CN212271353U - Precast concrete steel construction combination building structure - Google Patents
Precast concrete steel construction combination building structure Download PDFInfo
- Publication number
- CN212271353U CN212271353U CN202021957027.7U CN202021957027U CN212271353U CN 212271353 U CN212271353 U CN 212271353U CN 202021957027 U CN202021957027 U CN 202021957027U CN 212271353 U CN212271353 U CN 212271353U
- Authority
- CN
- China
- Prior art keywords
- precast concrete
- steel
- plate
- pouring
- fixedly connected
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model relates to a building field discloses a precast concrete steel construction combination building structure, including two at least precast concrete slab subassemblies that set up side by side interval, pour board and self-leveling layer. The precast concrete plate assemblies comprise concrete plates and steel beams, the steel beams are fixedly connected to the side parts of the concrete plates, the tops of the steel beams of two adjacent precast concrete plate assemblies are fixedly connected with each other, and the side walls of the concrete plates fixedly connected with the steel beams are matched with the tops of the steel beams to form pouring grooves with upward notches; pouring the pouring plate into the pouring groove; the self-leveling layer covers the upper surfaces of the precast concrete plate component and the pouring plate. Compare steel construction building floor, the utility model has the advantages of rigidity is high, stable in structure and the damage of being difficult for droing of levelling layer certainly, and it only pours the board and need pour the shaping, consequently need not the large tracts of land and pours the construction, after precast concrete plate subassembly sets up side by side the interval, the staff can carry out other constructions in step, has improved the building efficiency of construction.
Description
Technical Field
The utility model relates to a building technical field especially relates to a precast concrete steel construction combined building structure.
Background
The modular building is an emerging building structure system, each room is taken as a module unit, prefabricated production is carried out in a factory, and the prefabricated building is transported to the site after completion and assembled into a building whole in a reliable connection mode.
The construction of the existing modularized factory building mostly adopts a steel structure, and the floor slab mostly adopts a steel plate. However, for some industrial plants with special requirements, the steel structure floor slab has more defects. Such as pharmaceutical factories, which have cleanliness requirements for the ground, and therefore, it is usually considered to lay an epoxy mortar surface course. However, the epoxy mortar is thin, and cannot form good adhesion with a steel plate, so that the epoxy mortar surface layer is easy to fall off and damage; meanwhile, due to the fact that the rigidity of the steel plate is not enough, when personnel move and equipment or a material trolley moves, the epoxy mortar surface layer is prone to cracking and falling off. Therefore, the floor slab of the steel structure paved with the epoxy mortar surface layer can not meet the special requirements of production or working environment. Although some modular plants adopt a concrete floor slab formed by in-situ concrete pouring to solve the problems, the maintenance period is long after the concrete is poured, and other installation works in the building process need to be carried out until the concrete reaches a certain strength, so that the construction efficiency is reduced.
Therefore, it is highly desirable to provide a precast concrete steel structure combined building structure capable of solving the above problems.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a precast concrete steel construction combination building structure, it has the advantage that rigidity is high, stable in structure and the leveling layer is difficult for droing the damage of flowing automatically, can improve staff's building efficiency of construction simultaneously.
To achieve the purpose, the utility model adopts the following technical proposal:
a precast concrete steel structure combination building structure, comprising:
the prefabricated concrete plate components are arranged side by side at intervals and comprise concrete plates and steel beams, the steel beams are fixedly connected to the side portions of the concrete plates, the tops of the steel beams of two adjacent prefabricated concrete plate components are fixedly connected with each other, and the side walls of the concrete plates fixedly connected with the steel beams are matched with the tops of the steel beams to form pouring grooves with upward notches;
the pouring plate is poured and formed in the pouring groove;
and the self-leveling layer covers the upper surfaces of the precast concrete plate component and the pouring plate.
Optionally, the precast concrete steel structure combination building structure further includes:
and the tops of the steel beams of the two adjacent precast concrete plate assemblies are fixedly connected through the connecting plate.
Optionally, one end of the connecting plate is welded to one of the two adjacent steel beams, and the other end of the connecting plate is welded to the other of the two adjacent steel beams.
Optionally, one end of the connecting plate is bolted and connected to one of the two adjacent steel beams, and the other end of the connecting plate is bolted and connected to the other of the two adjacent steel beams.
Optionally, the precast concrete steel structure combination building structure further includes:
and the lower end surface of the anti-cracking gridding cloth covers the connecting seams formed between the precast concrete plate assemblies and the pouring plates, and the upper end surface of the anti-cracking gridding cloth is attached to the lower surface of the self-leveling layer.
Optionally, the anti-cracking mesh cloth covers the upper surface of the pouring plate, and one end of the anti-cracking mesh cloth extends into the length of the upper surface of one of the precast concrete plate assemblies and the other end of the anti-cracking mesh cloth extends into the length of the upper surface of the other precast concrete plate assembly, which are not less than 150 mm.
Optionally, the precast concrete panel assembly further includes:
and the angle steel is fixedly connected to the side wall of the concrete slab, and the top of the steel beam is fixedly connected to the angle steel.
Optionally, an anti-cracking steel mesh is arranged in the pouring plate.
Optionally, the self-leveling layer is an epoxy self-leveling layer or a cement self-leveling layer.
Optionally, the steel beam is an i-shaped steel.
The utility model has the advantages that:
compared with a steel structure floor slab in the prior art, the precast concrete steel structure combined building structure has the advantages that the steel structure and the concrete structure are combined, the tops of the steel beams of the two adjacent precast concrete plate assemblies are fixedly connected with each other, the side wall of the concrete plate fixedly connected with each steel beam is matched with the top of each steel beam to form a pouring groove with an upward notch, and the pouring plate is poured and formed in the pouring groove to form a whole; the self-leveling layer covers the upper surfaces of the precast concrete plate assembly and the pouring plate, and has the advantages of high rigidity, stable structure and difficult falling and damage of the self-leveling layer; and moreover, only the pouring plate needs to be poured and molded, the precast concrete plate assemblies are all of a pre-molded structure, large-area pouring construction is not needed, and after the precast concrete plate assemblies are arranged side by side at intervals, workers can synchronously carry out other construction operations while pouring and molding the pouring plate, so that the building construction efficiency is improved.
Drawings
Fig. 1 is a schematic cross-sectional plan view of a precast concrete steel structure composite building structure provided by the present invention;
FIG. 2 is an enlarged view of a portion of FIG. 1 at A;
fig. 3 is a schematic cross-sectional view of a precast concrete panel assembly provided by the present invention.
In the figure:
x-horizontal direction; y-vertical direction;
1-prefabricating a concrete plate component; 11-a concrete slab; 12-a steel beam; 13-angle steel; 2, pouring a plate; 3-self-leveling layer; 4-connecting plates; 5-anti-cracking mesh cloth; 6-anti-cracking reinforcing steel bar mesh.
Detailed Description
In order to make the technical problem solved by the present invention, the technical solution adopted by the present invention and the technical effect achieved by the present invention clearer, the technical solution of the present invention will be further explained by combining the drawings and by means of the specific implementation manner.
In the description of the present invention, unless expressly stated or limited otherwise, the terms "connected," "connected," and "fixed" are to be construed broadly, e.g., as meaning permanently connected, detachably connected, or integral to one another; can be mechanically or electrically connected; either directly or indirectly through intervening media, either internally or in any other relationship. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
In the present disclosure, unless expressly stated or limited otherwise, the first feature "on" or "under" the second feature may comprise direct contact between the first and second features, or may comprise contact between the first and second features not directly. Also, the first feature being "on," "above" and "over" the second feature includes the first feature being directly on and obliquely above the second feature, or merely indicating that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature includes the first feature being directly under and obliquely below the second feature, or simply meaning that the first feature is at a lesser elevation than the second feature.
In the description of the present embodiment, the terms "upper", "lower", "left", "right", and the like are used in the orientation or positional relationship shown in the drawings only for convenience of description and simplicity of operation, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and thus should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used only for descriptive purposes and are not intended to have a special meaning.
Example one
As shown in fig. 1-2, the embodiment provides a precast concrete steel structure combined building structure, which is used for replacing a floor slab with a pure steel plate structure of a modular factory building, and has the advantages of high rigidity, stable structure and difficulty in falling and damage from a leveling layer, and meanwhile, the building construction efficiency of workers can be improved, wherein X represents a horizontal direction, and Y represents a vertical direction. The precast concrete steel structure combined building structure mainly comprises at least two precast concrete plate assemblies 1 arranged side by side at intervals, a pouring plate 2 and a self-leveling layer 3, wherein the self-leveling layer 3 can be an epoxy self-leveling layer or a cement self-leveling layer, in the embodiment, the self-leveling layer 3 can be an epoxy self-leveling layer, has chemical properties such as water resistance, oil resistance, acid and alkali resistance, salt mist corrosion resistance and the like, and physical properties such as wear resistance, punching resistance, scrubbing resistance and the like, has a bright surface, is smooth, attractive, seamless, easy to clean, easy to maintain and durable, and can meet the requirements of modern industry on terraces. The precast concrete panel assemblies 1 comprise concrete plates 11 and steel beams 12, wherein the steel beams 12 are fixedly connected to the side parts of the concrete plates 11, the top parts of the steel beams 12 of two adjacent precast concrete panel assemblies 1 are fixedly connected with each other, and the side wall of the concrete plate 11 fixedly connected with each steel beam 12 is matched with the top part of each steel beam 12 to form a pouring groove (not marked in the figure) with an upward notch; the pouring plate 2 is poured and formed in the pouring groove; the self-leveling layer 3 covers the upper surfaces of the precast concrete plate component 1 and the pouring plate 2.
Compare steel construction floor among the prior art, the precast concrete steel construction combination building structure of this embodiment has carried out the integrated design with steel construction and concrete structure, has integrated respective advantage. The tops of the steel beams 12 of the two adjacent precast concrete plate assemblies 1 are fixedly connected with each other and matched with the side wall of the concrete plate 11 fixedly connected with each steel beam 12 to form a pouring groove with an upward notch, and the pouring plates 2 are poured and formed in the pouring grooves to form a whole; the self-leveling layer 3 covers the upper surfaces of the precast concrete plate assemblies 1 and the pouring plates 2, and a ground structure formed by combining a concrete structure and a steel frame structure is adopted to replace the ground of a steel plate structure, so that the self-leveling layer has the advantages of high rigidity, stable structure and difficulty in falling off and damage of the self-leveling layer 3; moreover, only the pouring plates 2 need to be poured and formed, and the precast concrete plate assemblies 1 are all pre-formed structures, so that when the facility building of the floor slab of the modular plant is carried out, large-area pouring construction is not needed, after the precast concrete plate assemblies 1 are arranged side by side at intervals, other construction operations can be synchronously carried out when the pouring plates 2 are poured and formed by workers, and further the building construction efficiency is improved.
In addition, according to different floor construction needs, the spacing distance of precast concrete panel assemblies 1 that set up side by side at intervals may need to be different, so in order to improve the flexibility of spacing distance adjustment when fixedly connecting between the girder 12 of adjacent precast concrete panel assemblies 1. Further, as shown in fig. 1-2, in this embodiment, the precast concrete steel structure combined building structure further includes a connecting plate 4, tops of the steel beams 12 of two adjacent precast concrete plate assemblies 1 are fixedly connected through the connecting plate 4, so that a worker can flexibly adjust a spacing distance between the precast concrete plate assemblies 1, and then the tops of the steel beams 12 of two adjacent precast concrete plate assemblies 1 are fixedly connected through the connecting plate 4. Specifically, one end of the connecting plate 4 is welded to one of the two adjacent steel beams 12, and the other end of the connecting plate 4 is welded to the other of the two adjacent steel beams 12, so that the welding connection structure is stable and simple. In other embodiments, one end of the connecting plate 4 can also be connected to one of the two adjacent steel beams 12 through bolt fastening, and the other end of the connecting plate 4 can also be connected to the other of the two adjacent steel beams 12 through bolt fastening, so that compared with welding, through bolt fastening, equipment such as a welding machine required by construction is omitted, electric welding operation is not required, and construction is relatively safer.
Further, in order to improve the rigidity of the concrete slab 11 and the stability of the connection with the steel beam 12. As shown in fig. 1-2, in this embodiment, the precast concrete panel assembly 1 further includes angle iron 13. The angle steel 13 is fixedly connected to the side wall of the concrete slab 11, and the top of the steel beam 12 is fixedly connected to the angle steel 13.
Further, as shown in fig. 1-3, in the present embodiment, the steel beam 12 is an i-shaped steel. In other embodiments, the prefabricated concrete steel structure combined building structure can also be H-shaped, T-shaped or other shapes, and the I-shaped steel has good compression resistance and deformation resistance, so that the rigidity and stability of the prefabricated concrete steel structure combined building structure can be effectively improved.
As can be seen, in the present embodiment, the precast concrete panel assembly 1 includes a concrete panel 11, a steel beam 12, and angle irons 13. When a factory building floor is constructed, the precast concrete plate assembly 1 replaces a steel structure floor, so that the ground formed by the precast concrete plate assembly 1 is the ground of a concrete structure, the structure is stable, and the self-leveling layer 3 is not easy to separate from and damage; meanwhile, the precast concrete board assembly 1 is produced, processed and manufactured in advance in a precast structural member factory building, therefore, when the floor is built, the precast concrete board assembly 1 can be directly spliced and lapped on different floors of the factory building to form the floor, compared with the floor formed by pouring concrete on site, the precast concrete board assembly 1 of the embodiment greatly improves the construction efficiency of the factory building floor construction, large-area pouring operation is not needed, only pouring work of the pouring plate 2 needs to be completed, meanwhile, workers can also synchronously perform other construction operations, therefore, the construction efficiency of the factory building floor construction is further improved, the construction period is greatly shortened, and the time cost and the construction cost are saved.
Further, in order to improve the rigidity, stability and crack resistance of the casting plate 2. As shown in fig. 1-2, in the present embodiment, an anti-cracking steel mesh 6 is disposed in the casting plate 2. When the casting plate 2 is cast, the anti-cracking reinforcing mesh 6 is firstly placed in the casting groove, and then the casting of the casting plate 2 is carried out, so that the anti-cracking reinforcing mesh 6 can be integrally formed in the casting plate 2, and the rigidity, the stability and the anti-cracking capability of the casting plate 2 are further improved.
In addition, as shown in fig. 2, the precast concrete steel structure combined building structure further includes an anti-cracking mesh fabric 5. The lower end face of the anti-cracking gridding cloth 5 covers a connecting seam (not marked in the drawing) formed between each precast concrete plate component 1 and the pouring plate 2, the upper end face of the anti-cracking gridding cloth 5 is attached to the lower surface of the self-leveling layer 3, and the anti-cracking performance of the self-leveling layer 3 can be improved by additionally arranging the anti-cracking gridding cloth 5. Specifically, in this embodiment, anti-cracking gridding cloth 5 covers in the upper surface of pouring board 2, and the one end of anti-cracking gridding cloth 5 stretches into the length of one of precast concrete board components 1's upper surface and the other end of anti-cracking gridding cloth 5 stretches into the length of another precast concrete board components 1's upper surface all is not less than 150mm, and then can effectually cover the joint line that forms between each precast concrete board component 1 and the pouring board 2, avoid the joint line excessive fracture and lead to the appearance of 3 short circuit phenomena of flowing flat layer. The anti-cracking mesh cloth 5 in the embodiment is an alkali-resistant mesh cloth, has the characteristics of light weight, high strength, temperature resistance, alkali resistance, water resistance, corrosion resistance, cracking resistance and stable size, and can effectively avoid surface tension shrinkage at the joint position and cracking caused by external force.
Example two
The present embodiment proposes a method for manufacturing a precast concrete steel structure composite building structure as shown in fig. 1 to 3, which is proposed in the first embodiment, and the method for manufacturing the precast concrete steel structure composite building structure comprises the following steps:
prefabricated precast concrete panel assembly 1: completing the prefabrication and molding of the precast concrete plate component 1 in a prefabrication factory;
the precast concrete board subassembly 1 is assembled and connected: assembling the two precast concrete plate assemblies 1 on the installation position of a factory building at intervals side by side, and then fixedly connecting the steel beams 12 of the two precast concrete plate assemblies 1 to form a pouring groove;
pouring, molding and pouring the plate 2: pouring and filling pouring concrete into the pouring groove to form a pouring plate 2;
laying a self-leveling layer 3: and laying a self-leveling layer 3 on the upper surfaces of the pouring plate 2 and the precast concrete plate component 1.
Compare the concrete floor that current pure concrete field pouring formed and the floor that adopts steel sheet structure to build, the manufacturing method of the precast concrete steel structure combined building structure of this embodiment has following advantage:
1. the ground structure formed by combining the concrete structure and the steel frame structure is adopted to replace the ground with the steel plate structure, and the self-leveling floor has the advantages of high rigidity, stable structure and difficult falling and damage of the self-leveling floor 3;
2. it only need pour the shaping to pour board 2, and precast concrete board subassembly 1 is the preformed structure, consequently when carrying out the floor of module factory building and building the facility, need not the construction of pouring of large tracts of land, and after precast concrete board subassembly 1 sets up side by side at interval, the staff can carry out other construction operation in step when pouring shaping and pouring board 2, and then has improved building construction efficiency.
The concrete steps for prefabricating the precast concrete panel assembly 1 of the present embodiment mainly include:
firstly, a concrete slab 11 is cast and formed in advance in a prefabricating factory, angle steel 13 is placed in a mould for forming the concrete slab 11 in the casting process, and then the angle steel 13 is finally fixedly connected to the lower position of the side wall of the cast and formed concrete slab 11;
then, the I-shaped steel is welded on the angle steel 13 in a welding mode, the I-shaped steel is enabled to be parallel to the side wall of the concrete slab 11, a single precast concrete slab assembly 1 is further obtained, and the formed precast concrete slab assembly 1 can be directly put into the floor slab construction of a factory building for use.
In addition, in order to improve the flexibility of adjusting the gap when fixedly connecting the steel beams 12 of the adjacent precast concrete panel assemblies 1. The step of splicing and connecting the precast concrete plate components 1 specifically comprises the following steps:
firstly, after two precast concrete plate assemblies 1 are assembled on the installation position of a factory building at intervals side by side, adjusting the horizontal distance between steel beams 12 of the two precast concrete plate assemblies 1 to enable the interval distance between the two precast concrete plate assemblies 1 to reach the required distance;
then, cover the space that forms between two girder steels 12 through connecting plate 4, the rethread welding mode is with connecting plate 4 welding on the top of two girder steels 12, and then realizes the fixed connection between the girder steel 12.
The distance between the two precast concrete plate assemblies 1 is more flexible and adjustable by additionally arranging the connecting plates 4, the precast concrete plate assemblies 1 only need to be processed and manufactured in a prefabricating factory according to a uniform design standard, and the steel beams 12 of the two precast concrete plate assemblies 1 can be fixedly connected through the connecting plates 4 in actual use, so that the flexibility of gap adjustment during fixed connection between the steel beams 12 of the adjacent precast concrete plate assemblies 1 is improved.
Further, in order to improve the compression and crack resistance of the casting plate 2. Before the step of casting the casting plate 2 and after the step of splicing and connecting the precast concrete plate components 1, the method also comprises the following steps:
additionally arranging an anti-cracking reinforcing mesh 6: and laying an anti-cracking reinforcing mesh 6 in the pouring groove.
By additionally arranging the anti-cracking reinforcing mesh 6, the anti-cracking reinforcing mesh 6 is used as a matrix of the pouring plate 2, and the compression resistance and the anti-cracking resistance of the pouring plate 2 are improved.
In addition, in order to improve the crack resistance of the self-leveling layer 3, the service life is prolonged. Before the step of laying the self-leveling layer and after the step of pouring and forming the pouring plate, the method further comprises the following steps of:
additionally arranging an anti-cracking grid cloth 5: and paving anti-cracking gridding cloth 5 on the upper surfaces of the precast concrete plate assemblies 1 and the pouring plates 2, so that the anti-cracking gridding cloth 5 covers connecting seams formed between the precast concrete plate assemblies 1 and the pouring plates 2.
By additionally arranging the anti-cracking gridding cloth 5, the characteristics of light weight, high strength, temperature resistance, alkali resistance, water resistance, corrosion resistance, anti-cracking property and stable size of the anti-cracking gridding cloth 5 are utilized, and the surface tension contraction of the connecting seam position formed between each precast concrete plate component 1 and the pouring plate 2 and the cracking caused by external force can be effectively avoided.
The above description is only for the preferred embodiment of the present invention, and for those skilled in the art, there are variations on the detailed description and the application scope according to the idea of the present invention, and the content of the description should not be construed as a limitation to the present invention.
Claims (10)
1. A precast concrete steel structure combined building structure, comprising:
at least two precast concrete plate assemblies (1) arranged side by side at intervals, wherein each precast concrete plate assembly (1) comprises a concrete plate (11) and a steel beam (12), the steel beams (12) are fixedly connected to the side parts of the concrete plates (11), the tops of the steel beams (12) of two adjacent precast concrete plate assemblies (1) are fixedly connected with each other, and the side wall of the concrete plate (11) fixedly connected with each steel beam (12) is matched with the top of each steel beam (12) to form a pouring groove with an upward notch;
the pouring plate (2) is poured and formed in the pouring groove;
and the self-leveling layer (3) covers the upper surfaces of the precast concrete plate component (1) and the pouring plate (2).
2. A precast concrete steel structure composite building structure according to claim 1, further comprising:
the top of the steel beam (12) of each two adjacent precast concrete plate assemblies (1) is fixedly connected with the connecting plate (4).
3. A precast concrete steel structure combination building structure according to claim 2, wherein the connection plate (4) has one end welded to one of the adjacent two steel beams (12) and the other end welded to the other of the adjacent two steel beams (12).
4. A precast concrete steel structure combination building structure according to claim 2, wherein the connection plate (4) is bolt-fastened to one of the adjacent two steel beams (12) at one end and bolt-fastened to the other of the adjacent two steel beams (12) at the other end.
5. A precast concrete steel structure composite building structure according to claim 1, further comprising:
and the lower end face of the anti-cracking gridding cloth (5) covers connecting joints formed between the precast concrete plate assemblies (1) and the pouring plates (2), and the upper end face of the anti-cracking gridding cloth (5) is attached to the lower surface of the self-leveling layer (3).
6. A precast concrete steel structure combined building structure according to claim 5, wherein the anti-cracking mesh cloth (5) covers the upper surfaces of the pouring slabs (2), and the length of one end of the anti-cracking mesh cloth (5) extending into the upper surface of one precast concrete slab assembly (1) and the length of the other end of the anti-cracking mesh cloth (5) extending into the upper surface of the other precast concrete slab assembly (1) are not less than 150 mm.
7. A precast concrete steel structure combination building structure according to claim 1, wherein the precast concrete plate assembly (1) further comprises:
the angle steel (13) is fixedly connected to the side wall of the concrete plate (11), and the top of the steel beam (12) is fixedly connected to the angle steel (13).
8. A precast concrete steel structure combination building structure according to claim 1, characterized in that an anti-cracking steel mesh sheet (6) is provided in the casting slab (2).
9. A precast concrete steel structure combination building structure according to claim 1, wherein the self-leveling layer (3) is an epoxy self-leveling layer or a cement self-leveling layer (3).
10. A precast concrete steel structure combination building structure according to claim 1, wherein the steel beam (12) is an i-shaped steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021957027.7U CN212271353U (en) | 2020-09-09 | 2020-09-09 | Precast concrete steel construction combination building structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021957027.7U CN212271353U (en) | 2020-09-09 | 2020-09-09 | Precast concrete steel construction combination building structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212271353U true CN212271353U (en) | 2021-01-01 |
Family
ID=73870412
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021957027.7U Active CN212271353U (en) | 2020-09-09 | 2020-09-09 | Precast concrete steel construction combination building structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212271353U (en) |
-
2020
- 2020-09-09 CN CN202021957027.7U patent/CN212271353U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107489098B (en) | Concrete prefabricated welding type guardrail and installation construction method | |
CN106013455B (en) | A kind of manufacture of Prefabricated composite steel reinforcement cage component assembly method, reinforced concrete structure body method of construction | |
CN109371836A (en) | A kind of prefabricated assembled floorings splicing structure | |
CN108222347A (en) | A kind of big module welding overlapping beam slab of the assembled with plane girder temporary support | |
CN109518858A (en) | Fabricated Beam-Slab connection structure and its construction method | |
CN105952060A (en) | Precast beam reinforcement cage component and assembling method thereof | |
CN111851825A (en) | Fabricated form-removal-free prefabricated steel bar truss floor and construction method thereof | |
CN111119378A (en) | Prefabricated hollow superposed shear wall with vertical steel bars penetrating through edge members | |
CN111980255A (en) | Precast concrete steel structure combined building structure and manufacturing method thereof | |
CN110815511A (en) | Integral toilet box mold and manufacturing and mounting method thereof | |
CN214574603U (en) | 3D prints assembled box structure | |
CN113123504A (en) | Laminated floor slab with detachable additional rigidity device | |
CN212271353U (en) | Precast concrete steel construction combination building structure | |
CN110468723B (en) | Installation and construction method for wrapping steel plate outside main pier of swivel bridge | |
CN113047417A (en) | 3D printing assembly type box structure and connecting method thereof | |
CN210238896U (en) | Concrete superimposed sheet construction is with stabilizing connection structure | |
CN209292893U (en) | A kind of prefabricated assembled floorings splicing structure | |
CN109267578B (en) | Inclined plane plain concrete structure and construction method thereof | |
CN110067198B (en) | Steel-concrete composite girder bridge and construction method thereof | |
CN207392451U (en) | A kind of building armored concrete overhangs girder construction | |
CN215290896U (en) | Composite floor slab with detachable additional rigidity device | |
CN216810535U (en) | Prestressed PC truss bidirectional laminated slab | |
CN206457971U (en) | A kind of prefabricated overlapped hollow plate of prestressing force | |
CN213805869U (en) | Steel beam and prefabricated floor connecting structure | |
CN210288825U (en) | Assembled and cast-in-situ combined beam plate structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |