CN207392451U - A kind of building armored concrete overhangs girder construction - Google Patents

A kind of building armored concrete overhangs girder construction Download PDF

Info

Publication number
CN207392451U
CN207392451U CN201721242389.6U CN201721242389U CN207392451U CN 207392451 U CN207392451 U CN 207392451U CN 201721242389 U CN201721242389 U CN 201721242389U CN 207392451 U CN207392451 U CN 207392451U
Authority
CN
China
Prior art keywords
fixedly connected
bracket
construction
cantilever beams
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721242389.6U
Other languages
Chinese (zh)
Inventor
吴建坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nanjing Building Engineering Co Ltd
Original Assignee
China Nanjing Building Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nanjing Building Engineering Co Ltd filed Critical China Nanjing Building Engineering Co Ltd
Priority to CN201721242389.6U priority Critical patent/CN207392451U/en
Application granted granted Critical
Publication of CN207392451U publication Critical patent/CN207392451U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model is related to building structure technology fields, in particular a kind of building armored concrete overhanging girder construction, including frame column, the frame column is internally provided with embedded part, the embedded part right side is fixedly connected with built-in fitting, and the built-in fitting lower face is fixedly connected with eave tile round steel through walls, and the built-in fitting right side is fixedly connected with steel diagonal brace, the steel diagonal brace lower face is fixedly connected with the second bracket, and the second bracket end is fixedly connected with channel steel of putting more energy into;The utility model is novel in design, multiple functional, improves construction efficiency, reduce construction cost and security risk, suitable for the construction of all kinds of Cantilever Beams, eliminate beam base fabric and set after template to the leveling process of template, simplify working procedure, save the construction time, the cantilever span of cantilevered structure part is added, reduces the construction risk of large-scale Cantilever Beams, safety coefficient increases, with huge economic benefit and extensive market prospects, it is worth of widely use.

Description

A kind of building armored concrete overhangs girder construction
Technical field
The utility model is related to building structure technology fields, are specially a kind of building armored concrete overhanging girder construction.
Background technology
Because technique needs, set up in the tall and big frame structure engineering of industrial building and count some Cantilever Beams, a portion is Large-size bearing Cantilever Beams, Cantilever Beams are not that both ends have support, but one end is embedded in or pours on a support, and the other end is stretched Go out or choose the beam of supporter, existing common overhanging beam construction method to set up landing support for shuttering construction, suitable for floor compared with Low small-sized Cantilever Beams construction, when the higher independent large-size bearing Cantilever Beams of construction location, since load of overhanging beam is larger, high Degree is higher, so the requirement to formwork scaffold and ground is very high, this has been resulted in, and construction cost is high, efficiency is low, and when height When spending superelevation, construction risk coefficient is very big, there are serious security risk, therefore, to building armored concrete Cantilever Beams knot The demand of structure is growing.
Concrete itself tensile property is poor, and the cantilever span of the reinforced concrete buildings with large cantilever is shorter;It passes The large-size bearing Cantilever Beams of system, load is larger, height is higher, so the requirement to formwork scaffold and ground is very high, this is just Cause that construction cost is high, efficiency is low, and when height superelevation, construction risk coefficient is very big, there are serious security risk, Therefore, a kind of building armored concrete overhanging girder construction is proposed regarding to the issue above.
Utility model content
The purpose of this utility model is to provide a kind of building armored concrete to overhang girder construction, to solve above-mentioned background The problem of being proposed in technology.
To achieve the above object, the utility model provides following technical solution:
A kind of building armored concrete overhangs girder construction, and including frame column, the frame column is internally provided with embedded part, described Embedded part right side is fixedly connected with built-in fitting, and the built-in fitting lower face is fixedly connected with eave tile round steel through walls, the built-in fitting Right side is fixedly connected with steel diagonal brace, and the steel diagonal brace lower face is fixedly connected with the second bracket, and the second bracket end is consolidated Surely channel steel of putting more energy into is connected with, the first bracket is inlaid on the frame column, formwork steel pipe is fixedly connected on first bracket, Longitudinal prestressing muscle is vertically arranged on first bracket, the presstressed reinforcing steel top is fixedly connected with transversely prestressed bars, The transversely prestressed bars are equipped with Cantilever Beams.
Preferably, the angle between the steel diagonal brace and Cantilever Beams is 15 degree.
Preferably, the transversely prestressed bars are arranged in a mutually vertical manner with longitudinal prestressing muscle.
Preferably, the connection relation between first bracket and the second bracket and embedded part is welding.
Preferably, the angle between the Cantilever Beams and frame column is 90 degree.
Compared with prior art, the beneficial effects of the utility model are:
1st, in the utility model, by setting bracket embedded part and Cantilever Beams joint bar, by the use of embedded part mount type steel corbel as Cantilever Beams hang formwork platform, carry out form work engineering construction, solve the construction difficult problem of large-scale high-altitude load-bearing Cantilever Beams, reduce Scaffold building process during high or ultra high-formwork construction avoids the high request problem to formwork scaffold and ground, improves Construction efficiency, reduces construction cost and security risk, suitable for the construction of all kinds of Cantilever Beams;
2nd, it is two right-angle sides by setting frame column and the first bracket, in this way, it is outstanding to be equivalent in the utility model Outrigger has unified floor height, and template is directly laid on the bracket of sustained height, eliminates beam base fabric and sets after template to template Leveling process, simplify working procedure, save the construction time;
3rd, in the utility model, by setting solder type steel corbel, this kind of shaped steel can arbitrarily process with engineering, design and Combination, section torque, section factor, hold loading at compression resistance, far above the hot calender shaped steel of commensurate's weight, thus can have Effect ground ensures the load-bearing capacity of suspension scaffold;
4th, in the utility model, by the way that transversely prestressed bars and longitudinal prestressing muscle is set to form spatial and prestressed structure body System improves the overall structure rigidity of overhanging part, reduces the distress in concrete and tip deflection of overhanging part, adds outstanding The cantilever span of structure division is chosen, reduces the construction risk of large-scale Cantilever Beams, safety coefficient increases, and has huge economic benefit With extensive market prospects, it is worth of widely use.
Description of the drawings
Fig. 1 is the utility model overall structure diagram;
Fig. 2 is structure diagram at the A of the utility model Fig. 1.
In figure:1- frame columns, 2- embedded parts, the first brackets of 3-, 4- formworks steel pipe, 5- Cantilever Beams, the second brackets of 6-, 7- are horizontal Presstressed reinforcing steel, 8- put more energy into channel steel, 9- steel diagonal brace, 10- eave tile round steel through walls, 11- built-in fittings, 12- longitudinal prestressing muscle.
Specific embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out It clearly and completely describes, it is clear that the described embodiments are only a part of the embodiments of the utility model rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work All other embodiments obtained shall fall within the protection scope of the present invention.
- 2 are please referred to Fig.1, the utility model provides a kind of technical solution:
A kind of building armored concrete overhangs girder construction, and including frame column 1, the frame column 1 is internally provided with embedded part 2, Construction efficiency is improved, reduces construction cost and security risk, suitable for the construction of all kinds of Cantilever Beams, 2 right end of embedded part Face is fixedly connected with built-in fitting 11, and 11 lower face of built-in fitting is fixedly connected with eave tile round steel 10 through walls, the built-in fitting 11 Right side is fixedly connected with steel diagonal brace 9, and 9 lower face of steel diagonal brace is fixedly connected with the second bracket 6,6 end of the second bracket End is fixedly connected with channel steel 8 of putting more energy into, and is inlaid on the frame column 1 on first bracket 3, eliminates beam base fabric and sets after template to mould The leveling process of plate, simplifies working procedure, saves the construction time, formwork steel pipe is fixedly connected on first bracket 3 4, longitudinal prestressing muscle 12 is vertically arranged on first bracket 3, and 12 top of longitudinal prestressing muscle is fixedly connected with horizontal stroke To presstressed reinforcing steel 7, the overall structure rigidity for overhanging part is improved, reduces the construction risk of large-scale Cantilever Beams, safety coefficient increases Add, the transversely prestressed bars 7 are equipped with Cantilever Beams 5.
Angle between the steel diagonal brace 9 and Cantilever Beams 5 is 15 degree, fixation, the transversely prestressed bars 7 and longitudinal direction Presstressed reinforcing steel 12 is arranged in a mutually vertical manner, uniform force, the connection relation between 3 and second bracket 6 of the first bracket and embedded part 2 For welding, make entirety firmer, the angle between the Cantilever Beams 5 and frame column 1 is 90 degree, rational in infrastructure.
When the utility model is used, frame column 1 of first constructing, the reinforced bar engineering of completion frame column 1, form work engineering, reinforcing bar Engineering, form work engineering construction can refer to conventional technical means;Interval installation from top to down on frame column 1 below Cantilever Beams 5 Embedded part group, and the joint bar for Cantilever Beams 5 of constructing;The concrete of pouring frame column 1 is following steps to the bottom position of Cantilever Beams 5 The installation of Cantilever Beams bottom formwork and bracket in rapid is prepared;On welded and installed the first bracket 3, the second bracket 6 to embedded part 2, and Corresponding first bracket 3,6 respective right endpoint of the second bracket are welded together, and in the first bracket 3 and 5 bottom surface of Cantilever Beams Between preset clearance, Cantilever Beams bottoms formwork steel pipe 4 is laid in the gap, it is preferable that form above-mentioned right angled triangle, also need The first bracket of leveling 3 arranges its left and right horizontal;It is platform with mounted first bracket 3, the second bracket 6, with laying Cantilever Beams bottom formwork steel pipe 4 carry out Cantilever Beams 5 form work engineering and reinforced bar engineering construction, reinforced bar engineering, form work engineering are applied Work can refer to conventional technical means;To Cantilever Beams 5, frame column 1 carry out concrete pouring construction, pour 5 body of Cantilever Beams and with The frame column 1 of 5 connecting portion of Cantilever Beams and above section, is finally completed the construction of Cantilever Beams 5;To after construction Cantilever Beams 5, Frame column 1 carries out watering health;The intensity of Cantilever Beams 5 after test construction, after reaching collapsible die intensity, removes the first bracket 3, the The template used in two brackets 6 and form work engineering.
While there has been shown and described that the embodiment of the utility model, for the ordinary skill in the art, It is appreciated that in the case where not departing from the principle of the utility model and spirit can these embodiments be carried out with a variety of variations, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (5)

1. a kind of building armored concrete overhangs girder construction, including frame column (1), it is characterised in that:In the frame column (1) Portion is equipped with embedded part (2), and embedded part (2) right side is fixedly connected with built-in fitting (11), and built-in fitting (11) lower face is fixed Eave tile round steel (10) through walls is connected with, built-in fitting (11) right side is fixedly connected with steel diagonal brace (9), the steel diagonal brace (9) Lower face is fixedly connected with the second bracket (6), and the second bracket (6) end is fixedly connected with channel steel of putting more energy into (8), the frame The first bracket (3) is inlaid on column (1), formwork steel pipe (4), first bracket are fixedly connected on first bracket (3) (3) longitudinal prestressing muscle (12) is vertically arranged on, longitudinal prestressing muscle (12) top is fixedly connected with transverse prestress Muscle (7), the transversely prestressed bars (7) are equipped with Cantilever Beams (5).
2. a kind of building armored concrete overhanging girder construction according to claim 1, it is characterised in that:The steel diagonal brace (9) angle between Cantilever Beams (5) is 15 degree.
3. a kind of building armored concrete overhanging girder construction according to claim 1, it is characterised in that:The transverse direction is pre- Stress rib (7) is arranged in a mutually vertical manner with longitudinal prestressing muscle (12).
4. a kind of building armored concrete overhanging girder construction according to claim 1, it is characterised in that:Described first N Connection relation between leg (3) and the second bracket (6) and embedded part (2) is welding.
5. a kind of building armored concrete overhanging girder construction according to claim 1, it is characterised in that:The Cantilever Beams (5) angle between frame column (1) is 90 degree.
CN201721242389.6U 2017-09-26 2017-09-26 A kind of building armored concrete overhangs girder construction Expired - Fee Related CN207392451U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721242389.6U CN207392451U (en) 2017-09-26 2017-09-26 A kind of building armored concrete overhangs girder construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721242389.6U CN207392451U (en) 2017-09-26 2017-09-26 A kind of building armored concrete overhangs girder construction

Publications (1)

Publication Number Publication Date
CN207392451U true CN207392451U (en) 2018-05-22

Family

ID=62405128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721242389.6U Expired - Fee Related CN207392451U (en) 2017-09-26 2017-09-26 A kind of building armored concrete overhangs girder construction

Country Status (1)

Country Link
CN (1) CN207392451U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755973A (en) * 2018-07-19 2018-11-06 中建三局集团有限公司 A kind of Cantilever Beams construction joint position H profile steel embedded system
CN113417372A (en) * 2021-07-01 2021-09-21 中铁大桥局第七工程有限公司 Concrete tower column embedded bracket system and installation method
CN119308428A (en) * 2024-11-27 2025-01-14 中建科工集团有限公司 Sliding bearing nodes at cantilever beams of exterior walls

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755973A (en) * 2018-07-19 2018-11-06 中建三局集团有限公司 A kind of Cantilever Beams construction joint position H profile steel embedded system
CN108755973B (en) * 2018-07-19 2024-03-01 中建三局集团有限公司 H-shaped steel embedded system at cantilever beam construction joint part
CN113417372A (en) * 2021-07-01 2021-09-21 中铁大桥局第七工程有限公司 Concrete tower column embedded bracket system and installation method
CN113417372B (en) * 2021-07-01 2023-02-28 中铁大桥局第七工程有限公司 Concrete tower column embedded bracket system and installation method
CN119308428A (en) * 2024-11-27 2025-01-14 中建科工集团有限公司 Sliding bearing nodes at cantilever beams of exterior walls

Similar Documents

Publication Publication Date Title
CN103352429B (en) Bracket reverse drawing loads the stretch-draw preloading method of prepressing device
CN203188589U (en) Rigid-frame continuous beam zero block construction bracket supporting system
CN109457814B (en) Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN104389419A (en) Cantilevered formwork platform installation structure and construction method
CN111005324B (en) Support-free suspension and locking construction method for assembled type segmental box girder
CN207392451U (en) A kind of building armored concrete overhangs girder construction
CN107724540A (en) Steel plate shear force wall and the attachment structure and its construction method of steel bar girder floor plates
CN205024833U (en) Reinforcing bar concrete combination prefabricated component
CN206319597U (en) A kind of cantilever steel girder erecting device
CN203373666U (en) Bracket pull-counter loading prepressing device
CN204690763U (en) Long side slope protection concrete continuous fast pouring drawing-die system
CN213953189U (en) Supporting device for ensuring smooth surface of lower cone shell of prefabricated water tank
CN222991120U (en) A cantilever concrete structure formwork scaffolding structure
CN211447283U (en) Connecting beams of the main building and the podium
CN221590607U (en) A truss-type substation structure with reinforced flat arch hanger rods
CN108797380B (en) Suspension construction device and construction method for suspension irrigation continuous beam bracket
CN202766974U (en) Bent cap bearing frame without full framing
CN109024685A (en) A kind of mass concrete invert reinforcing steel support system and its construction method
CN209066488U (en) A kind of mass concrete invert reinforcing steel support system
CN217353122U (en) Assembled exempts from to prop up mould building carrier plate
CN104806012A (en) Large-scale high-altitude bearing cantilever beam device and construction method thereof
CN214739138U (en) Prefabricated steel truss free formwork
CN212176358U (en) Energy-concerving and environment-protective type concrete prefabricated staircase
CN210530084U (en) Open type steel reinforced concrete composite truss floor
CN102454295B (en) Large-scale cantilever beam at ultrahigh position construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180522

Termination date: 20180926

CF01 Termination of patent right due to non-payment of annual fee