CN212560984U - Novel glue injection road - Google Patents

Novel glue injection road Download PDF

Info

Publication number
CN212560984U
CN212560984U CN202020684950.1U CN202020684950U CN212560984U CN 212560984 U CN212560984 U CN 212560984U CN 202020684950 U CN202020684950 U CN 202020684950U CN 212560984 U CN212560984 U CN 212560984U
Authority
CN
China
Prior art keywords
layer
gravel
soil layer
road
thickness
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020684950.1U
Other languages
Chinese (zh)
Inventor
刘颂
刘岩
赵玉忠
甘泉
王俊源
付强
王莹莹
王洋
孙方岩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin Province Road And Bridge Design Co ltd
Original Assignee
Jilin Province Road And Bridge Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin Province Road And Bridge Design Co ltd filed Critical Jilin Province Road And Bridge Design Co ltd
Priority to CN202020684950.1U priority Critical patent/CN212560984U/en
Application granted granted Critical
Publication of CN212560984U publication Critical patent/CN212560984U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a novel injecting glue road, include: basic soil layer, metalling, bonding glue film, thin soil layer, concrete layer and pitch layer, basic soil layer is located the below, for the bottom sprag. This novel injecting glue road is one kind and adds gluey in the rubble layer, fills the expansion joint between the rubble for the rubble is connected stably, guarantees the road structure that the ground supported safety.

Description

Novel glue injection road
Technical Field
The utility model relates to a road field provides a novel injecting glue road very much.
Background
A road is a building structure used for walking.
In some areas, a lot of relatively heavy vehicles can run on the road, if the structure of the road is unstable, the road is easily extruded and deformed by the heavy vehicles, the road is uneven, and the driving safety of the vehicles is extremely influenced, in the prior art, for the stable support of the bottom of the road, a gravel layer is added, more gaps are formed in the conventional gravel layer, the conventional gravel layer is easily deformed, in order to reduce the deformation degree, the fine sand is usually only used for filling and supporting, but sand grains in the fine sand are also in a three-dimensional structure and only are in lap joint with the gravel layer, when strong extrusion force is applied, appropriate deviation is easily generated, the stability of the whole structure of the road is influenced, and expansion joints are still left on the structures of the gravel or the gravel and the fine sand, so that the road for frequently running heavy vehicles is still unstable, and therefore, in order to solve the problems, the safety of the road structure is better guaranteed, and it is necessary to design a road structure which fills the expansion joints between the broken stones through the adhesive glue.
SUMMERY OF THE UTILITY MODEL
In view of this, in order to solve the above-mentioned problem, the utility model aims at providing a novel injecting glue road.
The utility model provides a technical scheme is: the novel glue injection road comprises a foundation soil layer, a gravel layer, a bonding glue layer, a fine soil layer, a concrete layer and an asphalt layer, wherein the foundation soil layer is located at the bottom and used for bottom support, the gravel layer is located on the upper surface of the foundation soil layer, the bonding glue layer is completely immersed inside the gravel layer and used for enhancing connection between the gravels, the fine soil layer is laid on the upper surface of the gravel layer, the concrete layer is located on the upper surface of the fine soil layer, and the asphalt layer is uniformly laid on the upper surface of the concrete layer.
Further preferably, the thickness of the crushed stone layer is larger than that of the fine soil layer.
Further preferably, the thickness of the concrete layer is between the thickness of the fine soil layer and the thickness of the gravel layer.
Further preferably, a moisture-proof cloth layer is arranged at the center in the foundation soil layer.
Preferably, the gravel layer is divided into upper gravel, middle gravel and lower gravel, and the size of the gravel in the upper gravel and the lower gravel is the same and larger than that of the gravel in the middle gravel.
Preferably, the vertical sections of the gravel layer and the foundation soil layer are both trapezoidal.
The utility model provides a novel injecting glue road, one kind adds gluey in the rubble layer, fills the expansion joint between the rubble for the rubble is connected stably, guarantees the road structure that the ground supported safety.
Drawings
The present invention will be described in further detail with reference to the accompanying drawings and embodiments:
FIG. 1 is a schematic structural view of the novel glue injection road;
fig. 2 is a front sectional view of the novel glue injection road, in which the foundation soil layer, the crushed stone layer, the adhesive layer, the fine soil layer, the concrete layer, the asphalt layer and the moisture-proof cloth layer are matched;
in the figure: 1. a foundation soil layer; 2. a crushed stone layer; 3. bonding the adhesive layer; 4. a fine soil layer; 5. a concrete layer; 6. an asphalt layer; 7. a moisture-proof cloth layer.
Detailed Description
The invention will be further explained below with reference to specific embodiments, without limiting the invention.
As shown in fig. 1-2, the utility model provides a novel glue injection road, which comprises a foundation soil layer 1, a gravel layer 2, a bonding glue layer 3, a fine soil layer 4, a concrete layer 5 and an asphalt layer 6, wherein the foundation soil layer 1 is positioned at the bottom for bottom support, the gravel layer 2 is positioned on the upper surface of the foundation soil layer 1, the bonding glue layer 3 is completely immersed in the gravel layer 2 for enhancing the connection between the gravels, the fine soil layer 4 is laid on the upper surface of the gravel layer 2, the concrete layer 5 is positioned on the upper surface of the fine soil layer 4, the asphalt layer 6 is uniformly laid on the upper surface of the concrete layer 5, when the structure is used for laying the ground, firstly, the ground surface is paved, and a plurality of soil layers for bedding, namely the foundation soil layer 1, are laid, because the foundation soil layer 1 has a certain thickness, in order to ensure the overall stability, therefore, when a certain height is paved, an external road roller is needed to compact the foundation soil layer 1, the foundation soil layer 1 with a certain thickness is paved, the compaction needs to be carried out for a plurality of times, the specific compaction times are determined according to the thickness of the actually paved foundation soil layer 1, after the compaction, the gravel layer 2 is paved on the upper surface of the foundation soil layer 1, the bottom support is good due to the fact that the gravel has strong supporting capacity, because the gravel is used in the gravel layer 2 and can not be completely contacted, a large amount of space capable of moving properly is left between the gravel layers 2, the space can meet the requirement that after the ground is paved, the proper heat expansion and cold contraction are carried out according to the conditions of weather and use environment, the ground can be adapted, and moisture received under the ground can be condensed and then flows out in the gap of the gravel layer 2, the water is not convenient to be stored, the ground base part is kept dry, wherein the structure is used as a road surface, the firmness degree of the road surface is important for the safety of people walking above the road surface and vehicles, therefore, when a heavier machine passes through the road surface of the structure, the road surface is pressed downwards with a larger force, so that the proper telescopic deformation is generated inside the gravel layer 2, therefore, after the gravel layer 2 is paved, the bonding glue layer 3 is filled in the gap inside the gravel layer 2, when the gravel layer 2 is paved, the compaction is required for a plurality of times, so that the gap between the gravel is smaller, the support is stable, wherein the bonding glue layer 3 is used for filling the melted glue into the gravel layer 2, and as the gravel layer 2 has a certain thickness, a part of the bonding glue layer 3 is filled after each compaction, compacting, filling and compacting for multiple times, and then paving the fine soil layer 4 after the adhesive glue layer 2 is cooled in the gravel layer 2, wherein the adhesive glue layer 3 only fills up the expansion joints in the gravel layer 2, so that the gravels between every two adjacent gravels are bonded through glue, the inside of the gravel layer 2 is better fixed, and the foundation is more firm, wherein the adhesive glue layer 3 only plays a role in connection and filling, including but not limited to asphalt liquid or silicone glue, and the like, wherein the fine soil layer 4 to be laid also needs to be laid in multiple layers, compacting is carried out, so that firmness and reliability are realized, wherein the fine soil can flow into the expansion joints which are not filled up in the gravel layer 2 in the compacting process and is properly filled, and the filling amount required by filling is extremely small due to the filling of the adhesive glue layer 3 of the shell, so that the whole thickness of the fine soil layer 4 cannot be influenced, wherein because the inside granule of thin soil layer 4 is more thin, the space of granule each other is also more, consequently also be better on absorbing bottom moisture, wherein concrete layer 5 on 4 upper surface laying of compacted thin soil layer, with bottom upper end capping, be convenient for bear the asphalt layer 6 of upper surface, make asphalt layer 6 good at concrete layer 5 fixed surface, because concrete layer 5 has certain hard degree, consequently make asphalt layer 6 after laying and shaping, holistic durable degree is better, make holistic road surface structure bearing capacity better.
As can be seen from fig. 1-2 of the specification, the thickness of the gravel layer 2 is greater than that of the fine soil layer 4, and the support stability is good because the thickness of the gravel layer 2 is relatively large and the hard part is relatively thick.
As can be seen from fig. 1-2 of the specification, the thickness of the concrete layer 5 is between the thickness of the fine soil layer 4 and the thickness of the gravel layer 2, and the thickness of the concrete layer 5 is higher than that of the fine soil layer 4 due to the function of fixing the asphalt layer 6, but is lower than that of the gravel layer 2, if the thickness is too large, the ground foundation is too high, and the cost of the concrete is too high, which is not practical.
As can be seen from fig. 1-2 of the specification, a moisture-proof cloth layer 7 is provided at the center inside the foundation soil layer 1, wherein the moisture-proof cloth layer 7 is placed inside the foundation soil layer 1, and is placed in real time during each lamination, and is compacted after the placement, so that moisture inside the foundation soil layer 1 is properly isolated, and excessive moisture is prevented from going upwards to affect the stability of the pavement structure, wherein the moisture-proof cloth layer 7 is only used for performing moisture-proof operations, and includes but is not limited to a geotextile layer or a non-woven fabric layer.
As can be known from the description attached drawings 1-2, the rubble layer 2 divide into upper rubble, middle level rubble and lower floor's rubble, the upper rubble with rubble size in the lower floor's rubble is the same, and is greater than rubble size in the middle level rubble, wherein in order to make holistic structure more stable for stability between 2 rubble layers is good, when laying, chooses for use upper strata bold rubble, middle level fritter, the overlapping mode of lower floor's bold rubble is placed, middle level fritter is convenient for when carrying out the extrusion, enter into inside the bold rubble of upper strata or lower floor, make the gap fill more full, when satisfying the thickness requirement, make the fructification degree increase.
As can be seen from the attached figures 1-2 in the specification, the vertical sections of the gravel layer 2 and the foundation soil layer 1 are both trapezoidal, and due to the trapezoidal structure, the whole structure is more stable, and the supporting effect is better.
The embodiments of the present invention are written in a progressive manner, emphasizing the differences of the various embodiments, and similar parts can be referred to each other.
The embodiments of the present invention have been described in detail with reference to the drawings, but the present invention is not limited to the above embodiments, and various changes can be made without departing from the spirit of the present invention within the knowledge of those skilled in the art.

Claims (6)

1. The novel glue injection road is characterized by comprising a foundation soil layer (1), a gravel layer (2), a bonding glue layer (3), a fine soil layer (4), a concrete layer (5) and an asphalt layer (6), wherein the foundation soil layer (1) is located at the bottom and used for bottom support, the gravel layer (2) is located on the upper surface of the foundation soil layer (1), the bonding glue layer (3) is completely immersed inside the gravel layer (2) and used for enhancing connection between gravels, the fine soil layer (4) is laid on the upper surface of the gravel layer (2), the concrete layer (5) is located on the upper surface of the fine soil layer (4), and the asphalt layer (6) is uniformly laid on the upper surface of the concrete layer (5).
2. A novel glue injection road according to claim 1, characterized in that the thickness of the gravel layer (2) is greater than the thickness of the fine soil layer (4).
3. A novel injected road according to claim 1, characterized in that the thickness of the concrete layer (5) is between the thickness of the fine soil layer (4) and the thickness of the gravel layer (2).
4. A novel glue injection road according to claim 1, characterized in that a moisture-proof cloth layer (7) is arranged at the center of the foundation soil layer (1).
5. A novel glue injection road as claimed in claim 1, wherein the gravel layer (2) is divided into upper gravel, middle gravel and lower gravel, and the gravel in the upper gravel and the lower gravel has the same size and is larger than the gravel in the middle gravel.
6. A novel glue injection road according to claim 1, characterized in that the vertical cross-sections of the gravel layer (2) and the foundation soil layer (1) are both trapezoidal.
CN202020684950.1U 2020-04-29 2020-04-29 Novel glue injection road Active CN212560984U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020684950.1U CN212560984U (en) 2020-04-29 2020-04-29 Novel glue injection road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020684950.1U CN212560984U (en) 2020-04-29 2020-04-29 Novel glue injection road

Publications (1)

Publication Number Publication Date
CN212560984U true CN212560984U (en) 2021-02-19

Family

ID=74607815

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020684950.1U Active CN212560984U (en) 2020-04-29 2020-04-29 Novel glue injection road

Country Status (1)

Country Link
CN (1) CN212560984U (en)

Similar Documents

Publication Publication Date Title
CN206666931U (en) A kind of area of heavy rainfull ballastless track of high-speed railway road structure
CN106192646B (en) Vcehicular tunnel car-driving shock-absorbing denoising structure and its construction method
CN105926406A (en) Splicing method and structure for new and old roads in reconstruction and extension of pavement
CN106638213A (en) Cement road construction method
CN205276086U (en) Expansion joint device is handled to combined type road surface tip
CN204401444U (en) A kind of high embankment filled soil end of the bridge anti-settling structure
CN112921738B (en) Highway pavement structure and construction method thereof
CN112048955B (en) Construction method for backfilling gravel roadbed
CN107386047B (en) Water permeable brick pavement structure and construction method thereof
CN107747261A (en) A kind of new Soft Clay seasonal frozen soil region highway subgrade structure and construction method
CN109944125B (en) Asphalt concrete pavement structure and paving process thereof
CN108729437A (en) Composite, water-drain isolating pad, bedding waterproof/drainage structure and side slope are layered waterproof/drainage structure
CN207727452U (en) A kind of back filling behind abutment structure sheaf for preventing culvert jump vehicle
CN206736675U (en) A kind of cell pavement
CN205501750U (en) Supporting structure of be used for pavement to widen transformation
CN110820456A (en) Anti-settling and replacement-filling alternate airport runway and construction method thereof
CN212560984U (en) Novel glue injection road
CN106087639A (en) A kind of highway, Irish bridge structure and Irish bridge construction method
CN107268373A (en) A kind of water permeability asphalt concrete road and its construction method
CN1732315B (en) Method for constructing a rigid pavement, and a rigid pavement carriageway
CN206127789U (en) Structure of making an uproar falls in highway tunnel driving damping
CN212895900U (en) Gravity type U-shaped abutment rear drainage structure
CN112746570B (en) Protection device for highway reconstruction and extension slope
US7431536B2 (en) Method of making a flat foundation for a floor without substantial excavation and foundation made by said method
CN214401394U (en) Bridgehead roadbed structure

Legal Events

Date Code Title Description
GR01 Patent grant