration lower thick liquid barreled and put
CN217556976U (en) Water conservancy construction cofferdam device
CN210654677U (en) Construction site garbage pool
CN215107693U (en) Movable tea booth
CN2249265Y (en) Automatic sedimentation die for hole-digging pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Dou Hongxin

Inventor after: Yang Zhe

Inventor after: Jiang Kun

Inventor after: Cao Ning

Inventor after: Wang Jun

Inventor after: Song Yue

Inventor after: Jia Yuedong

Inventor after: Yu Qinghe

Inventor after: Hou Wenke

Inventor after: Zhang Zhenyong

Inventor after: Sun Guowei

Inventor after: Sun Shuwei

Inventor after: Cao Xiangyun

Inventor before: Dou Hongxin

Inventor before: Jiang Kun

Inventor before: Cao Ning

Inventor before: Wang Jun

Inventor before: Song Yue

Inventor before: Jia Yuedong

Inventor before: Hou Wenke

Inventor before: Zhang Zhenyong

Inventor before: Sun Guowei

Inventor before: Sun Shuwei

Inventor before: Cao Xiangyun

Inventor before: Yang Zhe

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210511