CN212648513U - Electric power tower earthing device convenient to installation - Google Patents

Electric power tower earthing device convenient to installation Download PDF

Info

Publication number
CN212648513U
CN212648513U CN202021599428.XU CN202021599428U CN212648513U CN 212648513 U CN212648513 U CN 212648513U CN 202021599428 U CN202021599428 U CN 202021599428U CN 212648513 U CN212648513 U CN 212648513U
Authority
CN
China
Prior art keywords
base
stand
hole
power tower
seted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021599428.XU
Other languages
Chinese (zh)
Inventor
雷立强
刘刚
徐晓娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Yongda Tower Manufacturing Co ltd
Original Assignee
Qingdao Yongda Tower Manufacturing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Yongda Tower Manufacturing Co ltd filed Critical Qingdao Yongda Tower Manufacturing Co ltd
Priority to CN202021599428.XU priority Critical patent/CN212648513U/en
Application granted granted Critical
Publication of CN212648513U publication Critical patent/CN212648513U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The utility model discloses an electric power tower earthing device convenient to installation, including base and sealing washer, the mounting hole has all been seted up to the inner wall all around to the base, and the welding of mounting hole outer end has the spring post to spring post inner is fixed with spacing post, and the inside screw hole of all having seted up in base top moreover, and the inboard threaded connection in screw hole has the bolt simultaneously, the base is the inboard through-hole of all having seted up all around, and through-hole inboard bearing is connected with the drill bit, the stand is installed to the base inboard, and the stand has all seted up spacing hole all around to the stand inner wall all around all is fixed with the welding nut, and the laminating of the stand. This electric power tower earthing device convenient to installation installs spring and spacing post, carries out the block with the stand through spacing post of spacing hole and base inner wall, and this structure has mainly utilized the resilience of spring post to hold the power effect to make stand and base carry out preliminary fixed, be convenient for on next step fixed mounting, increased practicality and convenience.

Description

Electric power tower earthing device convenient to installation
Technical Field
The utility model relates to an electric power tower technical field specifically is an electric power tower earthing device convenient to installation.
Background
The electric power iron tower is the facility for supporting the overhead line used in the transmission of the high-voltage overhead line, and structurally comprises: the angle steel tower is generally used in the field, and the steel pipe pole and the steel pipe narrow base tower are generally used in urban areas because the occupied area is smaller than that of the angle steel tower;
the existing power tower and power tower base are complex in installation process, and need assistance of multiple persons, so that the waste of manpower and time is caused, and the inconvenience is brought to people;
therefore, the power tower grounding device convenient to install can well solve the problems.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an electric power tower earthing device convenient to installation to solve electric power tower and electric power tower base on the existing market that above-mentioned background art provided more complicated in the installation, need many people's assistance, leaded to the extravagant problem of manpower and time.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an electric power tower earthing device convenient to installation, includes base and sealing washer, the mounting hole has all been seted up to the base inner wall all around, and the welding of mounting hole outer end has the spring post to spring post inner is fixed with spacing post, and the inside screw hole that all sets up in base top moreover, and the inboard threaded connection of screw hole has the bolt simultaneously, the base is inboard all around seted up the through-hole, and through-hole inboard bearing is connected with the drill bit, the stand is installed to the base inboard, and the stand has all seted up spacing hole all around to the stand inner wall all around all is fixed with welding nut, and the laminating of the stand outside.
Preferably, the mounting holes are circular, and the mounting holes and the spring columns are in one-to-one correspondence.
Preferably, the limiting columns and the limiting holes on the periphery of the stand column form a clamping structure, and the limiting columns and the limiting holes are in one-to-one correspondence.
Preferably, the bolt penetrates through the base and the upright column, the outer side of the tail end of the bolt is fixedly connected with the welding nut in a threaded mode, and the bolt is perpendicular to the upright column.
Preferably, the drill head extends out of one half of the base, and the drill heads are symmetrically arranged in 2 groups relative to the vertical central line of the base, and each group of the drill heads is 2.
Preferably, the stand is mutually perpendicular with the base, and the sealing washer in the stand outside is laminated with the base each other.
Compared with the prior art, the beneficial effects of the utility model are that: the power tower grounding device convenient to install;
(1) the drill bit is arranged to flatly attach the bottom of the base to the ground, the drill bit is driven by the electric drill, and the base is fixed on the ground through the drill bit, so that the stability of the base is improved, and the phenomenon that the base is loosened in a long-term process is avoided;
(2) the structure mainly utilizes the resilience force storage effect of the spring column, so that the stand column and the base are preliminarily fixed, only one person is needed to operate, the labor cost is saved, the structure is simple, the operation is easy, the next step of fixed installation is facilitated, the problems in the background technology are solved, and the practicability and convenience are improved;
(3) the bolt and the welding nut are arranged, and the bolt is connected and fixed with the welding nut on the inner wall of the upright post through the threaded hole of the base, so that the base and the upright post are further fixed, the phenomenon that the upright post is shaken and loosened in the long-term use process is avoided, and the stability and the practicability are improved;
(4) be provided with the sealing washer, the junction of stand and base is provided with the sealing washer, and the main objective here is to avoid the inside phenomenon that corrodes to appear of base, has prolonged the life of whole device, has increased the practicality.
Drawings
FIG. 1 is a schematic view of the main sectional structure of the present invention;
FIG. 2 is a schematic top view of the present invention;
FIG. 3 is an enlarged schematic view of the structure at A of FIG. 1 according to the present invention;
fig. 4 is an enlarged schematic structural diagram of the point B in fig. 2 according to the present invention.
In the figure: 1. a base; 2. mounting holes; 3. a spring post; 4. a limiting column; 5. a threaded hole; 6. a bolt; 7. a through hole; 8. a drill bit; 9. a column; 10. a limiting hole; 11. welding a nut; 12. and (5) sealing rings.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: the utility model provides an electric power tower earthing device convenient to installation, the on-line screen storage device comprises a base 1, mounting hole 2, spring post 3, spacing post 4, screw hole 5, bolt 6, through-hole 7, the drill bit 8, stand 9, spacing hole 10, weld nut 11 and sealing washer 12, mounting hole 2 has all been seted up to base 1 inner wall all around, and the welding of 2 outer ends of mounting hole has spring post 3, and spring post 3 the inner is fixed with spacing post 4, and the inside screw hole 5 that has all seted up in base 1 top, 5 inboard threaded connection in screw hole have bolt 6 simultaneously, base 1 is inboard all around has seted up through- hole 7, and 7 inboard bearings in through-hole are connected with drill bit 8, stand 9 is installed to base 1 inboard, and stand 9 has all seted up spacing hole 10 all around, and stand 9 inner wall all around all is fixed with weld nut 11, the.
Mounting hole 2 is circular form, and mounting hole 2 is the one-to-one correspondence with spring post 3, and the design of above-mentioned structure for spring post 3 is effectual to be fixed in the inside of mounting hole 2, has increased the usability.
Spacing post 4 constitutes the block structure with stand 9 spacing hole 10 all around, and spacing post 4 and spacing hole 10 are the one-to-one relation, and the design of above-mentioned structure, this structure has mainly utilized the resilience of spring post 3 to hold the power effect to make stand 9 and base 1 tentatively fixed, increased the practicality.
Bolt 6 runs through in base 1 and stand 9, and the terminal outside of bolt 6 is fixed for threaded connection with weld nut 11 to bolt 6 and stand 9 mutually perpendicular, the design of above-mentioned structure, this structure make base 1 and stand 9 obtain further fixed, have avoided stand 9 to appear rocking not hard up phenomenon in long-term use, have increased steadiness and practicality.
Drill bit 8 stretches out base 1's half, and drill bit 8 is provided with 2 groups about base 1's vertical center line symmetry to 8 every groups of drill bits are 2, the design of above-mentioned structure, and this structure has increased base 1's steadiness, has avoided base 1 to appear not hard up phenomenon at long-term in-process.
The stand 9 and base 1 mutually perpendicular, and the sealing washer 12 in the stand 9 outside laminates with base 1 each other, the design of above-mentioned structure, and the main objective here is to avoid base 1 the phenomenon of corruption in long-term use inside appearance, has prolonged the life of whole device, has increased the practicality.
The working principle is as follows: when the electric power tower grounding device convenient to install is used, firstly, as shown in a figure 1-2, all parts are placed in a designated area, then, the bottom of a base 1 is flatly attached to the ground, then, an electric drill is used for driving a drill bit 8, the base 1 is fixed on the ground through the drill bit 8, the stability of the base 1 is improved through the structure, the phenomenon that the base 1 is loosened in a long-term process is avoided, as shown in a figure 1 and a figure 3, then, an upright post 9 is clamped with a limiting post 4 on the inner wall of the base 1 through a limiting hole 10, the structure mainly utilizes the resilience and the force accumulation effect of a spring post 3, so that the upright post 9 and the base 1 are preliminarily fixed, only one person is needed to operate, the labor cost is saved, the structure is simple, the operation is easy, the next step of fixed installation is facilitated, meanwhile, the problems in the background technology are solved, and the practicability and the convenience, as shown in fig. 2 and 4, the bolt 6 is then screwed and fixed with the welding nut 11 on the inner wall of the upright post 9 through the threaded hole 5 of the base 1, the structure further fixes the base 1 and the upright post 9, avoids the phenomenon that the upright post 9 is shaken and loosened in the long-term use process, increases the stability and the practicability, and as shown in fig. 1-2, the joint of the upright post 9 and the base 1 is provided with a sealing ring 12, the main purpose here is to avoid the phenomenon that the base 1 is corroded in the long-term use process, prolongs the service life of the whole device, increases the practicability, and thus completes a series of work, and the content which is not described in detail in the specification belongs to the prior art which is well known by a person skilled in the art.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (6)

1. The utility model provides an electric power tower earthing device convenient to installation, includes base (1) and sealing washer (12), its characterized in that: mounting hole (2) have all been seted up to base (1) inner wall all around, and the welding of mounting hole (2) outer end has spring post (3) to spring post (3) inner is fixed with spacing post (4), and base (1) top is inside all seted up threaded hole (5) moreover, and threaded hole (5) inboard threaded connection has bolt (6) simultaneously, base (1) inboard all has seted up through-hole (7) all around, and through-hole (7) inboard bearing is connected with drill bit (8), stand (9) are installed to base (1) inboard, and stand (9) have all seted up spacing hole (10) all around to stand (9) inner wall all around all is fixed with weld nut (11), and the laminating of stand (9) outside has sealing washer (12) simultaneously.
2. An easy-to-install power tower grounding device as claimed in claim 1, wherein: the mounting holes (2) are circular, and the mounting holes (2) and the spring columns (3) are in one-to-one correspondence.
3. An easy-to-install power tower grounding device as claimed in claim 1, wherein: the limiting columns (4) and the limiting holes (10) on the periphery of the upright column (9) form a clamping structure, and the limiting columns (4) and the limiting holes (10) are in one-to-one correspondence.
4. An easy-to-install power tower grounding device as claimed in claim 1, wherein: the bolt (6) penetrates through the base (1) and the upright post (9), the outer side of the tail end of the bolt (6) is fixedly connected with the welding nut (11) in a threaded mode, and the bolt (6) is perpendicular to the upright post (9).
5. An easy-to-install power tower grounding device as claimed in claim 1, wherein: the drill bit (8) extends out of one half of the base (1), 2 groups of the drill bit (8) are symmetrically arranged relative to the vertical central line of the base (1), and each group of the drill bit (8) is 2.
6. An easy-to-install power tower grounding device as claimed in claim 1, wherein: the upright post (9) is vertical to the base (1), and the sealing ring (12) on the outer side of the upright post (9) is attached to the base (1).
CN202021599428.XU 2020-08-05 2020-08-05 Electric power tower earthing device convenient to installation Expired - Fee Related CN212648513U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021599428.XU CN212648513U (en) 2020-08-05 2020-08-05 Electric power tower earthing device convenient to installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021599428.XU CN212648513U (en) 2020-08-05 2020-08-05 Electric power tower earthing device convenient to installation

Publications (1)

Publication Number Publication Date
CN212648513U true CN212648513U (en) 2021-03-02

Family

ID=74786710

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021599428.XU Expired - Fee Related CN212648513U (en) 2020-08-05 2020-08-05 Electric power tower earthing device convenient to installation

Country Status (1)

Country Link
CN (1) CN212648513U (en)

Similar Documents

Publication Publication Date Title
CN212648513U (en) Electric power tower earthing device convenient to installation
CN218152719U (en) A laying device for assembled water and electricity pipeline
CN108678527B (en) Auxiliary supporting device
CN201573769U (en) Total assembly-piggybacking combined type adjustable support frock
CN216388571U (en) Supporting device for installing signboard
CN210273901U (en) Connecting assembly for photovoltaic support and prestressed concrete pipe pile
CN211949855U (en) Three-way cross arm steel pipe pole for double-circuit overhead line breaking
CN210007289U (en) Support frame suitable for electric power capital construction job site interim cable supports
CN111395855A (en) Wire pole auxiliary stay device
CN215007741U (en) Aluminum grading ring for insulator
CN220014658U (en) Telegraph pole convenient to assemble and erect
CN218295555U (en) Solar street lamp pole adapter sleeve device
CN220504667U (en) Distribution frame
CN219910249U (en) Electric power iron tower base structure
CN215335798U (en) Carbon fiber composite gas cylinder convenient to carry
CN210780193U (en) Solar power supply device of monitoring system
CN215443381U (en) Urban intelligent monitoring tower utilizing clean energy
CN212783843U (en) Quickly-installed field grounding electrode
CN221034999U (en) Flood disaster monitoring and early warning display screen column
CN214579766U (en) Improved computer signal receiving and adjusting device
CN210849903U (en) Steel pipe bundle combined fixing structure
CN214069403U (en) Portable rotatable cable head manufacturing support
CN110289572B (en) Split conductor supporting device
CN217083736U (en) Be used for bridge to turn upward carousel slope monitoring of turning and use hydrostatic level appearance
CN214847959U (en) Grading ring convenient to dismantle installation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210302