CN213013950U - Pier stud construction operation platform - Google Patents

Pier stud construction operation platform Download PDF

Info

Publication number
CN213013950U
CN213013950U CN202021330246.2U CN202021330246U CN213013950U CN 213013950 U CN213013950 U CN 213013950U CN 202021330246 U CN202021330246 U CN 202021330246U CN 213013950 U CN213013950 U CN 213013950U
Authority
CN
China
Prior art keywords
main frame
fixed
plane
operation plane
movable plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021330246.2U
Other languages
Chinese (zh)
Inventor
郭庆新
张贵州
张忠
刘培军
祁清宝
闫乐
闫宁
岳飞龙
孟和达来
李冠华
郑永峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inner Mongolia Road And Bridge Group Co ltd
Original Assignee
Inner Mongolia Road And Bridge Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inner Mongolia Road And Bridge Group Co ltd filed Critical Inner Mongolia Road And Bridge Group Co ltd
Priority to CN202021330246.2U priority Critical patent/CN213013950U/en
Application granted granted Critical
Publication of CN213013950U publication Critical patent/CN213013950U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a pier stud construction operating platform, which comprises a main frame, an operating plane and a baffle; the operation plane comprises four operation planes, each operation plane comprises a fixed plate and a movable plate, the fixed plate is connected with the movable plate through a hinge, each operation plane is fixed on a top surface frame of the main frame, a support frame is fixed on the main frame below each operation plane, and the four operation planes surround to form a square shape; and surrounding baffles are fixed around the main frame. By fixing the operation plane on the top of the main frame, workers can carry out construction in a short distance when sleeving stirrups, and construction efficiency is improved; by arranging the fixed plate and the movable plate, after the movable plate is turned over, the distance between the operation plane and the pier stud main rib can be increased, and the pouring template can be conveniently hoisted; the whole pier construction operation platform is simple to assemble and convenient to use, and further the construction efficiency is improved.

Description

Pier stud construction operation platform
The technical field is as follows:
the utility model relates to a building field, concretely relates to pier stud construction operation platform.
Background art:
when the bridge pier column is constructed, a scaffold and an operation platform need to be erected to meet construction requirements and guarantee safety of constructors, but the existing scaffold and other supports are complicated to assemble, long in time needed for erection or removal, large in number of workers and time needed, and greatly influences the construction period; and in case the support such as current scaffold is assembled, in order to ensure to support intensity, can't dismantle according to the construction situation at will, it is extremely inconvenient to use.
The utility model has the following contents:
an object of the utility model is to provide a pier stud construction operation platform that suitability is strong, the security is high.
The utility model discloses by following technical scheme implement:
an operating platform for pier column construction comprises a main frame, an operating plane and a fence;
the operation plane comprises four operation planes, each operation plane comprises a fixed plate and a movable plate, the fixed plate is connected with the movable plate through a hinge, each operation plane is fixed on a top surface frame of the main frame, a support frame is fixed on the main frame below each operation plane, and the four operation planes surround to form a square shape;
and surrounding baffles are fixed around the main frame.
Preferably, the operation plane is detachably fixed to the main frame.
The utility model has the advantages that: by fixing the operation plane on the top of the main frame, workers can carry out construction in a short distance when sleeving stirrups, and construction efficiency is improved; by arranging the fixed plate and the movable plate, after the movable plate is turned over, the distance between the operation plane and the pier stud main rib can be increased, and the pouring template can be conveniently hoisted; the whole pier construction operation platform is simple to assemble and convenient to use, and further the construction efficiency is improved.
Description of the drawings:
fig. 1 is a schematic structural diagram of the present invention;
FIG. 2 is a schematic view of the structure below the operation plane of the present invention;
fig. 3 is a schematic structural diagram of the operation plane of the present invention.
In the figure: the device comprises a main frame 1, an operation plane 2, a fixed plate 2.1, a movable plate 2.2, a fence 3, a hinge 4 and a support frame 5.
The specific implementation mode is as follows:
as shown in fig. 1, an operating platform for pier stud construction comprises a main frame 1, an operating plane 2 and a fence 3;
the operating plane 2 comprises four operating planes, each operating plane 2 comprises a fixed plate 2.1 and a movable plate 2.2, the fixed plate 2.1 is connected with the movable plate 2.2 through a hinge 4, each operating plane 2 is fixed on a top frame of the main frame 1, a support frame 5 is fixed on the main frame 1 below each operating plane 2, and the four operating planes 2 are enclosed into a square shape;
a surrounding baffle 3 is fixed around the main frame 1;
the operation plane 2 and the main frame 1 are detachably fixed;
the main frame 1 is assembled by a plurality of steel frames, the height of the main frame 1 is 2 meters, the width of each operating plane 2 is 0.8 meter, and the operating planes 2 are fixed on the main frame 1 after the main frame 1 is assembled;
the supporting frame 5 is used for supporting the fixed plate 2.1 and the movable plate 2.2 of the operation plane 2 when the movable plate 2.2 is turned back;
when the device is used, the device is fixed on the peripheral ground of a pier column to be constructed, main reinforcements of the pier column are connected one by one, stirrups are sleeved downwards from the top end of the main reinforcements of the pier column in sequence to bind the main reinforcements of the pier column, then a movable plate 2.2 of an operation plane 2 is turned over, the distance between the operation plane 2 and the main reinforcements of the pier column is increased, and a pouring template is convenient to hoist; hoisting and fixing the pouring template from the upper part, then turning back the movable plate 2.2 for pouring, and standing on the operation plane 2 by a constructor for operation when pouring concrete; after a section of pier stud is constructed, assembling another pier stud construction operation platform at the top end of the lower pier stud construction operation platform to perform construction of the next section of pier stud, wherein when a plurality of pier stud construction operation platforms are assembled, the pier stud construction operation platforms can be matched with a cage ladder for use;
through setting up and enclosing fender 3, avoid the workman to fall, protect constructor's safety.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (2)

1. The utility model provides a pier stud construction operation platform which characterized in that: comprises a main frame, an operation plane and a fence;
the operation plane comprises four operation planes, each operation plane comprises a fixed plate and a movable plate, the fixed plate is connected with the movable plate through a hinge, each operation plane is fixed on a top surface frame of the main frame, a support frame is fixed on the main frame below each operation plane, and the four operation planes surround to form a square shape;
and surrounding baffles are fixed around the main frame.
2. The pier construction operating platform of claim 1, wherein: the operation plane and the main frame are detachably fixed.
CN202021330246.2U 2020-07-08 2020-07-08 Pier stud construction operation platform Active CN213013950U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021330246.2U CN213013950U (en) 2020-07-08 2020-07-08 Pier stud construction operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021330246.2U CN213013950U (en) 2020-07-08 2020-07-08 Pier stud construction operation platform

Publications (1)

Publication Number Publication Date
CN213013950U true CN213013950U (en) 2021-04-20

Family

ID=75501109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021330246.2U Active CN213013950U (en) 2020-07-08 2020-07-08 Pier stud construction operation platform

Country Status (1)

Country Link
CN (1) CN213013950U (en)

Similar Documents

Publication Publication Date Title
CN113293694B (en) Turnover formwork frame structure for efficient pier body construction and construction process
CN206873307U (en) Movable type bridge justifies pier stud work high above the ground operating platform
CN211143305U (en) Steel structure building
CN214831957U (en) Assembled multi-high-rise steel column butt joint operation platform
CN207933894U (en) A kind of bridge double-limb Thin-Wall Piers pier stud reinforcing bar binding device
CN213013950U (en) Pier stud construction operation platform
CN206015531U (en) Quick assembled type ladder cage
CN212561215U (en) Back cage platform channel device
CN204626257U (en) A kind of bridge column construction operation platform
CN210151590U (en) Highway bridge cylindrical mold top operation platform
CN209523123U (en) A kind of working job platform
CN210658029U (en) Integral hoisting type steel bar construction platform
CN211815605U (en) Construction device for pile column type pier tie beam and capping beam
CN211947968U (en) Integral assembling type construction platform for high-altitude pier column construction
CN210977265U (en) Can have enough to meet need unitized lattice tower crane basis and go up people's device
CN211818054U (en) Fixing structure of safety protection device for cast-in-place part on periphery of assembly type shear wall
CN210263834U (en) Pier stud safety protection construction platform
CN217810514U (en) Pier inner supporting frame capable of being used for binding pier body steel bars and being used for turnover
CN202611250U (en) Concreting platform for concrete filled steel tube column
CN208792738U (en) A kind of upper and lower safety climbing ladder of bridge pier column binder pouring construction
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN220686833U (en) Protection device for small-sized hole of outer wall of climbing frame aluminum mould system
CN111188489A (en) External frame-free safety protection structure of fabricated building and construction method thereof
CN219118715U (en) Elevator well safety protection and operation platform integrated device
CN211621238U (en) Bridge pier stud turns over mould construction reinforcing bar operation safety protection cage

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant