CN212888230U - Combined structure for preventing prefabricated foam board from floating - Google Patents

Combined structure for preventing prefabricated foam board from floating Download PDF

Info

Publication number
CN212888230U
CN212888230U CN202022092949.2U CN202022092949U CN212888230U CN 212888230 U CN212888230 U CN 212888230U CN 202022092949 U CN202022092949 U CN 202022092949U CN 212888230 U CN212888230 U CN 212888230U
Authority
CN
China
Prior art keywords
concrete cushion
cystosepiment
upper portion
fixing device
control block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022092949.2U
Other languages
Chinese (zh)
Inventor
郭振翔
杨蕾
胡晨晞
孙清臣
李敏仪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN202022092949.2U priority Critical patent/CN212888230U/en
Application granted granted Critical
Publication of CN212888230U publication Critical patent/CN212888230U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a composite structure for prefabricated cystosepiment is anti floats, including concrete slab elevation control block, upper portion concrete cushion, cystosepiment fixing device and the lower part concrete cushion that from top to bottom links together in proper order, concrete slab elevation control block, upper portion concrete cushion and lower part concrete cushion are the cube structure, all set up mutually perpendicular's vertical "U" shape groove and horizontal "U" shape groove at the top of upper portion concrete cushion and lower part concrete cushion, still set up mutually perpendicular's vertical semicircular groove and horizontal semicircular groove in the bottom of lower part concrete cushion. The utility model discloses a cystosepiment fixing device fixes the cystosepiment, effectively solves prefabricated cystosepiment's anti problem of floating, fixes a position two-way board reinforcing bar and one-way board reinforcing bar through vertical "U" shape groove and horizontal "U" shape groove on upper portion concrete cushion and the lower part concrete cushion simultaneously, avoids the reinforcing bar to shift.

