Prior art keywords
steel
pipe pile
steel pipe
concrete
annular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020856681.2U
Other languages
Chinese (zh)
Inventor
田贵洪
杨勇
朱绍阳
李先兵
高飞
梅文超
葛宇桥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Luhang Building Engineering Co ltd
Original Assignee
Sichuan Luhang Building Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Luhang Building Engineering Co ltd filed Critical Sichuan Luhang Building Engineering Co ltd
Priority to CN202020856681.2U priority Critical patent/CN212983917U/en
Application granted granted Critical
Publication of CN212983917U publication Critical patent/CN212983917U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a steel-pipe pile foundation stress diffusion structure has following characteristics: the structure comprises an annular steel plate and a triangular stiffening steel plate which are welded at the bottom of the steel pipe pile, and the annular steel plate and the triangular stiffening steel plate are embedded into the concrete pile foundation together with the steel pipe pile. The utility model has the advantages of as follows: the utility model discloses an at steel pipe bottom welding annular steel sheet, increased the area of contact of steel pipe bottom and concrete, made the basic concrete change into by the shear state and used the pressurized to give first place to, make full use of the bearing capacity of concrete, improved the atress condition of steel-pipe pile and concrete. The steel pipe pile foundation stress diffusion structure can greatly reduce the embedding depth of the steel pipe in the concrete under the same load condition, saves resources, and is safe and reliable.

Description

Steel-pipe pile foundation stress diffusion structure
Technical Field
The utility model relates to a steel pipe and concrete combined pile foundation field, particularly stress diffusion structure in steel-pipe pile root embedding concrete.
Background
With the rapid development of the national traffic infrastructure construction, the construction of various cast-in-place structures on land or in water is completed by adopting temporary engineering measures such as large-diameter steel pipe pile supports, steel pipe pile platforms, steel pipe pile trestles and the like. The foundation treatment of the steel pipe pile, especially under the unfavorable conditions such as wading, is vital, often directly imbeds the steel pipe into the concrete and forms the combination pile foundation, receives to cut through the concrete and provides the support counter-force or the resistance to plucking of steel pipe pile, and this method often needs to imbed the steel pipe of great degree of depth in the concrete and just can satisfy the atress demand, and consequently, the material waste is great, and engineering cost is higher relatively, also does not do benefit to energy saving and consumption reduction.
SUMMERY OF THE UTILITY MODEL
Therefore, in order to solve the above insufficiency, the utility model provides a steel-pipe pile foundation stress diffusion structure here improves the atress condition of steel-pipe pile and concrete, reduces the material waste by a wide margin.
The utility model is realized in such a way, a steel pipe pile foundation stress diffusion structure is constructed, which is characterized in that; including welding in the annular steel sheet and the triangle-shaped steel sheet of putting more energy into of steel-pipe pile bottom, along with the steel-pipe pile together imbeds in the concrete pile foundation to at the concrete pile foundation top of newly pouring do the temporary fixation to the steel-pipe pile with shaped steel, remove the temporary fixation after waiting the concrete hardening.
The steel pipe pile foundation stress diffusion structure is characterized in that the steel pipe pile foundation stress diffusion structure comprises a steel pipe pile foundation and a steel pipe pile foundation; the annular steel plate is 12mm thick, and its outside diameter is 220mm bigger than the steel-pipe pile diameter, and the internal diameter is 100mm less than the steel-pipe pile diameter, and annular steel plate is perpendicular to the steel-pipe pile, and its center coincidence is in the steel-pipe pile axis, and annular steel plate and steel-pipe pile bottom full weld are connected.
The steel pipe pile foundation stress diffusion structure is characterized in that the steel pipe pile foundation stress diffusion structure comprises a steel pipe pile foundation and a steel pipe pile foundation; the triangle-shaped steel sheet of putting more energy into is thick 20mm, and the steel sheet is isosceles right triangle-shaped, and right angle length of a side 100mm, the triangle-shaped steel sheet of putting more energy into is arranged 4 according to every annular steel sheet and evenly arranges in the symmetry all around the steel-pipe pile, and the triangle-shaped steel sheet of putting more energy into is perpendicular welding respectively on annular steel sheet and steel-pipe pile.
The steel pipe pile foundation stress diffusion structure is characterized in that the steel pipe pile foundation stress diffusion structure comprises a steel pipe pile foundation and a steel pipe pile foundation; the length of the steel pipe pile is 2-3 m, and the pile top is exposed out of the ground or the water surface after the steel pipe pile is embedded into concrete, so that the steel pipe pile is convenient to heighten and lengthen.
The steel pipe pile foundation stress diffusion structure is characterized in that the steel pipe pile foundation stress diffusion structure comprises a steel pipe pile foundation and a steel pipe pile foundation; after the steel pipe pile is embedded into newly poured concrete, the steel pipe pile is temporarily fixed at the top of a concrete pile foundation by using profile steel, and the temporary fixation is removed after the concrete is hardened.
The utility model has the advantages of as follows: the utility model discloses an at steel pipe bottom welding annular steel sheet, increased the area of contact of steel pipe bottom and concrete, made the basic concrete change into by the shear state and used the pressurized to give first place to, make full use of the bearing capacity of concrete, improved the atress condition of steel-pipe pile and concrete. The steel pipe pile foundation stress diffusion structure can greatly reduce the embedding depth of the steel pipe in the concrete under the same load condition, saves resources, and is safe and reliable.
Drawings
FIG. 1 is a schematic diagram of the implementation process of the present invention;
FIG. 2 is a schematic diagram of the construction of the present invention;
FIG. 3 is a schematic sectional view of the structure of the present invention;
fig. 4 is a schematic view of the annular steel plate of the present invention.
Wherein: annular steel sheet 1, triangle-shaped steel sheet 2 of putting more energy into, steel-pipe pile 3, interim fixed shaped steel 4.
Detailed Description
The present invention will be described in detail with reference to fig. 1 to 4, and the technical solutions in the embodiments of the present invention will be clearly and completely described, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example (c); the utility model provides a steel pipe pile foundation stress diffusion structure through improvement, which improves the stress condition of the steel pipe pile and the concrete and greatly reduces the material waste; as shown in fig. 1 to 4, it can be implemented as follows;
the utility model discloses a weld in annular steel sheet 1 and triangle-shaped stiffening steel sheet 2 of 3 bottoms of steel-pipe pile, utilize hoisting machinery before pile foundation concrete initial set in the 3 embedding pile foundation concrete of steel-pipe pile that will install steel-pipe pile foundation stress diffusion structure, and make interim fixing at the concrete pile foundation top of newly pouring with shaped steel 4 to steel-pipe pile 3, remove interim fixing after treating the concrete hardening, can weld behind the concrete strength reaches more than 10MPa and lengthen steel-pipe pile to the height (length) that needs.
The utility model has the advantages of as follows: the utility model discloses an at steel pipe bottom welding annular steel sheet, increased the area of contact of steel pipe bottom and concrete, made the basic concrete change into by the shear state and used the pressurized to give first place to, make full use of the bearing capacity of concrete, improved the atress condition of steel-pipe pile and concrete. The steel pipe pile foundation stress diffusion structure can greatly reduce the embedding depth of the steel pipe in the concrete under the same load condition, saves resources, and is safe and reliable.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (2)

1. A steel pipe pile foundation stress diffusion structure is characterized in that;
the steel pipe pile foundation structure comprises an annular steel plate (1) and a triangular stiffening steel plate (2) which are welded at the bottom of a steel pipe pile (3), the annular steel plate and the triangular stiffening steel plate are embedded into pile foundation concrete along with the steel pipe pile (3), and the steel pipe pile (3) is temporarily fixed by section steel (4) at the top of a concrete pile foundation;
the annular steel plate (1) is 12mm thick, the outer diameter of the annular steel plate is 220mm larger than the diameter of the steel pipe pile, the inner diameter of the annular steel plate is 100mm smaller than the diameter of the steel pipe pile, the annular steel plate (1) is perpendicular to the steel pipe pile (3), the center of the annular steel plate is coincided with the axis of the steel pipe pile (3), and the annular steel plate (1) is in full-weld connection with the bottom end of the steel pipe pile (;
triangle-shaped steel sheet (2) of putting more energy into is 20mm thick, and the steel sheet is isosceles right triangle-shaped, and right angle length of side 100mm, triangle-shaped steel sheet (2) of putting more energy into are arranged 4 according to every annular steel sheet (1) and are evenly arranged at steel-pipe pile (3) symmetry all around, and triangle-shaped steel sheet (2) of putting more energy into is perpendicularly welded respectively on annular steel sheet (1) and steel-pipe pile (3).
2. The steel pipe pile foundation stress diffusion structure according to claim 1, characterized in that; the length of the steel pipe pile (3) is 2-3 m, and the pile top is exposed out of the ground or the water surface after the steel pipe pile is embedded into concrete, so that heightening and lengthening are facilitated.
CN202020856681.2U 2020-05-21 2020-05-21 Steel-pipe pile foundation stress diffusion structure Active CN212983917U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020856681.2U CN212983917U (en) 2020-05-21 2020-05-21 Steel-pipe pile foundation stress diffusion structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020856681.2U CN212983917U (en) 2020-05-21 2020-05-21 Steel-pipe pile foundation stress diffusion structure

Publications (1)

Publication Number Publication Date
CN212983917U true CN212983917U (en) 2021-04-16

Family

ID=75420837

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020856681.2U Active CN212983917U (en) 2020-05-21 2020-05-21 Steel-pipe pile foundation stress diffusion structure

Country Status (1)

Country Link
CN (1) CN212983917U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319320A (en) * 2021-12-29 2022-04-12 中交二航局第二工程有限公司 Temporary pier steel pipe pile and floating installation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319320A (en) * 2021-12-29 2022-04-12 中交二航局第二工程有限公司 Temporary pier steel pipe pile and floating installation method thereof

Similar Documents

Publication Publication Date Title
CN104790424B (en) The hardened system on generation power foundation of wind power ring basis and reinforcement means thereof
WO2017049809A1 (en) Cement-soil mixing pile having stiffening core pile with variable diameter
CN212983917U (en) Steel-pipe pile foundation stress diffusion structure
CN206052767U (en) The construction elevator basis that can be used in turn
CN209703838U (en) Steel bar connecting structure between reinforcing bar connector and precast concrete
CN205188999U (en) Vertical supporting system of reverse construction method
CN108277817B (en) Construction method of high-pile bearing platform tower crane foundation reinforcing structure
CN109667388A (en) Steel bar connecting structure between reinforcing bar connector and precast concrete
CN213773450U (en) Tower crane retaining wall construction equipment
CN211229633U (en) Anti-punching pre-buried structure for large-aperture static crushing of reinforced concrete member
CN211713955U (en) Slip casting type steel pipe screw pile
CN207314348U (en) A kind of fixed structure of flare template
CN206457827U (en) A kind of shaped steel coupling beam structure detachably reclaimed
CN210002365U (en) Reinforcing and anchoring structure of square section steel liners
CN206736950U (en) A kind of special-shaped anchor ear applied to glass steel formwork
CN206299039U (en) The square concrete hollow column of centrifugal forming prestressing force
CN205777810U (en) A kind of steel tower being applicable to high slope
CN211006690U (en) Underground foundation pit supporting reinforcement structure based on energy station
CN218541008U (en) Novel structure is handled to superimposed sheet makeup board seam
CN214219717U (en) Bridge pile foundation and bearing platform connecting structure
CN215053865U (en) Prefabricated assembled concrete member convenient to installation
CN211523186U (en) Prestressed concrete hollow pipe pile
CN220550583U (en) Bridge tubular pile convenient to hoist and mount
CN214143792U (en) Foundation ring structure
CN214616875U (en) Fan tower section of thick bamboo and basic strenghthened type connection structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant