- CN212403099U CN212403099U CN202020370924.1U CN202020370924U CN212403099U CN 212403099 U CN212403099 U CN 212403099U CN 202020370924 U CN202020370924 U CN 202020370924U CN 212403099 U CN212403099 U CN 212403099U
- Authority
- CN
- China
- Prior art keywords
- door
- lower door
- cage
- platform
- case
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model relates to a construction elevator with platform of cominging in and going out, including the case cage and the platform of cominging in and going out, the platform of cominging in and going out includes upper door and lower door, and the width of upper door and lower door is the same with the case cage width, and upper door and case cage lateral wall sliding connection, lower door bottom and case cage diapire rotate through the round pin axle and are connected, and this application is through the transformation to the outer door, can be when opening on the concrete structure face is directly put to the one end of steel sheet, has constituted the platform of cominging in and going out that need not set up the scaffold frame.
Description
Technical Field
The utility model belongs to the technical field of the construction, especially, relate to a construction elevator with discrepancy platform.
Background
The installation of current construction elevator all can set up the platform of cominging in and going out of scaffold frame along with the floor, and this scaffold frame often is tall and big scaffold frame, must demolish original scaffold frame when setting up, sets up difficult danger greatly, needs to set up according to expert's demonstration requirement, produces a not little expense. Moreover, when constructing the outer wall, the construction is not completed at one time, and a construction elevator such as a basket must be left for construction after removal, which causes extra cost and danger of re-installing the basket.
SUMMERY OF THE UTILITY MODEL
The utility model provides a use lift with discrepancy platform through the transformation to the outer door, can be when opening the one end of steel sheet directly put the concrete structure face on, constituted the discrepancy platform that need not set up the scaffold frame.
In order to solve the problems in the background art, the present invention is realized by the following technical solutions: the utility model provides a construction elevator with come in and go out platform, includes the case cage and goes in and go out the platform, it includes upper door and lower door to go in and go out the platform, the width of upper door and lower door is the same with the case cage width, upper door and case cage lateral wall sliding connection, lower door bottom and case cage diapire are connected through the round pin axle rotation.
As a practical further explanation: the top of the upper door is provided with a limiting plate extending towards the direction of the box cage, the bottom of the upper door is provided with a slot, and the top wall inside the box cage is provided with a bolt matched with the slot.
As a practical further explanation: the top of the side wall of the upper door is provided with a clamping groove, and the side wall of the outer part of the box cage is provided with a clamping hook matched with the clamping groove.
As a practical further explanation: the lower door is provided with a plurality of sleeves towards the lateral wall of the cage, the edges on two sides of the inlet and outlet direction are symmetrically provided with guardrails, the guardrails comprise a plurality of vertical rods and horizontal rods, the vertical rods are perpendicular to the horizontal rods, and the vertical rods are consistent in number with the sleeves and are matched with the sleeves.
As a practical further explanation: the height of the guardrail is 1.2 m.
As a practical further explanation: and a plurality of steel ropes are connected between the lower door and the box cage, the steel ropes are symmetrically arranged on two sides of the lower door, one ends of the steel ropes are fixed with two sides of the lower door, and the other ends of the steel ropes are fixed on two sides of the box cage.
As a practical further explanation: and a rubber layer is sleeved at the top end of the lower door.
Compared with the prior art, this practicality has following profitable technological effect:
1. when opening the platform of cominging in and going out, can be directly put the concrete structure face with the one end of steel sheet on, constituted the platform of cominging in and going out that need not set up the scaffold, make things convenient for personnel from top to bottom, make construction elevator set up the time simultaneously, need not set up the scaffold platform of going up and down again, this kind of method installation easy operation, greatly reduced construction cost.
2. The guardrails and the steel ropes on the two sides of the lower door form two safety protections, and the safety of the platform entering and exiting is greatly improved.
Drawings
FIG. 1 is a schematic structural diagram of the present invention;
fig. 2 is a plan view of the lower door in the present application.
Description of the reference numerals
1. A cage; 2. an access platform; 3. a door is arranged; 4. a lower door; 5. a limiting plate; 6. a slot; 7. a bolt; 8. a card slot; 9. a hook is clamped; 10. a sleeve; 11. a guardrail; 12. a steel cord.
Detailed Description
In order that the above objects, features and advantages of the present invention can be more clearly understood, a detailed description of the present invention will be given below with reference to the accompanying drawings and specific embodiments. It should be noted that the embodiments and features of the embodiments of the present application may be combined with each other without conflict.
In the description of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings or orientations or positional relationships that the present application product is conventionally placed in use, and are merely used for convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present application. Furthermore, the terms "first," "second," "third," and the like are used solely to distinguish one from another and are not to be construed as indicating or implying relative importance.
Furthermore, the terms "horizontal", "vertical" and the like do not imply that the components are required to be absolutely horizontal or pendant, but rather may be slightly inclined. For example, "horizontal" merely means that the direction is more horizontal than "vertical" and does not mean that the structure must be perfectly horizontal, but may be slightly inclined.
In the description of the present application, it is further noted that, unless expressly stated or limited otherwise, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present application can be understood in a specific case by those skilled in the art.
As shown in fig. 1 and 2, a construction elevator with an access platform 2 comprises a box cage 1 and the access platform 2, wherein the access platform 2 comprises an upper door 3 and a lower door 4, the width of the upper door 3 and the width of the lower door 4 are the same as the width of the box cage 1, the upper door 3 is slidably connected with the side wall of the box cage 1, a limiting plate 5 extending towards the box cage 1 is arranged at the top of the upper door 3, a slot 6 is arranged at the bottom of the upper door 3, and a plug pin 7 matched with the slot 6 is arranged on the top wall inside the box cage 1;
4 bottoms of lower door 4 are connected through the round pin axle rotation with 1 diapire of case cage, are equipped with draw-in groove 8 at 3 lateral wall tops of upper door, are equipped with the trip 9 that sets up with draw-in groove 8 cooperation at 1 outside lateral wall of case cage, rotate when lower door 4 and open, and its top overlap joint is equipped with the rubber layer on its top when the roof, has reduced the probability of wearing and tearing.
The application provides a pair of construction elevator with platform of cominging in and going out still includes on the lateral wall of lower door 4 orientation case cage 1, is located a plurality of sleeves 10 that the border symmetry on business turn over direction both sides set up, is equipped with guardrail 11 in case cage 1 simultaneously, and guardrail 11 includes a plurality of vertical poles and horizon bar, and vertical pole and horizon bar set up perpendicularly, and simultaneously, vertical pole and sleeve 10 unanimous and cooperation setting to the height of guardrail 11 is 1.2 m.
In order to improve the safety of the safe box, a plurality of steel ropes 12 are connected between the lower door 4 and the box cage 1, the steel ropes 12 are symmetrically arranged at two sides of the lower door 4, one end of each steel rope 12 is fixed with two sides of the lower door 4, and the other end of each steel rope 12 is fixed at two sides of the box cage 1
The embodiments given above are preferable examples for implementing the present invention, and the present invention is not limited to the above-described embodiments. Any non-essential addition and replacement made by the technical features of the technical solution of the present invention by those skilled in the art belong to the protection scope of the present invention.
Claims (7)
1. The utility model provides a construction elevator with discrepancy platform which characterized in that: including case cage (1) and discrepancy platform (2), discrepancy platform (2) are including last door (3) and lower door (4), the width of going up door (3) and lower door (4) is the same with case cage (1) width, go up door (3) and case cage (1) lateral wall sliding connection, lower door (4) bottom is connected through the round pin axle rotation with case cage (1) diapire.
2. The construction hoist with an access platform of claim 1, wherein: go up door (3) top and be provided with limiting plate (5) that stretch out to case cage (1) direction the bottom of going up door (3) is equipped with slot (6), is equipped with bolt (7) that set up with slot (6) cooperation on the inside roof of case cage (1).
3. The construction hoist with an access platform of claim 1, wherein: the top of the side wall of the lower door (4) is provided with a clamping groove (8), and the side wall of the outer part of the box cage (1) is provided with a clamping hook (9) matched with the clamping groove (8).
4. The construction hoist with an access platform of claim 1, wherein: lower door (4) are equipped with a plurality of sleeves (10) towards on the lateral wall on case cage (1) along the symmetry on border on business turn over direction both sides, are in simultaneously be equipped with guardrail (11) in case cage (1), guardrail (11) include a plurality of vertical poles and horizon bar, vertical pole sets up with the horizon bar is perpendicular, simultaneously, vertical pole and sleeve (10) quantity unanimous and cooperation setting.
5. The construction elevator with an access platform according to claim 4, wherein: the height of the guardrail (11) is 1.2 m.
6. The construction hoist with an access platform of claim 1, wherein: a plurality of steel ropes (12) are connected between the lower door (4) and the box cage (1), the steel ropes (12) are symmetrically arranged on two sides of the lower door (4), one ends of the steel ropes (12) are fixed to two sides of the lower door (4), and the other ends of the steel ropes are fixed to two sides of the box cage (1).
7. The construction hoist with an access platform of claim 1, wherein: the top end of the lower door (4) is sleeved with a rubber layer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020370924.1U CN212403099U (en) | 2020-03-23 | 2020-03-23 | Construction elevator with go in and out platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020370924.1U CN212403099U (en) | 2020-03-23 | 2020-03-23 | Construction elevator with go in and out platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212403099U true CN212403099U (en) | 2021-01-26 |
Family
ID=74378455
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020370924.1U Active CN212403099U (en) | 2020-03-23 | 2020-03-23 | Construction elevator with go in and out platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212403099U (en) |
-
2020
- 2020-03-23 CN CN202020370924.1U patent/CN212403099U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206408920U (en) | A kind of collapsible operating platform for narrow space | |
CN212403099U (en) | Construction elevator with go in and out platform | |
CN205188839U (en) | Movably -assembled anti -collision bridge wall construction hanging basket | |
CN207267961U (en) | A kind of bridge pier shaft pours operating platform | |
CN207277870U (en) | A kind of elevator protective device with shaped | |
AU2015295620B2 (en) | Mobile hall construction | |
CN211775618U (en) | Assembled folding walkways system | |
CN109203218B (en) | Prefabricated T roof beam concrete placement protection canopy of railway | |
CN207739605U (en) | Elevator shaft three-dimensional construction protection system | |
CN206476307U (en) | A kind of frock placed for bus front bridge | |
CN206091013U (en) | Novel convertible canopy steel construction | |
CN216641382U (en) | Turnover plate protection device between external scaffold and building main body | |
CN204571249U (en) | The load module of hoist material receiving and hoist material receiving thereof | |
CN206736745U (en) | Goods-shelf type pier shaft external scaffolding | |
CN201671311U (en) | Elevator shaft inside construction protecting rack | |
CN219137432U (en) | Bent cap standardization platform adopting foldable bottom plate | |
CN108487623A (en) | A kind of building safety device cage | |
CN205346682U (en) | Tower crane anchor rod adheres to roof beam articulated elements | |
CN208996467U (en) | A kind of floor rack device dividing slotting formula and integral hoisting | |
CN215287622U (en) | Construction elevator protection and channel panel turnover mechanism for high-rise residential building construction | |
CN216949371U (en) | Combined high-grade tool | |
CN214980994U (en) | Steel case roof beam pterygoid lamina welding movable type platform | |
CN213234357U (en) | Protection platform of collapsible tower cloth machine elevartor shaft | |
CN215520133U (en) | Safety ladder for building construction | |
CN216157124U (en) | High altitude faces limit post construction operating means |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |