CN212153135U - Cable crane - Google Patents

Cable crane Download PDF

Info

Publication number
CN212153135U
CN212153135U CN202020717107.9U CN202020717107U CN212153135U CN 212153135 U CN212153135 U CN 212153135U CN 202020717107 U CN202020717107 U CN 202020717107U CN 212153135 U CN212153135 U CN 212153135U
Authority
CN
China
Prior art keywords
cable
tower
bridge
bank
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020717107.9U
Other languages
Chinese (zh)
Inventor
魏玉吉
蔡俊华
江超
钟厚成
庄燕珍
廖小平
张正宾
王福桂
陈理辉
王赟
秦小晶
张滔
张佑义
吴杨
郑强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sanming Puyan Highway Co ltd
CCCC SHEC Fourth Engineering Co Ltd
Original Assignee
Sanming Puyan Highway Co ltd
CCCC SHEC Fourth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanming Puyan Highway Co ltd, CCCC SHEC Fourth Engineering Co Ltd filed Critical Sanming Puyan Highway Co ltd
Priority to CN202020717107.9U priority Critical patent/CN212153135U/en
Application granted granted Critical
Publication of CN212153135U publication Critical patent/CN212153135U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a cable crane, which belongs to the field of bridges, wherein two banks are provided with two main anchor blocks, the two main anchor blocks of each bank are symmetrically arranged at two sides of the central line of a main bridge of the bridge, two banks of towers are respectively and correspondingly arranged on the transition pier tops of the corresponding banks, the two banks of towers are provided with two groups of cable saddles capable of transversely moving, a group of main bearing cable is arranged between the two cable saddles corresponding to the two banks, and two ends of the main bearing cable are respectively fixed on the corresponding main anchor blocks of the two banks; the main bearing cable is provided with a hoisting trolley, the hoisting trolley is provided with a traction cable and a hoisting cable, and the traction cable and the hoisting cable are respectively connected to a traction winch and a hoisting winch on the corresponding bank through cable saddles; through locating the pier top of transition mound and through designing specific gate-type pier stud frame with the pylon in this scheme, not only do not influence the installation and construction of main bridge steel truss, but also satisfied the construction of pier top approach bridge framed bent pier, and then in the good continuous rigid frame bridge of variable cross section steel truss who has used span ability big with the cable crane.

Description

Cable crane
Technical Field
The utility model relates to a bridge construction technical field, more specifically say, relate to a cable loop wheel machine.
Background
The continuous rigid frame bridge with the large-span variable-section steel truss girder has large spanning capacity and light upper structure weight, and is a reasonable bridge structure form for spanning deep ditches and canyons and rivers. However, due to the limited terrain conditions, these bridges are often difficult to install using large cranes, and large transport vehicles are more difficult to reach each construction work surface.
The traditional construction process at present of domestic and foreign continuous rigid frame bridges generally adopts a pushing (dragging) method and a bridge deck crane cantilever splicing method; for a large-span steel truss girder bridge, if a cantilever is too large, a main girder cannot meet the stress requirement, a temporary buttress needs to be arranged between spans or a cantilever assembly is carried out by adopting an inclined pull buckle hanging method.
In the face of the existing main bridge is a variable-section steel truss girder continuous rigid frame bridge, the approach bridges on two sides are longer, and the approach bridges are located on curves, and the technology for constructing the bridge is not solved at home and abroad at present. The factors such as long variable-section steel trussed beams and approach bridges and the fact that the approach bridges are located on curves determine that the installation of the main beams is not suitable for the traditional construction methods such as pushing, even if the pushing method can be adopted for construction, the mountainous-area bridge does not have a rear balance section assembling field, and meanwhile, the temporary buttress is difficult to arrange; if the cantilever assembling construction of the bridge deck crane is adopted, the weight of the bridge deck crane can increase the stress of the pier-beam joint part, and the horizontal and vertical transportation of the components to the construction operation surface from the assembling field is very difficult. Therefore, what kind of device is adopted to construct the main bridge part of the bridge is a problem which needs to be solved at present.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved by the utility model
An object of the utility model is to overcome not enough among the prior art, provide a cable crane, pier top through locating the transition mound with the pylon and through designing specific gate-type pier structure in this scheme not only does not influence the erection construction of main bridge steel truss, but also has satisfied the pier top and has drawn the construction of bridge bent frame mound, and then the good variable cross section steel truss bridge that has used cable crane that span ability is big in the continuous rigid frame bridge.
Technical scheme
In order to achieve the above purpose, the utility model provides a technical scheme does:
the utility model discloses a cable crane, which comprises a main anchor, a main bearing cable, a wind cable, a crane trolley, a cable saddle, a left bank tower and a right bank tower;
two main anchor spindles are arranged on the left bank and the right bank, and the two main anchor spindles on each bank are symmetrically arranged on two sides of the central line of the bridge main bridge and are respectively arranged corresponding to the left bridge and the right bridge;
the left bank tower frame and the right bank tower frame are respectively and correspondingly arranged on the pier tops of transition piers of corresponding banks, two groups of cable saddles capable of transversely moving are arranged on the left bank tower frame and the right bank tower frame, and tower cranes are arranged on one sides of the left bank tower frame and the right bank tower frame;
a group of main bearing cables are arranged between two cable saddles corresponding to the two banks, two ends of each main bearing cable extend outwards and are fixed on main anchor ingots corresponding to the two banks respectively, and a group of working cables are arranged corresponding to the group of main bearing cables;
the main bearing cable is provided with a hoisting trolley, the hoisting trolley is provided with a traction cable and a hoisting cable, and the traction cable and the hoisting cable are respectively connected to a traction winch and a hoisting winch on the corresponding bank through a traction pulley and a hoisting pulley on a cable saddle;
the left shore tower comprises an upper tower and a lower tower, a tower foot hinge is arranged between two branches of the upper tower and the lower tower, a door type pier frame is arranged between two branches of the lower tower and the transition pier, the door type pier frame is fixedly connected with the top of the transition pier, and the left shore tower and the right shore tower are identical in structure.
As a further improvement of the utility model, the included angle between the rear stay cable of the main bearing cable on the left bank and the horizontal plane is 20.4 degrees, and the included angle between the rear stay cable of the main bearing cable on the right bank and the horizontal plane is 13.64 degrees;
the bridge comprises a curve section and a straight line section, wherein a left bank approach bridge and a main bridge are the straight line section, a right bank approach bridge is the curve section, a transition pier of the right bank is a transition point of the curve section and the straight line section, the direction of a central line of the bridge main bridge is the direction of a longitudinal axis of a cable crane, the included angle between the longitudinal axis of the cable crane and the transverse axis of the transition pier of the right bank is 89.25 degrees, and the center of a right bank tower deviates from the vertical central line of the transition pier of the right bank and moves upstream by 0.335 meters.
As a further improvement, the utility model is provided with a hoisting platform under the main bridge of the bridge.
As a further improvement of the present invention, the tower foot hinge comprises three V-shaped supports arranged in parallel, wherein the vertex angle of each V-shaped support is hinged with a base, the opening of each V-shaped support is provided with a steel box girder i, both ends of each steel box girder i extend out of the V-shaped support to form an extending part, the lower end surface of the extending part is provided with a vertically downward connecting side lug, in addition, a connecting rod is arranged between both ends of adjacent steel box girders i, and a reinforcing connecting rod is arranged between corresponding support arms of adjacent V-shaped supports;
the base of the tower foot hinge is fixedly connected to the top of the lower tower frame, and the bottom of the upper tower frame is connected with the steel box girder I.
As a further improvement of the utility model, the portal pier frame comprises four upright posts II vertically fixedly connected to the tops of the transition piers, the connecting lines of the four upright posts II together enclose a rectangular structure, the upper part of each upright post II is connected with an upright post I through a flange, one ends of the four upright posts I, which are far away from the transition piers, are sequentially connected end to end through two steel box girders II and two connecting plates, wherein the two steel box girders II are arranged along the central line direction of the main bridge of the bridge, and the two connecting plates are arranged along the direction vertical to the central line direction of the main bridge of the bridge;
two horizontal connecting plates and an oblique connecting plate I are arranged between two vertical columns II and I in the direction perpendicular to the central line of the main bridge of the bridge, wherein the two horizontal connecting plates and the oblique connecting plate I between the two vertical columns I form a Z shape; two horizontal connecting plates and an oblique connecting plate I between the two upright posts II form a reverse Z shape;
all be equipped with the level between II, the coexistence post I of edge bridge main bridge central line direction and prop a tub slant and prop the pipe, wherein the level between two stands I props the pipe and props the pipe with two slants and constitute triangle-shaped, and two slants prop tub one end and be connected with stand I, and the other end slant upwards is connected with steel box girder II.
As a further improvement, the stand I is gone up two levels and is propped and be equipped with a slant even board II between the pipe, stand II is gone up two levels and is propped also to be equipped with a slant even board II between the pipe, and this two slants even board II intercrossing arranges.
As a further improvement of the utility model, four left bank rear wind cables and four left bank front wind cables are respectively arranged on the upper tower frame and the lower tower frame of the left bank tower frame, and four left bank upstream transverse wind cables and two left bank downstream transverse wind cables are arranged on the left bank tower frame;
four right bank front wind cables and four right bank rear wind cables are respectively arranged on an upper tower frame and a lower tower frame of the right bank tower frame, four oblique front wind cables are also arranged on the right bank upper tower frame, and four right bank upstream cross wind cables and two right bank downstream cross wind cables are arranged on the right bank tower frame;
the four left shore front wind cables on the left shore tower and the four right shore front wind cables on the right shore tower are ventilation cables which are oppositely pulled at the tops of the two shore towers.
Advantageous effects
Adopt the technical scheme provided by the utility model, compare with prior art, have following beneficial effect:
(1) the utility model discloses a cable crane, wherein, the gate-type pier frame of net height 10m has been designed on the basis of current pylon, it solidifies with the mound top of transition mound through this gate-type pier frame, when constructing the access bent mound, can stretch into the inside of gate-type pier frame with the tip of access bent mound, thereby effectively avoided the pylon to the influence of mound top access bent mound construction, and can satisfy the overall stability's of whole pylon demand again through this gate-type pier frame of reasonable structural design, two gate-type pier frames are arranged respectively on the transition mound and are advanced and do not influence the installation of main bridge steel truss girder and access bridge face roof beam in the both ends of transition mound.
(2) The utility model discloses a cable loop wheel machine, wherein, through all being equipped with a tower foot hinge between two branches at last pylon and lower pylon, it is articulated to go up to realize between pylon and the lower pylon promptly, sets pylon upper portion to the mast type through this setting, then can make the top of the tower horizontal load that cable system produced overcome through wind cable around the pylon, and the transition mound mainly bears the vertical load that the pylon transmitted, thereby effectively avoid the transition mound to produce too big moment of flexure.
Drawings
Fig. 1 is a front view of a cable crane according to the present invention;
fig. 2 is a top view of a cable crane according to the present invention;
FIG. 3 is a front view of the two-bank tower of the present invention;
FIG. 4 is a side view of a mid-shore tower of the present invention;
FIG. 5 is an enlarged view taken at A in FIG. 3;
FIG. 6 is a front view of a middle tower leg hinge according to the present invention;
fig. 7 is a side view of the middle tower leg hinge of the present invention;
fig. 8 is a top view of the middle tower leg hinge of the present invention;
fig. 9 is a front view of the middle door type pier frame of the present invention;
fig. 10 is a side view of the middle door type pier frame of the present invention;
fig. 11 is a top view of the middle door type pier frame of the present invention;
FIG. 12 is a view taken along the line B-B in FIG. 10;
FIG. 13 is a view in the direction C-C of FIG. 10;
fig. 14 is an enlarged view at the right bank transition pier.
The reference numerals in the schematic drawings illustrate:
01. a main anchor ingot; 02. a main load bearing cable; 03. a traction cable; 04. hoisting cables;
05. a left shore tower; 51. mounting a tower;
52. hinging tower legs; 521. a base; 522. a connecting rod; 523. a V-shaped bracket; 524. a steel box girder I; 525. connecting the side lug; 526. a reinforcing connecting rod;
53. a lower tower;
54. a door type pier frame; 541. a steel box girder II; 542. a connecting plate; 543. a stand column I; 544. a column II; 545. horizontally bracing the pipe; 546. obliquely bracing the pipe; 547. a horizontal connecting plate; 548. an oblique connecting plate I; 549. an oblique connecting plate II;
061. a left shore rear wind cable; 062. a left shore front wind cable; 063. a left bank upstream transverse wind cable; 064. a left bank downstream crosswind cable; 065. an upstream cross wind cable on the right bank; 066. a right bank downstream crosswind cable; 067. a right shore front wind cable; 068. a right bank rear wind cable;
07. a right bank tower; 08. hoisting the platform; 09. tower crane; 010. transition piers; 011. bridge approach bent pier.
Detailed Description
For a further understanding of the present invention, reference will be made to the following detailed description taken in conjunction with the accompanying drawings and examples.
Example 1
As shown in fig. 1 and 2, a cable crane of the present embodiment includes a main anchor 01, a main bearing cable 02, a wind cable, a hoist trolley, a cable saddle, and towers including a left-shore tower 05 and a right-shore tower 07; the left bank and the right bank are both provided with two main anchor ingots 01, the two main anchor ingots 01 on each bank are symmetrically arranged on two sides of the central line of a main bridge of the bridge and are respectively arranged corresponding to the left bridge and the right bridge, the two main anchor ingots 01 on each bank are respectively arranged right opposite to the central line of the left bridge and the right bridge, the distance between each main anchor 01 and the longitudinal axis of the cable crane (the central line of the main bridge of the bridge) is 8.5m, and the main anchor ingots 01 on the two banks are anchored by adopting a reinforced concrete pile foundation bearing platform structure.
It should be noted that the bridge in this embodiment includes a curved section and a straight section, where the left bank approach bridge and the main bridge are the straight section, the right bank approach bridge is the curved section, the transition pier 010 of the right bank is a transition point between the curved section and the straight section, and a center line direction of the bridge main bridge is a longitudinal axis direction of the cable crane, as shown in fig. 14, an included angle a between the longitudinal axis of the cable crane and a transverse axis of the right bank transition pier 010 is 89.25 °, and a center of the right bank tower 07 deviates from a vertical center line of the right bank transition pier 010 by 0.335 m upstream, as shown in fig. 2, the right bank approach bridge bends downstream, where, it should be noted that the upstream and the downstream in this embodiment represent the upstream and the downstream of a river under the span of the main bridge.
Left bank pylon 05, right bank pylon 07 correspond the mound top that sets up the transition mound 010 at corresponding bank respectively, set up the pylon in the top of two bank transition mounds 010 in this embodiment, have reduced the span of cable system, have reduced the height of pylon, and this arranges not only great saving construction cost for the construction progress, ensured simultaneously that the cable crane is applied to the construction safety in the continuous rigid frame bridge of long-span, variable cross section steel truss.
Two groups of cable saddles capable of transversely moving are arranged on the left bank tower frame 05 and the right bank tower frame 07 respectively, the cable saddles can transversely move in an idle load state so as to meet the requirements of different installation positions of girder trusses of a left bridge and a right bridge, and tower cranes 09 are arranged on one sides of the left bank tower frame 05 and the right bank tower frame 07 respectively; a group of main bearing cables 02 are arranged between two cable saddles corresponding to two banks, two ends of each main bearing cable 02 extend outwards and are fixed on main anchor spindles 01 corresponding to the two banks, a group of working cables are arranged corresponding to the group of main bearing cables 02, specifically, an included angle between a rear cable of the main bearing cable 02 on the left bank and a horizontal plane is 20.4 degrees, an included angle between a rear cable of the main bearing cable 02 on the right bank and the horizontal plane is 13.64 degrees, in addition, a hoisting platform 08 is arranged below a bridge main bridge, specifically, the hoisting platform of the embodiment is arranged at a position right below the main bridge welded in a group splicing field, a steel structure is transported to a position right below the main bearing cable 02 through a crane after the group splicing welding is completed and the steel structure meets the quality requirements through inspection in the bridge field, and then is hoisted and installed through the cable crane; the main bearing cable 02 is also provided with a hoisting trolley, the hoisting trolley is provided with a traction cable 03 and a hoisting cable 04, and the traction cable 03 and the hoisting cable 04 are respectively connected to a traction winch and a hoisting winch on the corresponding bank through a traction pulley and a hoisting pulley on a cable saddle.
As shown in fig. 3, 4 and 5, the left-shore tower 05 of this embodiment includes an upper tower 51 and a lower tower 53, a tower foot hinge 52 is disposed between each of two branches of the upper tower 51 and the lower tower 53, a gate-type pier 54 is disposed between each of two branches of the lower tower 53 and the transition pier 010, the gate-type pier 54 is fixed to a pier top of the transition pier 010, the gate-type pier 54 is respectively fixed to two ends of the transition pier 010, the left-shore tower 05 and the right-shore tower 07 have the same structure, specifically, the height of the left-shore tower 05 of this embodiment is 74.69m, and the height of the right-shore tower 07 is 80.69 m.
In the embodiment, the wind cables are reasonably arranged, so that the stability of the whole cable system is ensured even if the bridge approach of the bridge is long, wherein the upper tower frame 51 and the lower tower frame 53 of the left-bank tower frame 05 are respectively provided with four left-bank rear wind cables 061 and four left-bank front wind cables 062, and the left-bank tower frame 05 is also provided with four left-bank upstream transverse wind cables 063 and two left-bank downstream transverse wind cables 064; four right shore front wind cables 067 and four right shore rear wind cables 068 are respectively arranged on an upper tower 51 and a lower tower 53 of the right shore tower 07, and because the right shore front wind cables 067 and the right shore rear wind cables 068 on the right shore tower 51 are both longer and have weak constraint capacity on the towers, four oblique front wind cables are also arranged on the right shore tower 51 in the embodiment, and four right shore upstream transverse wind cables 065 and two right shore downstream transverse wind cables 066 are arranged on the right shore tower 07; four left shore front wind cables 062 on the left shore tower 51 and four right shore front wind cables 067 on the right shore tower 51 are ventilation cables which are oppositely pulled at the top of the two shore towers, wherein the rear wind cables of the two shore towers are anchored on the main anchor 01, and the front wind cables (excluding the oppositely pulled ventilation cables) and the transverse wind cables are additionally and independently provided with anchor anchors for anchoring.
In order to avoid interference between the upstream transverse air cables on the two banks and the tower crane 09, the four upstream transverse air cables 063 on the left bank tower 05 and the four upstream transverse air cables 065 on the right bank tower 07 are divided into one group, the two groups are divided into splayed air cables, anchors are arranged on each group according to a single pile, and the two groups are symmetrically arranged at a distance of about 20 meters from the transverse axis of the tower.
As shown in fig. 6, 7 and 8, specifically, the tower foot hinge 52 of the present embodiment includes three V-shaped brackets 523 arranged in parallel, wherein a top corner of each V-shaped bracket 523 is hinged to a base 521, an opening of each V-shaped bracket 523 is provided with a steel box girder i 524, two ends of each steel box girder i 524 extend out of the V-shaped bracket 523 to form an extending portion, a vertically downward connecting side ear 525 is provided on a lower end surface of the extending portion, it should be noted that the connecting side ear 525 is used for connecting one end of a universal connecting rod, and the other end of the universal connecting rod is connected with the lower tower 53 to temporarily restrain and fix the tower foot hinge 52, and after the installation of a cable saddle at the top of the tower is completed and the wind cable is pre-tightened, the universal rod is removed to enable the tower foot hinge 52 to be in a free hinge state.
In addition, a connecting rod 522 is arranged between two ends of each adjacent steel box girder I524, a reinforcing connecting rod 526 is arranged between corresponding support arms of each adjacent V-shaped support 523, a base 521 of each tower foot hinge 52 is fixedly connected to the top of the lower tower 53, and the bottom of the upper tower 51 is connected with the steel box girder I524.
In the embodiment, the tower foot hinges 52 are arranged between the two branches of the upper tower 51 and the lower tower 53, that is, the upper tower 51 is hinged to the lower tower 53, and the upper part of the tower is arranged to be in a mast type, so that the horizontal load of the tower top generated by a cable system can be overcome through the front wind cable and the rear wind cable of the tower, and the transition pier 010 mainly bears the vertical load transmitted by the tower, so that the transition pier 010 is effectively prevented from generating an overlarge bending moment, and meanwhile, the tower foot hinges 52 of the embodiment are simple in structure and high in stability.
As shown in fig. 9, fig. 10, fig. 11, fig. 12 and fig. 13, specifically, the portal pier frame 54 of the present embodiment includes four pillars ii 544 vertically fixed on the top of the transition pier 010, the connecting lines of the four pillars ii 544 together enclose a rectangular structure, the upper portion of each pillar ii 544 is connected with a pillar i 543 through a flange, one end of the four pillars i 543 away from the transition pier 010 is connected end to end sequentially through two steel box girders ii 541 and two connecting plates 542, wherein the two steel box girders ii 541 are arranged along the central line direction of the main bridge of the bridge, and the two connecting plates 542 are arranged along the central line direction perpendicular to the main bridge of the bridge;
two horizontal connecting plates 547 and an oblique connecting plate I548 are arranged between two upright posts II 544 and two upright posts I543 in the direction perpendicular to the central line of the main bridge of the bridge, wherein the two horizontal connecting plates 547 and the oblique connecting plate I548 between the two upright posts I543 form a Z shape; two horizontal connecting plates 547 and an oblique connecting plate I548 between the two upright posts II 544 form a reverse Z shape; horizontal supporting tubes 545 are arranged between the two upright posts II 544 and the two upright posts I543 along the central line direction of the main bridge of the bridge, wherein the horizontal supporting tubes 545 between the two upright posts I543 and the two oblique supporting tubes 546 form a triangle, one end of each of the two oblique supporting tubes 546 is connected with the upright post I543, and the other end of each of the two oblique supporting tubes 546 is connected with the steel box girder II 541 in an oblique upward direction.
Specifically, in this embodiment, an oblique connecting plate ii 549 is disposed between two horizontal supporting tubes 545 on the column i 543, an oblique connecting plate ii 549 is also disposed between two horizontal supporting tubes 545 on the column ii 544, and the two oblique connecting plates ii 549 are arranged in a mutually crossing manner.
The important points to be explained are: in this embodiment, in order to ensure that the main bridge deck and the two side access bridge decks of the bridge can be located on the same horizontal plane, the access bent pier 011 needs to be arranged on the transition pier 010 between the main bridge and the access bridge, but how to construct the access bent pier 011 on the transition pier 010 without being affected by a pier top tower and without causing a tower to interfere with the installation of the main bridge steel truss girder and the access bridge deck girder, which becomes one of the problems to be solved in this embodiment, starting from using the existing equipment, a portal pier 54 with a net height of 10m is designed on the basis of the existing tower, the portal pier 54 is fixedly connected with the pier top of the transition pier 010, as shown in fig. 3 and fig. 4, when constructing the access bent pier 011, the end of the access bent pier 011 can extend into the interior of the portal pier 54 through the space between the upright column i 543 and the two upper horizontal support pipes 545 of the upright column 544, thereby effectively avoided the influence of pylon to pier top approach bridge framed bent pier 011 construction, and can satisfy the overall stability's of whole pylon demand again through this gate-type pier frame 54 of reasonable structural design, two gate-type pier frames 54 are arranged respectively at the both ends of transition pier 101 on the transition pier 010 simultaneously, and then do not influence the installation of main bridge steel truss girder and approach bridge face roof beam again.
Adopt the cable loop wheel machine to carry out the construction of continuous steel truss bridge in this embodiment, there is following advantage: the acting force of the weight of the bridge deck crane on the main truss is eliminated, so that the stress of a pier-beam joint part in the construction process is reduced, and the construction is safer; secondly, symmetrical cantilever assembly can be realized relative to each bridge main pier without balancing weights; the 2 symmetrical construction operation surfaces are arranged relative to each main pier, so that the construction operation surfaces are increased, and the construction progress is accelerated; fourthly, the construction is carried out by utilizing the cable crane, and the vertical and horizontal transportation of the components is facilitated.
The present invention and its embodiments have been described above schematically, and the description is not limited thereto, and what is shown in the drawings is only one of the embodiments of the present invention, and the actual structure is not limited thereto. Therefore, if the person skilled in the art receives the teaching of the present invention, without departing from the inventive spirit of the present invention, the person skilled in the art should also design the similar structural modes and embodiments without creativity to the technical solution, and all shall fall within the protection scope of the present invention.

Claims (7)

1. A cable crane, its characterized in that: the cable-stayed bridge crane comprises a main anchor (01), a main bearing cable (02), a wind cable, a crane trolley, a cable saddle, a left shore tower (05) and a right shore tower (07);
the left bank and the right bank are both provided with two main anchor spindles (01), and the two main anchor spindles (01) on each bank are symmetrically arranged on two sides of the central line of the bridge main bridge and respectively arranged corresponding to the left bridge and the right bridge;
the left shore tower frame (05) and the right shore tower frame (07) are respectively and correspondingly arranged on the tops of transition piers (010) of corresponding banks, two groups of cable saddles capable of transversely moving are respectively arranged on the left shore tower frame (05) and the right shore tower frame (07), and tower cranes (09) are respectively arranged on one sides of the left shore tower frame (05) and the right shore tower frame (07);
a group of main bearing cables (02) are arranged between two cable saddles corresponding to the two banks, two ends of each main bearing cable (02) extend outwards and are fixed on main anchor blocks (01) corresponding to the two banks respectively, and a group of working cables are arranged corresponding to the group of main bearing cables (02);
a hoisting trolley is arranged on the main bearing cable (02), a traction cable (03) and a hoisting cable (04) are arranged on the hoisting trolley, and the traction cable (03) and the hoisting cable (04) are respectively connected to a traction winch and a hoisting winch on the corresponding bank through a traction pulley and a hoisting pulley on a cable saddle;
wherein, left side bank tower (05) are including going up tower (51) and lower tower (53), it all is equipped with a tower foot hinge (52) to go up between two branches of tower (51) and lower tower (53), all be equipped with a gate-type pier frame (54) down between two branches of tower (53) and transition mound (010), gate-type pier frame (54) concreties with the mound top of transition mound (010), just left side bank tower (05) are the same with right bank tower (07) structure.
2. A cable hoist as claimed in claim 1, characterized in that: an included angle between the rear stay cable of the main bearing cable (02) on the left bank and the horizontal plane is 20.4 degrees, and an included angle between the rear stay cable of the main bearing cable (02) on the right bank and the horizontal plane is 13.64 degrees;
the bridge comprises a curve section and a straight line section, wherein a left bank approach bridge and a main bridge are the straight line section, a right bank approach bridge is the curve section, a transition pier (010) of the right bank is a transition point of the curve section and the straight line section, the direction of the center line of the bridge main bridge is the direction of the longitudinal axis of the cable crane, the included angle between the longitudinal axis of the cable crane and the transverse axis of the right bank transition pier (010) is 89.25 degrees, and the center of a right bank tower (07) deviates from the vertical center line of the right bank transition pier (010) and is upstream 0.335 meters.
3. A cable hoist as claimed in claim 1, characterized in that: a hoisting platform (08) is arranged below the bridge main bridge.
4. A cable hoist as claimed in claim 1, characterized in that: the tower foot hinge (52) comprises three V-shaped supports (523) which are arranged in parallel, wherein a base (521) is hinged at the top corner of each V-shaped support (523), a steel box girder I (524) is arranged at an opening of each V-shaped support (523), two ends of each steel box girder I (524) extend out of the V-shaped supports (523) to form a protruding part, a vertical downward connecting side lug (525) is arranged on the lower end face of the protruding part, in addition, a connecting rod (522) is arranged between two ends of the adjacent steel box girders I (524), and a reinforcing connecting rod (526) is arranged between corresponding support arms of the adjacent V-shaped supports (523);
the base (521) of the tower foot hinge (52) is fixedly connected to the top of the lower tower (53), and the bottom of the upper tower (51) is connected with the steel box girder I (524).
5. A cable hoist as claimed in claim 1, characterized in that: the gate-type pier frame (54) comprises four upright posts II (544) vertically fixedly connected to the tops of transition piers (010), connecting lines of the four upright posts II (544) jointly form a rectangular structure, the upper part of each upright post II (544) is connected with an upright post I (543) through a flange, one end, far away from the transition piers (010), of each upright post I (543) is sequentially connected end to end through two steel box girders II (541) and two connecting plates (542), wherein the two steel box girders II (541) are arranged along the central line direction of a main bridge of the bridge, and the two connecting plates (542) are arranged along the direction perpendicular to the central line direction of the main bridge of the bridge;
two horizontal connecting plates (547) and an oblique connecting plate I (548) are arranged between two vertical columns II (544) and two vertical columns I (543) in the direction perpendicular to the central line of the main bridge of the bridge, wherein the two horizontal connecting plates (547) and the oblique connecting plate I (548) between the two vertical columns I (543) form a Z shape; two horizontal connecting plates (547) and an oblique connecting plate I (548) between the two upright posts II (544) form a reverse Z shape;
horizontal supporting tubes (545) are arranged between two vertical columns II (544) and two vertical columns I (543) along the central line direction of the main bridge of the bridge, wherein the horizontal supporting tubes (545) between the two vertical columns I (543) and the two oblique supporting tubes (546) form a triangle, one ends of the two oblique supporting tubes (546) are connected with the vertical columns I (543), and the other ends of the two oblique supporting tubes are connected with the steel box girder II (541) in an oblique upward direction.
6. A cable hoist as claimed in claim 5, characterized in that: an oblique connecting plate II (549) is arranged between the two horizontal supporting tubes (545) on the upright post I (543), an oblique connecting plate II (549) is also arranged between the two horizontal supporting tubes (545) on the upright post II (544), and the two oblique connecting plates II (549) are arranged in a mutually crossed manner.
7. A cable hoist as claimed in claim 1, characterized in that: four left bank rear wind cables (061) and four left bank front wind cables (062) are respectively arranged on an upper tower frame (51) and a lower tower frame (53) of the left bank tower frame (05), and four left bank upstream transverse wind cables (063) and two left bank downstream transverse wind cables (064) are arranged on the left bank tower frame (05);
four right shore front wind cables (067) and four right shore rear wind cables (068) are respectively arranged on an upper tower frame (51) and a lower tower frame (53) of the right shore tower frame (07), four oblique front wind cables are also arranged on the right shore tower frame (51), and four right shore upstream transverse wind cables (065) and two right shore downstream transverse wind cables (066) are arranged on the right shore tower frame (07);
the four left shore front wind cables (062) on the left shore tower (51) and the four right shore front wind cables (067) on the right shore tower (51) are ventilation cables which are oppositely pulled at the tops of two shore towers.
CN202020717107.9U 2020-05-06 2020-05-06 Cable crane Active CN212153135U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020717107.9U CN212153135U (en) 2020-05-06 2020-05-06 Cable crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020717107.9U CN212153135U (en) 2020-05-06 2020-05-06 Cable crane

Publications (1)

Publication Number Publication Date
CN212153135U true CN212153135U (en) 2020-12-15

Family

ID=73722306

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020717107.9U Active CN212153135U (en) 2020-05-06 2020-05-06 Cable crane

Country Status (1)

Country Link
CN (1) CN212153135U (en)

Similar Documents

Publication Publication Date Title
CN201106155Y (en) Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN114482280B (en) Hexagonal section assembled annular supporting system and installation method thereof
CN111764282B (en) Rigid suspension cable stiffening steel truss bridge construction method based on inclined pull buckling hanging method
CN2597531Y (en) Single rope face tracting rope hanging cage
CN111608078B (en) Construction method of combined Bailey cable crane tower
CN111573521A (en) Construction process of cable crane hoisting system
CN212153136U (en) Tower frame for cable crane
CN101368370A (en) Wind-proof temporary rest pier and wind-proof method for large span stayed-cable bridge cantilever construction
CN111945569B (en) Small-angle inclined steel arch tower support-free in-situ assembly type asymmetric tensioning assembly construction method
CN210856954U (en) Support-free cable hoisting construction structure of steel arch center for deck arch bridge
CN111472285A (en) Method for mounting main bridge variable-section continuous steel truss girder by using cable crane
CN212153135U (en) Cable crane
CN210086024U (en) Marine large-span ground anchor type suspension cable stayed cooperative system bridge structure
CN212714535U (en) Portal pier frame structure for pylon
CN112323647B (en) Rigid frame bridge hanging basket suspension casting system and construction method thereof
CN212533734U (en) Cable buckle integrated tower
CN113802461A (en) Steel box girder erection method
CN112695607A (en) Construction method and system for asymmetric cantilever beam of cable-stayed bridge
CN210856953U (en) Tower for hoisting construction of steel arch frame support-free cable
CN219862432U (en) Steel tower vertical rotating device
CN212475848U (en) Bridge component hoisting device
CN216193962U (en) Track foundation reinforcing structure of water gantry crane
CN219972971U (en) Hollow slab reinforced structure system
CN213804942U (en) Suspension casting system for rigid frame bridge hanging basket
CN113718626B (en) Construction method suitable for highway and railway dual-purpose cable-stayed suspension cooperative system bridge