CN212427171U - Steel column installation elevation quick adjustment device - Google Patents

Steel column installation elevation quick adjustment device Download PDF

Info

Publication number
CN212427171U
CN212427171U CN202020226247.6U CN202020226247U CN212427171U CN 212427171 U CN212427171 U CN 212427171U CN 202020226247 U CN202020226247 U CN 202020226247U CN 212427171 U CN212427171 U CN 212427171U
Authority
CN
China
Prior art keywords
steel column
elevation
parallels
installation
group
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020226247.6U
Other languages
Chinese (zh)
Inventor
王代发
刘建夫
郭立召
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN202020226247.6U priority Critical patent/CN212427171U/en
Application granted granted Critical
Publication of CN212427171U publication Critical patent/CN212427171U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a quick adjusting device of steel column installation elevation, including steel column and parallels group, parallels group sets up in the steel column bottom, and the thickness of parallels group equals the elevation of design installation and the difference of basic cup bottom surface elevation. By adopting the utility model, the sizing block group can be welded on the steel column base in advance, and is integrated with the steel column and then installed in the basic cup mouth structure, so that the sizing block group is in place once without secondary adjustment; meanwhile, the construction speed is accelerated, the mechanical and labor cost is saved, and the cost is reduced and the efficiency is improved.

Description

Steel column installation elevation quick adjustment device
Technical Field
The utility model relates to an elevation adjustment field particularly, relates to a steel column installation elevation quick adjustment device.
Background
At present, the column foundation of the industrial factory building almost adopts a cup mouth type, and a secondary grouting layer with the thickness of 50mm is reserved to facilitate the adjustment of the installation elevation of the column. Generally, when the installation elevation of the cup-rim type foundation steel column is adjusted, the elevation of the bottom of the foundation in the cup rim is measured in advance, then, sizing blocks with different thicknesses are placed on the bottom surface of the cup-rim foundation to adjust and level, and finally, the steel column is inserted into the cup rim.
By adopting the method, for each foundation, a constructor always needs to place an adjusting sizing block in the cup opening. Because the internal space of the cup opening is narrow and small, the steel column is easy to knock down or scratch and move the sizing block when being inserted into the cup opening, so that the sizing block needs to be adjusted again, unnecessary trouble is brought to installation, and the operation efficiency is reduced.
SUMMERY OF THE UTILITY MODEL
To above defect, the utility model provides a device of quick adjustment steel column installation elevation.
The utility model provides a technical scheme that its technical problem adopted as follows:
the utility model provides a quick adjusting device of steel column installation elevation, includes steel column and parallels group, and parallels group sets up in the steel column bottom, and the thickness of parallels group designs the elevation of installation and the difference of basic cup bottom surface elevation.
The adoption of the technical scheme has the advantages that the sizing block group with the calculated thickness can be welded on the steel column base on the ground in advance, and is installed in the basic cup rim structure after being integrated with the steel column, so that the sizing block group is in place once without secondary adjustment; meanwhile, the construction speed is accelerated, the mechanical and labor cost is saved, and the cost is reduced and the efficiency is improved.
Furthermore, the sizing block group consists of a plurality of sizing blocks,
further, the number of the sizing blocks is not more than 5.
Drawings
FIG. 1 is a schematic view of the present invention during installation;
FIG. 2 is an enlarged schematic view of the bottom of the steel column and the pad set of the present invention;
in the figure, 1, a cup mouth base; 2, steel columns; and 3, a sizing block group.
Detailed Description
The invention will be further described with reference to the accompanying drawings. It is to be understood that the above description is intended to illustrate and not to limit the invention.
Referring to fig. 1 and 2, a steel column installation elevation quick adjustment device is composed of a steel column 2 and a sizing block group 3 arranged at the bottom of the steel column 2. The thickness of the sizing block group 3 is equal to the difference value between the designed elevation of the corresponding steel column 2 in the base cup mouth and the corresponding elevation of the bottom surface of the base cup mouth 1. A plurality of sizing blocks form a sizing block group 3, and the number of sizing blocks is determined by the thickness of the sizing blocks and the total thickness of the sizing block group, and is usually not more than 5.
When the steel column is to be installed, the elevation and the axis deviation of the bottom surface of each basic cup opening are retested according to the basic installation center line, and the elevation data of the bottom surface of the corresponding basic cup opening 1 are recorded. And calculating the difference value between the designed elevation data and the corresponding elevation of the bottom surface of the basic cup opening 1, so as to determine the total thickness of the sizing block groups correspondingly arranged at the bottom of each steel column, and arranging the sizing block groups with proper sizes according to the total thickness, wherein the number of the sizing blocks contained in each sizing block group is not more than 5. And welding a certain number of sizing pads with proper sizes to the bottoms of the column feet of the corresponding steel columns to be installed to form a whole with the steel columns. And integrally hoisting the steel column by using a crane and inserting the steel column into the foundation cup mouth 1, and adjusting and fixing the steel column 2. And (5) the steel column is qualified through verification, the steel column is installed according to the designed elevation, and finally, the cup mouth is subjected to secondary grouting to finish the installation of the steel column.
By adopting the method, the installation speed is greatly increased, the installation efficiency is improved, and the mechanical and labor costs are saved.
The above description is only a few of the more detailed description of the invention. The person skilled in the art can make various modifications and variations within the scope of the inventive idea, which all belong to the protection scope of the invention.

Claims (3)

1. The utility model provides a quick adjusting device of steel column installation elevation, includes the steel column, its characterized in that still includes parallels group, and parallels group sets up in the steel column bottom, and parallels the thickness of parallels group and designs the elevation of installation and the difference value of basic cup bottom surface elevation, sets up the parallels group that the size is suitable according to parallels group's thickness, welds the parallels in the column base bottom of the corresponding steel column of installing, forms wholly with the steel column.
2. The steel column installation elevation quick adjustment device of claim 1, wherein the set of sizing blocks comprises a plurality of sizing blocks.
3. The steel column installation elevation quick adjustment device of claim 2, wherein the number of the sizing blocks is not more than 5.
CN202020226247.6U 2020-02-28 2020-02-28 Steel column installation elevation quick adjustment device Active CN212427171U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020226247.6U CN212427171U (en) 2020-02-28 2020-02-28 Steel column installation elevation quick adjustment device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020226247.6U CN212427171U (en) 2020-02-28 2020-02-28 Steel column installation elevation quick adjustment device

Publications (1)

Publication Number Publication Date
CN212427171U true CN212427171U (en) 2021-01-29

Family

ID=74276930

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020226247.6U Active CN212427171U (en) 2020-02-28 2020-02-28 Steel column installation elevation quick adjustment device

Country Status (1)

Country Link
CN (1) CN212427171U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114086593A (en) * 2021-11-26 2022-02-25 中冶(上海)钢结构科技有限公司 Method for quickly adjusting elevation of bottom of cup foundation steel column

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114086593A (en) * 2021-11-26 2022-02-25 中冶(上海)钢结构科技有限公司 Method for quickly adjusting elevation of bottom of cup foundation steel column

Similar Documents

Publication Publication Date Title
CN101831917B (en) Mounting construction method of liner plates during mounting large-scale precision equipment
CN106706416B (en) Test device for simulating basement bottom plate stress under action of pressurized water and application method
CN107806205B (en) Mounting structure and mounting method of lining-free steel dome
CN212427171U (en) Steel column installation elevation quick adjustment device
CN111451764B (en) Staggered installation method for lower furnace shell of hot blast stove and equipment in stove
CN106320193A (en) Method for leveling bridge support during replacement and new installation
CN115417290A (en) Steel lining module construction method, hoisting tool and limiting tool
CN110937075B (en) FPSO module and integrated installation process
CN106088756A (en) A kind of method of the cartridge type steel storage tank hydraulic pressure lift upside-down mounting based on BIM technology
CN102634616A (en) Blast furnace top flange jackscrew aligning method
CN107489163A (en) A kind of metallurgical industry body of heater annular bolt installation method
CN103862251A (en) Hoisting method of large device constrained by three-dimensional space and an auxiliary device of large device
CN108103936B (en) The method that prefabricated bent cap is installed on column
CN110470133B (en) Installation method of rotary kiln
CN104422125B (en) Benzene hydrogenation engineering organic heat carrier gas-fired heater installation method
CN202302573U (en) Base plate for inclined mortar filling
CN110284529A (en) Foundation deformation measurement method and device in larger hydrocarbon platform construction
CN210216525U (en) Quick detection die for pre-buried anchor bolt hole of foundation of T-shaped groove test bed
CN106677557A (en) Supporting protective structure capable of replacing large air spring through jacking and construction technique
CN210658418U (en) Novel prestressed anchor bolt fan foundation
CN110144927B (en) Device for embedding foundation bolt group
CN109295971B (en) High-precision control method for underground continuous wall steel bar cage
CN203594264U (en) Clamp special for angle steel iron tower rectification and tool for angle steel iron tower rectification
KR200340114Y1 (en) The structure of measurable bridge bearing
CN111826490B (en) Device and method for measuring and adjusting roundness of furnace shell wall of hot blast furnace