CN212477593U - Temporary water retaining device for hydraulic engineering construction - Google Patents

Temporary water retaining device for hydraulic engineering construction Download PDF

Info

Publication number
CN212477593U
CN212477593U CN202020738550.4U CN202020738550U CN212477593U CN 212477593 U CN212477593 U CN 212477593U CN 202020738550 U CN202020738550 U CN 202020738550U CN 212477593 U CN212477593 U CN 212477593U
Authority
CN
China
Prior art keywords
mainboard
water retaining
hydraulic engineering
retaining device
threaded rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020738550.4U
Other languages
Chinese (zh)
Inventor
杨勇
邵明学
赵田雨
栾荣伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020738550.4U priority Critical patent/CN212477593U/en
Application granted granted Critical
Publication of CN212477593U publication Critical patent/CN212477593U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Barrages (AREA)

Abstract

The utility model provides a hydraulic engineering construction is with interim manger plate device relates to hydraulic engineering technical field. This water conservancy project construction is with interim water retaining device, including mounting bracket and mainboard, the mounting bracket is located the place ahead of mainboard, and the upper surface of mainboard articulates there are two dwangs, and the one side that the mainboard was kept away from to two dwangs all is articulated with the front of mainboard, and the inside of mainboard is well accuse structure, and the side inner wall all slides about the mainboard and runs through there is the subplate, and the interior bottom wall of mainboard is located to rotate between two subplates and pegs graft there is two-way threaded rod. This water conservancy project construction is with interim water retaining device through setting up two-way threaded rod, thread bush, hinge bar and subplate, has reached the width that changes the device and has carried out the effect of shutoff to the breach, has solved the breach and has slightly greater than interim board sometimes, but can not place the interim water retaining plate of second, and this just causes and can't carry out inseparable shutoff to the breach, still needs other devices to carry out the problem of filling.

Description

Temporary water retaining device for hydraulic engineering construction
Technical Field
The utility model relates to a hydraulic engineering technical field specifically is a hydraulic engineering construction is with interim water retaining device.
Background
Hydraulic engineering is an engineering constructed for controlling and allocating surface water and underground water in the nature to achieve the purposes of removing harm and benefiting, different types of hydraulic buildings such as dams, water gates, water inlets, channels, transition tanks, rafts, fishways and the like need to be constructed for the hydraulic engineering so as to achieve the aims, and temporary water baffles are sometimes used for temporarily blocking partial gaps as temporary water retaining devices in the hydraulic engineering construction process.
The existing temporary water retaining device is generally fixed in width, but a gap is sometimes slightly larger than a temporary plate, but a second temporary water retaining plate cannot be placed, so that the gap cannot be tightly sealed, and other devices are required to be filled.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The utility model provides a not enough to prior art, the utility model provides a water conservancy project construction is with interim water retaining device has solved the breach and has slightly been greater than interim board sometimes, but can not place the interim water retaining plate of second, and this just causes and can't carry out inseparable shutoff to the breach, still needs other devices to carry out the problem of filling.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a hydraulic engineering construction is with interim water retaining device, including mounting bracket and mainboard, the mounting bracket is located the place ahead of mainboard, the upper surface of mainboard articulates there are two dwangs, the one side that the mainboard was kept away from to two dwangs all is articulated with the front of mainboard, the inside of mainboard is well accuse structure, the side inner wall all slides about the mainboard and runs through there is the subplate, the interior diapire of mainboard is located to rotate between two subplates and pegs graft and has two-way threaded rod, the interior roof that slides and runs through the mainboard in the upper end of two-way threaded rod, the inside setting of mainboard is located and is provided with two thread sleeves between two subplates, the surface at two-way threaded rod is cup jointed to the equal screw thread of two thread sleeves, the circumference side of two thread sleeves all articulates there are two hinge bars, the one end that two thread sleeves.
The equal fixedly connected with of bottom surface four corners department of mounting bracket well pole, the below of mounting bracket is provided with worker's word board, the four corners of worker's word board slides respectively and runs through the one side that is close to each other of four well poles, the upper surface of worker's word board rotates and pegs graft threaded shaft, the upper end screw thread of threaded shaft runs through the bottom surface of mounting bracket, the inside below that is located worker's word board of four well poles all is provided with the removal structure, peg graft in the bottom surface of worker's word board all is rotated to the upper end of four removal structures, the left and right sides of mounting bracket all articulates there is the bracing piece, two stop collars of the back fixedly connected with of mainboard, the inside of inlaying at the stop collar is rotated respectively to the upper end of two bracing pieces, the fixed cover of one end that the threaded shaft.
Preferably, the surfaces, far away from each other, of the two auxiliary plates are fixedly connected with inserting plates, and the two inserting plates are triangular.
Preferably, the bottom surfaces of the four hollow rods are fixedly connected with the barb plates, and the lower ends of the four moving structures respectively penetrate through the upper surfaces of the four barb plates in a sliding mode.
Preferably, the upper surface of the mounting rack is fixedly connected with a protective ring, and the adjusting handle is located inside the protective ring.
Preferably, the two rotating rods are both L-shaped, and are symmetrically distributed on the left side and the right side of the threaded shaft along the axis of the threaded shaft.
Preferably, the two auxiliary plates are positioned on the same plane, and the two auxiliary plates are symmetrically distributed on the left side and the right side of the bidirectional threaded rod along the axis of the bidirectional threaded rod.
(III) advantageous effects
The utility model provides a hydraulic engineering construction is with interim water retaining device. The method has the following beneficial effects:
1. this water conservancy project construction is with interim water retaining device, through setting up two-way threaded rod, the thread bush, hinge bar and subplate, when the size of breach slightly is greater than the mainboard, it rotates to rotate the handle and drives two-way threaded rod, two thread bushes are close to each other through meshing with two-way threaded rod, then drive the hinge bar and rotate, thereby promote two subplates and keep away from each other, the width that has reached the change gear carries out the effect of shutoff to the breach, it slightly is greater than the interim board sometimes to have solved the breach, but can not place the interim water retaining plate of second, this just causes and can't carry out inseparable shutoff to the breach, still need other devices to carry out the problem of filling.
2. This water conservancy project construction is with interim watertight fittings, through setting up the barb board, when breakwater and plugboard, the in-process of keeping away from each other at two subplates drives two plugboards and removes, thereby inside pegging graft the breach with the plugboard, carry out the in-process of work at the breakwater, the device atress has the trend of backward movement, thereby the time barb board nail goes into the bottom surface darker, the effect of the stability of the device that has increased has been reached, the problem that the breakwater can not be stabilized to the emergence removal cause after bearing the water pressure has been solved.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the connection between the I-shaped plate and the moving structure of the present invention;
FIG. 3 is a schematic view of the connection between the adjusting handle and the threaded shaft of the present invention;
fig. 4 is a schematic view of the connection between the two-way threaded shaft and the threaded sleeve of the present invention.
Wherein, 1 mounting bracket, 2 mainboards, 3 dwang, 4 subplates, 5 two-way threaded rods, 6 thread bush, 7 articulated rod, 8 hollow rod, 9I board, 10 threaded shaft, 11 mobile structure, 12 bracing pieces, 13 stop collar, 14 regulation handles, 15 twist stems, 16 plugboards, 17 barb boards, 18 protective rings.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The embodiment of the utility model provides a temporary water retaining device for hydraulic engineering construction, as shown in figures 1-4, comprising a mounting frame 1 and a main board 2, wherein the mounting frame 1 is positioned in front of the main board 2, the upper surface of the main board 2 is hinged with two rotating rods 3, the two rotating rods 3 are both L-shaped, the two rotating rods 3 are symmetrically distributed on the left and right sides of the threaded shaft 10 by the axis of the threaded shaft 10, one surfaces of the two rotating rods 3 far away from the main board 2 are both hinged with the front surface of the main board 2, the interior of the main board 2 is a central control structure, the inner walls of the left and right sides of the main board 2 are both slidably penetrated with auxiliary plates 4, one surfaces of the two auxiliary plates 4 far away from each other are both fixedly connected with inserting plates 16, the two inserting plates 16 are both triangular, the inner bottom wall of the main board 2 is positioned between the two auxiliary plates 4 and rotatably inserted with a bidirectional threaded rod 5, the two auxiliary plates 4 are positioned on the same plane, the upper end of two-way threaded rod 5 slides and runs through mainboard 2's interior roof, the inside setting of mainboard 2 is located and is provided with two thread bush 6 between two subplates 4, two equal screw-thread cup joints at two-way threaded rod 5's surface of 6, can drive thread bush 6 when two-way threaded rod 5 rotates and keep away from each other or be close to each other, the circumference side of two thread bush 6 all articulates there are two articulated rods 7, four articulated rods 7 keep away from the one end of two thread bush 6 respectively and articulate with the one side that two subplates 4 are close to each other.
The four corners of the bottom surface of the mounting frame 1 are fixedly connected with hollow rods 8, an I-shaped plate 9 is arranged below the mounting frame 1, the four corners of the I-shaped plate 9 respectively penetrate through the mutually close surfaces of the four hollow rods 8 in a sliding manner, a threaded shaft 10 is rotatably inserted into the upper surface of the I-shaped plate 9, the upper end threads of the threaded shaft 10 penetrate through the bottom surface of the mounting frame 1, moving structures 11 are arranged inside the four hollow rods 8 and below the I-shaped plate 9, the upper ends of the four moving structures 11 are rotatably inserted into the bottom surface of the I-shaped plate 9, barb plates 17 are respectively and fixedly connected with the bottom surfaces of the four hollow rods 8, the lower ends of the four moving structures 11 respectively penetrate through the upper surfaces of the four barb plates 17 in a sliding manner, the barb plates 17 and the insertion plates 16 are arranged to improve the stability of the device, the device is prevented from moving when being impacted by water, the left side and the right side of the, two stop collars 13 of back fixedly connected with of mainboard 2, the upper end of bracing piece 12 is spherical, the inside of inlaying at stop collar 13 is rotated respectively to the upper end of two bracing pieces 12, threaded shaft 10 is located the fixed cover of one end of mounting bracket 1 top and has connect regulation handle 14, the last fixed surface of mounting bracket 1 is connected with protective ring 18, regulation handle 14 is located the inside of protective ring 18, set up protective ring 18 and prevent that mainboard 2 from rotating with regulation handle 14 contact when 1 top of mounting bracket, the fixed cover of one end that two-way threaded rod 5 is located mainboard 2 top has connect turning handle 15.
Theory of operation, when the size of breach slightly is greater than mainboard 2, it rotates change handle 15 and drives two-way threaded rod 5 and rotates, two thread bush 6 are through being close to each other with 5 meshing of two-way threaded rod, then drive hinge bar 7 and rotate, thereby promote two subplates 4 and keep away from each other, change means's width carries out the shutoff to the breach, when needing to receive up mainboard 2, it drives in subplate 4 income mainboard 2 to rotate change handle 15, then rotation bracing piece 12 lifts off from mounting bracket 1, then rotate regulation handle 14 and drive threaded shaft 10 and mounting bracket 1 meshing, then drive I board 9 and make mobile structure 11 remove barb board 17 below, then rotate mainboard 2 and rotate mounting bracket 1 top, be convenient for remove mainboard 2.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a hydraulic engineering construction is with interim water retaining device, includes mounting bracket (1) and mainboard (2), its characterized in that: mounting bracket (1) is located the place ahead of mainboard (2), the upper surface of mainboard (2) articulates there are two dwang (3), the one side that mainboard (2) were kept away from in two dwang (3) all is articulated with the front of mainboard (2), the inside of mainboard (2) is well accuse structure, mainboard (2) about the side inner wall all slide to run through subplate (4), the interior bottom wall of mainboard (2) is located to rotate between two subplates (4) and is pegged graft and have two-way threaded rod (5), the interior roof that mainboard (2) were run through in the upper end slip of two-way threaded rod (5), the inside setting of mainboard (2) is located to be provided with two thread bush (6) between two subplates (4), two equal screw cup joints of thread bush (6) are at the surface of two-way threaded rod (5), the circumference side of two thread bush (6) all articulates there are two hinge rod (7), four one end that keep away from two thread bush (6) respectively leans on each other with two subplates (4) is leaned The near side is hinged;
the four corners of the bottom surface of the mounting rack (1) are fixedly connected with hollow rods (8), an I-shaped plate (9) is arranged below the mounting rack (1), the four corners of the I-shaped plate (9) respectively penetrate through the mutually adjacent surfaces of the four hollow rods (8) in a sliding manner, a threaded shaft (10) is rotatably inserted into the upper surface of the I-shaped plate (9), upper end threads of the threaded shaft (10) penetrate through the bottom surface of the mounting rack (1), moving structures (11) are arranged inside the four hollow rods (8) and below the I-shaped plate (9), the upper ends of the four moving structures (11) are rotatably inserted into the bottom surface of the I-shaped plate (9), supporting rods (12) are hinged to the left side and the right side of the mounting rack (1), two limiting sleeves (13) are fixedly connected to the back surface of the main board (2), the upper ends of the two supporting rods (12) are respectively rotatably embedded into the limiting sleeves (, the adjusting handle (14) is fixedly sleeved at one end of the threaded shaft (10) above the mounting frame (1), and the rotating handle (15) is fixedly sleeved at one end of the bidirectional threaded rod (5) above the main board (2).
2. The temporary water retaining device for the hydraulic engineering construction according to claim 1, is characterized in that: the surfaces, far away from each other, of the two auxiliary plates (4) are fixedly connected with inserting plates (16), and the two inserting plates (16) are triangular.
3. The temporary water retaining device for the hydraulic engineering construction according to claim 1, is characterized in that: the bottom surfaces of the four hollow rods (8) are fixedly connected with barb plates (17), and the lower ends of the four moving structures (11) respectively penetrate through the upper surfaces of the four barb plates (17) in a sliding mode.
4. The temporary water retaining device for the hydraulic engineering construction according to claim 1, is characterized in that: the upper surface of the mounting rack (1) is fixedly connected with a protective ring (18), and the adjusting handle (14) is located inside the protective ring (18).
5. The temporary water retaining device for the hydraulic engineering construction according to claim 1, is characterized in that: the two rotating rods (3) are both L-shaped, and the two rotating rods (3) are symmetrically arranged on the left side and the right side of the threaded shaft (10) by the axis of the threaded shaft (10).
6. The temporary water retaining device for the hydraulic engineering construction according to claim 1, is characterized in that: the two auxiliary plates (4) are positioned on the same plane, and the two auxiliary plates (4) are symmetrically distributed on the left side and the right side of the bidirectional threaded rod (5) by the axis of the bidirectional threaded rod (5).
CN202020738550.4U 2020-05-07 2020-05-07 Temporary water retaining device for hydraulic engineering construction Expired - Fee Related CN212477593U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020738550.4U CN212477593U (en) 2020-05-07 2020-05-07 Temporary water retaining device for hydraulic engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020738550.4U CN212477593U (en) 2020-05-07 2020-05-07 Temporary water retaining device for hydraulic engineering construction

Publications (1)

Publication Number Publication Date
CN212477593U true CN212477593U (en) 2021-02-05

Family

ID=74454630

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020738550.4U Expired - Fee Related CN212477593U (en) 2020-05-07 2020-05-07 Temporary water retaining device for hydraulic engineering construction

Country Status (1)

Country Link
CN (1) CN212477593U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115807439A (en) * 2022-12-28 2023-03-17 连云港市金河水利工程建设监理有限公司 Water stop device for hydraulic engineering construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115807439A (en) * 2022-12-28 2023-03-17 连云港市金河水利工程建设监理有限公司 Water stop device for hydraulic engineering construction
CN115807439B (en) * 2022-12-28 2023-08-22 连云港市金河水利工程建设监理有限公司 Hydraulic engineering construction sealing device

Similar Documents

Publication Publication Date Title
CN209760253U (en) Foundation pit supporting structure for excavation of foundation pit
CN212477593U (en) Temporary water retaining device for hydraulic engineering construction
CN205530427U (en) Clearance river silt's marine device
CN210461936U (en) Municipal water supply pipeline strutting arrangement
CN209425655U (en) Feed device is forced in the damping of shrub wood chipping equipment spring
CN215367312U (en) Foundation pit supporting device
CN109404682A (en) A kind of mining heading equipment support frame
CN219869337U (en) Blast hole plugging device for blasting of earth and stone engineering
CN218818629U (en) Hydraulic engineering pipeline fixing device
CN214738190U (en) Foundation pit drainage structure
CN208427489U (en) A kind of concrete storage conveyance conduit cleaning device
CN215252671U (en) Water conservancy project construction stagnant water prevention of seepage constructional device
CN213646689U (en) Clamping device is used in processing of curtain right angle aluminium alloy
CN114645672A (en) Rotary drilling rock drilling device
CN211872875U (en) Hydraulic engineering slope bearing structure
CN213923830U (en) Pipe burying device for hydraulic and hydroelectric engineering
CN212052774U (en) Hydraulic engineering construction cementer
CN109236340B (en) Multi-angle support rod for tunnel support
CN221255510U (en) Ecological slope protection reinforcing apparatus
CN208359532U (en) It is a kind of to roll vacuum evacuation device for CIPP hose material
CN215294293U (en) Auxiliary device for underground operation supervision
CN213359616U (en) Town road foundation ditch safety device
CN221752376U (en) Rapid defoaming device for rock slice paint
CN213896984U (en) Waterproof structure of building engineering
CN218758394U (en) Rain-proof device for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210205

Termination date: 20210507

CF01 Termination of patent right due to non-payment of annual fee