CN212317465U - Novel building engineering scaffold - Google Patents

Novel building engineering scaffold Download PDF

Info

Publication number
CN212317465U
CN212317465U CN202020923614.8U CN202020923614U CN212317465U CN 212317465 U CN212317465 U CN 212317465U CN 202020923614 U CN202020923614 U CN 202020923614U CN 212317465 U CN212317465 U CN 212317465U
Authority
CN
China
Prior art keywords
guardrail
connecting block
scaffold
building engineering
board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020923614.8U
Other languages
Chinese (zh)
Inventor
殷南明
黄德林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Changtian Construction Engineering Co ltd
Original Assignee
Shenzhen Changtian Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Changtian Construction Engineering Co ltd filed Critical Shenzhen Changtian Construction Engineering Co ltd
Priority to CN202020923614.8U priority Critical patent/CN212317465U/en
Application granted granted Critical
Publication of CN212317465U publication Critical patent/CN212317465U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model provides a novel building engineering scaffold frame relates to building engineering construction equipment technical field, including supporting the flat board and connecting a plurality of supporting legss that support dull and stereotyped lower surface, two relative long sides are provided with the guardrail on the support flat board, two be connected with between the guardrail and place the board, the lower surface of placing the board all is provided with the connecting block towards the both ends of guardrail, the storage tank that supplies the guardrail to pass is seted up at the connecting block middle part, the connecting block can slide on the guardrail. The utility model provides a novel building engineering scaffold not only can place the required instrument of construction, saves the time of the upper and lower scaffold of constructor, is used for placing the board of placing of instrument moreover and can follow the guardrail and remove, and it is more convenient to use, avoids the constructor to make a round trip to walk on the backup pad and gets and put the instrument, saves the engineering time.

Description

Novel building engineering scaffold
Technical Field
The utility model relates to a building engineering construction equipment technical field especially relates to a novel building engineering scaffold.
Background
The scaffold is a working platform which is erected for ensuring that each construction process is smoothly carried out, and is divided into an outer scaffold and an inner scaffold according to the erected position; the scaffold can be divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials; the scaffold is divided into a vertical rod type scaffold, a bridge type scaffold, a door type scaffold, a suspension type scaffold, a hanging type scaffold, a lifting type scaffold and a climbing type scaffold according to the structural form.
When using the scaffold to carry out construction operation, need carry some instruments or material sometimes and place and carry out construction operation at the scaffold, traditional scaffold does not have the device of placing the material, directly places not only can influence workman's removal on the platform of scaffold, probably still can cause danger.
SUMMERY OF THE UTILITY MODEL
Therefore, the utility model discloses the technical problem that solves lies in overcoming the not enough of prior art to a novel building engineering scaffold is provided, not only can place the required instrument of construction, saves the time of scaffold about the constructor, and the board of placing for placing the instrument moreover can be followed the guardrail and removed, and it is more convenient to use, avoids the constructor to make a round trip to walk on the backup pad and gets and put the instrument, saves the engineering time.
In order to realize the above-mentioned purpose, the utility model provides a novel building engineering scaffold, including supporting the flat board and connecting a plurality of supporting legss at the dull and stereotyped lower surface of support, support two relative long sides on the flat board and be provided with the guardrail, two be connected with between the guardrail and place the board, the lower surface of placing the board all is provided with the connecting block towards the both ends of guardrail, the storage tank that supplies the guardrail to pass is seted up at the connecting block middle part, the connecting block can slide on the guardrail.
Furthermore, the lower end of the containing groove is communicated to the lower surface of the connecting block, and the connecting block can be separated from the guardrail by upwards extracting.
Furthermore, the lower end of the connecting block transversely penetrates through the connecting block to be provided with a locking groove, the locking groove is located below the guardrail, and the locking rod can be detachably inserted into the locking groove.
Furthermore, the locking rod comprises a long rod and two short rods, the short rods are respectively arranged at two ends of the long rod, so that the locking rod is U-shaped, and the length of each short rod is greater than the height of the locking groove and less than the length of the locking groove.
Furthermore, the upper surface of the placing plate is provided with a check ring for fixing the barrel-shaped object.
The utility model provides a pair of novel building engineering scaffold puts up, places the board and is used for placing the required instrument when being under construction, accomplishes the back in one of them construction, at first promotes earlier and places the board, makes the connecting block of placing the board lower surface slide on the guardrail, makes the instrument be located the one side of treating construction department, then the constructor removes to treat that construction department is under construction. The utility model provides a scaffold frame not only can place the required instrument of construction, saves the time of scaffold frame about the constructor, is used for placing the board of placing the instrument moreover and can follow the guardrail removal, and it is more convenient to use, avoids the constructor to make a round trip to walk on the backup pad and gets to put the instrument, saves the engineering time.
Drawings
In order to more clearly illustrate the technical solution of the embodiments of the present invention, the following provides a detailed description of the present invention with reference to the embodiments of the present invention and the accompanying drawings.
Fig. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is an enlarged view taken at A in FIG. 1;
fig. 3 is a schematic structural view of the middle lock rod of the present invention inserted into the lock slot.
The reference numerals in the drawings are explained below.
100. Supporting the flat plate; 200. supporting legs; 300. a guardrail; 400. placing the plate; 500. connecting blocks; 600. a containing groove; 700. locking the groove; 800. a lock lever; 810. a long rod; 820. a short bar; 900. check ring.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings, and obviously, the described embodiments are some, but not all embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "front", "upper", "lower", "left", "right", "vertical", "horizontal", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
As shown in fig. 1 to 3, the novel scaffold for construction engineering comprises a supporting plate 100 and a plurality of supporting legs 200 connected to the lower surface of the supporting plate 100, wherein the supporting legs 200 are inclined towards the outer side of the supporting plate 100 to increase the supporting stability. The length of the support plate 100 and the height of the support foot 200 are designed according to requirements, and the support plate 100 and the support foot 200 can be fixedly connected, or the support foot 200 can be arranged on the lower surface of the support plate 100.
Two opposite long sides of the upper surface of the support plate 100 are provided with guardrails 300, the guardrails 300 refer to rods parallel to the sides of the support plate 100, and it should be noted that both ends of the guardrails 300 are connected to the support plate 100 through vertical rods. Two guardrails 300 are parallel to each other, and are connected with between two guardrails 300 and place board 400, and the lower surface of placing board 400 all is provided with connecting block 500 towards the both ends of guardrail 300, and storage tank 600 has been seted up along the length direction of guardrail 300 at the middle part of connecting block 500, and guardrail 300 passes storage tank 600. The end face of the guardrail 300 is rectangular, and the end face of the receiving groove 600 is rectangular adapted to the guardrail 300, so that the guardrail 300 and the receiving groove 600 are in transition fit. The connecting block 500 is clamped on the guardrail 300 by forming the accommodating groove 600, so that the connecting block 500 is connected with the guardrail 300, and the connecting block 500 can slide along the guardrail 300.
Place board 400 and be used for placing the required instrument of construction time, after one of them department construction is accomplished, at first promote and place board 400, make the connecting block 500 of placing board 400 lower surface slide on guardrail 300, make the instrument be located the one side of treating the construction department, then the constructor moves to treating the construction department and is under construction. The required instrument of construction not only can be placed to the scaffold that this embodiment provided, saves the time of scaffold about the constructor, is used for placing the board 400 of placing of instrument moreover and can follow guardrail 300 and remove, and it is more convenient to use, avoids the constructor to make a round trip to walk about in the backup pad and gets and put the instrument, saves the engineering time.
The lower end of the receiving groove 600 is connected to the lower surface of the connection block 500, and the connection block 500 is withdrawn upward such that the connection block 500 is disconnected from the guard rail 300. This allows the connection block 500 to be removed from the guard rail 300, and in some construction processes where construction is simple and many tools are not required, the presence of the placing plate 400 may hinder the movement of a constructor, so the placing plate 400 and the connection block 500 can be removed from the guard rail 300. The specific scheme is that the lower end of the accommodating groove 600 is communicated to the lower surface of the connecting block 500, and when the connecting block is required to be taken down, the accommodating plate 400 and the connecting block 500 are lifted upwards.
When the placing plate 400 is moved, since the receiving groove 600 communicates with the lower surface of the connecting block 500, the connecting block 500 slides down from the end of the guardrail 300 due to excessive force application, so that the tools fall off, which reduces the construction efficiency. In order to prevent this problem, the lower end of the connecting block 500 is transversely provided with a locking groove 700 in a penetrating manner, the position of the connecting block 500 provided with the locking groove 700 is located below the guardrail 300, and the locking groove 700 is detachably inserted with the locking rod 800. When the locking bar 800 is inserted into the locking groove 700, three sidewalls of the locking bar 800 and the receiving groove 600 form a closed ring shape to surround the guard rail 300, so that the connecting block 500 does not slide off the end of the guard rail 300.
In order to realize that the connection block 500 can be separated from the guard rail 300 under a certain condition and that the connection block 500 has a certain stability when in use, the locking lever 800 includes a long lever 810 and two short levers 820, and the two short levers 820 are respectively provided at both ends of the long lever 810 to make the locking lever 800 in a U-shape. The section of the end of the lock rod 800 is the center of a circle, and the length of the short rod 820 is greater than the diameter of the lock rod 800. The locking slot 700 is rectangular and the length of the short bar 820 is greater than the height of the locking slot 700 and less than the length of the locking slot 700. When the locking rod 800 is inserted, the axes of the short rod 820 and the long rod 810 are in the same horizontal plane, and since the length of the short rod 820 is smaller than that of the locking groove 700, the short rod 820 can horizontally enter the locking groove 700 until one of the short rods 820 penetrates out of the locking groove 700 from the other end, and due to gravity, the axis of the short rod 820 is vertical, and the short rod 820 abuts against the side wall of the connecting block 500, so that the locking rod 800 is relatively stably accommodated in the locking groove 700.
In order to facilitate the placement of the barrel-shaped object above the placement plate 400, the barrel-shaped object is placed stably and cannot be easily toppled over, a lattice retainer ring 900 is arranged on the upper surface of the placement plate 400, and the barrel-shaped object can be placed inside.
It should be understood that the above examples are only for clarity of illustration and are not intended to limit the embodiments. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. And obvious variations or modifications can be made without departing from the scope of the invention.

Claims (5)

1. The utility model provides a novel building engineering scaffold, is including supporting dull and stereotyped and connecting a plurality of supporting legss at the dull and stereotyped lower surface of support, its characterized in that, two relative long sides are provided with the guardrail on the support flat board, two be connected with between the guardrail and place the board, the lower surface of placing the board all is provided with the connecting block towards the both ends of guardrail, the storage tank that supplies the guardrail to pass is seted up at the connecting block middle part, the connecting block can slide on the guardrail.
2. The novel scaffold for building engineering according to claim 1, wherein the lower end of the containing groove is connected to the lower surface of the connecting block, and the connecting block can be separated from the guardrail by upward pulling.
3. The novel scaffold for building engineering as claimed in claim 2, wherein the lower end of the connecting block is transversely penetrated with a locking groove, the locking groove is located below the guardrail, and the locking bar is detachably inserted into the locking groove.
4. A novel scaffold for building engineering according to claim 3, wherein said locking rod comprises a long rod and two short rods, said short rods are respectively disposed at two ends of the long rod to make the locking rod in U-shape, and the length of said short rods is greater than the height of the locking groove and less than the length of the locking groove.
5. The novel scaffold for building engineering according to claim 1, wherein the upper surface of the placing plate is provided with a check ring for fixing barrel-shaped articles.
CN202020923614.8U 2020-05-27 2020-05-27 Novel building engineering scaffold Active CN212317465U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020923614.8U CN212317465U (en) 2020-05-27 2020-05-27 Novel building engineering scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020923614.8U CN212317465U (en) 2020-05-27 2020-05-27 Novel building engineering scaffold

Publications (1)

Publication Number Publication Date
CN212317465U true CN212317465U (en) 2021-01-08

Family

ID=74021763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020923614.8U Active CN212317465U (en) 2020-05-27 2020-05-27 Novel building engineering scaffold

Country Status (1)

Country Link
CN (1) CN212317465U (en)

Similar Documents

Publication Publication Date Title
CN212317465U (en) Novel building engineering scaffold
CN111217282A (en) Lifting platform for installation of waterproof heat-preservation engineering
CN112411992A (en) Construction platform is prevented shaking by suspension type for construction
CN206376503U (en) Heavy construction combined modular scaffold
CN215519816U (en) Detachable bolt-replacing protection platform for steel truss girder
CN212053680U (en) House building construction support with guardrail frame
CN209925011U (en) Locking device for operating handle of hydraulic support
CN209837631U (en) Multistage assembled lattice frame building structure
CN211110645U (en) Lifting appliance for precast beam template
CN212689494U (en) Construction platform for building construction
CN214462816U (en) High-rise building template construction safety device
CN217028750U (en) Safe vertical ladder
CN212387550U (en) Hoisting mechanism for mounting mine electromechanical equipment
CN221321723U (en) Construction ladder for building engineering construction
CN216997397U (en) Anti-falling mounting structure suitable for tower crane standard section ladder frame
CN217871710U (en) Vertical main frame of attached lifting protection platform
CN219691022U (en) Indoor building decoration mobile platform
CN217812226U (en) Construction scaffold
CN215594861U (en) Closed protection device for cantilever scaffold bottom plate
CN214520103U (en) Make things convenient for simple and easy toolbox that oil well cementation device used
CN2267294Y (en) Hanging scaffolds made of steel rope
CN216516975U (en) Novel electric self-elevating discharging platform
CN210973664U (en) Safety anti-falling device for hoisting machinery
CN218581134U (en) Construction scaffold
CN218541409U (en) Safe scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant