CN212947627U - Intelligent working platform for overhauling and maintaining valve piece - Google Patents

Intelligent working platform for overhauling and maintaining valve piece Download PDF

Info

Publication number
CN212947627U
CN212947627U CN202021123418.9U CN202021123418U CN212947627U CN 212947627 U CN212947627 U CN 212947627U CN 202021123418 U CN202021123418 U CN 202021123418U CN 212947627 U CN212947627 U CN 212947627U
Authority
CN
China
Prior art keywords
fixedly connected
platform
embedded
installation
mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021123418.9U
Other languages
Chinese (zh)
Inventor
王雪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui O'nei Rui St Electromechanical Technology Co ltd
Original Assignee
Anhui O'nei Rui St Electromechanical Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui O'nei Rui St Electromechanical Technology Co ltd filed Critical Anhui O'nei Rui St Electromechanical Technology Co ltd
Priority to CN202021123418.9U priority Critical patent/CN212947627U/en
Application granted granted Critical
Publication of CN212947627U publication Critical patent/CN212947627U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model discloses an intelligent working platform for valve maintenance, which comprises an installation seat platform, wherein the top of the installation seat platform is provided with an installation groove, the bottom of the installation groove is provided with an installation opening, the installation opening is internally and fixedly connected with an assembly platform, and the assembly platform is provided with a plurality of installation threaded holes; the bottom of the assembly table is fixedly connected with a central embedded mounting piece, the central embedded mounting piece comprises a plurality of steel rods fixedly connected to the assembly table, a plurality of embedded steel plates are fixedly connected to the steel rods, and the steel rods penetrate through the embedded steel plates; the bottom of the steel rod is fixedly connected with the top of the embedded steel plate; the pre-buried installed part of side that the interval set up about a plurality of is connected with fixedly on the preceding, the back groove limit of mounting groove. Adopt above-mentioned device component design to realize providing a work platform that can the stable support, ensure that the valve can maintain on comparatively stable basic platform.

Description

Intelligent working platform for overhauling and maintaining valve piece
Technical Field
The utility model relates to a coal mine equipment maintains the device field, what especially relate to is an intelligent work platform is maintained in valve member maintenance.
Background
In the coal mining process, coal mine equipment is required to be used, hydraulic control equipment is mostly adopted on the coal mine equipment, so that the valve is a core component of the hydraulic control equipment and is mostly a large-scale valve, in the coal mining process, particularly under a mine, once the valve is damaged, immediate maintenance is required, and in the maintenance process, an operator is required to maintain the valve.
In the prior art, when the valve is maintained, the large valve is placed on the support frame by designing the support frame, however, in the coal mining process, the earth surface is mined, the soil is soft, and the support frame disclosed in the prior art cannot realize stable support.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem that an intelligent work platform is maintained in valve member maintenance is provided.
The utility model discloses a solve above-mentioned technical problem through following technical scheme:
an intelligent working platform for valve member overhaul and maintenance comprises an installation base platform, wherein the top of the installation base platform is provided with an installation groove, the bottom of the installation groove is provided with an installation opening, an assembly platform is fixedly connected in the installation opening, and the assembly platform is provided with a plurality of installation threaded holes;
the bottom of the assembly table is fixedly connected with a central embedded mounting piece;
the central embedded mounting part comprises a plurality of steel rods fixedly connected to the assembly table, a plurality of embedded steel plates are fixedly connected to the steel rods, and the steel rods penetrate through the embedded steel plates;
the bottom of the steel rod is fixedly connected to the top of the embedded steel plate;
the side embedded mounting pieces are fixedly connected to the front groove edge and the rear groove edge of the mounting groove and are arranged at left and right intervals.
Preferably, the transverse cross-sectional shape of the mounting opening is rectangular;
the side wall of the assembling table is welded on the opening part of the mounting opening.
Preferably, the front and rear groove sides of the mounting groove are fixedly connected with two side embedded mounting pieces arranged at left and right intervals.
Preferably, the side embedded mounting piece comprises a traction rod connected to the mounting base platform in a sliding manner, and the bottom of the traction rod is fixedly connected with an embedded part;
and the top of the traction rod is fixedly connected with a limiting steel plate.
Preferably, the embedding part comprises a top disc fixedly connected with the traction rod;
the bottom of the top plate is fixedly connected with a plurality of steel bar rods.
Preferably, the bottom of a plurality of the reinforcing steel bars is fixedly connected with a chassis.
Preferably, the traction rod penetrates through the top disc downwards;
the traction rod is welded at the center of the top of the chassis.
Preferably, the limiting steel plate is connected to the mounting base through a bolt and a thread.
Compared with the prior art, the utility model has the following advantages:
the utility model discloses an intelligent working platform for valve member maintenance, which comprises an installation seat platform, wherein the top of the installation seat platform is provided with an installation groove, the bottom of the installation groove is provided with an installation opening, the installation opening is internally and fixedly connected with an assembly platform, and the assembly platform is provided with a plurality of installation threaded holes; the bottom of the assembly table is fixedly connected with a central embedded installation part, the central embedded installation part comprises a plurality of steel rods fixedly connected to the assembly table, a plurality of embedded steel plates are fixedly connected to the steel rods, and the steel rods penetrate through the embedded steel plates; the bottom of the steel rod is fixedly connected to the top of the embedded steel plate; the side embedded mounting pieces are fixedly connected to the front groove edge and the rear groove edge of the mounting groove and are arranged at left and right intervals.
Adopt above-mentioned device component design to realize providing a work platform that can the stable support, ensure that the valve can maintain on comparatively stable basic platform.
Drawings
Fig. 1 is a schematic overall structure diagram of an embodiment of the present invention;
fig. 2 is a schematic structural diagram of another view angle in fig. 1 according to the embodiment of the present invention;
fig. 3 is a front view of the embodiment of the present invention shown in fig. 1;
fig. 4 is a top view of the embodiment of the present invention in fig. 1;
fig. 5 is a schematic structural diagram in the practice of the present invention.
Detailed Description
The embodiments of the present invention will be described in detail below, and the present embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation manner and a specific operation process are given, but the scope of the present invention is not limited to the following embodiments.
As shown in fig. 1-5, an intelligent work platform for maintenance and repair of valve members comprises a mounting base platform 1, a mounting groove 11 is formed in the top of the mounting base platform 1, a mounting opening (the transverse section of the mounting opening is rectangular) is formed in the bottom of the mounting groove 11, an assembly table 2 is fixedly connected in the mounting opening (the side wall of the assembly table 2 is welded in the opening of the mounting opening), and a plurality of mounting threaded holes 21 are formed in the assembly table 2. The positioning fixture (in the maintenance process, the valve is positioned through the fixture, the fixture is positioned on the assembly table 2) for repairing the valve is arranged on the assembly table 2 through the installation threaded hole.
In order to increase the working stability of the working platform, a central embedded mounting piece 3 is fixedly connected to the bottom of the assembling table 2; the central embedded mounting part 3 comprises a plurality of steel rods 32 fixedly connected to the assembly table 2, a plurality of embedded steel plates 31 are fixedly connected to the steel rods 32, and the steel rods 32 penetrate through the embedded steel plates 31; the bottom of the steel rod 32 is fixedly connected to the top of the buried steel plate 31.
The center embedded part 3 is stably embedded in the ground after cement is poured.
The central embedded part 3 with the structural design can be stably embedded in the ground, and the stability of the installation and assembly table 2 of the lifting maintenance equipment is improved.
The pre-buried installed part of side that the interval set up about fixedly connected with a plurality of in the front of mounting groove 11, back trough is limit, further improves stability through the pre-buried installed part of side, specifically, the pre-buried installed part of side that two left and right intervals of fixedly connected with set up in the front of mounting groove 11, back trough is limit.
The concrete structure of the side embedded mounting part is as follows:
the side edge embedded mounting piece comprises a traction rod 45 which is connected to the mounting base platform 1 in a sliding mode, and an embedded part is fixedly connected to the bottom of the traction rod 45; the top of the traction rod 45 is fixedly connected with a limiting steel plate 44. The embedding part comprises a top disc 42 fixedly connected with a traction rod 45; the bottom of the top plate 42 is fixedly connected with a plurality of steel bar rods 43. The bottom of a plurality of the reinforcing steel bar rods 43 is fixedly connected with a chassis 41. The traction rod 45 penetrates through the top disc 42 downwards; the traction rod 45 is welded to the top center portion of the bottom plate 41. The limiting steel plate 44 is connected to the mounting base 1 through bolts and threads.
When burying the pre-buried installed part 3 in center underground, bury the pre-buried installed part of side underground downthehole underground, the pre-buried installed part of side of above-mentioned structural design realizes with work platform
Through the design of the device components, the front and back traction of the side embedded mounting piece mounting base 1 is maintained stably, and the mounting base 1 is kept in a horizontal state.
Adopt above-mentioned device part design to realize providing one kind can be comparatively stable, steady maintenance platform, above-mentioned device part design realizes placing the large-scale valve that needs detection, maintenance on comparatively stable platform and detects, has improved the maintenance efficiency of valve.
The above description is only exemplary of the present invention and should not be taken as limiting the scope of the present invention, as any modifications, equivalents, improvements and the like made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.

Claims (8)

1. An intelligent working platform for overhauling and maintaining a valve piece is characterized by comprising an installation base platform, wherein the top of the installation base platform is provided with an installation groove, the bottom of the installation groove is provided with an installation opening, an assembly platform is fixedly connected in the installation opening, and the assembly platform is provided with a plurality of installation threaded holes;
the bottom of the assembly table is fixedly connected with a central embedded mounting piece; the central embedded mounting part comprises a plurality of steel rods fixedly connected to the assembly table, a plurality of embedded steel plates are fixedly connected to the steel rods, and the steel rods penetrate through the embedded steel plates;
the bottom of the steel rod is fixedly connected to the top of the embedded steel plate;
the side embedded mounting pieces are fixedly connected to the front groove edge and the rear groove edge of the mounting groove and are arranged at left and right intervals.
2. The valve service maintenance intelligent work platform of claim 1, wherein the transverse cross-sectional shape of the mounting port is rectangular;
the side wall of the assembling table is welded on the opening part of the mounting opening.
3. The intelligent working platform for overhauling and maintaining the valve piece as claimed in claim 2, wherein two side embedded installation pieces are fixedly connected to the front and rear groove sides of the installation groove at intervals.
4. The valve overhaul and maintenance intelligent working platform according to claim 3, wherein the side embedded mounting piece comprises a traction rod which is slidably connected to the mounting base platform, and an embedded part is fixedly connected to the bottom of the traction rod;
and the top of the traction rod is fixedly connected with a limiting steel plate.
5. The valve service maintenance intelligent work platform of claim 4, wherein the embedded portion comprises a top disk fixedly connected to the draw bar;
the bottom of the top plate is fixedly connected with a plurality of steel bar rods.
6. The valve service maintenance intelligent work platform of claim 5, wherein the bottom of a plurality of the reinforcement bars is fixedly connected with a chassis.
7. The valve service maintenance intelligent work platform of claim 6, wherein said tie rods extend downwardly through said top disk;
the traction rod is welded at the center of the top of the chassis.
8. The valve service maintenance intelligent work platform of claim 7, wherein the limiting steel plate is screwed on the mounting seat platform through bolts.
CN202021123418.9U 2020-06-17 2020-06-17 Intelligent working platform for overhauling and maintaining valve piece Active CN212947627U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021123418.9U CN212947627U (en) 2020-06-17 2020-06-17 Intelligent working platform for overhauling and maintaining valve piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021123418.9U CN212947627U (en) 2020-06-17 2020-06-17 Intelligent working platform for overhauling and maintaining valve piece

Publications (1)

Publication Number Publication Date
CN212947627U true CN212947627U (en) 2021-04-13

Family

ID=75386692

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021123418.9U Active CN212947627U (en) 2020-06-17 2020-06-17 Intelligent working platform for overhauling and maintaining valve piece

Country Status (1)

Country Link
CN (1) CN212947627U (en)

Similar Documents

Publication Publication Date Title
CN108166506B (en) Foundation pit supporting structure
CN210395435U (en) Collapse-proof supporting device for open excavation method construction of urban underground comprehensive pipe gallery
CN212947627U (en) Intelligent working platform for overhauling and maintaining valve piece
CN210684727U (en) Construction safety supporting construction
CN212534125U (en) Deep foundation pit waist rail construction design template system
CN101723240B (en) Special fixture for hoisting rectangular section steel column and hoisting method by using same
CN205222562U (en) Crane quick travel installation device with lift platform
CN203361170U (en) Supporting upright column pile for building foundation pit support
CN210239674U (en) Dismantled and assembled excavation rack
CN112482564A (en) Steel rib column foundation bolt embedding structure
CN217174890U (en) Tool for positioning street lamp basic embedded part
CN202401800U (en) A lower bearing frame of a three-dimensional parking place
CN205399270U (en) A base for monitoring rod and traffic signal lamp fixed mounting
CN218757021U (en) Steel bridge construction supports temporarily with assembled basic base
CN217272329U (en) Push pipe construction structures convenient to installation
CN204919646U (en) Multi -functional hydraulic pressure quartering hammer
CN201671040U (en) Ramming equipment
CN204282933U (en) A kind of communication tower
CN219487979U (en) Novel section roof beam transportation support frame
CN215215367U (en) Winch ground anchor die carrier for coal mine
CN212271231U (en) Column base connecting piece
CN216711349U (en) Hoisting beam for penetrating steel grating floor
CN211226110U (en) Special hoisting tool of cantilever type
CN218060383U (en) Foundation block with hoisting hole
CN204212510U (en) 110KV line project improvement column foot plated construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant