CN213059881U CN202021459176.0U CN202021459176U CN213059881U CN 213059881 U CN213059881 U CN 213059881U CN 202021459176 U CN202021459176 U CN 202021459176U CN 213059881 U CN213059881 U CN 213059881U
Authority
CN
China
Prior art keywords
hoist
clamping
hoisting
mount
centre gripping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021459176.0U
Other languages
Chinese (zh)
Inventor
刘慧梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Haochen Municipal Engineering Co ltd
Original Assignee
Anhui Haochen Municipal Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Haochen Municipal Engineering Co ltd filed Critical Anhui Haochen Municipal Engineering Co ltd
Priority to CN202021459176.0U priority Critical patent/CN213059881U/en
Application granted granted Critical
Publication of CN213059881U publication Critical patent/CN213059881U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model relates to a construction technical field just discloses an effectual hoisting clamp holds device for construction of centre gripping, including the hoist and mount board, the middle part fixedly connected with hoist and mount hook of hoist and mount board upper surface, the equal fixedly connected with hydraulic power unit in the left and right sides of hoist and mount board upper surface, the left and right sides of hoist and mount board lower surface all is provided with hydraulic clamping device, the middle part fixedly connected with mount of hoist and mount board lower surface. This hoist and mount clamping device for construction that centre gripping is effectual drives through the pneumatic cylinder and promotes the rack, running gear and centre gripping pole carry out the centre gripping to the pipeline fixed, have better centre gripping effect, need not staff's supplementary use rope and bind, simplified the centre gripping process to the pipeline, it is more simple and convenient to operate, labour saving and time saving more, improved the operation progress of pipeline hoist and mount, effectively improved efficiency of construction and duty cycle, further improved the construction progress of pipeline hoist and mount.

Description

Effectual hoist and mount clamping device for construction of centre gripping
Technical Field
The utility model relates to a construction technical field specifically is an effectual hoisting clamp holds device for construction of centre gripping.
Background
The hoisting of the building thin-wall pipeline inside a building is an important part in installation engineering, the building thin-wall pipeline is generally positioned at the upper part of a house and has a higher distance from the ground, and the installation of the building thin-wall pipeline is assisted by a hoisting point at the upper part of the house; at present, in the hoisting process, the pipeline needs to be manually fixed on the clamping device and is bound by a rope sometimes, and the process of clamping the pipeline is complex, so that the hoisting progress is slow, and the construction period is slowly increased.
For example, a lifting clamp holding device for building construction with chinese patent application No. 201921326162.9 is basically described as follows: including suspending in midair the base plate on the lifting hook, the downside of base plate articulates there are two sets of linking arms, and the lower extreme of two sets of linking arms all rotates and is connected with first pivot, and this hoist and mount clamping device for construction drives the clamping jaw through the linking arm and carries out the centre gripping to the pipeline, but this centre gripping mode is difficult to the automation when putting down the pipeline and unclamps, needs staff's auxiliary operation, and the process that leads to the centre gripping pipeline is comparatively loaded down with trivial details, has reduced the construction progress of pipeline hoist and mount.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides an effectual hoisting clamp of centre gripping holds device for construction has solved the problem that proposes among the above-mentioned background art.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an effectual hoisting clamp holds device for construction of centre gripping, includes the hoist and mount board, the middle part fixedly connected with hoist and mount hook of hoist and mount board upper surface, the equal fixedly connected with hydraulic power unit in the left and right sides of hoist and mount board upper surface, the left and right sides of hoist and mount board lower surface all is provided with hydraulic clamping device, the middle part fixedly connected with mount of hoist and mount board lower surface, the bottom of mount is provided with the gangbar, the middle part of gangbar is provided with the axis of rotation, the bottom fixedly connected with clamping jaw of gangbar, the bottom of gangbar is provided with the rotation axis, the middle part fixedly connected with electric putter of hoist and mount board lower surface.
The hydraulic clamping device comprises a fixed side plate, a hydraulic cylinder is arranged at the top of the inner side surface of the fixed side plate, a connecting shaft is arranged at the output end of the hydraulic cylinder, a pushing rack is sleeved on the outer surface of the connecting shaft, a rotating gear is arranged at the bottom of the inner side surface of the fixed side plate, the pushing rack is meshed with the rotating gear, stabilizing chutes are formed in the front side and the rear side of the inner side surface of the fixed side plate, stabilizing sliding blocks are arranged inside the stabilizing chutes, clamping rods are fixedly connected to the lower surfaces of the stabilizing sliding blocks, moving racks are fixedly connected to the upper surfaces of the clamping rods, the rotating gears are meshed with the moving racks, and clamping rings.
Preferably, the inner side surface of the clamping ring is provided with an anti-slip layer, and anti-slip lines are uniformly arranged on the outer surface of the anti-slip layer.
Preferably, the linkage rod and the clamping rod are made of cast iron, and the outer surfaces of the linkage rod and the clamping rod are uniformly coated with antirust coatings.
Preferably, the inner side surface of the hoisting plate is provided with a T-shaped sliding groove, the outer side surface of the pushing rack is provided with a T-shaped sliding block, and the T-shaped sliding groove is connected with the T-shaped sliding block in a sliding mode.
Preferably, the number of the linkage rods is four, and the length of each linkage rod in the four groups is three hundred millimeters.
Preferably, the number of the clamping rods is two, and the two groups of clamping rods are all arranged in a forty-five-degree inclined mode.
(III) advantageous effects
Compared with the prior art, the utility model provides an effectual hoist and mount clamping device for construction of centre gripping possesses following beneficial effect:
1. this hoist and mount clamping device for construction that centre gripping is effectual drives through the pneumatic cylinder and promotes the rack, running gear and centre gripping pole carry out the centre gripping to the pipeline fixed, have better centre gripping effect, need not staff's supplementary use rope and bind, simplified the centre gripping process to the pipeline, it is more simple and convenient to operate, labour saving and time saving more, improved the operation progress of pipeline hoist and mount, effectively improved efficiency of construction and duty cycle, further improved the construction progress of pipeline hoist and mount.
2. This effectual hoist and mount clamping device for construction of centre gripping drives gangbar and clamping jaw through electric putter and assists the centre gripping fixed to the pipeline, further improves the centre gripping effect to the pipeline, avoids the in-process pipeline of hoist and mount to drop, has improved the security when the construction, improves work efficiency.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic side view of the present invention;
fig. 3 is a schematic structural view of the hydraulic clamping device of the present invention.
In the figure: 1. hoisting the plate; 2. hoisting hooks; 3. a hydraulic pump station; 4. a hydraulic clamping device; 401. fixing the side plate; 402. a hydraulic cylinder; 403. a connecting shaft; 404. pushing the rack; 405. a rotating gear; 406. a stabilizing chute; 407. stabilizing the slide block; 408. a clamping rod; 409. moving the rack; 410. a clamp ring; 5. a fixed mount; 6. a linkage rod; 7. a rotating shaft; 8. a clamping jaw; 9. a rotating shaft; 10. an electric push rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: a hoisting and clamping device with good clamping effect for building construction comprises a hoisting plate 1, a hoisting hook 2 is fixedly connected to the middle of the upper surface of the hoisting plate 1, hydraulic pump stations 3 are fixedly connected to the left side and the right side of the upper surface of the hoisting plate 1, the specific model of the hydraulic pump stations 3 is FLD-DB63, hydraulic clamping devices 4 are arranged on the left side and the right side of the lower surface of the hoisting plate 1, a fixing frame 5 is fixedly connected to the middle of the lower surface of the hoisting plate 1, a linkage rod 6 is arranged at the bottom of the fixing frame 5, a rotating shaft 7 is arranged in the middle of the linkage rod 6, a clamping jaw 8 is fixedly connected to the bottom end of the linkage rod 6, the linkage rod 6 and the clamping jaw 8 are driven by an electric push rod 10 to perform auxiliary clamping and fixing on a pipeline, the clamping effect on the pipeline is further improved, the pipeline is prevented from falling in the hoisting process, the safety during construction is improved, the, the middle part of the lower surface of the hoisting plate 1 is fixedly connected with an electric push rod 10, and the specific model of the electric push rod 10 is LAP 22.
The hydraulic clamping device 4 comprises a fixed side plate 401, a hydraulic cylinder 402 is arranged at the top of the inner side surface of the fixed side plate 401, a connecting shaft 403 is arranged at the output end of the hydraulic cylinder 402, a pushing rack 404 is sleeved on the outer surface of the connecting shaft 403, a rotating gear 405 is arranged at the bottom of the inner side surface of the fixed side plate 401, the pushing rack 404 is meshed with the rotating gear 405, stabilizing chutes 406 are arranged on the front side and the rear side of the inner side surface of the fixed side plate 401, stabilizing sliding blocks 407 are arranged inside the stabilizing chutes 406, clamping rods 408 are fixedly connected to the lower surface of the stabilizing sliding blocks 407, the pushing rack 404, the rotating gear 405 and the clamping rods 408 are driven by the hydraulic cylinder 402 to clamp and fix the pipeline, the clamping device has better clamping effect, does not need workers to use ropes for binding, simplifies the clamping process of the, effectively improved efficiency of construction and duty cycle, further improved the construction progress of pipeline hoist and mount, the last fixed surface of supporting rod 408 is connected with removes rack 409, and rotating gear 405 meshes with removing rack 409, and the bottom of supporting rod 408 is provided with grip ring 410.
The utility model discloses in order to improve anti-skidding effect to be provided with the skid resistant course at the medial surface of grip ring 410, the surface of skid resistant course evenly is provided with anti-skidding line, and the anti-skidding line increase frictional force of grip ring 410 medial surface improves anti-skidding effect.
The utility model discloses in order to improve life to the material that sets up gangbar 6 and supporting rod 408 is cast iron, and the surface of gangbar 6 and supporting rod 408 is evenly scribbled and is brushed anti rust coating, and the anti rust coating of gangbar 6 and supporting rod 408 surface prevents to corrode, improves life.
The utility model discloses in order to improve gliding stability to T shape spout has been seted up at the medial surface of hoist and mount board 1, the lateral surface that promotes rack 404 is provided with T shape slider, T shape spout and T shape slider sliding connection, and the T shape spout of hoist and mount board 1 medial surface is mutually supported with the T shape slider that promotes rack 404 lateral surface, improves gliding stability.
The utility model discloses in order to improve the convenience of using to the quantity that sets up gangbar 6 is four groups, and the length of four groups of gangbar 6 is three hundred millimeters, and four groups of gangbar 6 mutually support, improve the convenience of using.
The utility model discloses in order to improve the centre gripping effect to the quantity that sets up supporting rod 408 is two sets of, and two sets of supporting rod 408 all are the slope setting of forty-five degrees, and two sets of supporting rod 408 are the slope setting of forty-five degrees, improvement centre gripping effect that can be better.
The electrical components presented in the document are all electrically connected with an external master controller and 220V mains, and the master controller can be a conventional known device controlled by a computer or the like.
When the lifting clamping device is used, the lifting clamping device is moved to a proper position, the electric push rod 10 is started, the output end of the electric push rod 10 drives the rotating shaft 9 to move downwards, the rotating shaft 9 drives the linkage rod 6 and the clamping jaw 8 to open, a pipeline is sleeved into the clamping jaw 8, the output end of the electric push rod 10 is controlled to drive the rotating shaft 9 to move upwards, the rotating shaft 9 drives the linkage rod 6 and the clamping jaw 8 to tighten up for clamping, then the hydraulic pump station 3 is started, the output end of the hydraulic pump station 3 driving hydraulic cylinder 402 drives the pushing rack 404 to move downwards, the pushing rack 404 drives the rotating gear 405 to rotate, the rotating gear 405 is meshed with the moving rack 409 to drive the clamping rod 408 to move upwards, the clamping rod 408 drives the clamping ring 410 to clamp the pipeline, after clamping is completed, the pipeline is driven to move upwards through the.
To sum up, this effectual hoist and mount clamping device for construction of centre gripping drives through pneumatic cylinder 402 and promotes rack 404, rolling gear 405 and supporting rod 408 and carry out the centre gripping to the pipeline fixed, has better centre gripping effect, need not staff's supplementary use rope and bindes, has simplified the centre gripping process to the pipeline, and it is more simple and convenient to operate, labour saving and time saving more, has improved the operation progress of pipeline hoist and mount, has effectively improved efficiency of construction and duty cycle, has further improved the construction progress of pipeline hoist and mount.
This effectual hoist and mount clamping device for construction of centre gripping drives gangbar 6 and clamping jaw 8 through electric putter 10 and assists the centre gripping fixed to the pipeline, further improves the centre gripping effect to the pipeline, avoids the in-process pipeline of hoist and mount to drop, has improved the security when the construction, improves work efficiency.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides an effectual hoisting clamp holds device for construction of centre gripping, includes hoisting plate (1), its characterized in that: the middle of the upper surface of the hoisting plate (1) is fixedly connected with a hoisting hook (2), the left side and the right side of the upper surface of the hoisting plate (1) are fixedly connected with hydraulic pump stations (3), the left side and the right side of the lower surface of the hoisting plate (1) are respectively provided with a hydraulic clamping device (4), the middle of the lower surface of the hoisting plate (1) is fixedly connected with a fixed frame (5), the bottom of the fixed frame (5) is provided with a linkage rod (6), the middle of the linkage rod (6) is provided with a rotating shaft (7), the bottom end of the linkage rod (6) is fixedly connected with a clamping jaw (8), the bottom end of the linkage rod (6) is provided with a rotating shaft (9), and the middle of the lower surface of the hoisting plate (1) is fixedly;
the hydraulic clamping device (4) comprises a fixed side plate (401), a hydraulic cylinder (402) is arranged at the top of the inner side surface of the fixed side plate (401), a connecting shaft (403) is arranged at the output end of the hydraulic cylinder (402), a pushing rack (404) is sleeved on the outer surface of the connecting shaft (403), a rotating gear (405) is arranged at the bottom of the inner side surface of the fixed side plate (401), the pushing rack (404) is meshed with the rotating gear (405), stabilizing sliding chutes (406) are arranged on the front side and the rear side of the inner side surface of the fixed side plate (401), a stabilizing sliding block (407) is arranged inside the stabilizing sliding chute (406), a clamping rod (408) is fixedly connected to the lower surface of the stabilizing sliding block (407), a moving rack (409) is fixedly connected to the upper surface of the clamping rod (408), and the rotating gear (405, the bottom of the clamping rod (408) is provided with a clamping ring (410).
2. The hoisting clamp holding device with good holding effect for building construction according to claim 1, characterized in that: the inner side surface of the clamping ring (410) is provided with an anti-slip layer, and anti-slip lines are uniformly arranged on the outer surface of the anti-slip layer.
3. The hoisting clamp holding device with good holding effect for building construction according to claim 1, characterized in that: the linkage rod (6) and the clamping rod (408) are made of cast iron, and the outer surfaces of the linkage rod (6) and the clamping rod (408) are uniformly coated with antirust coatings.
4. The hoisting clamp holding device with good holding effect for building construction according to claim 1, characterized in that: the inner side surface of the hoisting plate (1) is provided with a T-shaped sliding groove, the outer side surface of the pushing rack (404) is provided with a T-shaped sliding block, and the T-shaped sliding groove is connected with the T-shaped sliding block in a sliding mode.
5. The hoisting clamp holding device with good holding effect for building construction according to claim 1, characterized in that: the number of the linkage rods (6) is four, and the length of each linkage rod (6) in the four groups is three hundred millimeters.
6. The hoisting clamp holding device with good holding effect for building construction according to claim 1, characterized in that: the number of the clamping rods (408) is two, and the two groups of clamping rods (408) are all arranged in a forty-five-degree inclined mode.
CN202021459176.0U 2020-07-22 2020-07-22 Effectual hoist and mount clamping device for construction of centre gripping Expired - Fee Related CN213059881U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021459176.0U CN213059881U (en) 2020-07-22 2020-07-22 Effectual hoist and mount clamping device for construction of centre gripping

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021459176.0U CN213059881U (en) 2020-07-22 2020-07-22 Effectual hoist and mount clamping device for construction of centre gripping

Publications (1)

Publication Number Publication Date
CN213059881U true CN213059881U (en) 2021-04-27

Family

ID=75574893

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021459176.0U Expired - Fee Related CN213059881U (en) 2020-07-22 2020-07-22 Effectual hoist and mount clamping device for construction of centre gripping

Country Status (1)

Country Link
CN (1) CN213059881U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113351404A (en) * 2021-06-18 2021-09-07 嘉兴学院 Auto-parts sprays paint and hangs conveyor with over-and-under type
CN113757450A (en) * 2021-07-31 2021-12-07 安徽五千年建设工程有限公司 Pipeline laying device for road construction for municipal construction and method thereof
CN113879960A (en) * 2021-11-05 2022-01-04 大连海事大学 Slender rod piece anti-rolling attitude-fixing device installed on crane
CN117819370A (en) * 2024-03-06 2024-04-05 徐州冠华机械制造有限公司 Foundry goods hoist device

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113351404A (en) * 2021-06-18 2021-09-07 嘉兴学院 Auto-parts sprays paint and hangs conveyor with over-and-under type
CN113757450A (en) * 2021-07-31 2021-12-07 安徽五千年建设工程有限公司 Pipeline laying device for road construction for municipal construction and method thereof
CN113757450B (en) * 2021-07-31 2023-02-28 安徽五千年建设工程有限公司 Pipeline laying device for road construction for municipal construction and use method thereof
CN113879960A (en) * 2021-11-05 2022-01-04 大连海事大学 Slender rod piece anti-rolling attitude-fixing device installed on crane
CN117819370A (en) * 2024-03-06 2024-04-05 徐州冠华机械制造有限公司 Foundry goods hoist device
CN117819370B (en) * 2024-03-06 2024-05-17 徐州冠华机械制造有限公司 Foundry goods hoist device

Similar Documents

Publication Publication Date Title
CN213059881U (en) Effectual hoist and mount clamping device for construction of centre gripping
CN113213330B (en) Electric pole hoisting device for electric power construction
CN211687957U (en) Quick overhead hoist of aerated concrete block
CN212425137U (en) Concrete block hoist device
CN215558390U (en) Hoisting apparatus for fire control construction
CN213569232U (en) Prevent hindering hand ceramic tile hoisting machine for architectural decoration constructs
CN108726358A (en) A kind of towering concrete structure main reinforcement batch hanging apparatus and method
CN213085198U (en) Balance hanging beam group lifting appliance
CN212024601U (en) Building engineering lifting device
CN112499521A (en) A handling device for industrial automation equipment
CN210809657U (en) Building engineering cost budgets auxiliary device
CN210856390U (en) Hoisting device is handled to auto-parts surface electrophoresis lacquer
CN209905924U (en) High-efficient sign indicating number brick machine
CN210127034U (en) Material lifting equipment for civil engineering
CN209797241U (en) Capping structure for construction building
CN207482767U (en) One kind is for building to remove brick machine
CN218707027U (en) Move ladle car with automatic feeding function
CN220334554U (en) Special cleaning lifting appliance for workpieces with holes
CN218708709U (en) Novel aluminum coil feeding machine
CN220033871U (en) Scaffold for building engineering
CN219296973U (en) Casting crane lifting appliance
CN217146089U (en) Waterproofing membrane's integral type turning device
CN220723280U (en) Chimney steel inner barrel lifting device
CN213505590U (en) House building material lifting equipment
CN217478878U (en) Feeding device capable of reducing labor intensity

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210427