CN212742621U - Unloading type pile plate retaining wall - Google Patents
Unloading type pile plate retaining wall Download PDFInfo
- Publication number
- CN212742621U CN212742621U CN202021270799.3U CN202021270799U CN212742621U CN 212742621 U CN212742621 U CN 212742621U CN 202021270799 U CN202021270799 U CN 202021270799U CN 212742621 U CN212742621 U CN 212742621U
- Authority
- CN
- China
- Prior art keywords
- retaining
- pile
- plate
- unloading
- platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Retaining Walls (AREA)
Abstract
The utility model relates to an off-load formula pile sheet barricade belongs to the technical field of retaining structure, including retaining pile, connect the retaining plate between two adjacent retaining piles and set firmly the off-load platform behind the retaining pile. The unloading platform is arranged to reduce the stress of the retaining pile, so that the section size of the retaining pile can be reduced, and the construction cost is greatly reduced.
Description
Technical Field
The utility model belongs to the technical field of a fender structure, especially, relate to an off-load formula stake board barricade.
Background
In the process of mountain town construction, in order to reasonably utilize the site, mountains are often dug to fill gullies, so that a plurality of high slopes and deep foundation pits are formed. The supporting and retaining structure is a structure for preventing collapse or deformation instability of a rock body frame, and is one of important research subjects of geotechnical engineering.
In recent years, with the development of new technologies and new materials, retaining structures have been developed from retaining walls that have been balanced by gravity alone, and have been developed to new lightweight retaining technologies such as supporting, soil-reinforced composite structures, and anchoring technologies, for example, new types of retaining walls such as cantilever type, buttress type, anchor rod type, reinforced soil type, and anchor plate type, and new retaining structures such as slide piles, pile plate type walls, soil nailing walls, and prestressed anchor cables.
Pile sheet formula barricade has pile position as the representative of novel retaining structure and arranges advantages such as nimble, the construction is simple and convenient, the interference is few, has obtained extensive development and application in practice, but this kind of retaining structure adopts increase pile shaft cross-sectional dimension and improves the arrangement of reinforcement rate and ensures the retaining effect of friction pile often, and structural engineering volume is great, and the utilization ratio of material is not high, and engineering cost is very high.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an off-load formula stake board barricade, can reduce the soil pressure that retaining pile received to reduce retaining pile cross sectional dimension, practice thrift construction cost.
The above object of the present invention can be achieved by the following technical solutions:
the unloading type pile-plate retaining wall comprises retaining piles which are uniformly arranged at intervals, wherein each retaining pile comprises an embedded section below a base and a loaded section above the base, and an unloading platform is further arranged on the soil facing surface of the loaded section.
By adopting the technical scheme, the unloading platform is arranged on the back side of the retaining pile and is rigidly connected with the retaining pile, the rock-soil pressure borne by the retaining pile below the unloading platform is reduced due to the curtain action of the unloading platform, and meanwhile, the filler load on the unloading platform provides a reverse bending moment Mk for the retaining pile, so that a part of overturning bending moment Mq generated by the soil pressure acting on the retaining pile is balanced.
Due to the arrangement of the unloading platform, the stress state of the structure is changed, the maximum bending moment and the shearing force of the retaining pile are reduced, and the force distribution in the structure is more balanced and reasonable; meanwhile, the deformation of the structure is limited, so that the deformation of the wall body is obviously reduced.
The present invention may be further configured in a preferred embodiment as: the unloading platform comprises a platform plate, and the platform plate is fixed on the soil facing surface of the loaded section of the retaining pile.
Through adopting above-mentioned technical scheme, the off-load platform bears the soil gravity of landing slab top through the landing slab, makes the unable below that passes to of the soil gravity of landing slab top, reduces the soil pressure that retaining pile received.
The present invention may be further configured in a preferred embodiment as: and the retaining pile is fixedly provided with a bracket, and the platform plate is fixedly arranged on the bracket.
Through adopting above-mentioned technical scheme, the landing slab passes through the bracket to be connected simple to operate with retaining pile.
The present invention may be further configured in a preferred embodiment as: and a retaining plate is connected between every two adjacent retaining piles at the load-bearing section.
Through adopting above-mentioned technical scheme, through the closed barricade structure that the fender apron formed, make the ground at retaining wall rear can not the landing.
The present invention may be further configured in a preferred embodiment as: the soil blocking plate is a precast concrete plate or a cast-in-place concrete plate.
Through adopting above-mentioned technical scheme, keep off the native board and be concrete slab, structural strength is high.
The present invention may be further configured in a preferred embodiment as: and a crown beam is arranged at the top of the retaining pile.
Through adopting above-mentioned technical scheme, the crown beam links a whole in city with many retaining piles, strengthens retaining pile wholeness and deformation harmony effect to prevent that foundation ditch top edge from producing and collapsing.
To sum up, the utility model discloses a following beneficial technological effect:
1. due to the arrangement of the unloading platform, the stress state of the structure is changed, the maximum bending moment and the shearing force of the retaining pile are reduced, the distribution of the internal force of the structure is more balanced and reasonable, the deformation of the structure is limited, and the deformation of the wall body is obviously reduced, so that the section size of the retaining pile is reduced, and the construction cost is saved;
2. a plurality of retaining piles are connected into a whole through the crown beam, so that the coordination effect of the integrity and the deformation of the retaining piles is enhanced, and the collapse of the top edge of the foundation pit is prevented;
3. through the closed retaining wall structure that the retaining plate formed, the ground behind the retaining wall can not the landing.
Drawings
Fig. 1 is a schematic view of the unloading pile-plate retaining wall structure.
Fig. 2 is a side view of the unloading pilaster retaining wall.
In the figure, 1, a retaining pile; 11. a loaded section; 12. a fixing section; 2. an unloading platform; 21. a platform plate; 22. a bracket; 3. a soil guard plate; 4. a crown beam; 5. mounting on a wall; 6. and (5) lowering the wall.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1 and 2, for the utility model discloses an off-load formula pile sheet barricade can be used in the system of strutting such as foundation ditch, bank protection to the foundation ditch barricade is exemplified, and off-load formula pile sheet barricade includes retaining pile 1, connects retaining plate 3 between two adjacent retaining piles 1 and sets firmly the off-load platform 2 behind retaining pile 1.
The retaining piles 1 are evenly arranged along the direction of the foundation pit at intervals. The retaining pile 1 is divided into an upper section and a lower section, wherein the upper section is a loading section 11 which is positioned above a substrate and mainly bears the soil pressure behind a wall; the lower section is the embedded section 12 below the substrate.
The retaining pile 1 can be of a reinforced concrete structure or a stiff steel structure, and the cross section of the retaining pile 1 can be rectangular, square, circular or in other shapes.
The unloading platform 2 is arranged on the back side of the loaded section 11 of the retaining pile 1 and comprises a bracket 22 and a platform plate 21, wherein the bracket 22 is fixedly arranged on the back side of the retaining pile 1 and is perpendicular to the retaining pile 1, and the bracket 22 can be connected with the retaining pile by bolts and is used for supporting the platform plate 21. The platform plate 21 is horizontally and fixedly installed on the upper surface of the bracket 22 and is used for bearing the load applied by the filler. The width and the burial depth of the unloading platform 2 are determined according to the requirements needed during construction and are not limited. The unloading platform 2 divides the retaining wall into two parts up and down, the part of the retaining wall above the unloading platform 2 is called an upper wall 5, and the part from the unloading platform 2 to the base is called a lower wall 6.
The top of the retaining pile 1 is provided with a top beam 4, the top beam 4 connects a plurality of retaining piles 1 into a whole, the top beam 4 can be a reinforced concrete continuous beam, the function of strengthening the integrity and the deformation coordination of the retaining wall is achieved, and collapse of the top edge of the foundation pit is prevented.
Retaining wall board 3 can be for prefabricating, also can be cast in situ concrete rectangular plate, and its is installed in retaining pile 1's load-bearing section 11 to vertical connection forms confined retaining wall structure between two adjacent retaining piles 1, makes the ground at retaining wall rear can not the landing.
Further, the retaining wall can also be used in combination with anchor structures such as traditional anchor rods, anchor cables and the like to form a composite retaining wall, and the combination form of the retaining wall is not limited.
In the scheme, the loading platform bears the gravity action of the upper part of soil, so that the soil gravity above the loading platform cannot be transmitted to the lower part, and the rock-soil pressure borne by the lower wall 6 is reduced. Meanwhile, the load applied to the platform plate 21 by the soil above the unloading platform 2 provides a bending moment for the soil retaining pile 1, and the direction of the bending moment is opposite to that of the bending moment generated to the soil retaining pile 1 by the soil pressure of the lower wall 6 part, so that the bending moment generated by the soil pressure is balanced. Thereby the stress state of the structure is changed, the maximum bending moment and the shearing force borne by the lower wall 6 are reduced, the force distribution in the structure is more balanced and reasonable, and the deformation of the retaining wall is obviously reduced.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.
Claims (6)
1. The utility model provides an off-load formula stake board barricade which characterized in that: the soil retaining pile structure comprises soil retaining piles (1) which are uniformly arranged at intervals, wherein each soil retaining pile (1) comprises an embedding section (12) which is positioned below a base and a loaded section (11) which is positioned above the base, and an unloading platform (2) is further arranged on the soil facing surface of the loaded section (11).
2. The unloading pile-plate retaining wall according to claim 1, wherein: the unloading platform (2) comprises a platform plate (21), and the platform plate (21) is fixed on the soil-facing surface of the loaded section (11) of the retaining pile (1).
3. The unloading pile-plate retaining wall according to claim 2, wherein: the retaining pile (1) is fixedly provided with a bracket (22), and the platform plate (21) is fixedly arranged on the bracket (22).
4. The unloading pile-plate retaining wall according to claim 1, wherein: and a retaining plate (3) is connected between two adjacent retaining piles (1) at the load bearing section (11).
5. The unloading pile-plate retaining wall according to claim 4, wherein: the retaining plate (3) is a precast concrete plate or a cast-in-place concrete plate.
6. The unloading pile-plate retaining wall according to claim 1, wherein: and a crown beam (4) is arranged at the top of the retaining pile (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021270799.3U CN212742621U (en) | 2020-07-02 | 2020-07-02 | Unloading type pile plate retaining wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021270799.3U CN212742621U (en) | 2020-07-02 | 2020-07-02 | Unloading type pile plate retaining wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212742621U true CN212742621U (en) | 2021-03-19 |
Family
ID=75020366
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021270799.3U Active CN212742621U (en) | 2020-07-02 | 2020-07-02 | Unloading type pile plate retaining wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212742621U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113802605A (en) * | 2021-11-08 | 2021-12-17 | 北京航天地基工程有限责任公司 | Pile plate type retaining wall with pressure reducing plates |
-
2020
- 2020-07-02 CN CN202021270799.3U patent/CN212742621U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113802605A (en) * | 2021-11-08 | 2021-12-17 | 北京航天地基工程有限责任公司 | Pile plate type retaining wall with pressure reducing plates |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6280121B1 (en) | Reinforced retaining wall | |
AU2014237379B2 (en) | Precast concrete retaining wall | |
CN101914925B (en) | Basement by using optimized composite prefabricated arch wall as external wall | |
US6050749A (en) | Concrete masonry unit for reinforced retaining wall | |
CN103510531A (en) | Split type open caisson pile-added combined anchorage foundation and construction method thereof | |
CN110777806B (en) | Multi-connecting-rod plane frame permanent supporting structure and construction process thereof | |
CN109577365A (en) | A kind of pile formula drainage anchor rod barrier wall structure and its construction method | |
CN210288428U (en) | Combined supporting structure | |
JP2645899B2 (en) | High horizontal strength foundation method using solidification method | |
JP2021063404A (en) | Improvement structure and improvement method of existing quay wall | |
CN212742621U (en) | Unloading type pile plate retaining wall | |
CN204919602U (en) | Compound anchored retaining wall by tie rods | |
CN203639929U (en) | Split open caisson and pile composite anchor foundation | |
CN217354388U (en) | Combined retaining type tunnel portal structure suitable for bias steep slope terrain | |
CN203498863U (en) | Three-dimensional continuous-frame-type reinforced concrete structural retaining wall | |
CN214993514U (en) | Landscape river levee reinforced retaining wall | |
CN214832844U (en) | Small-size antidumping assembled pile structure | |
CN111794102B (en) | Sheet pile type anchorage structure and construction method thereof | |
CN111676740B (en) | Construction and design method of anti-arching roadbed structure of ballastless track of cutting section | |
CN210887256U (en) | Straight combined sheet pile-ground wall-connecting type frame of water retaining cofferdam | |
CN112921956A (en) | Construction method of h-shaped oblique cross beam shock-absorbing slide-resistant pile | |
CN208009466U (en) | The tower crane composite foundation of cast-in-situ bored pile and shaped steel lattice column | |
Marchand | A DEEP BASEMENT IN ALDERSGATE STREET, LONDON. PART 1: CONTRACTOR'S DESIGN AND PLANNING. | |
CN1037286C (en) | Multi-layer integrate working pile supporting system and working method | |
CN220704537U (en) | Deep foundation pit supporting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |