CN212273274U CN202020964282.8U CN202020964282U CN212273274U CN 212273274 U CN212273274 U CN 212273274U CN 202020964282 U CN202020964282 U CN 202020964282U CN 212273274 U CN212273274 U CN 212273274U
Authority
CN
China
Prior art keywords
natural gas
gas pipeline
block
connecting seat
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020964282.8U
Other languages
Chinese (zh)
Inventor
龙瑞钧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Ganghua Construction Co ltd
Original Assignee
Shenzhen Ganghua Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Ganghua Construction Co ltd filed Critical Shenzhen Ganghua Construction Co ltd
Priority to CN202020964282.8U priority Critical patent/CN212273274U/en
Application granted granted Critical
Publication of CN212273274U publication Critical patent/CN212273274U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model belongs to the technical field of the natural gas line installation technique and specifically relates to a natural gas line bearing structure is related to, its technical scheme main points are: the natural gas pipeline connecting device comprises a base, a connecting seat and a supporting piece, wherein the connecting seat is arranged on the base in a sliding mode along the direction perpendicular to the length direction of a natural gas pipeline; a horizontal adjusting component is arranged between the connecting seat and the base and is used for adjusting the horizontal position of the connecting seat; the support piece is arranged on the connecting seat in a sliding manner along the vertical direction and used for supporting the natural gas pipeline; a vertical adjusting component is arranged between the connecting seat and the supporting piece and used for adjusting the height of the supporting piece. This bearing structure can realize supporting well the natural gas line.

Description

Natural gas line bearing structure
Technical Field
The utility model belongs to the technical field of the natural gas line installation technique and specifically relates to a natural gas line bearing structure is related to.
Background
The natural gas pipeline is a pipeline for transporting natural gas, including associated gas produced in oil fields, from a mining place or a processing plant to a city gas distribution center or an industrial enterprise user, and is also called a gas transmission pipeline. The natural gas pipeline is used for conveying natural gas, and is a main mode for conveying a large amount of natural gas on land. At present, natural gas line is assembled by a plurality of sections pipeline usually and is constituteed, can use bearing structure to provide the support for natural gas line usually, realizes the relative fixed between natural gas line and the ground.
Chinese patent with publication number CN206419565U discloses a natural gas pipeline supporting structure, which comprises a supporting base and a supporting frame, wherein the supporting frame is installed on the supporting base and used for providing support for the natural gas pipeline. Meanwhile, a vertical hole is formed in the middle of the supporting table, a connecting rod is arranged below the supporting frame and inserted into the vertical hole, and an inclined part with an inclined plane is arranged at the bottom of the connecting rod. The supporting seat is provided with a horizontal hole communicated with the lower end of the vertical hole, and a pushing block matched with the inclined part of the connecting rod is arranged in the horizontal hole in a sliding manner; the horizontal hole is also connected with a screw rod in a threaded manner, the end part of the screw rod, which is positioned in the horizontal hole, is rotatably connected with the pushing block, and the other end of the screw rod is provided with a rotating rod. This bearing structure can cross to support the altitude and suitably adjust, has better suitability.
By using the supporting structure, in the installation process of the natural gas pipeline, if the supporting structure is not level to the height of the natural gas pipeline, the height of the supporting frame can be adjusted through the screw rod, so that the supporting frame is conveniently matched with the natural gas pipeline; however, in the actual installation process, there may be a horizontal position deviation between the support structure and the natural gas pipeline, which may also affect the support stability of the natural gas pipeline by the support structure.
Disclosure of Invention
Not enough to prior art exists, one of the purposes of the utility model is to provide a natural gas line bearing structure, this bearing structure can realize supporting well to natural gas line.
The above technical purpose of the present invention can be achieved by the following technical solutions: a natural gas pipeline supporting structure comprises a base, a connecting seat and a supporting piece, wherein the connecting seat is arranged on the base in a sliding mode along the direction perpendicular to the length direction of a natural gas pipeline; a horizontal adjusting component is arranged between the connecting seat and the base and is used for adjusting the horizontal position of the connecting seat; the support piece is arranged on the connecting seat in a sliding manner along the vertical direction and used for supporting the natural gas pipeline; and a vertical adjusting component is arranged between the connecting seat and the supporting piece and used for adjusting the height of the supporting piece.
By adopting the technical scheme, in the installation process of the natural gas pipeline, if the height of the supporting piece is not level with the height of the natural gas pipeline, the height of the supporting piece can be adjusted through the vertical adjusting assembly; meanwhile, under the condition that the horizontal position of the supporting piece and the horizontal position of the natural gas pipeline have deviation, the horizontal adjusting assembly can be used for adjusting the position of the connecting seat, and the effect of adjusting the horizontal position of the supporting piece is achieved; and then can make the support piece among the bearing structure keep with natural gas line's good cooperation, promote bearing structure to natural gas line's support stability.
Preferably, the base upper surface is equipped with the spout along perpendicular and natural gas line length direction, the lower surface of connecting seat is equipped with the slider, the slider slides with the spout and cooperates.
Through adopting above-mentioned technical scheme, the slider cooperates with the spout slides, realizes sliding between connecting seat and the base and is connected, and simple structure is practical.
Preferably, the base is internally provided with a mounting groove communicated with the sliding groove, the length direction of the mounting groove is the same as that of the sliding groove, and the sliding block extends into the mounting groove; the horizontal adjusting assembly comprises a first screw rod and a holding piece, and the first screw rod is rotatably arranged in the mounting groove along the length direction of the mounting groove; the first screw penetrates through the sliding block and is in threaded connection with the sliding block; one end of the first screw rod penetrates through the side wall of the base from the groove wall of the mounting groove, and the holding piece is arranged at one end, located outside the side wall of the base, of the first screw rod.
Through adopting above-mentioned technical scheme, the slider slides with the spout and is connected and with first screw rod threaded connection, uses the gripping member to rotate first screw rod, can drive the slider along the length direction motion of first screw rod, reaches the effect that the drive connecting block moved along the spout direction.
Preferably, the upper surface of the connecting seat is provided with an accommodating groove along the vertical direction, and the lower surface of the supporting piece is provided with a lifting block; the lifting block is accommodated in the accommodating groove and is matched with the accommodating groove in a sliding manner.
Through adopting above-mentioned technical scheme, the elevator block holding is in the storage tank to with the storage tank cooperation of sliding, realize the sliding connection between support piece and the connecting seat.
Preferably, the vertical adjusting assembly comprises a second screw rod, a connecting block, a limiting piece and a connecting rod; the second screw rod is horizontally and rotatably arranged in the accommodating groove, two connecting blocks are arranged, the two connecting blocks are sleeved on the second screw rod, one connecting block is in forward threaded connection with the second screw rod, and the other connecting block is in reverse threaded connection with the second screw rod; the limiting piece is used for limiting the connecting block, so that the connecting block is driven by the second screw rod to move along the length direction of the second screw rod; the connecting rod has two, two the one end one-to-one of connecting rod articulates in two connecting blocks, and the other end all articulates in the elevator.
Through adopting above-mentioned technical scheme, rotate the second screw rod, two connecting blocks are close to each other or keep away from along the length of second screw rod in the effect of locating part, utilize two connecting rods to the transmission effect of power, and the drive elevator goes up and down to the realization is to the regulation of support piece height.
Preferably, the limiting piece is a limiting rod, and the limiting rod is arranged in the accommodating groove along the length direction of the second screw rod; the limiting rod penetrates through the connecting block and is matched with the connecting block in a sliding mode.
Through adopting above-mentioned technical scheme, the direction that the gag lever post set up is the same with the length direction of second screw, utilizes sliding between gag lever post and the connecting block to be connected, can play the limiting displacement to the connecting block to make the connecting block receive the drive to move along the length direction of second screw.
Preferably, the support member comprises a first half ring and a second half ring which are spliced with each other, and the inner annular walls of the first half ring and the second half ring are matched with the outer wall of the natural gas pipeline.
Through adopting above-mentioned technical scheme, the support piece that uses first semi-ring and second semi-ring amalgamation to form supports the natural gas line, can keep the stable connection between support piece and the natural gas line, reduces the natural gas line and receives the external force effect and break away from the condition mutually with support piece.
Preferably, both ends of the first half ring are provided with first connecting plates, and both ends of the second half ring are provided with second connecting plates; the first connecting plate is abutted against the second connecting plate, and the first connecting plate and the second connecting plate are relatively fixed through bolts.
Through adopting above-mentioned technical scheme, use the bolt to be connected first connecting plate with the second connecting plate, realize the amalgamation of first semi-ring and second semi-ring, easy and simple to handle and stability height.
To sum up, the utility model discloses a following at least one useful technological effect:
1. the height and the horizontal position of the supporting piece can be adjusted, so that the supporting piece in the supporting structure keeps good fit with the natural gas pipeline, and the supporting stability of the supporting structure on the natural gas pipeline is improved;
2. the natural gas pipeline is supported by the supporting piece formed by splicing the first half ring and the second half ring, so that the stable connection between the supporting piece and the natural gas pipeline can be kept, and the condition that the natural gas pipeline is separated from the supporting piece under the action of external force is reduced.
Drawings
Fig. 1 is a schematic sectional structure diagram of an embodiment of the present invention.
Reference numerals: 1. a base; 1a, a chute; 1b, mounting grooves; 2. a connecting seat; 2a, a sliding block; 2b, a containing groove; 3. a support member; 31. a first half ring; 31a, a first connecting plate; 32. a second half ring; 32a, a second connecting plate; 4. a level adjustment assembly; 41. a first screw; 42. rotating the block; 5. a vertical adjustment assembly; 51. a second screw; 52. connecting blocks; 53. a limiting rod; 54. a connecting rod; 6. a lifting block.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1, a natural gas pipeline supporting structure disclosed by the present invention comprises a base 1, a connecting seat 2 and a supporting member 3, wherein the base 1 is rectangular plate-shaped, and the base 1 is installed on the ground; meanwhile, the upper surface of the base 1 is provided with a chute 1a along a direction perpendicular to the natural gas pipeline. The connecting seat 2 is arranged on the base 1, and the lower surface of the connecting seat 2 is abutted against the upper surface of the base 1; meanwhile, the lower surface of the connecting seat 2 is fixedly provided with a sliding block 2 a. The slider 2a is located the spout 1a, and the slider 2a and the cooperation of sliding of spout 1a realize the connection of sliding between connecting seat 2 and the base 1.
Referring to fig. 1, a horizontal adjusting assembly 4 is installed between a base 1 and a connecting seat 2, and is used for adjusting the horizontal position of the connecting seat 2; simultaneously, mounting groove 1b has been seted up along the length direction of spout 1a in the inside of base 1, and mounting groove 1b is linked together with spout 1a, and the one end that connecting seat 2 was kept away from to slider 2a stretches into in mounting groove 1 b. The horizontal adjusting assembly 4 comprises a first screw rod 41 and a rotary block 42; the first screw 41 is rotatably mounted in the mounting groove 1b along the length direction of the mounting groove 1b, and the first screw 41 penetrates through the sliding block 2a and is in threaded connection with the sliding block 2 a. One end of the first screw rod 41 penetrates through the wall of the mounting groove 1b to the outer wall of the base 1, and the rotary block 42 is fixedly mounted at one end of the first screw rod 41 penetrating out of the outer wall of the base 1 and used for being held by a worker.
Referring to fig. 1, a support member 3 is installed above the connection seat 2 to provide support for the natural gas pipeline; specifically, the support 3 comprises a first half ring 31 and a second half ring 32 which are spliced with each other, and the inner annular walls of the first half ring 31 and the second half ring 32 are both matched with the outer wall of the natural gas pipeline; meanwhile, both ends of the first half ring 31 are provided with first connection plates 31a, and both ends of the second half ring 32 are provided with second connection plates 32 a. When the first half ring 31 and the second half ring 32 are connected, the surfaces of the first connecting plate 31a opposite to the second connecting plate 32a abut against each other, and the first connecting plate 31a and the second connecting plate 32a are fixed to each other by bolts. In addition, the lifting block 6 is welded on the lower surface of the first half ring 31, and correspondingly, the vertical accommodating groove 2b is formed in the upper surface of the connecting seat 2; the lifting block 6 is accommodated in the accommodating groove 2b, and the lifting block 6 is in sliding fit with the accommodating groove 2b, so that the sliding connection between the first half ring 31 and the connecting seat 2 along the vertical direction is realized.
Referring to fig. 1, a vertical adjusting assembly 5 is installed between the connecting seat 2 and the lifting block 6 for adjusting the height of the lifting block 6; specifically, the vertical adjustment assembly 5 includes a second screw 51, a connection block 52, a limit rod 53, and a connection rod 54. The second screw 51 is horizontally arranged, and the second screw 51 is rotatably arranged between two opposite groove walls of the accommodating groove 2b along a direction perpendicular to the length of the natural gas pipeline; meanwhile, one end of the first screw rod 41 penetrates from the groove wall of the accommodating groove 2b to the outer wall of the connecting seat 2, and is provided with a holding piece for holding by a worker.
Referring to fig. 1, there are two connection blocks 52, two connection blocks 52 are both sleeved on the second screw 51, one connection block 52 and the second screw 51 form a forward threaded connection, and the other connection block 52 and the second screw 51 form a reverse threaded connection. The limiting rod 53 is installed in the accommodating groove 2b along the length direction of the second screw 51, and the limiting rod 53 penetrates through the connecting block 52 and is in sliding fit with the connecting block 52; the connecting block 52 is limited by the sliding connection between the limiting rod 53 and the connecting block 52, so that the connecting block 52 can move along the length direction of the second screw 51 after being driven. Two connecting rods 54 are provided, one ends of the two connecting rods 54 are correspondingly hinged to the two connecting blocks 52 one by one, and the other ends of the two connecting rods 54 are hinged to the upper surface of the lifting block 6; when the two connecting blocks 52 are driven by the screw to approach or separate from each other, the effect of driving the lifting block 6 to lift is realized by the transmission action of the connecting rod 54 between the connecting blocks 52 and the lifting block 6.
The implementation principle of the embodiment is as follows: in the installation process of the natural gas pipeline, if the supporting piece 3 is not level with the height of the natural gas pipeline, the second screw 51 is rotated to drive the two connecting blocks 52 to be close to or far away from each other, and the height of the supporting piece 3 is adjusted by utilizing the transmission effect of the connecting rod 54 between the connecting blocks 52 and the lifting block 6. Meanwhile, under the condition that the horizontal position of the support member 3 and the natural gas pipeline has deviation, the knob is used for driving the first screw rod 41 to rotate, the sliding block 2a moves along the length direction of the first screw rod 41, and the horizontal position of the connecting seat 2 is adjusted, namely the horizontal position of the support member 3 is adjusted. And then can make support piece 3 among the bearing structure keep with natural gas line's good cooperation, promote bearing structure to natural gas line's support stability.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.

Claims (8)

1. A natural gas pipeline bearing structure which characterized in that: the natural gas pipeline connecting device comprises a base (1), a connecting seat (2) and a supporting piece (3), wherein the connecting seat (2) is arranged on the base (1) in a sliding manner along the direction vertical to the length direction of a natural gas pipeline;
a horizontal adjusting component (4) is arranged between the connecting seat (2) and the base (1) and is used for adjusting the horizontal position of the connecting seat (2); the support piece (3) is arranged on the connecting seat (2) in a sliding manner along the vertical direction and used for supporting the natural gas pipeline;
a vertical adjusting component (5) is arranged between the connecting seat (2) and the supporting piece (3) and used for adjusting the height of the supporting piece (3).
2. A natural gas pipeline support structure as claimed in claim 1, wherein: the base (1) upper surface is equipped with spout (1a) along perpendicular and natural gas line length direction, the lower surface of connecting seat (2) is equipped with slider (2a), slider (2a) and spout (1a) cooperation of sliding.
3. A natural gas pipeline support structure as claimed in claim 2, wherein: the inner part of the base (1) is provided with a mounting groove (1b) communicated with the sliding groove (1a), the length direction of the mounting groove (1b) is the same as that of the sliding groove (1a), and the sliding block (2a) extends into the mounting groove (1 b);
the horizontal adjusting component (4) comprises a first screw rod (41) and a holding piece, and the first screw rod (41) is rotatably arranged in the mounting groove (1b) along the length direction of the mounting groove (1 b);
the first screw rod (41) penetrates through the sliding block (2a) and is in threaded connection with the sliding block (2 a);
one end of the first screw rod (41) penetrates out of the side wall of the base (1) from the groove wall of the mounting groove (1b), and the holding piece is arranged at one end, located outside the side wall of the base (1), of the first screw rod (41).
4. A natural gas pipeline support structure as claimed in claim 1, wherein: an accommodating groove (2b) is formed in the upper surface of the connecting seat (2) in the vertical direction, and a lifting block (6) is arranged on the lower surface of the supporting piece (3);
the lifting block (6) is accommodated in the accommodating groove (2b) and is matched with the accommodating groove (2b) in a sliding manner.
5. The natural gas pipeline support structure of claim 4, wherein: the vertical adjusting assembly (5) comprises a second screw rod (51), a connecting block (52), a limiting piece and a connecting rod (54);
the second screw rods (51) are horizontally and rotatably arranged in the accommodating groove (2b), two connecting blocks (52) are arranged, the two connecting blocks (52) are sleeved on the second screw rods (51), one connecting block (52) is in forward threaded connection with the second screw rods (51), and the other connecting block (52) is in reverse threaded connection with the second screw rods (51);
the limiting piece is used for limiting the connecting block (52) and enabling the connecting block (52) to be driven by the second screw rod (51) to move along the length direction of the second screw rod (51);
the number of the connecting rods (54) is two, one end of each connecting rod (54) is hinged to the two connecting blocks (52) in a one-to-one correspondence mode, and the other end of each connecting rod is hinged to the lifting block (6).
6. A natural gas pipeline support structure as claimed in claim 5, wherein: the limiting piece is a limiting rod (53), and the limiting rod (53) is arranged in the accommodating groove (2b) along the length direction of the second screw (51); the limiting rod (53) penetrates through the connecting block (52) and is matched with the connecting block (52) in a sliding mode.
7. A natural gas pipeline support structure as claimed in claim 1, wherein: the support piece (3) comprises a first half ring (31) and a second half ring (32) which are spliced with each other, and the inner ring walls of the first half ring (31) and the second half ring (32) are matched with the outer wall of the natural gas pipeline.
8. A natural gas pipeline support structure as claimed in claim 7, wherein: two ends of the first half ring (31) are respectively provided with a first connecting plate (31a), and two ends of the second half ring (32) are respectively provided with a second connecting plate (32 a); the first connecting plate (31a) is abutted against the second connecting plate (32a), and the first connecting plate (31a) and the second connecting plate (32a) are relatively fixed through bolts.
CN202020964282.8U 2020-05-29 2020-05-29 Natural gas line bearing structure Active CN212273274U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020964282.8U CN212273274U (en) 2020-05-29 2020-05-29 Natural gas line bearing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020964282.8U CN212273274U (en) 2020-05-29 2020-05-29 Natural gas line bearing structure

Publications (1)

Publication Number Publication Date
CN212273274U true CN212273274U (en) 2021-01-01

Family

ID=73880040

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020964282.8U Active CN212273274U (en) 2020-05-29 2020-05-29 Natural gas line bearing structure

Country Status (1)

Country Link
CN (1) CN212273274U (en)

Similar Documents

Publication Publication Date Title
CN212273274U (en) Natural gas line bearing structure
CN210361949U (en) Simple and easy air conditioner installation wall body drilling equipment
CN207484978U (en) A kind of civil construction support device
CN214101097U (en) Base structure of generator set
CN212918098U (en) Multifunctional carrier roller device
CN110451439B (en) Hand-push type aviation hydraulic comprehensive vehicle
CN211681955U (en) Power station equipment maintenance auxiliary device
CN210324916U (en) Movable warning board for coal mine safety
CN2342097Y (en) Simple and adjustable mould lining-building step-building vehicle for double line channel
CN210193247U (en) Wall-hanging crane frame
CN221092515U (en) Groove type carrier roller frame
CN207944148U (en) A kind of crane
CN218478115U (en) Rotation angle adjusting mechanism for carrier roller of belt conveyor
CN212387103U (en) Portable simple single-rod cap opener
CN217078595U (en) Adjustable scaffold for water conservancy construction
CN212356747U (en) Liftable aeration and filling integrated device
CN214356200U (en) A quick handling device for teaching equipment
CN220331315U (en) Gantry type manipulator for overturning photovoltaic inverter
CN212579912U (en) Prefabricated component transfer conveyer is built in room
CN210958020U (en) Base capable of adjusting position of motor
CN215796591U (en) Modular groove-shaped carrier roller
CN210879646U (en) Robot base casting convenient for height adjustment
CN214377163U (en) Sand table is used in tourism management teaching
CN218703168U (en) Jacking device for new energy power conversion station
CN217996671U (en) Heavy-load jacking mechanism

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant