CN212404877U - Steel pad roof beam lifting means - Google Patents

Steel pad roof beam lifting means Download PDF

Info

Publication number
CN212404877U
CN212404877U CN202021759239.4U CN202021759239U CN212404877U CN 212404877 U CN212404877 U CN 212404877U CN 202021759239 U CN202021759239 U CN 202021759239U CN 212404877 U CN212404877 U CN 212404877U
Authority
CN
China
Prior art keywords
steel
lifting
jack
main body
lifting platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021759239.4U
Other languages
Chinese (zh)
Inventor
孟祥乾
郭之起
常军强
张奉春
张永江
张秀峰
张常轩
郝登科
李忠军
王豪杰
胡爱香
孙亚伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Investment Group Co Ltd
Third Engineering Co Ltd of China Railway 14th Bureau Co Ltd
Original Assignee
China Railway Construction Investment Group Co Ltd
Third Engineering Co Ltd of China Railway 14th Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Investment Group Co Ltd, Third Engineering Co Ltd of China Railway 14th Bureau Co Ltd filed Critical China Railway Construction Investment Group Co Ltd
Application granted granted Critical
Publication of CN212404877U publication Critical patent/CN212404877U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C25/00Cranes not provided for in groups B66C17/00 - B66C23/00
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66DCAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
    • B66D1/00Rope, cable, or chain winding mechanisms; Capstans
    • B66D1/02Driving gear
    • B66D1/08Driving gear incorporating fluid motors
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C2700/00Cranes
    • B66C2700/06Cranes in which the lifting movement is done with a hydraulically controlled plunger

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a steel pad beam lifting device, in particular to a lifting installation for a high pier steel beam pushing auxiliary facility, which comprises a main body portal frame, wherein two sides of the main body portal frame are provided with tracks; the lifting platforms are arranged on two sides above the main body gantry, matched with the rails and slide along the rails; the lifting platform is also provided with a falling hole; the jack system is arranged above the lifting platform and comprises a lifting jack, a steel strand wire coil, a steel strand wire rack and a jack pump station; one end of the steel strand is connected with the lifting jack through the steel strand lead frame and extends to the lower part of the lifting platform through the falling hole; the jack pump station is connected with the lifting jack. This device can promote construction equipment such as steel backing roof beam safely, fast, and the hoist and mount position is accurate, does not cause the influence to bridge stability, can target in place equipment fixing fast, saves the time limit for a project, save material and manual work, and safety can guarantee in the work progress.

Description

Steel pad roof beam lifting means
Technical Field
The utility model relates to a building engineering technical field, concretely relates to steel backing beam lifting means places in the nose girder front end and can be used to highway deck formula steel longeron walking top and push away the construction.
Background
In the pushing construction process of the road steel beam, large auxiliary equipment such as a steel pad beam is often required to be prepared on the pier top, and machinery such as a crane can be adopted for assisting when the pier stud is not high, but the crane is difficult to realize when the bridge has a complex terrain and is higher in pier stud.
When bridge superstructure adopted the girder steel structure, adopt the synchronous top push method of multiple spot to be under construction more, when adopting the synchronous top push method of multiple spot to be under construction, must all install one set of top pushing equipment at every mound top, and the small-size equipment can adopt the supplementary hoist and mount of tower crane because weight is lighter, but when large-scale auxiliary facilities such as steel backing roof beam are used to needs, hoist and mount work can not all be accomplished to tower crane, crane etc..
The traditional method is to arrange a slide way on the top of the steel beam and transport the equipment to a designated position from one end of the bridge, but the construction method has the disadvantages of high labor intensity, low working efficiency, time and labor consumption and unsatisfactory operation effect, and the installation of the slide way transport equipment from the top of the steel beam affects the safety and stability of the steel beam, and the personnel are unsafe in the construction process.
For safe, accomplish large-scale mound top equipment hoist and mount fast on complicated, the high mound bridge of topography, according to the actual conditions of construction utility model's a place in steel pad roof beam lifting means of nose girder front end.
SUMMERY OF THE UTILITY MODEL
In order to solve the problems in the prior art, the steel pad beam lifting equipment is provided, and is particularly used for lifting and mounting high pier steel beam pushing auxiliary facilities.
The utility model provides a technical scheme that its technical problem adopted is:
the utility model provides a steel backing roof beam lifting means, include:
the main body gantry is provided with tracks on two sides;
the lifting platforms are arranged on two sides above the main body gantry, matched with the rails and slide along the rails; the lifting platform is also provided with a falling hole;
the jack system is arranged above the lifting platform and comprises a lifting jack, a steel strand wire coil, a steel strand wire frame and a jack pump station; one end of the steel strand is connected with the lifting jack through the steel strand lead frame and extends to the lower part of the lifting platform through the falling hole; the jack pump station is connected with the lifting jack.
Preferably, the main body door frame is made of section steel and is made of I40I-shaped steel through welding.
Preferably, the jack system and the lifting platform are fixed by a profile steel fastener.
Preferably, the lifting platform is made of section steel and is made of I20I-shaped steel and [100 ] channel steel through welding.
Preferably, a steel pipe fence is welded above the lifting platform.
Preferably, the main body portal is connected with the guide beam through an L-shaped steel plate.
The use method of the steel pad beam lifting equipment comprises the following steps:
s1: before the steel beam is pushed, the steel pad beam lifting equipment is fixed at the front end of the guide beam;
s2: in the steel beam pushing construction process, when the front end of the guide beam reaches the pier top, stopping pushing; then, operating the steel pad beam lifting equipment, firstly, lowering the steel strand to the bottom of the pier, after ground personnel fix a heavy object, starting a jack pump station by the operator, and lifting the jack to lift the steel pad beam;
s3: after the steel pad beam is lifted to the pier top, an operator slowly falls the steel pad beam to the pier top by using the chain block for fixing, and the lifting equipment finishes working.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the equipment and material investment is reduced. In the traditional method, the slideway is arranged on the top of the steel beam, a through long slideway needs to be arranged on the top of the steel beam, so that more equipment and materials are input, and the operation is difficult; because this device overall structure is less, it is more convenient when the hoist and mount is loaded onto the bridge, adopt general crane can accomplish, lifting means installs simply, has saved manpower, equipment input, and the security is high.
2. The working efficiency is high. In the traditional method, the slideway is arranged on the top of the steel beam, all equipment needs to be transported to one end of the bridge and then transported from one end of the bridge to the other end of the bridge step by step, and the method is slow in speed and low in construction efficiency during high-altitude operation. The steel pad beam lifting equipment is adopted to avoid the time consumed by long-distance transportation, objects need to be lifted in advance and placed at the bottom of a pier, after the lifting equipment reaches the proper position, the jack system is directly operated to complete lifting, the working efficiency is greatly improved, and especially after the steel beam is pushed to a certain distance, the efficiency contrast is more obvious.
3. The economic effect is good. The steel pad beam lifting equipment can greatly reduce the manual use amount, reduce the equipment investment and save the construction period.
4. The operation is safe. The steel pad beam lifting equipment is used, potential safety hazards existing when a slideway is arranged on the top of a beam for operation are avoided, workers complete operation on the platform, and the steel pad beam lifting equipment is safe and reliable.
5. This lifting means places in the girder steel front end, and when the girder steel pushed away the construction, because the girder steel cantilever downwarps, must take the safety and stability that the measure guaranteed front end lifting means. This device overall height of structure is less, and relative stability is better, and lifting means and girder steel adopt shaped steel to be connected, have strengthened equipment overall stability, and for other lifting means, this equipment specially adapted girder steel pushes away uses as the hoist when constructing.
Drawings
The above and/or additional aspects and advantages of the present invention will become apparent and readily appreciated from the following description of the embodiments, taken in conjunction with the accompanying drawings of which:
fig. 1 is a top view of the structure of the present invention (the jack system is omitted).
Fig. 2 is a top view of the structure of the present invention shown in fig. 1 after installation.
Fig. 3 is a side view of the present invention after installation.
Fig. 4 is an enlarged schematic view of the present invention shown in fig. 3.
Fig. 5 is a schematic structural diagram of the present invention during pushing construction.
Description of reference numerals:
1, a main body portal frame; 2, lifting the platform; 3, track; 4, a main bridge steel truss girder; 5 lifting the jack; 6, a steel strand lead frame; 7, winding the steel stranded wire; 8, steel strand wires; 9, dropping a hole; 10 steel tube enclosure.
Detailed Description
Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the drawings are exemplary only for the purpose of explaining the present invention, and should not be construed as limiting the present invention.
As shown in fig. 1 to 5, the steel pad beam lifting apparatus provided in this embodiment includes:
the main body portal frame 1 is made of section steel and is formed by welding I40I-shaped steel, the whole frame is of a portal structure, and two sides of the main body portal frame 1 are provided with tracks 3; the main body portal 1 is divided into an upper layer and a lower layer, the upper layer portal is 100cm wider than one end of a front end guide beam of the main bridge steel truss beam 4, and a steel plate stiffening rib is arranged at the fulcrum of the main body portal 1; the main body portal 1 is connected with the guide beam through an L-shaped steel plate.
And the lifting platforms 2 are arranged on two sides above the main body gantry 1 and are matched and connected with the rails 3, the lifting platforms can slide along the rails 3, and the lifting platforms can be properly adjusted front and back by arranging the rails 3 to meet the requirement of accurate installation positions of lifted objects. The lifting platform 2 is made of section steel and is made of I20I-shaped steel and [100 ] channel steel in a welding mode, the lifting platform 2 is arranged on the left side and the right side of the main body portal frame 1 respectively, and during lifting, two sides are lifted simultaneously to keep balance. Through setting up the lift platform, made things convenient for personnel's operation, equipment to place.
The lifting platform 2 is also provided with a falling hole 9.
The lifting platform is arranged above the lifting platform 2 and comprises a lifting jack 5, a steel strand wire coil 7, a steel strand wire frame 6 and a jack pump station; the steel strand 8 is wound on a steel strand wire coil 7, one end of the steel strand wire coil is connected with the lifting jack 5 through a steel strand wire rack 6, and the steel strand wire coil penetrates through the falling hole 9 and extends to the lower part of the lifting platform 2; the jack pump station is connected with the lifting jack 5 through a high-pressure oil pipe to provide power for the lifting jack. When the lifting platform is lifted, auxiliary equipment such as a pier bottom steel pad beam can be quickly lifted to the pier top by the lifting jack 5 positioned on the lifting platform 2 for installation.
The jack system and the lifting platform 2 are fixed by a profile steel fastener.
A steel pipe fence 10 is welded above the lifting platform 2, and safety and usability are improved.
Because this device overall structure is less, the utility model discloses it is more convenient when the hoist and mount is put on the bridge, adopt general crane to accomplish, the lifting means installation is simple, has saved manpower and equipment input, and the security is high.
The working principle is as follows:
before the steel beam is pushed, the device is fixed at the front end of the guide beam, and after the guide beam slides to the pier top position, the steel pad beam placed at the bottom of the pier is hung to the pier top for installation by the device.
In the steel beam pushing construction process, when the front end of the guide beam reaches the pier top, the pushing is stopped, the steel strand 8 is put down, the required hoisting equipment is fixed at the bottom of the pier, and the continuous jack on the hoisting equipment is operated to gradually complete the hoisting.
The use method of the steel pad beam lifting equipment comprises the following steps:
s1: before the steel beam is pushed, the steel pad beam lifting equipment is fixed at the front end of the guide beam;
s2: in the steel beam pushing construction process, when the front end of the guide beam reaches the pier top, stopping pushing; then, operating the steel pad beam lifting equipment, firstly, lowering the steel strand 8 to the bottom of the pier, after ground personnel fix a heavy object, starting a jack pump station by the operator, and lifting the jack 5 to lift the steel pad beam;
s3: after the steel pad beam is lifted to the pier top, an operator slowly falls the steel pad beam to the pier top by using the chain block for fixing, and the lifting equipment finishes working.
This lifting means places in the girder steel front end, and when the girder steel pushed away the construction, because the girder steel cantilever downwarps, must take the safety and stability that the measure guaranteed front end lifting means. This device overall height of structure is less, and relative stability is better, and lifting means and girder steel adopt shaped steel to be connected, have strengthened equipment overall stability, and for other lifting means, this equipment specially adapted girder steel pushes away uses as the hoist when constructing.
As can be seen from the above description, the present device has the following advantages:
1. the equipment and material investment is reduced. In the prior art, the slideway is arranged on the top of the steel beam, a through long slideway needs to be arranged on the top of the steel beam, so that more equipment and materials are required to be put into the slideway, and the operation is difficult; the device has a small integral structure, is convenient to hoist and mount the upper bridge, can be completed by adopting a common crane, is simple in lifting equipment installation, saves manpower and equipment investment, and is high in safety;
2. the working efficiency is high. The tradition sets up the slide at the girder steel top, need all transport all equipment to bridge one end, then from bridge one end toward the other end progressively transport, during high altitude operation, speed is slow, the efficiency of construction is low. The steel pad beam lifting equipment is adopted to avoid the time consumed by long-distance transportation, objects to be lifted are placed at the bottom of the pier in advance, and after the lifting equipment reaches the position, the jack system is directly operated to complete lifting, so that the working efficiency is greatly improved, and especially when the steel beam is pushed to a certain distance, the efficiency contrast is more obvious;
3. the economic effect is good. The steel pad beam lifting equipment can greatly reduce the number of workers, reduce equipment investment and save the construction period;
4. the operation is safe. The steel pad beam lifting equipment is used, potential safety hazards existing when a slideway is arranged on the top of a beam for operation are avoided, workers complete operation on the platform, and the steel pad beam lifting equipment is safe and reliable.
While embodiments of the present invention have been shown and described, it will be understood by those of ordinary skill in the art that: various changes, modifications, substitutions and alterations can be made to the embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the claims and their equivalents.

Claims (6)

1. A steel bolster lifting device, characterized by includes:
the main body gantry is provided with tracks on two sides;
the lifting platforms are arranged on two sides above the main body gantry, matched with the rails and slide along the rails; the lifting platform is also provided with a falling hole;
the jack system is arranged above the lifting platform and comprises a lifting jack, a steel strand wire coil, a steel strand wire frame and a jack pump station; one end of the steel strand is connected with the lifting jack through the steel strand lead frame and extends to the lower part of the lifting platform through the falling hole; the jack pump station is connected with the lifting jack.
2. The steel bolster lifting device of claim 1, wherein the main body gantry is made of section steel and welded from I40I-section steel.
3. The steel bolster lifting device of claim 1, wherein the jack system and the lifting platform are secured with steel fasteners.
4. The steel pad beam lifting device as claimed in claim 1, wherein the lifting platform is made of section steel, and is made of I20I-steel and [100 ] channel steel by welding.
5. The steel pad beam lifting device of claim 1, wherein a steel tube fence is welded above the lifting platform.
6. The steel mat beam lifting device according to claim 1, wherein the joint of the main body gantry and the guide beam is connected by an L-shaped steel plate.
CN202021759239.4U 2020-03-27 2020-08-21 Steel pad roof beam lifting means Active CN212404877U (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2020102333300 2020-03-27
CN202010233330 2020-03-27

Publications (1)

Publication Number Publication Date
CN212404877U true CN212404877U (en) 2021-01-26

Family

ID=72969613

Family Applications (2)

Application Number Title Priority Date Filing Date
CN202010847264.6A Active CN111851314B (en) 2020-03-27 2020-08-21 Steel bolster lifting equipment and using method thereof
CN202021759239.4U Active CN212404877U (en) 2020-03-27 2020-08-21 Steel pad roof beam lifting means

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN202010847264.6A Active CN111851314B (en) 2020-03-27 2020-08-21 Steel bolster lifting equipment and using method thereof

Country Status (1)

Country Link
CN (2) CN111851314B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851314A (en) * 2020-03-27 2020-10-30 中铁十四局集团第三工程有限公司 Steel pad beam lifting equipment and using method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114908883B (en) * 2022-07-04 2024-04-26 中国建筑第四工程局有限公司 Lifting device for vertical rotation installation of steel awning of stadium and operation method thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202492807U (en) * 2012-03-27 2012-10-17 中交四航局第一工程有限公司 Steel box girder walking-type multi-point incremental launching construction system
CN102587291B (en) * 2012-03-27 2014-11-05 中交四航局第一工程有限公司 Walking type multipoint pushing construction method and walking type multipoint pushing construction system for steel box girder
CN202936736U (en) * 2012-11-27 2013-05-15 中交第二公路工程局有限公司 Cable-stayed bridge composite beam construction bridge floor crane
CN108265628A (en) * 2018-02-01 2018-07-10 中交路桥建设有限公司 One kind rides cable-styled erection crane lifting cable-stayed bridge girder steel and bridge floor board construction method
CN111851314B (en) * 2020-03-27 2024-10-29 中铁十四局集团第三工程有限公司 Steel bolster lifting equipment and using method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851314A (en) * 2020-03-27 2020-10-30 中铁十四局集团第三工程有限公司 Steel pad beam lifting equipment and using method thereof
CN111851314B (en) * 2020-03-27 2024-10-29 中铁十四局集团第三工程有限公司 Steel bolster lifting equipment and using method thereof

Also Published As

Publication number Publication date
CN111851314B (en) 2024-10-29
CN111851314A (en) 2020-10-30

Similar Documents

Publication Publication Date Title
CN105152032A (en) Installing method for bridge crane in enclosed environment workshop
CN212404877U (en) Steel pad roof beam lifting means
CN107013038B (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN105386411B (en) Suspension cable top of bridge pier multifunction gate rack device
CN208122371U (en) On across the high-speed rail safe guarding shed fast dismounting device of operation line
CN111139743A (en) Method for improving speed of highway beam frame and installation method of gantry crane
CN105781210B (en) A kind of conical tower and its tool section assist punching construction method for lifting whole
CN109573851A (en) Arcuated roof internode steel truss hangs, fills integrated apparatus and docking hanging method
CN103821084B (en) Operational method at the bottom of implement at the bottom of beam and beam
CN101818563B (en) Jack-up integral lifting mobile platform and using method
CN112252741A (en) Full-rail crane for super high-rise unit curtain wall and installation and use method thereof
CN108277994A (en) On across the high ferro safe guarding shed quick method for dismounting of operation line
CN110316662B (en) Installation and construction method of large-span portal crane
CN210366808U (en) Lifting and dismantling device for rail walking
CN204983693U (en) Hoist device slides in mountain area corridor truss high altitude
CN203257106U (en) Multifunctional power-driven walking type walking system
CN214062384U (en) Full-rail crane for super high-rise unit curtain wall
CN109487696A (en) A kind of armored concrete cable-carried arch bridge unloads frame method and apparatus
CN210636823U (en) Rail type overhead connecting device for pier body steel bar overhead connecting construction
CN111139742B (en) Method for mounting and dismounting highway bridge girder erection machine
JP2023074170A (en) Floor slab replacing method and construction machine used therefor
CN114426243A (en) Gantry crane rail overhanging support suitable for dangerous waste rigid landfill
CN208636051U (en) Multifunctional motor-driven cucurbit testing stand
CN214194169U (en) Large-span steel truss bridge high bolt construction sliding platform
CN218205793U (en) Steel structure air accumulation traction sliding device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant