CN212561489U - Pile frame structure of cast-in-situ bored pile - Google Patents

Pile frame structure of cast-in-situ bored pile Download PDF

Info

Publication number
CN212561489U
CN212561489U CN202021241738.4U CN202021241738U CN212561489U CN 212561489 U CN212561489 U CN 212561489U CN 202021241738 U CN202021241738 U CN 202021241738U CN 212561489 U CN212561489 U CN 212561489U
Authority
CN
China
Prior art keywords
mud jacking
segment
pile
jacking pipe
protection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021241738.4U
Other languages
Chinese (zh)
Inventor
薛阳洁
李丰琦
佟帅宏
喻皓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mcc Construction Engineering Group Tianjin Construction Engineering Co Ltd
Original Assignee
Mcc Construction Engineering Group Tianjin Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mcc Construction Engineering Group Tianjin Construction Engineering Co Ltd filed Critical Mcc Construction Engineering Group Tianjin Construction Engineering Co Ltd
Priority to CN202021241738.4U priority Critical patent/CN212561489U/en
Application granted granted Critical
Publication of CN212561489U publication Critical patent/CN212561489U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a pile frame structure of drilling bored concrete pile, including pile frame and mud jacking pipe, the pile frame is used for cast-in-place concrete to form the bored concrete pile, the mud jacking pipe is provided with the mud jacking valve along the vertical setting in the pile frame outside, still includes the whole protection muscle that sets up along vertical direction, it has the protection section and the erection segment of at least one vertical setting, be connected so that protection section, linkage segment and erection segment form a whole through the linkage segment between protection section and the erection segment, the outer diameter of horizontal interval more than or equal to mud jacking pipe between protection section and the erection segment, the erection segment welded fastening is on the pile frame outside, the protection section outside is used for meeting with the drilling pore wall, the mud jacking pipe is located between erection segment and the protection segment and through pricking the silk ligature on the linkage segment. When transferring, the protection section lateral wall contacts with the pore wall to avoid the mud jacking pipe direct and pore wall to contact the collision, avoid the mud jacking pipe to take place the damage, the effectual mud jacking pipe of having protected.

Description

Pile frame structure of cast-in-situ bored pile
Technical Field
The utility model belongs to the technical field of civil engineering, especially, relate to a pile frame structure of drilling bored concrete pile.
Background
The cast-in-place pile is a pile formed by forming a hole in place and pouring concrete or reinforced concrete. Commonly used are: (1) drilling a cast-in-place pile: the pile is formed by using a spiral drilling machine, a diving drilling machine and the like to form holes on site and pouring concrete, and the construction has no vibration and does not squeeze soil, but the settlement amount of the pile is slightly larger.
(2) And sinking the pipe and pouring the pile: the steel pipe with reinforced concrete pile shoe (pile tip) or valve type pile shoe is sunk into the soil by hammering or vibration, then concrete is poured in and the pipe is pulled out simultaneously to form the pile.
When the cast-in-situ bored pile is constructed, firstly, holes are drilled through equipment, then a pile frame formed by the steel mesh cage is sunk into the holes, and then concrete or reinforced concrete is poured into the holes to form the cast-in-situ bored pile. In the construction process, a post-grouting construction method is used, wherein the post-grouting is to fill slurry into a pre-embedded grouting pipe through a high-pressure pump when the concrete of a pile body reaches a certain strength after the pile is formed, the slurry breaks through a valve at the bottom of the grouting pipe to crack the soil body at the bottom of the pile body, and the slurry enters the crack, so that the strength of the soil body and the coaction performance of the pile body and the soil body are improved. The quality of the grouting is therefore directly dependent on the integrity and openness of the mud jacking pipe.
The conventional installation to the mud jacking pipe is with the mud jacking pipe direct welding and pile frame steel reinforcement cylinder mould outside, and the drawback of doing so has: welding must lead to the fact the damage to the mud jacking pipe wall, and the mud jacking pipe is in the pile frame outside, and the in-process is transferring can be difficult to avoid frequently bumping with the pore wall, and the mud jacking pipe of modelling is buckled the dislocation easily like this, and is difficult to carry out position control after the mud jacking pipe welding is accomplished, and the fault-tolerant rate is low, and the rework cost is high.
SUMMERY OF THE UTILITY MODEL
To the not enough of above-mentioned prior art, the utility model aims to solve the technical problem that: how to provide a pile frame structure of drilling bored concrete pile, its mud jacking pipe can not bump with the pore wall when transferring, does not link firmly through welding and pile frame simultaneously, avoids causing the damage to the mud jacking pipe body, effectively protects the mud jacking pipe.
In order to solve the technical problem, the utility model discloses a following technical scheme:
the utility model provides a pile frame structure of bored concrete pile, includes pile frame and mud jacking pipe, the pile frame is used for cast-in-place concrete to form the bored concrete pile, the mud jacking pipe is provided with the mud jacking valve along the vertical setting in the pile frame outside, still includes the whole protection muscle that sets up along vertical direction, it has the protection section and the erection segment of at least one vertical setting, be connected so that protection section, linkage segment and erection segment form a whole through the linkage segment between protection section and the erection segment, horizontal interval more than or equal to mud jacking pipe's between protection section and the erection segment outer diameter, erection segment welded fastening is on the pile frame outside, the protection section outside is used for meeting with the drilling pore wall, the mud jacking pipe is located between erection segment and the protection section and through pricking the silk ligature on the linkage segment.
Preferably, the protection rib is provided with a protection section, two installation sections and two connecting sections, the two installation sections are respectively positioned on the upper side and the lower side of the protection section, the upper end and the lower end of the protection section are respectively connected with one end of the installation section through one connecting section, and the grouting pipe is bound and fixed with the two connecting sections through binding wires.
Preferably, the protection ribs are arranged at equal intervals in the vertical direction, and the connecting section of each protection rib is fixedly bound with the mud jacking pipe through binding wires.
Preferably, the number of the mud jacking pipes is at least two, and the mud jacking pipes are uniformly distributed along the peripheral direction of the pile frame.
Compared with the prior art, the utility model following beneficial effect has: the mud jacking pipe in this pile frame structure passes through the protection muscle to be connected with the pile frame, avoid with pile frame welded fastening, the protection muscle has erection segment and protection section simultaneously, erection segment and pile frame welded fastening, can guarantee that the protection muscle is connected firmly, the outer diameter of interval more than or equal to mud jacking pipe between protection segment and the erection segment simultaneously, can make the mud jacking pipe be located between protection segment and the erection segment, the protection segment is located the mud jacking outside of tubes, when transferring, protection segment lateral wall contacts with the pore wall, thereby avoid the mud jacking pipe directly to contact the collision with the pore wall, avoid the mud jacking pipe to take place the damage, the effectual mud jacking pipe of having protected, and the mud jacking pipe then can be fixed through the linkage segment ligature of bundling and protection muscle.
Drawings
Fig. 1 is a front view of an embodiment of the invention;
fig. 2 is a top view of an embodiment of the invention;
fig. 3 is a schematic structural view of the embodiment of the present invention when the protection rib is connected to the grouting pipe.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
In the specific implementation: referring to fig. 1 to 3, a pile frame structure of bored concrete pile, including pile frame 1 and mud jacking pipe 2, the pile frame is used for the cast-in-place concrete to form the bored concrete pile, the mud jacking pipe is along the vertical setting in the pile frame outside, is provided with mud jacking valve 3 in the bottom of mud jacking pipe, still includes whole protection muscle 4 that sets up along vertical direction, and it has at least one vertical protection section 5 and the installation section 6 that sets up, is connected so that protection section, linkage segment and installation section form a whole through linkage segment 7 between protection section and the installation section, and the horizontal interval between protection section and the installation section is more than or equal to the external diameter of mud jacking pipe 2, and the installation section welded fastening is on the pile frame outside, and the protection section outside is used for meeting with the drilling pore wall, and the mud jacking pipe is located between installation section and the protection section and through 8 ligatures on the linkage segment.
Therefore, the mud jacking pipe in the pile frame structure is connected with the pile frame through the protection rib, avoid being directly welded and fixed with the pile frame, the protection rib has installation section and protection section simultaneously, installation section and pile frame welded and fixed, can guarantee that the protection rib is connected firmly, the outside diameter of interval more than or equal to mud jacking pipe between protection section and the installation section simultaneously, can make the mud jacking pipe be located between protection section and the installation section, the protection section is located the mud jacking outside of tubes, when transferring, the protection section lateral wall contacts with the pore wall, thereby avoid the mud jacking pipe directly to contact the collision with the pore wall, avoid the mud jacking pipe to take place the damage, the effectual mud jacking pipe of having protected, and the mud jacking pipe then can be fixed through the linkage segment ligature of tying silk and protection rib.
Preferably, the protection rib is provided with a protection section, two installation sections and two connecting sections, the two installation sections are respectively positioned on the upper side and the lower side of the protection section, the upper end and the lower end of the protection section are respectively connected with one end of the installation section through one connecting section, and the grouting pipe is bound and fixed with the two connecting sections through binding wires.
Therefore, the protection rib is arranged in such a way, the protection rib can be welded with the pile frame firmly through the upper installation section and the lower installation section, the grouting pipe can be isolated from the hole wall through the protection section, and the upper connecting section and the lower connecting section can be bound together through the binding wires and the grouting pipe, so that the grouting pipe cannot deviate and be dislocated.
Preferably, the protection ribs are arranged at equal intervals in the vertical direction, and the connecting section of each protection rib is fixedly bound with the mud jacking pipe through binding wires.
Therefore, for the connection steadiness of reinforcing mud jacking pipe, can establish a plurality ofly along the mud jacking pipe axial, the linkage segment of every protection muscle all ties together through the ligature silk with the mud jacking pipe to make mud jacking union coupling steadiness strengthen greatly, compare protection muscle as the vertical setting of a whole edge mud jacking pipe, this kind of segmentation can also practice thrift the cost under the prerequisite that has good connection steadiness.
Preferably, the number of the mud jacking pipes is at least two, and the mud jacking pipes are uniformly distributed along the peripheral direction of the pile frame.
The grouting pipe is arranged in such a way, so that the grout can be filled in the soil body more uniformly, and the grouting pipe is beneficial to the reinforcement effect of the soil body and the interaction of pile and soil.

Claims (4)

1. The utility model provides a pile frame structure of bored concrete pile, includes pile frame and mud jacking pipe, the pile frame is used for cast-in-place concrete to form bored concrete pile, the mud jacking pipe is provided with mud jacking valve, its characterized in that along the vertical setting in the pile frame outside in the mud jacking pipe's bottom: still including whole protection muscle that sets up along vertical direction, it has the protection section and the installation segment of at least one vertical setting, be connected so that the protection section through the linkage segment between protection section and the installation segment, linkage segment and installation segment form a whole, the outer diameter of horizontal interval more than or equal to mud jacking pipe between protection section and the installation segment, installation segment welded fastening is on the pile frame outside, the protection section outside is used for meeting with the drilling pore wall, the mud jacking pipe is located between installation segment and the protection section and through the ligature of ligature silk on the linkage segment.
2. The pile frame structure of a bored pile according to claim 1, wherein: the protection muscle has a protection section, two installation sections and two linkage segments, and two installation sections are located the upper and lower both sides of protection section respectively, and the upper and lower both ends of protection section link to each other with the one end of installation section through a linkage segment respectively, and the mud jacking pipe is fixed with two linkage segments ligatures through tying the silk.
3. A pile frame structure of a bored pile according to claim 1 or 2, wherein: the protection muscle is equipped with a plurality of along vertical direction equidistant, and the linkage segment of every protection muscle all is fixed through pricking silk and mud jacking pipe ligature.
4. The pile frame structure of a bored pile according to claim 1, wherein: the mud jacking pipe is equipped with two at least, along pile frame periphery circumference equipartition.
CN202021241738.4U 2020-06-30 2020-06-30 Pile frame structure of cast-in-situ bored pile Active CN212561489U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021241738.4U CN212561489U (en) 2020-06-30 2020-06-30 Pile frame structure of cast-in-situ bored pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021241738.4U CN212561489U (en) 2020-06-30 2020-06-30 Pile frame structure of cast-in-situ bored pile

Publications (1)

Publication Number Publication Date
CN212561489U true CN212561489U (en) 2021-02-19

Family

ID=74615691

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021241738.4U Active CN212561489U (en) 2020-06-30 2020-06-30 Pile frame structure of cast-in-situ bored pile

Country Status (1)

Country Link
CN (1) CN212561489U (en)

Similar Documents

Publication Publication Date Title
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN210163913U (en) Asymmetric double-row pile-anchor rod combined supporting structure
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
KR100914158B1 (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
CN103628571B (en) Beam-column joint for reverse construction method and construction method
CN109024721B (en) Reinforced foundation and method for improving bending and shearing resistance of existing building rigid foundation
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN212561489U (en) Pile frame structure of cast-in-situ bored pile
CN210766861U (en) Portal formula building pile foundation underpins structure under narrow and small space
KR101210368B1 (en) Uniting Method of Temporary earth wall with basement exterior Wall using Couplers and Bolts.
CN209228377U (en) A kind of multistage set arch structure and pipe canopy set arch structure for tunnel portal supporting
CN214497488U (en) Splicing structure for final-setting cast-in-place pile
CN113605951B (en) Shallow tunnel supporting structure and construction method thereof
US20180230665A1 (en) Comprehensive excavation process
CN211113669U (en) Prestressed reinforced concrete breast wall pile
KR100711054B1 (en) A construction method of concrete retaining wall using anchor
CN113106982B (en) Construction method of building enclosure without embedding
CN105442528A (en) Cement grouting plate pile with sealing rings
CN215105252U (en) Pile bottom post-grouting reinforced concrete pre-tensioning method prestressed hollow square pile capable of being constructed in sections
CN213596965U (en) Prefabricated reinforced concrete soil nailing pile
CN217267482U (en) Simple and easy drilling bored concrete pile post-grouting device based on flexible slip casting pipe
CN214090040U (en) High-rise building pile foundation reinforced structure
CN212956513U (en) Precast concrete block for hole digging pile retaining wall and manual hole digging pile retaining wall mounting structure
CN217758722U (en) Anchor rod static pressure pile sealing pile node structure
CN115198787B (en) Steel tube column type tower crane foundation and construction method thereof, and cover-excavation reverse construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant