CN212336626U - High-rise building pipe well vertical pipeline structure assembled in sections - Google Patents

High-rise building pipe well vertical pipeline structure assembled in sections Download PDF

Info

Publication number
CN212336626U
CN212336626U CN202022191409.XU CN202022191409U CN212336626U CN 212336626 U CN212336626 U CN 212336626U CN 202022191409 U CN202022191409 U CN 202022191409U CN 212336626 U CN212336626 U CN 212336626U
Authority
CN
China
Prior art keywords
shaped steel
sleeve
frame
steel frame
vertical pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022191409.XU
Other languages
Chinese (zh)
Inventor
刘敏
黄河
杨荔荔
李小鹏
王文娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NO3 CONSTRUCTION Co Ltd OF CHONGQING CONSTRUCTION ENGINEERING GROUP
Chongqing Construction Engineering Group Co Ltd
No 3 Construction Co Ltd of Chongqing Construction Engineering Group
Original Assignee
NO3 CONSTRUCTION Co Ltd OF CHONGQING CONSTRUCTION ENGINEERING GROUP
Chongqing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NO3 CONSTRUCTION Co Ltd OF CHONGQING CONSTRUCTION ENGINEERING GROUP, Chongqing Construction Engineering Group Co Ltd filed Critical NO3 CONSTRUCTION Co Ltd OF CHONGQING CONSTRUCTION ENGINEERING GROUP
Priority to CN202022191409.XU priority Critical patent/CN212336626U/en
Application granted granted Critical
Publication of CN212336626U publication Critical patent/CN212336626U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the technical field of high-rise building pipeline laying, in particular to a segmented assembled high-rise building pipe well vertical pipeline structure, which comprises vertical pipelines and a hoisting frame for fixing a plurality of parallel vertical pipelines; the hoisting frame comprises a U-shaped steel frame, a baffle, a sleeve and a fixed connection plate; the number of the U-shaped steel frames is two, the two end plane side walls of each U-shaped steel frame are welded together through two baffles, the U-shaped steel frames and the baffles form a rectangular frame, and a plurality of sleeves are welded between the two U-shaped steel frames; one end of the sleeve is higher than one end face of the U-shaped steel frame, the other end of the sleeve is flush with the other end face of the U-shaped steel frame, the fixed connection plates are symmetrically welded to one end of the sleeve and are arranged along the length direction of the U-shaped steel frame, and through holes are symmetrically formed in each fixed connection plate.

Description

High-rise building pipe well vertical pipeline structure assembled in sections
Technical Field
The utility model belongs to the technical field of high-rise building pipe laying, specific high-rise building pipe shaft vertical pipeline structure that segmentation was assembled that says so.
Background
When the hoisting equipment hoists the vertical pipelines to the specified positions, if the vertical pipelines are hoisted to the specified positions one by one, the hoisting operation efficiency of the vertical pipelines is low, the time and the energy used by the hoisting equipment are wasted, and the hoisting operation cost is increased; therefore, the hoisting frame for fixing the plurality of side-by-side vertical pipelines is designed, the safety of hoisting operation is ensured, and meanwhile, the operation efficiency of hoisting the vertical pipelines is improved.
SUMMERY OF THE UTILITY MODEL
In order to compensate the deficiency of the prior art to solve the problem described by the background art, the utility model provides a high-rise building tube well vertical pipeline structure that segmentation was assembled.
The utility model provides a technical scheme that its technical problem adopted is: the utility model discloses a sectional assembly type high-rise building pipe well vertical pipeline structure, which comprises vertical pipelines and a hoisting frame for fixing a plurality of parallel vertical pipelines; the hoisting frame comprises a U-shaped steel frame, a baffle, a sleeve and a fixed connection plate; the number of the U-shaped steel frames is two, the two end plane side walls of each U-shaped steel frame are welded together through two baffles, the U-shaped steel frames and the baffles form a rectangular frame, and a plurality of sleeves are welded between the two U-shaped steel frames; one end of the sleeve is higher than one end face of the U-shaped steel frame, the other end of the sleeve is flush with the other end face of the U-shaped steel frame, the fixed connection plates are symmetrically welded to one end of the sleeve and are arranged along the length direction of the U-shaped steel frame, and through holes are symmetrically formed in each fixed connection plate.
Preferably, the inner diameter of the sleeve is designed according to the outer diameter of the vertical pipeline, and the outer ring of the vertical pipeline is in clearance fit with the inner ring of the sleeve; the length of the baffle is the same as the diameter of the outer ring of the sleeve with larger diameter of the inner ring and the outer ring of the frame.
Preferably, the side wall of the outer ring of the sleeve, which is shorter than the length of the baffle plate, is symmetrically provided with connecting blocks; the connecting block is provided with one end provided with an arc surface, the arc surface is adapted to the side wall of the outer ring of the sleeve, one end surface of the connecting block is welded on the side wall of the outer ring of the sleeve, and the other end surface of the connecting block is welded on the U-shaped steel frame.
Preferably, the side wall of the outer ring of each sleeve is symmetrically provided with a limiting plate; the limiting plate is arranged along the length direction of the baffle, one plate surface of the limiting plate is attached to one end surface of the U-shaped steel frame, and one end of the limiting plate is welded on the side wall of the outer ring of the sleeve.
Preferably, the side walls of the concave parts at the two ends of each U-shaped steel frame are respectively provided with a lifting lug, and the lifting lugs are welded on the U-shaped steel frames.
Preferably, a plurality of fastening bolts are arranged on the side walls of the concave parts at the two ends of each U-shaped steel frame; the end part of the fastening bolt penetrates through the U-shaped steel frame and the connecting plate and extends into the sleeve.
The utility model discloses a technological effect and advantage:
through this hoist and mount frame, can hoist a plurality of vertical pipelines simultaneously, reduce the hoist and mount number of times, improve hoist and mount efficiency, save time and cost to and fix vertical pipeline at hoist and mount frame through solid fishplate bar, avoid vertical pipeline to appear the emergence that vertical pipeline breaks away from hoist and mount frame phenomenon when hoist and mount, guarantee hoist and mount operation safety, the site operation security is good, the work risk of work process is low, the material loss is few, the time limit for a project is short, economic nature is good, energy-concerving and environment-protectively.
Drawings
The present invention will be further described with reference to the accompanying drawings and embodiments.
Fig. 1 is a perspective view of a hoisting frame in the utility model;
fig. 2 is a top view of the hoisting frame of the present invention;
fig. 3 is a bottom view of the hoisting frame of the utility model;
in the figure: the lifting frame 1, the U-shaped steel frame 11, the lifting lugs 111, the fastening bolts 112, the baffle 12, the sleeve 13, the connecting block 131, the limiting plate 132, the fixed connecting plate 14 and the through hole 141.
Detailed Description
In order to make the technical means, creation characteristics, achievement purpose and efficiency of the utility model easy to understand and understand, the utility model is further explained by combining the following embodiments.
As shown in fig. 1 to 3, the sectional assembled vertical pipeline structure of the pipe well of the high-rise building of the present invention comprises vertical pipelines and a hoisting frame 1 for fixing a plurality of parallel vertical pipelines; the hoisting frame 1 comprises a U-shaped steel frame 11, a baffle 12, a sleeve 13 and a fixed connection plate 14; the number of the U-shaped steel frames 11 is two, two planar side walls of two ends of each U-shaped steel frame 11 are welded together through two baffles 12, the U-shaped steel frames 11 and the baffles 12 enclose a rectangular frame, and a plurality of sleeves 13 are welded between the two U-shaped steel frames 11; one end of the sleeve 13 is higher than one end face of the U-shaped steel frame 11, the other end of the sleeve 13 is flush with the other end face of the U-shaped steel frame 11, fixing and connecting plates 14 are symmetrically welded at one end of the sleeve 13, the fixing and connecting plates 14 are arranged along the length direction of the U-shaped steel frame 11, and through holes 141 are symmetrically formed in each fixing and connecting plate 14; when the hoisting equipment hoists the vertical pipelines to the specified positions, if the vertical pipelines are hoisted to the specified positions one by one, the hoisting operation efficiency of the vertical pipelines is low, the time and the energy used by the hoisting equipment are wasted, and the hoisting operation cost is increased; therefore, by designing the hoisting frame 1 for fixing the plurality of parallel vertical pipelines, the operation efficiency of hoisting the vertical pipelines is improved while the safety of hoisting operation is ensured; the vertical pipelines are inserted into the sleeve 13, then the bolt connecting ends of the vertical pipelines are connected to the fixed connecting plate 14 through bolts, at the moment, the vertical pipelines are fixed on the hoisting frame 1, and then the hoisting frame 1 and the vertical pipelines are lifted together through hoisting equipment to be hoisted to a specified position; through this hoist and mount frame 1, can hoist a plurality of vertical pipelines simultaneously, reduce the hoist and mount number of times, improve hoist and mount efficiency, save time and cost to and fix vertical pipeline at hoist and mount frame 1 through solid fishplate bar 14, avoid vertical pipeline to appear the emergence that vertical pipeline breaks away from hoist and mount frame 1 phenomenon when hoist and mount, guarantee hoist and mount operation safety.
The inner diameter of the sleeve 13 is designed according to the outer diameter of the vertical pipeline, and the outer ring of the vertical pipeline is in clearance fit with the inner ring of the sleeve 13; the length of the baffle plate 12 is the same as the diameter of the outer ring of the sleeve 13 with larger diameter of the inner ring and the outer ring of the frame.
As a specific embodiment of the present invention, the side wall of the outer ring of the sleeve 13, which is shorter than the length of the baffle 12, is symmetrically provided with connecting blocks 131; one end of each connecting block 131 is provided with an arc surface, the arc surface is matched with the side wall of the outer ring of the sleeve 13, one end surface of each connecting block 131 is welded on the side wall of the outer ring of the sleeve 13, and the other end surface of each connecting block 131 is welded on the U-shaped steel frame 11; because the diameters of the vertical pipelines are different, the matching between the vertical pipeline and the sleeve 13 is considered when the diameter of the inner ring of the sleeve 13 is designed, so that the hoisting frame 1 can hoist the vertical pipelines with different outer diameters, the diameter of the inner ring of the sleeve is designed according to the vertical pipeline with the largest diameter of the outer ring on the hoisting frame 1, and meanwhile, the length of the baffle 12 is designed according to the sleeve 13 with the largest diameter of the outer ring, so that the adaptability of the hoisting frame 1 is improved.
As a specific embodiment of the present invention, a limiting plate 132 is symmetrically disposed on the outer ring side wall of each sleeve 13; the limiting plate 132 is arranged along the length direction of the baffle 12, one plate surface of the limiting plate 132 is attached to one end surface of the U-shaped steel frame 11, and one end of the limiting plate 132 is welded on the outer ring side wall of the sleeve 13; a limit plate 132 is arranged on the outer ring of each sleeve 13, so that the stability between the sleeves 13 and the U-shaped steel frame 11 is improved; if the not hard up phenomenon appears in sleeve pipe 13 and the 11 welding points of U-shaped steelframe, sleeve pipe 13 is pressed down to the gravity of vertical pipeline, leads to vertical pipeline to break away from hoist and mount frame 1, causes the hoist and mount accident, provides double-deck guarantee for the hoist and mount operation of vertical pipeline through limiting plate 132 for this reason.
As a specific embodiment of the present invention, the side walls of the concave portions at both ends of each U-shaped steel frame 11 are respectively provided with a lifting lug 111, and the lifting lugs 111 are welded on the U-shaped steel frames 11; through lug 111 for hoist and mount frame 1 is when hoist and mount operation, and hoist and mount wire rope not only ties in hoist and mount frame 1's rectangular frame, and hoist and mount wire rope also can tie on lug 111 simultaneously, provides double-deck guarantee for the hoist and mount operation of vertical pipeline on the one hand, and on the other hand selects more vertical pipeline angle of hoist and mount according to hoist and mount operation site space, improves the adaptability of hoist and mount frame 1.
As a specific embodiment of the present invention, a plurality of fastening bolts 112 are disposed on the side walls of the concave portions at both ends of each U-shaped steel frame 11; the end part of the fastening bolt 112 penetrates through the U-shaped steel frame 11 and the connecting plate and extends into the sleeve; through rotatory fastening bolt 112, increase the fastness between vertical pipeline and the sleeve once more, improve the security of hoist and mount operation.
The working principle is as follows: the vertical pipelines are inserted into the sleeve 13, then the bolt connecting ends of the vertical pipelines are connected to the fixed connecting plate 14 through bolts, at the moment, the vertical pipelines are fixed on the hoisting frame 1, and then the hoisting frame 1 and the vertical pipelines are lifted together through hoisting equipment to be hoisted to a specified position; through this hoist and mount frame 1, can hoist a plurality of vertical pipelines simultaneously, reduce the hoist and mount number of times, improve hoist and mount efficiency, save time and cost to and fix vertical pipeline at hoist and mount frame 1 through solid fishplate bar 14, avoid vertical pipeline to appear the emergence that vertical pipeline breaks away from hoist and mount frame 1 phenomenon when hoist and mount, guarantee hoist and mount operation safety.
Due to the fact that the diameters of the vertical pipelines are different, when the diameter of the inner ring of the sleeve 13 is designed, the vertical pipeline and the sleeve 13 are matched, the hoisting frame 1 can hoist the vertical pipelines with different outer diameters, the diameter of the inner ring of the sleeve is designed according to the vertical pipeline with the largest diameter of the outer ring of the hoisting frame 1, and meanwhile the length of the baffle 12 is designed according to the sleeve 13 with the largest diameter of the outer ring, so that the adaptability of the hoisting frame 1 is improved; a limiting plate 132 is arranged on the outer ring of each sleeve 13, so that the stability between the sleeves 13 and the U-shaped steel frame 11 is improved; if the welding point between the sleeve 13 and the U-shaped steel frame 11 is loosened, the sleeve 13 is pressed down by the gravity of the vertical pipeline, so that the vertical pipeline is separated from the hoisting frame 1, and a hoisting accident is caused, and therefore a double-layer guarantee is provided for the hoisting operation of the vertical pipeline through the limiting plate 132; meanwhile, the lifting lugs 111 are used, when the lifting frame 1 is subjected to lifting operation, the lifting steel wire rope is not only tied in the rectangular frame of the lifting frame 1, but also tied on the lifting lugs 111, on one hand, double-layer guarantee is provided for the lifting operation of the vertical pipeline, on the other hand, more lifting vertical pipeline angles are selected according to the lifting operation field space, and the adaptability of the lifting frame 1 is improved.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a high-rise building tubular well vertical pipeline structure that segmentation was assembled, its characterized in that: the device comprises vertical pipelines and a hoisting frame for fixing a plurality of parallel vertical pipelines; the hoisting frame comprises a U-shaped steel frame, a baffle, a sleeve and a fixed connection plate; the number of the U-shaped steel frames is two, the two end plane side walls of each U-shaped steel frame are welded together through two baffles, the U-shaped steel frames and the baffles form a rectangular frame, and a plurality of sleeves are welded between the two U-shaped steel frames; one end of the sleeve is higher than one end face of the U-shaped steel frame, the other end of the sleeve is flush with the other end face of the U-shaped steel frame, the fixed connection plates are symmetrically welded to one end of the sleeve and are arranged along the length direction of the U-shaped steel frame, and through holes are symmetrically formed in each fixed connection plate.
2. The sectionally assembled high-rise building pipe well vertical pipeline structure of claim 1, which is characterized in that: the inner diameter of the sleeve is designed according to the outer diameter of the vertical pipeline, and the outer ring of the vertical pipeline is in clearance fit with the inner ring of the sleeve; the length of the baffle is the same as the diameter of the outer ring of the sleeve with larger diameter of the inner ring and the outer ring of the frame.
3. The sectionally assembled high-rise building pipe well vertical pipeline structure of claim 1, which is characterized in that: connecting blocks are symmetrically arranged on the side wall of the outer ring of the sleeve, which is shorter than the length of the baffle; the connecting block is provided with one end provided with an arc surface, the arc surface is adapted to the side wall of the outer ring of the sleeve, one end surface of the connecting block is welded on the side wall of the outer ring of the sleeve, and the other end surface of the connecting block is welded on the U-shaped steel frame.
4. The sectionally assembled high-rise building pipe well vertical pipeline structure of claim 1, which is characterized in that: limiting plates are symmetrically arranged on the side wall of the outer ring of each sleeve; the limiting plate is arranged along the length direction of the baffle, one plate surface of the limiting plate is attached to one end surface of the U-shaped steel frame, and one end of the limiting plate is welded on the side wall of the outer ring of the sleeve.
5. The sectionally assembled high-rise building pipe well vertical pipeline structure of claim 1, which is characterized in that: and lifting lugs are respectively arranged on the side walls of the concave parts at the two ends of each U-shaped steel frame and welded on the U-shaped steel frames.
6. The sectionally assembled high-rise building pipe well vertical pipeline structure of claim 1, which is characterized in that: a plurality of fastening bolts are arranged on the side walls of the concave parts at the two ends of each U-shaped steel frame; the end part of the fastening bolt penetrates through the U-shaped steel frame and the connecting plate and extends into the sleeve.
CN202022191409.XU 2020-09-29 2020-09-29 High-rise building pipe well vertical pipeline structure assembled in sections Active CN212336626U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022191409.XU CN212336626U (en) 2020-09-29 2020-09-29 High-rise building pipe well vertical pipeline structure assembled in sections

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022191409.XU CN212336626U (en) 2020-09-29 2020-09-29 High-rise building pipe well vertical pipeline structure assembled in sections

Publications (1)

Publication Number Publication Date
CN212336626U true CN212336626U (en) 2021-01-12

Family

ID=74070924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022191409.XU Active CN212336626U (en) 2020-09-29 2020-09-29 High-rise building pipe well vertical pipeline structure assembled in sections

Country Status (1)

Country Link
CN (1) CN212336626U (en)

Similar Documents

Publication Publication Date Title
CN203845664U (en) Special lifting tool for lifting board girder of boiler
CN212336626U (en) High-rise building pipe well vertical pipeline structure assembled in sections
CN210684655U (en) Novel vibroflotation device guide rod
CN215167862U (en) Be used in no counter weight hanging flower basket of parapet
CN218204531U (en) Pipe jacking short-distance initial back wall
CN216512739U (en) Heavy well lid start-stop equipment of inspection shaft
CN108821127A (en) The devices and methods therefor of disassembly lifting open type TBM in a kind of hole
CN211713955U (en) Slip casting type steel pipe screw pile
CN210150559U (en) Hoisting assembly in groups for reinforcing steel bar formwork integrated component
CN109723059B (en) Improved full casing for sand pebble foundation construction and use method thereof
CN207048333U (en) A kind of lattice steel pipe column and material distributing machine pedestal attachment means
CN218595881U (en) Tool convenient for hoisting round pipe culvert
CN206188260U (en) Hoist top ping lift prevents kinking device and hoist
CN210366627U (en) A multi-functional scalable hoist for handling concrete prefabricated component
CN207700242U (en) Brush wall device for scrubbing ground-connecting-wall seam
CN214192283U (en) Large-diameter pipe jacking lifting device
CN210854974U (en) Riser pipe hoist device
CN213356663U (en) Portable hoisting moving platform
CN215946469U (en) Lifting appliance assembly for lifting basement equipment in place
CN212687323U (en) Hoisting system for hoisting converter vaporization cooling system equipment
CN219953343U (en) Construction system for breaking shield tunnel portal
CN211816405U (en) Concrete casting system for ultrahigh outer wall of basement
CN214087285U (en) Light lifting appliance for hoisting lattice beam cable of arch bridge
CN219731988U (en) Turnover hanging bar adjusting device under deep hole