CN212452313U - Bridge construction supporting equipment in field of bridge engineering - Google Patents

Bridge construction supporting equipment in field of bridge engineering Download PDF

Info

Publication number
CN212452313U
CN212452313U CN202021008150.4U CN202021008150U CN212452313U CN 212452313 U CN212452313 U CN 212452313U CN 202021008150 U CN202021008150 U CN 202021008150U CN 212452313 U CN212452313 U CN 212452313U
Authority
CN
China
Prior art keywords
plate
supporting
bridge
connecting plate
pmkd
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021008150.4U
Other languages
Chinese (zh)
Inventor
袁明冬
刘梅
尚树威
赵宗建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202021008150.4U priority Critical patent/CN212452313U/en
Application granted granted Critical
Publication of CN212452313U publication Critical patent/CN212452313U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a support equipment is used in bridge construction in bridge engineering field, be in including PMKD, setting PMKD upper end and bridge basis are in with fixed plate, the setting that the camber set up connecting plate, setting between fixed plate and the PMKD are in the supporting component and the even setting of connecting plate both sides are in mounting hole on the PMKD, the mounting hole sets up to the penetrability. The utility model relates to a bridge construction in bridge engineering field supports the bridge through the fixed plate with the support equipment, and is convenient for be connected fixed plate and PMKD through the connecting plate to be convenient for support the fixed plate through the connecting plate, and be convenient for through the effectual stability that the connecting plate supported the fixed plate that has improved of supporting component.

Description

Bridge construction supporting equipment in field of bridge engineering
Technical Field
The utility model relates to a relevant technical field specifically is a bridge construction in bridge engineering field is with supporting equipment.
Background
Bridge engineering refers to the working process of bridge surveying, designing, constructing, maintaining, detecting and the like, and the scientific and engineering technology for researching the process, and is a branch of civil engineering; the development of bridge engineering is mainly dependent on the need for transportation; the ancient bridge mainly takes pedestrians and livestock as traffic, the load is not large, the longitudinal slope of the bridge deck can be steeper, and even steps can be paved;
the inventor of the utility model finds that the supporting equipment for bridge construction in the prior art has simple structure and single use mode due to the design characteristics, is inconvenient for supporting the bridge foundation in the actual use process, and further reduces the efficiency of bridge construction, thereby being incapable of meeting various use requirements of the supporting equipment for bridge construction at present;
therefore, the supporting equipment for bridge construction in the field of bridge engineering is provided.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a support equipment is used in bridge construction in bridge engineering field aims at improving the support equipment is used in bridge construction among the prior art because the design characteristics of its own, and simple structure and using-way are single, in the use of reality, are not convenient for support the bridge basis, and then have reduced the efficiency to the bridge construction to can't satisfy the problem to the multiple user demand of support equipment is used in the bridge construction at present.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: a supporting device for bridge construction in the field of bridge engineering comprises a fixed base plate, a fixed plate, a connecting plate, supporting components and mounting holes, wherein the fixed plate is arranged at the upper end of the fixed base plate and is arranged at the same curvature as a bridge foundation;
as a preferable aspect of the present invention, the highest point of the radian of the fixing plate is set relative to the connecting plate, and the inner side of the fixing plate is set to be a smooth arc surface, so as to facilitate supporting the bridge foundation through the fixing plate, thereby effectively improving the stability of supporting the bridge foundation by the fixing plate;
as a preferable aspect of the present invention, one end of the connecting plate is fixedly connected to the lower end of the fixing plate, one end of the connecting plate is fixedly connected to the upper end of the fixing base plate, the upper end of the connecting plate and the fixing plate are arranged at the same curvature, and the connecting plate is arranged at the central position of the fixing plate, thereby effectively ensuring the stability of the connecting plate in connection with the fixing plate and the fixing base plate, and effectively ensuring the stability of the connecting plate in supporting the fixing plate;
as a preferable aspect of the present invention, the supporting component at each side includes a first supporting plate disposed at both ends of the connecting plate and a second supporting plate uniformly disposed at the middle position of the connecting plate, the inner side of the first supporting plate is fixedly connected to the connecting plate, and both ends of the first supporting plate are fixedly connected to the fixing plate and the fixing bottom plate, so as to fix both ends of the connecting plate through the first supporting plate, and effectively ensure the stability of the connecting plate supporting the fixing plate; the second backup pad sets up to three at least, and the distance between the adjacent second backup pad equals, the inboard of every second backup pad respectively with connecting plate fixed connection, and the lower extreme and the PMKD fixed connection of second backup pad, and then be convenient for support the intermediate position of connecting plate through the second backup pad, and then the effectual stability of having guaranteed that the connecting plate supports the fixed plate.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model has the characteristics of reasonable in design and easy operation, the utility model relates to a bridge construction in bridge engineering field is with support equipment includes PMKD, sets up PMKD upper end and the fixed plate, the setting that the same camber of bridge basis set up are in connecting plate, setting between fixed plate and the PMKD are in the supporting component and the even setting of connecting plate both sides are in mounting hole on the PMKD, the mounting hole sets up to the penetrability, and then is convenient for support the bridge through the fixed plate, and is convenient for be connected fixed plate and PMKD through the connecting plate to be convenient for support the fixed plate through the connecting plate, and be convenient for carry out the stability that supports to the fixed plate through the effectual improvement connecting plate of supporting component.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings that are required to be used in the embodiments will be briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present invention, and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to the drawings without inventive efforts.
Fig. 1 is a schematic structural diagram of an explosion diagram of the overall structure of the supporting equipment for bridge construction in the field of bridge engineering;
fig. 2 is a schematic structural view of another view angle of fig. 1 in the supporting device for bridge construction in the field of bridge engineering of the present invention;
fig. 3 is a schematic structural view of an overall structure of the supporting device for bridge construction in the field of bridge engineering of the present invention;
fig. 4 is a schematic structural diagram of the front view of fig. 3 in the supporting device for bridge construction in the field of bridge engineering.
In the figure: 1-fixed bottom plate, 10-mounting holes, 2-connecting plate, 31-first supporting plate, 32-second supporting plate and 4-fixed plate.
Detailed Description
To make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the drawings of the embodiments of the present invention are combined to clearly and completely describe the technical solutions of the embodiments of the present invention, and obviously, the described embodiments are some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention. Thus, the following detailed description of the embodiments of the present invention, presented in the accompanying drawings, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention.
Referring to fig. 1, fig. 2, fig. 3 and fig. 4, the present invention provides a technical solution: a supporting device for bridge construction in the field of bridge engineering comprises a fixed base plate 1, a fixed plate 4 which is arranged at the upper end of the fixed base plate 1 and is arranged at the same curvature as a bridge foundation, a connecting plate 2 which is arranged between the fixed plate 4 and the fixed base plate 1, supporting components which are arranged at two sides of the connecting plate 2 and mounting holes 10 which are uniformly arranged on the fixed base plate 1, wherein the mounting holes 10 are arranged to be through, so that the bridge is conveniently supported by the fixed plate 4, and the fixed plate 4 is conveniently connected with the fixed base plate 1 through the connecting plate 2, so that the fixed plate 4 is conveniently supported by the connecting plate 2, and the stability of the connecting plate 2 for supporting the fixed plate 4 is conveniently and effectively improved through the supporting components;
referring to fig. 1, 2, 3 and 4, the highest point of the radian of the fixing plate 4 is arranged relative to the connecting plate 2, and the inner side of the fixing plate 4 is provided with a smooth arc surface, so that the bridge foundation is conveniently supported by the fixing plate 4, and the stability of the fixing plate 4 for supporting the bridge foundation is effectively improved;
referring to fig. 1, 2, 3 and 4, one end of a connecting plate 2 is fixedly connected with the lower end of a fixing plate 4, one end of the connecting plate 2 is fixedly connected with the upper end of a fixing base plate 1, the upper end of the connecting plate 2 and the fixing plate 4 are arranged in the same curvature, and the connecting plate 2 is arranged at the center of the fixing plate 4, so that the stability of the connecting plate 2 respectively connected with the fixing plate 4 and the fixing base plate 1 is effectively ensured, and the stability of the connecting plate 2 supporting the fixing plate 4 is effectively ensured;
referring to fig. 1, 2, 3 and 4, the supporting assembly at each side includes first supporting plates 31 respectively disposed at two ends of the connecting plate 2 and second supporting plates 32 uniformly disposed at the middle position of the connecting plate 2, the inner sides of the first supporting plates 31 are respectively fixedly connected with the connecting plate 2, two ends of the first supporting plates 31 are respectively fixedly connected with the fixing plate 4 and the fixing base plate 1, so that two ends of the connecting plate 2 are conveniently fixed by the first supporting plates 31, and the stability of the connecting plate 2 supporting the fixing plate 4 is effectively ensured; second backup pad 32 sets up to three at least, and the distance between the adjacent second backup pad 32 equals, every second backup pad 32 inboard respectively with connecting plate 2 fixed connection, and the lower extreme and the PMKD 1 fixed connection of second backup pad 32, and then be convenient for support the intermediate position of connecting plate 2 through second backup pad 32, and then the effectual stability of having guaranteed that connecting plate 2 supports fixed plate 4.
The working principle is as follows: the utility model discloses a set up PMKD 1, the fixed plate 4 that sets up with the camber in the 1 upper end of PMKD and bridge basis, the connecting plate 2 of setting between fixed plate 4 and PMKD 1, the supporting component of setting in 2 both sides of connecting plate and the even mounting hole 10 of setting on PMKD 1, mounting hole 10 sets up to the penetrability, and then be convenient for support the bridge through fixed plate 4, and be convenient for be connected fixed plate 4 with PMKD 1 through connecting plate 2, thereby be convenient for support fixed plate 4 through connecting plate 2, and be convenient for through the effectual stability that has improved connecting plate 2 and carry out the support to fixed plate 4 of supporting component.
The device obtained through the design can basically meet the requirement of improving the supporting equipment for bridge construction in the prior art, and due to the design characteristics of the device, the structure is simple, the using mode is single, the supporting equipment is not convenient for supporting a bridge foundation in the actual using process, the efficiency of bridge construction is further reduced, the use of the problems of multiple using requirements of the supporting equipment for bridge construction at present cannot be met, the purpose of further improving the functions of the supporting equipment is further improved by a designer.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a support equipment is used in bridge construction in bridge engineering field which characterized in that: including PMKD (1), setting be in PMKD (1) upper end is in with fixed plate (4), the setting that the camber set up with the bridge basis connecting plate (2), the setting between fixed plate (4) and PMKD (1) are in the supporting component and the even setting of connecting plate (2) both sides are in mounting hole (10) on PMKD (1), mounting hole (10) set up to the penetrability.
2. The supporting device for bridge construction in the field of bridge engineering according to claim 1, wherein the highest point of the radian of the fixing plate (4) is arranged relative to the connecting plate (2), and the inner side of the fixing plate (4) is arranged to be a smooth arc surface.
3. The supporting device for bridge construction in the field of bridge engineering according to claim 2, wherein one end of the connecting plate (2) is fixedly connected with the lower end of the fixing plate (4), and one end of the connecting plate (2) is fixedly connected with the upper end of the fixing bottom plate (1).
4. The supporting apparatus for bridge construction in the field of bridge engineering according to claim 3, wherein the upper end of the connecting plate (2) is disposed at the same curvature as the fixing plate (4), and the connecting plate (2) is disposed at the center of the fixing plate (4).
5. The supporting device for bridge construction in the field of bridge engineering according to claim 4, wherein the supporting component at each side comprises a first supporting plate (31) and a second supporting plate (32), the first supporting plate (31) is respectively arranged at two ends of the connecting plate (2), the second supporting plate is uniformly arranged at the middle position of the connecting plate (2), the inner side of the first supporting plate (31) is respectively fixedly connected with the connecting plate (2), and two ends of the first supporting plate (31) are respectively fixedly connected with the fixing plate (4) and the fixing bottom plate (1).
6. The supporting equipment for bridge construction in the field of bridge engineering according to claim 5, wherein at least three second supporting plates (32) are provided, the distance between adjacent second supporting plates (32) is equal, the inner side of each second supporting plate (32) is fixedly connected with the connecting plate (2), and the lower end of each second supporting plate (32) is fixedly connected with the fixed bottom plate (1).
CN202021008150.4U 2020-06-04 2020-06-04 Bridge construction supporting equipment in field of bridge engineering Expired - Fee Related CN212452313U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021008150.4U CN212452313U (en) 2020-06-04 2020-06-04 Bridge construction supporting equipment in field of bridge engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021008150.4U CN212452313U (en) 2020-06-04 2020-06-04 Bridge construction supporting equipment in field of bridge engineering

Publications (1)

Publication Number Publication Date
CN212452313U true CN212452313U (en) 2021-02-02

Family

ID=74479006

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021008150.4U Expired - Fee Related CN212452313U (en) 2020-06-04 2020-06-04 Bridge construction supporting equipment in field of bridge engineering

Country Status (1)

Country Link
CN (1) CN212452313U (en)

Similar Documents

Publication Publication Date Title
CN103899004B (en) One is energy consumer stage by stage
CN205171994U (en) A stencil assembly for clear water concrete construction
CN212452313U (en) Bridge construction supporting equipment in field of bridge engineering
CN106906947A (en) A kind of spliced steel construction plate
CN108824923A (en) A kind of Double damping device amplifying device
CN208415290U (en) Outdoor substation's Steel Structure foundation construction structure
CN208563560U (en) The structural system of flatbed super high-rise building
CN203977274U (en) A kind of Truss Steel case beam
CN211174141U (en) Tunnel reinforcing device
CN208792856U (en) A kind of Double damping device amplifying device
CN207906215U (en) A kind of basis connection component
CN211850269U (en) High-strength floor support plate with reinforced stiffening ribs
CN212670850U (en) Assembled building supporting seat
CN205116859U (en) Modularization roofing communication tower
CN214885824U (en) Leveling-free prefabricated superposed beam supporting device
CN211848878U (en) Comprehensive shock-absorbing support for bridge
CN211715485U (en) Groove-shaped connecting sleeve of transmission mechanism of batching machine
CN208545679U (en) A kind of shared helideck in more buildings
CN217872091U (en) 220kV framework
CN217500697U (en) Keel connecting piece for assembled arc-shaped aluminum plate curtain wall
CN204370483U (en) A kind of for the building iron component in ground
CN103741841B (en) A kind of energy-dissipating and shock-absorbing double steel plate semi-girder wall and implementation method
CN217760046U (en) Building templates connects steelframe for civil engineering
CN216891820U (en) Assembled cement road surface connection structure
CN210217216U (en) Assembled building fixed knot constructs

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210202