CN212336080U - Assembled tower crane foundation structure - Google Patents
Assembled tower crane foundation structure Download PDFInfo
- Publication number
- CN212336080U CN212336080U CN202021721132.0U CN202021721132U CN212336080U CN 212336080 U CN212336080 U CN 212336080U CN 202021721132 U CN202021721132 U CN 202021721132U CN 212336080 U CN212336080 U CN 212336080U
- Authority
- CN
- China
- Prior art keywords
- tower crane
- box girder
- steel box
- girder
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses an assembled ballast formula tower crane foundation structure, including tower crane base, cross girder steel, atress steel box girder, bolt, ballast piece, atress steel box girder is rectangle rigid structure, bolt and basement frame column structure fixed connection are passed through to the bottom of atress steel box girder, four tip of cross girder steel are placed respectively on atress steel box girder, the tower crane base is placed on the atress steel box girder of cross girder steel both sides, the ballast piece piles up respectively on the tower crane base of cross girder steel both sides. The utility model discloses a ballast piece and can prefabricated atress steel box girder as tower crane foundation bearing member to through bolt and basement frame post structure fixed connection, both avoided traditional tubular pile structure construction time long, the problem that can not multiplex and the construction degree of difficulty is big, also avoided prefabricated reinforced concrete roof beam to have enough to meet the need inconvenient and fragile, the poor problem of anti-seismic performance, have that the dismouting is convenient, can repeat the turnover use, anti-seismic performance is good, safe and reliable's characteristics.
Description
Technical Field
The utility model relates to a construction technical field, concretely relates to dismouting is convenient, can repeat turnover use, anti-seismic performance is good, safe and reliable's assembly weighs formula tower crane foundation structure.
Background
The tower crane is the most common hoisting equipment on the building site, also called tower crane, which is lengthened section by section (called standard section for short) and is mainly used for vertical and horizontal conveying of materials and installation of building components in the building construction due to large operation space, and is also commonly used for pouring large-volume concrete in hydraulic engineering. The tower crane is hung by the hanging arm which is hung out, so that a very large dumping moment is generated, and the requirement on the bearing capacity of a bearing foundation is high, so that the foundation structure of the tower crane is a necessary condition for keeping the safe operation of the tower crane.
The tower crane foundation structure is generally formed by pouring concrete into a base, and the length, height, width and reinforcing bars of the base need to meet the requirements of the tower crane on overturning stability, foundation bearing capacity and base crack resistance. However, for installing a tower crane in an environment where a basement has been constructed and put into commercial use, a common method is a cast-in-place pile, a steel pipe pile + a lattice steel column, a steel pipe column + a concrete bearing platform or a profile steel platform, and although the above-mentioned various construction methods can meet the requirements of a tower crane foundation structure, due to the complex installation, high cost and poor seismic performance of a combined foundation, the cast-in-place pile or the steel pipe pile cannot be constructed when a multi-layer basement is encountered and a basement bottom plate is finished, the pulling resistance, torsion resistance and bearing capacity of the foundation cannot be guaranteed, and a part of space is occupied, so that the use function of the basement which is put into use is affected. Therefore, in the prior art, an integral reinforced concrete beam is used as a support of the tower crane, and the support column at the bottom of the reinforced concrete beam is supported on the frame column structure of the basement, so that although the construction time is shortened and the support column can be repeatedly used, the rigid reinforced concrete beam structure is poor in anti-seismic performance and is directly supported on the frame column structure of the basement through the support column, so that the connection reliability is poor, the anti-sliding capacity is weak, and the anti-seismic performance is further reduced. In addition, in the prior art, a prefabricated assembled reinforced concrete structure is adopted as a tower crane foundation, so that the problems of incapability of reuse, poor anti-seismic performance and high construction difficulty are solved, but the split assembled reinforced concrete structure is connected with a basement frame column structure through an anti-sliding shaft, so that the reliability is poor, the disassembly and assembly are difficult, the toughness of the reinforced concrete structure is poor, the reinforced concrete structure is easy to damage in the use and transportation process, and the use cost is high. Therefore, in order to solve the problems of the reinforced concrete beam in the prior art, the concrete pressing block is arranged on the longitudinal beam in a pressing mode, so that the longitudinal beam and the cross beam are pressed and fixed tightly to form a tower crane foundation, the tower crane foundation is arranged on a top plate of a basement through a support at the bottom, and although the tower crane foundation is simple to disassemble and assemble, low in cost and not easy to damage, a stacked structure of the tower crane foundation is poor in connection reliability, weak in anti-sliding capacity and poor in overall anti-seismic performance. Therefore, it is necessary to develop an assembled tower crane foundation structure capable of solving the above problems.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a dismouting is convenient, can repeat the turnover use, anti-seismic performance is good, safe and reliable's assembled ballast tower crane foundation structure.
The utility model discloses a realize like this: including tower crane base, cross girder steel, atress steel box girder, bolt, ballast piece, atress steel box girder is rectangle rigid structure, bolt and basement frame column structure fixed connection are passed through to the bottom of atress steel box girder, four tip of cross girder steel are placed respectively on atress steel box girder, the tower crane base is placed on the atress steel box girder of cross girder steel both sides, the ballast piece piles up respectively on the tower crane base of cross girder steel both sides.
The utility model has the advantages that:
1. the utility model discloses a can dismantle and ballast weight that the ballast volume can change to and but the atress steel box girder of industrial processing is as tower crane basis bearing member, with basement frame column structure as the basis, not only saved the expense of buildding the tower crane cushion cap in addition, but also all ballast weights and atress steel box girder size all can calculate in advance confirm and the batch production is prefabricated, but transport quick assembly disassembly after the scene, thereby can repetitious turnover use many times, and overall structure's dismouting and use can not influence the service function of basement.
2. The utility model discloses a atress steel box girder bottom is through bolt and basement frame post structure fixed connection, and not only atress steel box girder toughness is good, and the dismouting and use are not fragile, and its antitorque and shear capacity are strong on the basis of satisfying intensity moreover, and pass through bolted connection's reliability with basement frame post structure higher, can also effectively improve the anti-skidding performance of connecting, and whole anti-seismic performance is stronger.
Therefore, the utility model discloses be particularly suitable for the installation of the various tower cranes under the completion condition of basement bottom plate, have that the dismouting is convenient, can repeat the turnover use, anti-seismic performance is good, safe and reliable's characteristics.
Drawings
FIG. 1 is a schematic view of the present invention;
FIG. 2 is a left side view of FIG. 1;
FIG. 3 is a top view of FIG. 1;
FIG. 4 is a second schematic structural view of the present invention;
FIG. 5 is a schematic view of the connection of the stressed bracket of the present invention;
FIG. 6 is a schematic view of a converting flange according to the present invention;
FIG. 7 is a schematic view of the connection between the weight and the stressed steel box girder;
in the figure: the concrete-based vertical column comprises, by weight, 1-a tower crane base, 2-a cross steel beam, 3-a stressed steel box beam, 3A-a main beam, 3B-a secondary beam, 4-stressed brackets, 4A-supporting plates, 4B-brackets, 4C-side plates, 5-conversion flanges, 5A-top plates, 5B-partition plates, 5C-bottom plates, 6-bolts, 7-weight blocks, 8-fixed vertical columns, 9-lifting lugs, 10-rib plates, 11-basement frame column structures, 12-basement top plates and 13-concrete column piers.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
As shown in fig. 1 to 5, the utility model discloses a tower crane base 1, cross girder steel 2, atress steel box girder 3, bolt 6, ballast weight 7, atress steel box girder 3 is rectangle rigid structure, bolt 6 and basement frame column structure 11 fixed connection are passed through to the bottom of atress steel box girder 3, four tip of cross girder steel 2 are placed respectively on atress steel box girder 3, tower crane base 1 is placed on the atress steel box girder 3 of 2 both sides of cross girder steel, ballast weight 7 piles up respectively on tower crane base 1 of 2 both sides of cross girder steel.
The cross steel beam 2 is used for installing a tower crane underframe.
As shown in fig. 5, the face is accepted at four tip of cross girder steel 2 at 3 tops of atress steel box girder is provided with atress bracket 4, atress bracket 4 includes backup pad 4A, bracket 4B, curb plate 4C, backup pad 4A parallel arrangement is in the top of atress steel box girder 3, backup pad 4A's bottom bilateral symmetry vertical fixation is provided with curb plate 4C, curb plate 4C passes through bracket 4B fixed connection with backup pad 4A, atress bracket 4 passes through both sides board 4C card on the upper portion of atress steel box girder 3 of backup pad 4A bottom, four tip of cross girder steel 2 are placed respectively on backup pad 4A at 3 tops of atress steel box girder steel.
Stress steel box girder 3 includes two parallel arrangement's girder 3A, two parallel fixed secondary beam 3B that set up between girder 3A, bolt 6 and 11 fixed connection of basement frame post structure are passed through at girder 3A's both ends, stress bracket 4 is fixed respectively and is set up in secondary beam 3B's top.
The main beam 3A and the secondary beam 3B are rectangular beams, vertical rib plates 10 are fixedly arranged in the rectangular beams, and the rib plates 10 are fixedly arranged in the main beam 3A and the secondary beam 3B along the axis and/or perpendicular to the axis.
The cross-sectional area of the main beam 3A and/or the secondary beam 3B at any position is the same.
As shown in fig. 4, a concrete pier 13 is provided between the bottom of the secondary beam 3B and the basement roof 12 below the support plate 4A.
The bottom of atress steel box girder 3 is fixed and is provided with a plurality of conversion flanges 5, conversion flange 5 passes through bolt 6 and basement frame column structure 11 fixed connection.
As shown in fig. 6, the conversion flange 5 includes a top plate 5A, a partition plate 5B, and a bottom plate 5C, the top plate 5A and the bottom plate 5C are arranged in parallel and are fixedly connected through the partition plate 5B to form a structure with an open side, a plurality of connection holes are provided in the open side of the partition plate 5B on the bottom plate 5C, and the conversion flange 5 is fixedly connected with the basement frame column structure 11 through bolts 6 passing through the bottom plate 5C.
The baffle 5B is in an I-shaped, cross-shaped, I-shaped, well-shaped or Feng-shaped structure, and the upper end and the lower end of the baffle are respectively fixedly connected with the top plate 5A and the bottom plate 5C.
As shown in fig. 7, the fixed stationary mast 8 that is provided with in top of tower crane base 1, it is provided with the fixed orifices to correspond stationary mast 8 on the weight 7, weight 7 passes stationary mast 8 and piles up on tower crane base 1.
The utility model discloses an installation as follows:
as shown in fig. 1 to 7, before installation, the weight of the weight 7 and the section size of the stressed steel box girder 3 are designed and calculated according to site construction drawings, the bearing capacity of the basement frame column structure 11 is calculated and calculated, and then the weight 7 and the stressed steel box girder 3 are prefabricated in a factory according to the calculated structure. During installation, firstly, the secondary beam of the basement frame column structure 11 is jacked back, roof covering soil of the basement is cleaned, high-strength studs 6 are excavated and fixed on the secondary beam, or preset high-strength studs 6 are cleaned, then conversion flanges 5 are welded or connected through screws at the bottoms of stressed steel box girders 3, the conversion flanges 5 penetrate through the high-strength studs 6 on the basement frame column structure 11 and are screwed down through nuts, stressed brackets 4 are respectively welded on secondary beams 3B of the stressed steel box girders 3, four end parts of the cross-shaped steel girders 2 are respectively placed on supporting plates 4A of the stressed brackets 4, finally, two ends of the tower crane base 1 are respectively and directly placed or connected on the supporting plates 4A of the stressed brackets 4 through bolts, and fixing holes of the prefabricated weight blocks 7 penetrate through fixing upright columns 8 at the top ends of the tower crane base 1, so that the installation of the tower crane base structure is completed. The dismounting process is vice versa.
The above description is only for the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any changes or substitutions that can be easily conceived by those skilled in the art within the technical scope of the present invention should be covered by the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.
Claims (10)
1. The utility model provides an assembled tower crane foundation structure that weighs, its characterized in that includes tower crane base (1), cross girder steel (2), atress steel box girder (3), bolt (6), ballast piece (7), atress steel box girder (3) are rectangle rigid structure, bolt (6) and basement frame column structure (11) fixed connection are passed through to the bottom of atress steel box girder (3), four tip of cross girder steel (2) are placed respectively on atress steel box girder (3), tower crane base (1) is placed on atress steel box girder (3) of cross girder steel (2) both sides, ballast piece (7) are piled up respectively on tower crane base (1) of cross girder steel (2) both sides.
2. The assembled tower crane foundation structure according to claim 1, wherein the top of the stressed steel box girder (3) is provided with stressed brackets (4) on the bearing surfaces of the four ends of the cross-shaped steel girder (2), the stress bracket (4) comprises a support plate (4A), a bracket (4B) and a side plate (4C), the supporting plate (4A) is arranged at the top of the stressed steel box girder (3) in parallel, two sides of the bottom of the supporting plate (4A) are symmetrically and vertically provided with side plates (4C), the side plate (4C) is fixedly connected with the support plate (4A) through a bracket (4B), the stress bracket (4) is clamped at the upper part of the stress steel box girder (3) through two side plates (4C) at the bottom of the support plate (4A), four ends of the cross steel beam (2) are respectively placed on the supporting plate (4A) at the top of the stressed steel box girder (3).
3. The assembled tower crane foundation structure of claim 2, wherein the stressed steel box girder (3) comprises two parallel arranged main girders (3A) and two parallel arranged secondary girders (3B) fixedly arranged between the main girders (3A), the two ends of the main girders (3A) are fixedly connected with the basement frame column structure (11) through bolts (6), and the stressed brackets (4) are respectively and fixedly arranged at the top of the secondary girders (3B).
4. The assembled tower crane foundation structure according to claim 3, wherein the main beam (3A) and the secondary beam (3B) are rectangular beams and are fixedly provided with vertical rib plates (10) inside, and the rib plates (10) are fixedly arranged inside the main beam (3A) and the secondary beam (3B) along the axis and/or perpendicular to the axis.
5. The assembled tower crane substructure according to claim 3, characterized in that the cross-sectional area at any position of the main beams (3A) and/or the secondary beams (3B) is the same.
6. The assembled tower crane foundation structure according to claim 3, wherein lifting lugs (9) are respectively fixedly arranged at the upper parts of main beams (3A) at the two sides of the stressed steel box girder (3).
7. The assembled tower crane foundation structure of claim 1, wherein the bottom of the stressed steel box girder (3) is fixedly provided with a plurality of conversion flanges (5), and the conversion flanges (5) are fixedly connected with the basement frame column structure (11) through bolts (6).
8. The assembled tower crane substructure of claim 7, characterized in that said conversion flange (5) comprises a top plate (5A), a partition plate (5B), and a bottom plate (5C), said top plate (5A) and said bottom plate (5C) are arranged in parallel and are fixedly connected by said partition plate (5B) to form an open-sided structure, said bottom plate (5C) is provided with a plurality of connection holes in the open-sided structure of said partition plate (5B), said conversion flange (5) is fixedly connected with said basement frame column structure (11) by bolts (6) passing through said bottom plate (5C).
9. The assembled tower crane foundation structure of claim 8, wherein the partition (5B) is in an "I" -shaped, a "cross" -shaped, an "I" -shaped, a "well" -shaped or a "Feng" -shaped structure, and the upper and lower ends of the partition are respectively and fixedly connected with the top plate (5A) and the bottom plate (5C).
10. The assembled tower crane foundation structure according to any one of claims 1 to 9, wherein the top end of the tower crane base (1) is fixedly provided with a fixing upright post (8), the weight block (7) is provided with a fixing hole corresponding to the fixing upright post (8), and the weight block (7) passes through the fixing upright post (8) and is stacked on the tower crane base (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021721132.0U CN212336080U (en) | 2020-08-18 | 2020-08-18 | Assembled tower crane foundation structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021721132.0U CN212336080U (en) | 2020-08-18 | 2020-08-18 | Assembled tower crane foundation structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212336080U true CN212336080U (en) | 2021-01-12 |
Family
ID=74070891
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021721132.0U Active CN212336080U (en) | 2020-08-18 | 2020-08-18 | Assembled tower crane foundation structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212336080U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111809654A (en) * | 2020-08-18 | 2020-10-23 | 中建四局第五建筑工程有限公司 | Assembled tower crane foundation structure |
CN113431078A (en) * | 2021-07-20 | 2021-09-24 | 北京市第三建筑工程有限公司 | Tower crane foundation structure for transferring force to existing column and construction method thereof |
-
2020
- 2020-08-18 CN CN202021721132.0U patent/CN212336080U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111809654A (en) * | 2020-08-18 | 2020-10-23 | 中建四局第五建筑工程有限公司 | Assembled tower crane foundation structure |
CN113431078A (en) * | 2021-07-20 | 2021-09-24 | 北京市第三建筑工程有限公司 | Tower crane foundation structure for transferring force to existing column and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212336080U (en) | Assembled tower crane foundation structure | |
CN209941511U (en) | Supporting device for high-altitude folding of bridge steel box girder by section hoisting | |
CN103866784A (en) | Adjustable tower crane steel platform foundation | |
CN111809654A (en) | Assembled tower crane foundation structure | |
CN203808094U (en) | Adjustable tower crane steel platform foundation | |
CN204626266U (en) | Single column pier bridge exempts to build overturning or slip resistance analysis steel structure reinforcing device | |
CN212582721U (en) | Bearing platform of tower crane for vertical tower of top plate of foundation garage | |
CN212611890U (en) | Steel-concrete combined arch bridge crossing karst cave in tunnel | |
CN216892017U (en) | Tie beam integral casting template in template connecting piece and lower stand | |
CN113738125B (en) | Construction method for lifting limited-space large-span steel structure of station house under line | |
CN209906223U (en) | Beam gantry crane | |
CN113738156A (en) | Temporary support structure in limited space and dismantling method thereof | |
CN206844680U (en) | Steel gallery ground assembly load transfer device | |
CN114658031B (en) | Basement roof returning supporting structure of overweight steel structure truss and construction method | |
CN112049253A (en) | Truss body and concrete structure connecting node, truss and method | |
CN220851287U (en) | Integrally-spliced micro-vibration prevention base | |
CN220284900U (en) | Large-tonnage pile-loading extension type ballast platform for foundation piles | |
CN218912360U (en) | Basement reinforced structure | |
CN219343296U (en) | Tower crane foundation based on basement cast-in-situ structural column and steel bearing platform | |
CN216920023U (en) | Support for large cantilever bent cap construction | |
CN219175304U (en) | Steel construction foundation for construction | |
CN211713706U (en) | Large cantilever prefabricated bent cap installation lattice support device | |
CN213390582U (en) | Truss body and concrete structure connected node | |
CN214939356U (en) | Temporary pier | |
CN221052585U (en) | Installation system of full sand layer geological oversized-diameter composite pile steel pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |