CN213034858U - Cement reinforcing steel pouring support device - Google Patents

Cement reinforcing steel pouring support device Download PDF

Info

Publication number
CN213034858U
CN213034858U CN202020603975.4U CN202020603975U CN213034858U CN 213034858 U CN213034858 U CN 213034858U CN 202020603975 U CN202020603975 U CN 202020603975U CN 213034858 U CN213034858 U CN 213034858U
Authority
CN
China
Prior art keywords
groove
support plate
support
plate
connecting plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020603975.4U
Other languages
Chinese (zh)
Inventor
李光容
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changzhou China Carbon Building Industry Co.,Ltd.
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020603975.4U priority Critical patent/CN213034858U/en
Application granted granted Critical
Publication of CN213034858U publication Critical patent/CN213034858U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides a strutting arrangement is pour to cement reinforcing bar belongs to cement reinforcing bar and pours technical field, include: the supporting plate I, the supporting groove, the assembling plates, the mounting grooves, the connecting plates, the supporting plate II, the bolts, the vibration structures, the vibrators, the mounting plates, the springs, the mounting blocks, the through holes, the protrusions and the grooves, wherein the two ends of the two assembling plates are movably connected with the supporting plate I, the supporting plate II is movably connected between the supporting plate I, the connecting plates are movably connected between the supporting plate I and the assembling plates, the supporting groove is fixedly connected to the inner side surface of the supporting plate I, and the supporting groove is movably connected with the two ends of the supporting plate. This practicality is through setting up backup pad one, backup pad two, equipment board, connecting plate, bolt and vibrator and to this strutting arrangement convenient to detach equipment, can be better accomodate on the car when the transportation, the transportation of being convenient for.

Description

Cement reinforcing steel pouring support device
Technical Field
The utility model relates to a cement reinforcing bar pours technical field, particularly, relates to a strutting arrangement is pour to cement reinforcing bar.
Background
The cement steel bar pouring refers to a process of pouring the cement steel bars into a mold until plasticizing, materials such as concrete and the like are put into the mold to be made into a preset shape in civil and architectural engineering, the free height of the concrete is not more than 2m when the cement steel bars are poured, and corresponding measures are taken when the free height of the concrete is more than 3 m;
in prior art, when pouring the cement reinforcing bar, all need adopt earlier strutting arrangement will pour the mould and make out, and current strutting arrangement is not convenient for dismantle the installation, and contains the bubble in the cement when pouring, treats that cement solidification produces the cavity easily after, influences the wall body firm, consequently, an urgent need for a cement reinforcing bar and pours strutting arrangement.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problem of proposing in the background art to a strutting arrangement is pour to cement reinforcing bar is provided.
In order to achieve the above object, the utility model provides a following technical scheme: a concrete reinforcing bar pouring support device, comprising: the device comprises a first support plate, a support groove, assembling plates, a mounting groove, a connecting plate, a second support plate, a bolt, a vibration structure, a vibrator, a mounting plate, a spring, a mounting block, a through hole, a protrusion and a groove, wherein the two ends of the two assembling plates are movably connected with the first support plate, the first support plate is movably connected with the second support plate, the connecting plate is movably connected between the first support plate and the assembling plates, the inner side surface of the first support plate is fixedly connected with the support groove, the support groove is movably connected with the two ends of the second support plate, one side of the inner side surface of the first support plate is fixedly connected with the two sides of the inner side surface of the assembling plates and provided with the groove, one side of the outer side surface of the first support plate and the two sides of the outer side surface of the assembling plates are fixedly connected with the protrusion, the first support plate and the assembling, the utility model discloses a vibrating screen, including mounting panel, through hole, assembly board, mounting panel bottom, mounting panel, mounting.
Preferably, the first support plate, the assembly plate, the connecting plate, the second support plate and the bolt are assembled in a shape like a Chinese character 'hui'.
Preferably, the cross section of the connecting plate is T-shaped, and two sides of the connecting plate are inlaid in the grooves.
Preferably, the installation piece all is T style of calligraphy structure with the mounting groove cross section, and the installation piece is cup jointed the setting with the mounting groove.
Preferably, the second support plate is clamped with the support groove.
Preferably, sealing rubber is arranged inside each groove.
The utility model provides a strutting arrangement is pour to cement reinforcing bar has following beneficial effect:
1. the cement steel bar pouring support device is convenient to disassemble and assemble by arranging the support plate I, the support plate II, the assembling plate, the connecting plate, the bolt and the vibration device, the support device can be better stored on a vehicle during transportation, is convenient to transport, and is assembled through four support plates I, two support plates II, a plurality of assembling plates, a plurality of connecting plates, a plurality of bolts and a vibration device during assembly, the first support plate and the second support plate are assembled through the assembling groove and fixed through the through hole and the bolt, meanwhile, the support plate II is assembled with the assembly plate by assembling the groove and the bulge with the connecting plate and fixing the support plate II with the through hole and the bolt, meanwhile, the assembling plates can be spliced and assembled, so that different construction requirements are met, and the supporting device can be suitable for construction requirements with different lengths.
2. This strutting arrangement is pour to cement reinforcing bar is through setting up vibrations structure, makes strutting arrangement is pour to cement reinforcing bar when carrying out cement and pour, and when the electromagnetic shaker during operation, messenger's electromagnetic shaker drives this strutting arrangement vibrations, makes four backup pads one, two backup pads two, vibrations of a plurality of assembled plate and a plurality of connecting plate, makes cement when pouring, and the bubble that contains in making the cement can pass through the electromagnetic shaker vibrations, and the bubble that contains in the messenger's cement is discharged, and the messenger pours the cement wall body that comes out more durable.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention.
Fig. 2 is a side view of the vibration structure of the present invention.
Fig. 3 is an overall side view of the present invention.
In fig. 1 to 3, the corresponding relationship between the part names or lines and the reference numbers is:
the device comprises a support plate I-1, a support groove-101, an assembly plate-2, a mounting groove-201, a connecting plate-3, a support plate II-4, a bolt-5, a vibration structure-6, a vibrator-601, a mounting plate-602, a spring-603, a mounting block-604, a through hole-7, a protrusion-8 and a groove-9.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention relates to a supporting device for concrete reinforcing bar, including: a first support plate 1, a support groove 101, an assembly plate 2, a mounting groove 201, a connecting plate 3, a second support plate 4, a bolt 5, a vibration structure 6, a vibrator 601, a mounting plate 602, a spring 603, a mounting block 604, a through hole 7, a protrusion 8 and a groove 9, wherein both ends of the two assembly plates 2 are movably connected with the first support plate 1, the second support plate 4 is movably connected between the first support plates 1, the connecting plate 3 is movably connected between the first support plate 1 and the assembly plate 2, the inner side surface of the first support plate 1 is fixedly connected with the support groove 101, the support groove 101 is movably connected with both ends of the second support plate 4, one side of the inner side surface of the first support plate 1 is fixedly connected with both sides of the inner side surface of the assembly plate 2 and is provided with the groove 9, one side of the outer side surface of the first support plate 1 is fixedly connected with both sides of the outer side surface of the assembly plate 2 and, one 1 one side of backup pad, the equal fixed connection in connecting plate 3 one side and protruding 8 one side is equipped with a plurality of through holes 7, the inside swing joint of through hole 7 is equipped with bolt 5, 2 outside surface one end fixed connections of assembled sheet are equipped with mounting groove 201, the inside swing joint of mounting groove 201 is equipped with vibrations structure 6, the 6 one end fixed connection of vibrations structure is equipped with electromagnetic shaker 601, electromagnetic shaker 601 bottom fixed connection is equipped with mounting panel 602, fixed connection is equipped with installation piece 604 in the middle of the mounting panel 602 bottom, and installation piece 604 and mounting groove 201 swing joint, the equal fixed connection in mounting panel 602 bottom surface both sides is equipped with a plurality of springs 603.
In this embodiment, the equipment of backup pad 1, equipment board 2, connecting plate 3, backup pad two 4 and bolt 5 is back style of calligraphy setting, makes and can assemble between backup pad 1, equipment board 2, connecting plate 3, the backup pad two 4, makes this strutting arrangement convenient to detach equipment, the transportation of being convenient for simultaneously.
In this embodiment, the transversal T style of calligraphy setting of personally submitting of connecting plate 3, and 3 both sides of connecting plate all inlay with recess 9, when assembling, make connecting plate 3 be connected with recess 9, make the area of contact greatly increased in clearance between connecting plate 3 and backup pad 1 and the assembly plate 2, it is more even to make a point atress between backup pad 1 and the assembly plate 2 through connecting plate 3 simultaneously, when carrying out cement pouring, can prevent effectively that local atress is too big, and lead to bearing structure damage occurence of failure.
In this embodiment, installation piece 604 all is T style of calligraphy structure with mounting groove 201 cross section, and installation piece 604 is to cup jointing the setting with mounting groove 201, makes inside installation piece 603 can block into mounting groove 201, makes vibrations structure 6 install inside mounting groove 201.
In this embodiment, the second supporting plate 4 is clamped with the supporting grooves 101, so that the second supporting plate 4 can be fixed through the two supporting grooves 101, and the second supporting plate 4 is assembled with the first supporting plate 1.
In this embodiment, the grooves 9 are all provided with sealing rubber, so that cement cannot leak from the gap between the connecting plate 3 and the first support plate 1 and the assembling plate 2.
The working principle is as follows: firstly, a cement reinforcing steel bar pouring support device is assembled with the outer side of a reinforcing steel bar, so that the support device wraps the reinforcing steel bar;
when the support device is assembled, the support device is assembled through the four support plates I1, the two support plates II 4, the assembling plates 2, the connecting plates 3, the bolts 5 and the vibration device 6;
the first support plate 1 and the second support plate 4 are assembled through the assembling groove 101, are fixed through the through hole 7 and the bolt 5, are assembled with the connecting plate 3 through the groove 9 and the protrusion 8, are fixed through the through hole 7 and the bolt 5, are assembled with the second support plate 4 and the assembling plates 2, and can be spliced and assembled on the assembling plates 2, so that different construction requirements are met, and the support device can be suitable for construction requirements with different lengths;
when accomplishing through four backup pads one 1, two backup pads two 4, the equipment of a plurality of assembled panel 2 and a plurality of connecting plate 3, make again with vibrator 6 install inside mounting groove 201, under the spring 603 spring action, make installation piece 604 and mounting groove 201 zonulae occludens, when electromagnetic shaker 601 during operation, make electromagnetic shaker 601 drive this strutting arrangement vibrations, make four backup pads one 1, two backup pads two 4, a plurality of assembled panel 2 and a plurality of connecting plate 3 vibrations, make cement when pouring, make the bubble that contains in the cement can vibrate through electromagnetic shaker 601, make the bubble that contains in the cement discharge, the cement wall body that the messenger poured out is more durable.
The above is only the preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, without departing from the concept of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicability of the patent.

Claims (6)

1. A concrete reinforcing bar pouring support device, comprising: backup pad (1), supporting groove (101), equipment board (2), mounting groove (201), connecting plate (3), backup pad two (4), bolt (5), vibrations structure (6), electromagnetic shaker (601), mounting panel (602), spring (603), installation piece (604), through hole (7), arch (8) and recess (9), its characterized in that: the two ends of the two assembly plates (2) are respectively and movably connected with a first support plate (1), a second support plate (4) is movably connected between the first support plate (1), a connecting plate (3) is movably connected between the first support plate (1) and the assembly plates (2), a support groove (101) is fixedly connected to the inner side surface of the first support plate (1), the support groove (101) is movably connected with the two ends of the second support plate (4), a groove (9) is fixedly connected to one side of the inner side surface of the first support plate (1) and two sides of the inner side surface of the assembly plates (2), a protrusion (8) is fixedly connected to one side of the outer side surface of the first support plate (1) and two sides of the outer side surface of the assembly plates (2), the first support plate (1) and the assembly plates (2) are movably connected with the connecting plate (3) through the groove (9) and the protrusion (8), and the first support, Connecting plate (3) one side and the equal fixed connection in protruding (8) one side are equipped with a plurality of through holes (7), the inside swing joint of through hole (7) is equipped with bolt (5), assembled sheet (2) outside surface one end fixed connection is equipped with mounting groove (201), the inside swing joint of mounting groove (201) is equipped with vibrations structure (6), vibrations structure (6) one end fixed connection is equipped with electromagnetic shaker (601), electromagnetic shaker (601) bottom fixed connection is equipped with mounting panel (602), fixed connection is equipped with installation piece (604) in the middle of mounting panel (602) bottom, and installation piece (604) and mounting groove (201) swing joint, the equal fixed connection in mounting panel (602) bottom surface both sides is equipped with a plurality of springs (603).
2. The concrete steel pouring support device according to claim 1, wherein: the support plate I (1), the assembling plate (2), the connecting plate (3), the support plate II (4) and the bolt (5) are assembled to be arranged in a shape like a Chinese character 'hui'.
3. The concrete steel pouring support device according to claim 1, wherein: the cross section of the connecting plate (3) is T-shaped, and both sides of the connecting plate (3) are inlaid in the grooves (9).
4. The concrete steel pouring support device according to claim 1, wherein: installation piece (604) all are T style of calligraphy structure with mounting groove (201) cross section, and installation piece (604) are to cup joint the setting with mounting groove (201).
5. The concrete steel pouring support device according to claim 1, wherein: the second support plate (4) is clamped with the support groove (101).
6. The concrete steel pouring support device according to claim 1, wherein: and sealing rubber is arranged inside each groove (9).
CN202020603975.4U 2020-04-21 2020-04-21 Cement reinforcing steel pouring support device Active CN213034858U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020603975.4U CN213034858U (en) 2020-04-21 2020-04-21 Cement reinforcing steel pouring support device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020603975.4U CN213034858U (en) 2020-04-21 2020-04-21 Cement reinforcing steel pouring support device

Publications (1)

Publication Number Publication Date
CN213034858U true CN213034858U (en) 2021-04-23

Family

ID=75519429

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020603975.4U Active CN213034858U (en) 2020-04-21 2020-04-21 Cement reinforcing steel pouring support device

Country Status (1)

Country Link
CN (1) CN213034858U (en)

Similar Documents

Publication Publication Date Title
CN210888073U (en) Plugging structure of assembled template gap
CN213034858U (en) Cement reinforcing steel pouring support device
JP2001280089A (en) Reinforcing method when placing concrete in high- strength buried form and repairing method for tunnel wall
CN106437146A (en) Template used for casting floor beam and construction method of floor beam
JP2003328381A (en) Flexible rubber joint and its mounting structure and its constructing method
JP3257985B2 (en) Expansion device for road bridge joint
KR100809064B1 (en) The earthquake resistant reinforcement method for preexistence bridges
CN110424601A (en) A kind of fabricated construction laminated floor slab concreting anti-floating system and implementation method
CN214575016U (en) Laminated floor
CN211967866U (en) Vibrator device for improving qualification rate of dam prefabricated blocks
JP3439436B2 (en) Raising method of concrete frame
CN218406551U (en) Novel concrete vibrates device
CN109853793A (en) A kind of self-compaction regeneration monolith overlapped shear wall and its construction method
CN219528018U (en) Anti-vibration seam structure suitable for frame construction
JPH08170429A (en) Method for constructing arch concrete
CN216109360U (en) Novel cast in situ concrete floor's is fixed device
CN217500478U (en) Open ditch cast-in-situ combined die
CN221118907U (en) Assembled floor
CN218203919U (en) Support for quickly building large-span continuous rigid frame bridge
CN220150643U (en) Superimposed sheet ground mould
JP7145809B2 (en) Formwork structure
CN101260710A (en) Prefabricated concrete element for reinforcing steel bar concrete filled floor
CN219604673U (en) Post-cast strip is exempted from to pick chisel and is exempted from formwork construction mould
CN213741922U (en) Side wall reinforcing steel bar positioning control template
CN215053171U (en) Contact net foundation steel formwork

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221213

Address after: Room 308, West Building, Innovation and Research Center, No. 8, Yanzheng West Avenue (Changzhou Wujin Green Building Industry Cluster Demonstration Area), Wujin District, Changzhou City, Jiangsu Province, 213100

Patentee after: Changzhou China Carbon Building Industry Co.,Ltd.

Address before: No.91 Zhengdong street, Dongpo District, Meishan, Sichuan 620000

Patentee before: Li Guangrong