Description

Combined structure for preventing prefabricated foam board from floating
Technical Field
The utility model relates to a composite structure for prefabricated cystosepiment is anti floats belongs to building engineering prefabricated component technical field.
Background
In the process of pouring the prefabricated foam board in a prefabricated component factory, the foam board is taken as a wallboard of a filling material, the foam board has a floating problem due to the fact that the density of the foam board is lower than that of cement paste, and the floating problem still exists although a fixing measure is adopted; and because the foam board shelters from, the cement of foam board back is not closely knit, and the vacant shell condition produces, seriously influences component quality, and there is not effective instrument or device yet at present to fix the foam board.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a simple structure, installation are swift, fixed firm be used for anti integrated configuration who floats of prefabricated cystosepiment, and the device can effectively solve the anti problem of floating of prefabricated cystosepiment.
In order to achieve the above purpose, the utility model adopts the following technical scheme: the utility model provides a composite structure for prefabricated cystosepiment is anti floats, includes concrete slab elevation control block, upper portion concrete cushion, cystosepiment fixing device and the lower part concrete cushion that from top to bottom links together in proper order, concrete slab elevation control block, upper portion concrete cushion and lower part concrete cushion are the cube structure, all set up mutually perpendicular's vertical "U" shape groove and horizontal "U" shape groove at the top of upper portion concrete cushion and lower part concrete cushion, still set up mutually perpendicular's vertical semicircle groove and horizontal semicircle groove in the bottom of lower part concrete cushion.
Further, cystosepiment fixing device includes right-angle shape curb plate and roof and the bottom plate of fixed connection respectively at right-angle shape curb plate top and bottom, all has the board that turns over through hinge hinged joint on two right-angle edges of roof and bottom plate, has seted up the through-hole on turning over the board, and links together after turning over the board between roof and the bottom plate and inserting the through-hole through the location stick.
Further, concrete slab elevation control block, upper portion concrete cushion, cystosepiment fixing device and lower part concrete cushion pass through the mortise-tenon joint mode and link together.
Furthermore, the top equipartition of upper portion concrete cushion, cystosepiment fixing device and lower part concrete cushion has the tenon, all is provided with in concrete slab elevation control block, upper portion concrete cushion and cystosepiment fixing device's bottom with tenon complex mortise.
Furthermore, the depth of the longitudinal U-shaped groove is 2 times of that of the transverse U-shaped groove.
Since the technical scheme is used, the utility model discloses an advantage has below: the utility model discloses a cystosepiment fixing device fixes the cystosepiment, effectively solves prefabricated cystosepiment's anti problem of floating, fixes a position two-way board reinforcing bar and one-way board reinforcing bar through vertical "U" shape groove and horizontal "U" shape groove on upper portion concrete cushion and the lower part concrete cushion simultaneously, avoids the reinforcing bar to shift. Additionally, the utility model discloses with concrete slab elevation control block, upper portion concrete cushion, cystosepiment fixing device and four parts of lower part concrete cushion superpose back together, its whole height is floor thickness promptly, uses the top surface of concrete slab elevation control block to control floor thickness as the benchmark during construction, has set up vertical semicircular groove and horizontal semicircular groove in the bottom of lower part concrete cushion moreover, like this alright use the radius size in two semicircular grooves as protective layer thickness standard according to the engineering condition. Furthermore, the utility model discloses a four parts link together through tenon fourth of twelve earthly branches mode, and the equipment is convenient, and is fixed firm.
Drawings
Fig. 1 is an exploded view of the structure of the present invention;
fig. 2 is an assembly diagram of the structure diagram of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The embodiment of the utility model provides a: please refer to fig. 1 and 2, a combined structure for precast foam board anti-floating, including concrete slab elevation control block 1, upper portion concrete cushion 2, foam board fixing device 3 and lower part concrete cushion 4 that from top to bottom link together in proper order, concrete slab elevation control block 1, upper portion concrete cushion 2 and lower part concrete cushion 4 are the cube structure, all offer mutually perpendicular's vertical "U" shape groove 5 and horizontal "U" shape groove 6 at the top of upper portion concrete cushion 2 and lower part concrete cushion 4, still offer mutually perpendicular's vertical semicircular groove 7 and horizontal semicircular groove 8 in the bottom of lower part concrete cushion 4. Cystosepiment fixing device 3 includes right-angle shape curb plate 10 and respectively fixed connection at roof 11 and bottom plate 12 of right-angle shape curb plate 10 top and bottom, all has a board 13 that turns over through hinge 15 hinged joint on two right-angle edges of roof 11 and bottom plate 12, has seted up the through-hole on turning over the board 13, and links together after turning over board 13 between roof 11 and the bottom plate 12 inserts the through-hole through positioning rod 14. Concrete slab elevation control block 1, upper portion concrete cushion 2, cystosepiment fixing device 3 and lower part concrete cushion 4 link together through the tenon fourth of the twelve earthly branches mode. The top equipartition of upper portion concrete cushion 2, cystosepiment fixing device 3 and lower part concrete cushion 4 has tenon 9, all is provided with in concrete slab elevation control block 1, upper portion concrete cushion 2 and cystosepiment fixing device 3's bottom with 9 complex mortise holes of tenon. The depth of the longitudinal U-shaped groove 5 is 2 times of that of the transverse U-shaped groove 6.
When the concrete slab elevation control block is used, the concrete slab elevation control block 1, the upper concrete cushion block 2, the foam slab fixing device 3 and the lower concrete cushion block 4 are firstly combined together, and then the foam slab fixing device 3 is adopted to fix the corner of the foam slab. When fixing the cystosepiment, insert between cystosepiment fixing device 3's roof 11 and bottom plate 12 with the corner of cystosepiment earlier, then open the board 13 that turns over between roof 11 and bottom plate 12 to turn over on board 13, cystosepiment and the bottom plate 12 on inserting roof 11 in proper order with location stick 14 and turn over the board 13, like this alright through turning over board 13 from top to bottom increase with the area of contact of cystosepiment, improve fixed effect, prevent effectively that the cystosepiment from floating. After the foam board is fixed, concrete can be poured. Before concrete is poured, the two-way plate reinforcing steel bars and the one-way plate reinforcing steel bars are positioned through the longitudinal U-shaped grooves 5 and the transverse U-shaped grooves 6 on the upper concrete cushion block 2 and the lower concrete cushion block 4, and the reinforcing steel bars are prevented from shifting. When concrete is poured, the thickness of the floor slab is controlled by taking the top surface of the concrete slab elevation control block 1 as a reference; because the bottom of the lower concrete cushion block 4 is provided with the longitudinal semicircular groove 7 and the transverse semicircular groove 8, the radius of the two semicircular grooves can be used as the thickness standard of the protective layer. To sum up, the utility model discloses a cystosepiment fixing device 3 fixes the cystosepiment, effectively solves prefabricated cystosepiment's anti problem of floating, fixes a position two-way board reinforcing bar and one-way board reinforcing bar through vertical "U" shape groove 5 and horizontal "U" shape groove 6 on upper portion concrete cushion 2 and lower part concrete cushion 4 simultaneously, avoids the reinforcing bar to shift. Additionally, the utility model discloses with concrete slab elevation control block 1, upper portion concrete cushion 2, the back is in the same place in the superposition of four parts of cystosepiment fixing device 3 and lower part concrete cushion 4, its whole height is floor thickness promptly, use concrete slab elevation control block 1's top surface to control floor thickness as the benchmark during construction, set up vertical semicircular groove 7 and horizontal semicircular groove 8 in the bottom of lower part concrete cushion 4 in addition, like this alright regard as protective layer thickness standard with the radius size in two semicircular grooves according to the engineering condition. Furthermore, the utility model discloses a four parts link together through tenon fourth of twelve earthly branches mode, and the equipment is convenient, and is fixed firm.

Claims (5)

1. The utility model provides a be used for anti fixed modular structure that floats of prefabricated cystosepiment which characterized in that: including concrete slab elevation control block (1), upper portion concrete cushion (2), cystosepiment fixing device (3) and lower part concrete cushion (4) that from top to bottom link together in proper order, concrete slab elevation control block (1), upper portion concrete cushion (2) and lower part concrete cushion (4) are the cube structure, all offer vertical "U" shape groove (5) and horizontal "U" shape groove (6) of mutually perpendicular at the top of upper portion concrete cushion (2) and lower part concrete cushion (4), still offer vertical semicircular groove (7) and horizontal semicircular groove (8) of mutually perpendicular in the bottom of lower part concrete cushion (4).
2. The modular structure for the anti-floating fixation of prefabricated foam panels according to claim 1, characterized in that: cystosepiment fixing device (3) include right angle shape curb plate (10) and respectively fixed connection roof (11) and bottom plate (12) at right angle shape curb plate (10) top and bottom, all have through hinge (15) hinged joint to turn over board (13) on two right angle edges of roof (11) and bottom plate (12), have seted up the through-hole on turning over board (13), and link together after turning over board (13) between roof (11) and bottom plate (12) insert the through-hole through location stick (14).
3. The modular structure for the anti-floating fixation of prefabricated foam panels according to claim 1, characterized in that: concrete slab elevation control block (1), upper portion concrete cushion (2), cystosepiment fixing device (3) and lower part concrete cushion (4) link together through the tenon fourth of the twelve earthly branches mode.
4. A modular structure for the anti-floating fixation of prefabricated foam panels as claimed in claim 3, characterised in that: the top equipartition of upper portion concrete cushion (2), cystosepiment fixing device (3) and lower part concrete cushion (4) has tenon (9), all is provided with in the bottom of concrete slab elevation control block (1), upper portion concrete cushion (2) and cystosepiment fixing device (3) with tenon (9) complex mortise.
5. The modular structure for the anti-floating fixation of prefabricated foam panels according to claim 1, characterized in that: the depth of the longitudinal U-shaped groove (5) is 2 times of that of the transverse U-shaped groove (6).
CN202022092949.2U 2020-09-22 2020-09-22 Combined structure for preventing prefabricated foam board from floating Expired - Fee Related CN212888230U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022092949.2U CN212888230U (en) 2020-09-22 2020-09-22 Combined structure for preventing prefabricated foam board from floating

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022092949.2U CN212888230U (en) 2020-09-22 2020-09-22 Combined structure for preventing prefabricated foam board from floating

Publications (1)

Publication Number Publication Date
CN212888230U true CN212888230U (en) 2021-04-06

Family

ID=75258419

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022092949.2U Expired - Fee Related CN212888230U (en) 2020-09-22 2020-09-22 Combined structure for preventing prefabricated foam board from floating

Country Status (1)

Country Link
CN (1) CN212888230U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112078003A (en) * 2020-09-22 2020-12-15 中国建筑第四工程局有限公司 Combined fixing device for preventing prefabricated foam board from floating

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112078003A (en) * 2020-09-22 2020-12-15 中国建筑第四工程局有限公司 Combined fixing device for preventing prefabricated foam board from floating

Similar Documents

Publication Publication Date Title
CN205663075U (en) Precast concrete coincide floor
CN212888230U (en) Combined structure for preventing prefabricated foam board from floating
CN105756377B (en) A kind of swimming pool and its construction method
CN212670968U (en) Composite floor and building
CN113027021A (en) Support-free prefabricated floor slab with bracket
CN208309388U (en) The underwater bearing platform construction structure integrally transferred
CN213062620U (en) Prefabricated foam concrete filled double-sided superposed peripheral retaining wall and retaining wall combination
CN103031897A (en) Fabrication method of heat insulating component
CN205840082U (en) A kind of BRT Lightweight core mould close rib composite floor structure
CN112078003A (en) Combined fixing device for preventing prefabricated foam board from floating
CN210798011U (en) Fireproof floor
CN210597796U (en) Local superimposed sheet connected node
CN210316150U (en) A dense rib with filling concrete deep beam board for scale pig farm built-up layer
CN109267482B (en) Construction method for broken stone bridge floor of gallery bridge
CN106638956A (en) Concrete wallboard and ribbed slab dry type connection node
CN208088625U (en) Large-span concrete bucket shape grid shell roof structure
CN211923252U (en) Architectural design roof waterproof construction
CN217268077U (en) Connecting piece for connecting main body and chassis of toilet and toilet
CN216007553U (en) Water-stopping cushion block for reinforced concrete floor
CN210712900U (en) Soft soil auxiliary bearing platform structure
CN214301864U (en) Sump pit and post-cast strip collision node
CN212613735U (en) Non-dismantling formwork for caisson cement cover plate
CN107740525A (en) A kind of composite floor structure
CN220225866U (en) Full-light dense-rib sandwich roof board with gutter
CN212452768U (en) Post-cast strip protection architecture is backfilled in advance to underground outdoor side

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210406

Termination date: 20210922