CN212509819U CN202021145157.0U CN202021145157U CN212509819U CN 212509819 U CN212509819 U CN 212509819U CN 202021145157 U CN202021145157 U CN 202021145157U CN 212509819 U CN212509819 U CN 212509819U
Authority
CN
China
Prior art keywords
pipeline
locking
supplementary fixed
support
pipe gallery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021145157.0U
Other languages
Chinese (zh)
Inventor
韩涛
王小峰
舒卓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Tongfengyuan Construction Engineering Co ltd
Original Assignee
Sichuan Tongfengyuan Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Tongfengyuan Construction Engineering Co ltd filed Critical Sichuan Tongfengyuan Construction Engineering Co ltd
Priority to CN202021145157.0U priority Critical patent/CN212509819U/en
Application granted granted Critical
Publication of CN212509819U publication Critical patent/CN212509819U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model belongs to the technical field of city piping lane engineering construction technique and specifically relates to a city piping lane is with construction support that has supplementary fixed function is related to, and it includes the stake body, be provided with on the stake body and be used for the fixed locking Assembly of pipeline locking, the stake body is provided with the supplementary fixed subassembly that is used for fixed pipeline, supplementary fixed subassembly sets up side by side along the pipeline axis with locking Assembly, supplementary fixed subassembly including set up U type pole on the stake body and set up on U type pole be used for with the mounting of pipeline butt. The application has the following effects: can play supplementary fixed effect to the pipeline in supplementary fixed subassembly when locking Assembly becomes flexible and can't lock the fastening with the pipeline for a long time, prevent that the pipeline from directly taking place the drunkenness when the pipeline receives the vibration, even fall down from the piping lane support, avoided droing each other between the pipeline, the bad consequence of intraductal material leakage.

Description

City piping lane is with construction support that has supplementary fixed function
Technical Field
The utility model belongs to the technical field of city piping lane engineering construction technique and specifically relates to a city piping lane is with construction support that has supplementary fixed function is related to.
Background
The city pipe gallery engineering is a comprehensive engineering which builds a tunnel space under the city, intensively lays more than two municipal pipelines such as electric power, communication, gas, heat supply, water supply and drainage and the like in the tunnel space, is provided with a special access hole, a lifting hole and a monitoring system, and implements unified planning, unified design, unified construction and management. City piping lane engineering is used often to the piping lane support in the construction and is supported and fixed various pipelines.
The prior Chinese utility model patent with the publication number of CN208982791U discloses a combined pipe gallery support, which comprises a mounting plate, a mounting support, a sliding rod, a mounting seat, a rubber ring, a locking plate, a fitting body and a hoop, wherein the sliding rod is fixedly mounted on one side of the mounting plate, a first waist-shaped hole is formed in the sliding rod, a first slider is slidably mounted in the first waist-shaped hole, a plurality of positioning holes are formed in the front side of the sliding rod, the positioning holes penetrate through the first waist-shaped hole, through holes matched with the positioning holes are formed in the first slider, an opening communicated with the first waist-shaped hole is formed in one side of the sliding rod, which is far away from the mounting plate, a side plate is fixedly mounted on one side of the side plate, which is far away from the mounting plate, through the mounting opening, the mounting support is fixedly mounted on one side of the side plate, which is, the hoops are adopted to tightly fix the pipelines, the mode is simple, the installation and the disassembly are convenient, and the working efficiency of workers is improved.
With respect to the related art among the above, the inventors consider that the following drawbacks exist: the pipeline only holds tightly fixedly through the staple bolt, and fixed mode is single, but the pipe gallery internal environment is moist easily leads to the staple bolt to become flexible because of the age, and then leads to the pipeline can't be locked, when the pipeline receives the vibration, the pipeline easily takes place the drunkenness, drops from the pipe gallery support even and down, causes to drop each other between the pipeline, the harmful consequence of intraductal material leakage.
SUMMERY OF THE UTILITY MODEL
In order to avoid the staple bolt to be in reason when not hard up for a long time, the pipeline receives to shake and easily takes place the drunkenness and drop the problem down even from the support, this application provides a city piping lane with construction support that has supplementary fixed function.
The application provides a pair of city piping lane is with construction support that has supplementary fixed function adopts following technical scheme:
the utility model provides a city piping lane is with construction support that has supplementary fixed function, includes the stake body, be provided with on the stake body and be used for locking fixed locking Assembly with the pipeline, the stake body is provided with the supplementary fixed subassembly that is used for fixed pipeline, supplementary fixed subassembly sets up side by side along the pipeline axis with locking Assembly, supplementary fixed subassembly including set up U type pole on the stake body and set up on U type pole be used for with the mounting of pipeline butt.
Through adopting above-mentioned technical scheme, if locking Assembly is not hard up for a long time, can't be when fastening the pipeline lock, the mounting in the supplementary fixed subassembly supports and leans on the pipeline, and the mounting can also play supplementary fixed effect to the pipeline, prevents that the pipeline from directly taking place the drunkenness when receiving to shake, even falls down from the support, has avoided droing each other between the pipeline, the bad consequence of intraductal material leakage.
Preferably, the bracket body comprises two parallel upright posts and a cross beam arranged between the two parallel upright posts, and two ends of the cross beam are detachably connected with the two upright posts respectively.
Through adopting above-mentioned technical scheme, realize the firm installation of crossbeam and stand, crossbeam and stand can be dismantled and be connected, convenient and fast during the dismouting.
Preferably, the stand is equipped with first spout, and first spout between the coexistence post sets up in opposite directions, is provided with respectively on the coexistence post to be used for carrying out spacing locating part to the crossbeam, the locating part includes that two can follow the gliding limiting plate of stand vertical direction and be used for the retaining member of limiting plate location, the tip of crossbeam is located between two limiting plates.
Through adopting above-mentioned technical scheme, can realize crossbeam height-adjustable's function through adjusting the position of limiting plate on the stand, constructor can select the height of adaptation according to actual need when the installation, has strengthened this city piping lane with the practicality that has supplementary fixed function's construction support.
Preferably, the crossbeam is equipped with the second spout that is used for installing locking Assembly and the third spout that is used for installing supplementary fixed subassembly side by side along the pipeline axis, locking Assembly is including setting up the mount pad on the crossbeam top side and fixing the locking staple bolt in the mount pad top side.
By adopting the technical scheme, the position of the locking assembly on the cross beam is adjustable, and constructors can select the adaptive position to install according to actual requirements; if the locking assembly is loosened due to long time and can not be maintained, maintenance personnel can detach the locking assembly for replacement.
Preferably, waist-shaped holes are uniformly distributed in the closed end of the third sliding groove, and the two ends of one side of the opening of the U-shaped rod penetrate through the waist-shaped holes and are locked through the locking parts.
Through adopting above-mentioned technical scheme, the position of U type pole at the crossbeam is also adjustable, and constructor can select suitable waist shape hole according to actual need, makes supplementary fixed subassembly adaptation in locking Assembly's mounted position to supplementary fixed subassembly also can be torn open and take off, is convenient for maintain and maintain.
Preferably, the closed end of the U-shaped rod is provided with threaded through holes at equal intervals along the axis of the rod, the fixing piece penetrates through the threaded through holes, and the fixing piece comprises a butterfly bolt and a cushion arranged at the end part of the butterfly bolt.
Through adopting above-mentioned technical scheme, twist and move the butterfly bolt and can make it and pipeline butt, play supplementary fixed effect to the pipeline, the cushion can prevent that the surface of pipeline from receiving wearing and tearing.
Preferably, the stake body is equipped with auxiliary stay subassembly, auxiliary stay subassembly is including establishing the lead screw that draws to one side in the first spout both sides of stand, draws the lead screw to one side and includes two lead screws that are used for respectively being connected with the stand and draw the base and connect two to one side that draw the base to one side that are connected with the roof of piping lane.
Through adopting above-mentioned technical scheme, draw the lead screw to one side and can resist the tensile force, avoid the stake body to produce easily and rock.
Preferably, the auxiliary support assembly further comprises a support seat for connection with the top wall of the pipe gallery, the support seat being provided at the top end of the upright.
Through adopting above-mentioned technical scheme, the holistic steadiness of stake body has further been strengthened to the supporting seat.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the auxiliary fixing component can play an auxiliary fixing role on the pipeline when the locking component can not lock and fasten the pipeline due to looseness for a long time, and the pipeline is prevented from directly moving when being vibrated and even falling off from the pipe gallery bracket, so that adverse effects of mutual falling of the pipelines and leakage of substances in the pipeline are avoided;
2. the height-adjustable function of the cross beam can be realized by adjusting the position of the limiting plate on the upright post, and constructors can select the adaptive height according to actual needs during installation, so that the practicability of the construction support with the auxiliary fixing function for the urban pipe gallery is enhanced;
3. through setting up the auxiliary stay subassembly, strengthened the holistic steadiness of stake body.
Drawings
FIG. 1 is a schematic diagram of the overall structure of an embodiment of the present application;
FIG. 2 is an enlarged view of section H of FIG. 1;
FIG. 3 is a schematic structural view at a cross member in the embodiment;
FIG. 4 is a schematic structural view of an auxiliary support assembly according to an embodiment;
fig. 5 is a schematic view showing the support member and the bracket body in the embodiment.
Description of reference numerals: 1. a stent body; 11. a column; 111. a limiting plate; 112. a first T-bolt; 113. a first nut; 114. a first chute; 12. a cross beam; 121. a second chute; 122. a third chute; 1221. a waist-shaped hole; 1222. locking the nut; 2. A locking assembly; 21. a U-shaped plate; 211. a base; 212. a second T-bolt; 213. a second nut; 22. locking the hoop; 3. an auxiliary fixing component; 31. a U-shaped rod; 32. a fixing member; 321. a butterfly bolt; 322. a soft cushion; 4. an auxiliary support assembly; 41. a diagonal lead screw; 42. and (4) supporting the base.
Detailed Description
The present application is described in further detail below with reference to figures 1-5.
The embodiment of the application discloses city piping lane is with construction support that has supplementary fixed function. Referring to fig. 1, a city piping lane is with construction support that has supplementary fixed function includes stake body 1, is provided with on stake body 1 to be used for locking fixed locking Assembly 2 of pipeline locking and the supplementary fixed subassembly 3 that is used for fixed pipeline, supplementary fixed subassembly 3 sets up side by side along the pipeline axis with locking Assembly 2. Referring to fig. 2, the auxiliary fixing assembly 3 includes a U-shaped rod 31 disposed on the bracket body 1 and a fixing member 32 disposed on the U-shaped rod 31 for abutting against the pipeline.
If locking Assembly 2 is not hard up because of the age, when unable fastening the pipeline lock, the mounting 32 among the supplementary fixed subassembly 3 supports and leans on the pipeline, and mounting 32 can also play supplementary fixed effect to the pipeline, prevents that the pipeline from directly taking place the drunkenness when the pipeline receives the vibration, even falls down from the support. When maintenance personnel overhauls periodically, maintenance personnel maintain or change locking Assembly 2 that has become flexible again, supplementary fixed subassembly 3 has striven for abundant time for maintenance personnel's maintenance, has avoided droing each other between the pipeline, the bad consequence of intraductal material leakage.
Referring to fig. 1, the bracket body 1 includes two parallel upright posts 11 and a cross beam 12 disposed between the two parallel upright posts 11, and two ends of the cross beam 12 are detachably connected to the two upright posts 11 respectively: the stand 11 is equipped with first spout 114, and first spout 114 between the coexistence post 11 sets up in opposite directions, and in this embodiment, the stand 11 can adopt C shaped steel, and the type groove of C shaped steel is first spout 114 promptly, is provided with respectively on the two stands 11 to be used for carrying out spacing locating part to crossbeam 12, and the locating part includes two gliding limiting plate 111 of vertical direction of stand 11 and is used for the retaining member of limiting plate 111 location. The locking member comprises a first T-shaped bolt 112 positioned in the first sliding groove 114 and a first nut 113 matched with the first T-shaped bolt 112, and the first T-shaped bolt 112 penetrates through the limiting plate 111 to be in threaded connection with the first T-shaped bolt 112. In order to prevent the retainer plates 111 from rotating around the first T-bolt 112, two first T-bolts 112 are provided on one retainer plate 111 in the embodiment. The two ends of the beam 12 are respectively inserted into the groove of the upright post 11, and the beam 12 is located between the two limit plates 111.
When the pipe rack is installed, the bottom ends of the two vertical columns 11 are pre-buried into the bottom surface of the pipe rack, and then the matched cross beams 12 are selected. The height-adjustable function of the beam 12 can be realized by adjusting the position of the limiting plate 111 on the upright post 11, and the height of the adaptive part can be selected according to actual needs when the construction personnel are installed, so that the practicability of the construction support with the auxiliary fixing function for the urban pipe gallery is enhanced.
Referring to fig. 2, the cross beam 12 is provided with a second slide groove 121 for mounting the locking assembly 2 and a third slide groove 122 for mounting the auxiliary fixing assembly 3 side by side along the axis of the pipeline. The crossbeam can adopt two C shaped steel welded fastening side by side, and the type groove of two C shaped steel is second spout 121 and third spout 122 promptly. The locking assembly 2 comprises a mounting seat arranged on the top side of the cross beam 12 and a locking hoop 22 fixed on the top side of the mounting seat in a welding mode, and the locking hoop 22 is used for locking and fixing the pipeline. The mounting base comprises a U-shaped plate 21 for supporting the locking hoop 22, and two bases 211 are formed by extending the end parts of the two ends of the U-shaped plate 21 away from each other along the length direction of the cross beam 12, wherein the bases 211 are connected with the cross beam 12 through second T-shaped bolts 212 positioned in the second sliding grooves 121 and are locked through second nuts 213.
The position of the locking assembly 2 on the cross beam 12 is adjustable, and constructors can select the adaptive position to install according to actual needs. If the locking assembly 2 is loosened due to long time and the maintenance is impossible, the maintenance personnel can detach the locking assembly 2 for replacement.
Referring to fig. 3, waist-shaped holes 1221 are uniformly distributed at the closed end of the third chute 122, and both ends of the open side of the U-shaped rod 31 pass through the waist-shaped holes 1221 and are locked by the locking member. The locking piece can be selected from a locking nut 1222, and the two ends of the U-shaped rod 31 are provided with external thread sections corresponding to the locking nut 1222. The locking nut 1222 abuts against the bottom surface of the closed end of the third chute 122 when locking the U-shaped bar. The U-shaped bar 31 can pass through the waist-shaped holes 1221 at different positions and can slide a short distance within the waist-shaped holes 1221.
The lock nut 1222 of the U-shaped rod 31 is much larger than the fastener used for the locking hoop 22, and the thread of the thread has higher strength, so it is not easy to be rusted compared with the locking hoop 22. The position of the U-shaped rod 31 on the cross beam 12 is also adjustable, a constructor can select a proper waist-shaped hole 1221 according to actual needs, so that the auxiliary fixing component 3 is adapted to the installation position of the locking component 2, and the auxiliary fixing component 3 can be detached and taken down, thereby being convenient for maintenance.
Referring to fig. 4, the closed end of the U-shaped rod 31 is provided with threaded through holes at equal intervals along the axis of the rod, and in this embodiment, five threaded through holes are provided in the U-shaped rod 31. The fixing part 32 penetrates through the threaded through hole, the fixing part 32 comprises a butterfly bolt 321 and a cushion 322 arranged at the end part of the butterfly bolt 321, the cushion 322 is preferably made of a composite rubber material with high hardness and strength and good corrosion resistance, the cushion 322 can be sleeved at the end part of the butterfly bolt 321 and is bonded and fixed by structural adhesive, and the cushion 322 can prevent the surface of the pipeline from being abraded. When the pipe is mounted, the butterfly bolt 321 is screwed so that its end portion abuts against the pipe, thereby fixing the pipe.
Referring to fig. 5, the bracket body 1 is provided with the auxiliary supporting component 4, the auxiliary supporting component 4 is used for auxiliary supporting and fixing of the supporting bracket, the auxiliary supporting component 4 comprises oblique pull screws 41 arranged on two sides of the first sliding groove 114 of the upright post 11, and the oblique pull screws 41 comprise two oblique pull bases respectively used for being connected with the upright post 11 and being connected with the top wall of the pipe gallery and screws used for connecting the two oblique pull bases. The inclined lead screw 41 can resist the tensile force, and the bracket body 1 is prevented from shaking easily.
The auxiliary support assembly 4 further comprises a support seat 42 for connection with the top wall of the pipe gallery, the support seat 42 being provided at the top end of the upright 11. The supporting seat 42 is a square shell sleeved on the top end of the upright post 11, one end of the supporting seat 42 is opened, the other end is closed, and the closed end of the supporting seat 42 is abutted against the pipe gallery during installation and is connected with the pipe gallery through a connecting bolt. The supporting seat 42 connects the support body 1 with the top surface of the pipe gallery, further enhancing the overall stability of the support body 1.
The implementation principle of the embodiment is as follows: during installation, the bottom ends of the two vertical columns 11 are pre-buried into the top surface of the pipe gallery, the supporting seat 42 is connected with the top surface of the pipe gallery, one end of the diagonal lead screw 41 is connected with the vertical column 11, the other end of the diagonal lead screw is connected with the top surface of the pipe gallery through a bolt, and then the adaptive cross beam 12 is selected to keep the overall stability of the support body 1; selecting a proper height of the cross beam 12 by adjusting the position of the limiting plate 111 on the upright post 11, installing a locking component 2 at a proper position of the second sliding groove 121, locking the pipeline by using the locking component 2 after erecting the pipeline, installing an auxiliary fixing component 3 at a corresponding position of the third sliding groove 122, screwing the fixing component 32 to enable the fixing component to be abutted against the pipeline, and fixing the pipeline in an auxiliary manner; if locking Assembly 2 becomes flexible because of the age, when unable to fasten the pipeline lock, mounting 32 among the supplementary fixed subassembly 3 supports and leans on the pipeline, and mounting 32 can also play supplementary fixed effect to the pipeline, prevents that the pipeline from directly taking place the drunkenness, even falls down from the support to drop each other between the pipeline, the bad consequence of intraductal material leakage has been avoided.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a city piping lane is with construction support that has supplementary fixed function, includes stake body (1), be provided with on stake body (1) and be used for locking fixed locking Assembly (2), its characterized in that with the pipeline: the pipeline fixing support is characterized in that an auxiliary fixing component (3) used for fixing a pipeline is arranged on the support body (1), the auxiliary fixing component (3) and the locking component (2) are arranged side by side along the axis of the pipeline, and the auxiliary fixing component (3) comprises a U-shaped rod (31) arranged on the support body (1) and a fixing part (32) arranged on the U-shaped rod (31) and used for being abutted to the pipeline.
2. The construction support with the auxiliary fixing function for the urban pipe gallery according to claim 1, is characterized in that: the support body (1) comprises two parallel upright columns (11) and a cross beam (12) arranged between the two parallel upright columns (11), and two ends of the cross beam (12) are detachably connected with the two upright columns (11) respectively.
3. The construction support with the auxiliary fixing function for the urban pipe gallery according to claim 2, is characterized in that: stand (11) are equipped with first spout (114), and first spout (114) between coexistence post (11) set up in opposite directions, are provided with respectively on two stands (11) and are used for carrying out spacing locating part to crossbeam (12), the locating part includes that two can follow the gliding limiting plate (111) of stand (11) vertical direction and be used for the retaining member of limiting plate (111) location, the tip of crossbeam (12) is located between two limiting plates (111).
4. The construction support with the auxiliary fixing function for the urban pipe gallery according to claim 3, is characterized in that: crossbeam (12) are equipped with second spout (121) that are used for installing locking Assembly (2) and third spout (122) that are used for installing supplementary fixed subassembly (3) side by side along the pipeline axis, locking Assembly (2) are including setting up the mount pad on crossbeam (12) top side and fixing locking staple bolt (22) on the mount pad top side.
5. The construction support with the auxiliary fixing function for the urban pipe gallery according to claim 4, is characterized in that: the blind end equipartition of third spout (122) has waist shape hole (1221), waist shape hole (1221) and through retaining member locking are passed at the both ends of U type pole (31) opening one side.
6. The construction support with the auxiliary fixing function for the urban pipe gallery according to claim 5, is characterized in that: the closed end of the U-shaped rod (31) is provided with threaded through holes at equal intervals along the axis of the rod part, the fixing piece (32) penetrates through the threaded through holes, and the fixing piece (32) comprises a butterfly bolt (321) and a cushion (322) arranged at the end part of the butterfly bolt (321).
7. The construction support with the auxiliary fixing function for the urban pipe gallery according to claim 1, is characterized in that: the support body (1) is equipped with auxiliary stay subassembly (4), auxiliary stay subassembly (4) are including establishing oblique lead screw (41) that draw in first spout (114) both sides of stand (11), draw lead screw (41) to one side and include that two are used for respectively being connected with stand (11) and the lead screw of drawing the base to one side and connecting two oblique lead bases that draw the base to one side of being connected with the roof of piping lane.
8. The construction bracket with the auxiliary fixing function for the urban pipe gallery according to claim 7, is characterized in that: the auxiliary supporting assembly (4) further comprises a supporting seat (42) connected with the top wall of the pipe gallery, and the supporting seat (42) is arranged at the top end of the upright post (11).
CN202021145157.0U 2020-06-19 2020-06-19 City piping lane is with construction support that has supplementary fixed function Active CN212509819U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021145157.0U CN212509819U (en) 2020-06-19 2020-06-19 City piping lane is with construction support that has supplementary fixed function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021145157.0U CN212509819U (en) 2020-06-19 2020-06-19 City piping lane is with construction support that has supplementary fixed function

Publications (1)

Publication Number Publication Date
CN212509819U true CN212509819U (en) 2021-02-09

Family

ID=74388335

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021145157.0U Active CN212509819U (en) 2020-06-19 2020-06-19 City piping lane is with construction support that has supplementary fixed function

Country Status (1)

Country Link
CN (1) CN212509819U (en)

Similar Documents

Publication Publication Date Title
US20110272367A1 (en) Device for supporting solar modules
CN213897557U (en) Reinforced steel structure mounted in multiple ways
US11088654B2 (en) Dual pile cap
JP6363829B2 (en) Support stand for a planar article such as a solar panel and its support position adjusting member
CN212509819U (en) City piping lane is with construction support that has supplementary fixed function
CN210002595U (en) harmonious mass damper and girder steel connecting device
CN206530077U (en) A kind of support frame
JP2008214916A (en) Earthquake resisting floor structure of indoor arena
CN204057560U (en) Be attached to attached wall connection structure in the jacking system of section
CN211950515U (en) Two lining reinforcing bar positioning fixture in tunnel
CN109898680B (en) Connecting device and assembling method for tuned mass damper and steel beam
CN106704333B (en) Bolt mounting structure and the top drive cable saddle rack for using the bolt mounting structure
CN211036680U (en) Bracket for high pier variable-height curve continuous steel truss girder main pier
CN216714016U (en) Make things convenient for integration tower room structure of dismouting
CN104481032B (en) One nuclear power plant body of wall hanger and construction method thereof
CN220377903U (en) Temporary protection device for roof
CN106571775A (en) Combiner box support and combiner box
CN210530401U (en) High-strength steel supporting structure system
CN115075615B (en) Pedestrian up-down passage with retaining wall connecting structure and construction method thereof
CN219774265U (en) Tower center pillar
CN217634274U (en) Quick-mounting combined pipeline anti-seismic support
CN217076777U (en) Tower crane attachment system for frame structure
CN218667186U (en) Bracket structure for 0 # block of high-pier large-span continuous rigid frame bridge
CN211473290U (en) Join in marriage portable insulating scaffold frame in transformer district
CN217711115U (en) Beam column connecting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant