CN212129871U - A stand that is used for inserted lift scaffold of gradual change cross-section building - Google Patents

A stand that is used for inserted lift scaffold of gradual change cross-section building Download PDF

Info

Publication number
CN212129871U
CN212129871U CN202020641131.9U CN202020641131U CN212129871U CN 212129871 U CN212129871 U CN 212129871U CN 202020641131 U CN202020641131 U CN 202020641131U CN 212129871 U CN212129871 U CN 212129871U
Authority
CN
China
Prior art keywords
plate body
end plate
upright
rod
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020641131.9U
Other languages
Chinese (zh)
Inventor
张正
胡小铭
岑曦
严兆滔
林文锋
曹穗冬
吴有来
谢文海
李钊
郑绮瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Di-Er Construction & Engineering Co ltd
Original Assignee
Guangzhou Di-Er Construction & Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Di-Er Construction & Engineering Co ltd filed Critical Guangzhou Di-Er Construction & Engineering Co ltd
Priority to CN202020641131.9U priority Critical patent/CN212129871U/en
Application granted granted Critical
Publication of CN212129871U publication Critical patent/CN212129871U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a column of an attached lifting scaffold for a gradual-change cross-section building, which comprises a first plate body, a second plate body, a plurality of upright posts and an adjusting connecting piece for installing standard sections of horizontal wall-attached rod pieces; the first plate body and the second plate body are arranged in parallel; the vertical rods are parallel to each other, two ends of each vertical rod are fixedly connected with the first plate body and the second plate body respectively, and the length of each vertical rod is greater than or equal to the floor height of the building with the gradually-changed section; the adjusting connecting piece is arranged between the upright rods and can be adjusted up and down along the upright rods, and the adjusting connecting piece is provided with a connecting and fixing hole for fixedly connecting with the standard knot of the horizontal wall-attached rod piece. The utility model discloses a stand for inserted lift scaffold of gradual change cross-section building, it can the adaptation level attach wall standard member length, solves the technological problem that the superelevation floor support body of gradual change cross-section building attaches the wall.

Description

A stand that is used for inserted lift scaffold of gradual change cross-section building
Technical Field
The utility model belongs to the technical field of the scaffold frame, concretely relates to inserted lift scaffold's stand for gradual change cross-section building.
Background
The guide rail standard section of the attached lifting scaffold on the market is generally suitable for buildings with the standard floor height of 4-4.5 m, and the guide rail of the attached lifting scaffold is arranged on the inner side of a main frame of a frame body and attached to a wall-attached supporting structure or a vertical main frame to guide the lifting and descending of the scaffold.
If the building is a building with a gradually-changed cross section, the structure beam of the building shrinks inwards to enable the outer vertical face of the building to shrink gradually, the embedded part of the inward shrinkage part needs to be processed by a special vertical rod, and in addition, the gradual shrinkage of the outer vertical face of the building and a certain gradient of a guide rail of a frame body exist, so that the standard section of a horizontal wall-attaching rod is too long or too short, and the special vertical rod of the traditional attached lifting scaffold cannot provide a reliable wall-attaching function.
Therefore, a new technology is required to solve the problem of the unsuitable length of the horizontal wall-attached bar standard section of the lifting scaffold in the gradual-section building.
SUMMERY OF THE UTILITY MODEL
For solving the above-mentioned problem among the prior art, the utility model provides a stand for inserted lift scaffold of gradual change cross-section building, it can the adaptation level attach wall standard member length, solves the technological problem that the superelevation floor support body of gradual change cross-section building attached the wall.
The utility model adopts the following technical scheme:
a column of an attached lifting scaffold for a gradual-change cross-section building comprises a first plate body, a second plate body, a plurality of upright posts and adjusting connecting pieces for installing standard sections of horizontal wall-attached rod pieces;
the first plate body and the second plate body are arranged in parallel;
the vertical rods are parallel to each other, two ends of each vertical rod are fixedly connected with the first plate body and the second plate body respectively, and the length of each vertical rod is greater than or equal to the floor height of the building with the gradually-changed section;
the adjusting connecting piece is arranged between the upright rods and can be adjusted up and down along the upright rods, and the adjusting connecting piece is provided with a connecting and fixing hole for fixedly connecting with the standard section of the horizontal wall-attached rod piece.
As a technical scheme of the utility model further improve, the equidistance is equipped with a plurality of locating holes in the pole setting, be equipped with on the regulation connecting piece be used for with the setting element of locating hole grafting location, be equipped with on the regulation connecting piece and supply on the jack spare that the setting element passed.
As a further improvement of the technical proposal of the utility model, the upright stanchions are divided into two groups;
the adjusting connecting piece comprises a first end plate, a second end plate and a connecting rod;
the first end plate and the second end plate are parallel and are respectively positioned at two sides of the upright stanchions, the connecting rod is inserted between the two groups of upright stanchions, two ends of the connecting rod are respectively and fixedly connected with the first end plate and the second end plate, and the length of the first end plate and the length of the second end plate are both larger than the width between the left group of upright stanchions and the right group of upright stanchions; the connecting and fixing holes are formed in the first end plate and the second end plate.
As the utility model discloses technical scheme's further improvement still includes a plurality of horizontal poles that set up between two adjacent pole settings, the both ends of horizontal pole respectively with adjacent pole setting fixed connection.
As a further improvement of the technical scheme of the utility model, the pole setting is square pipe.
As a further improvement of the technical proposal of the utility model, the length of the vertical rod is 4-6m or 8-10 m.
As a further improvement of the technical proposal of the utility model, the length of the vertical rod is 4.5m or 9 m.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model discloses an attached lifting scaffold's for gradual change cross-section building stand is last to be set up and to have adjusted the connecting piece to the length of stand equals or is greater than the layer height of gradual change cross-section building, both ends are connected the building from top to bottom, install in variable cross-section department, fill the sunken of variable cross-section, and can attach wall member standard festival through adjusting the connecting piece connection level, owing to filled the sunken of variable cross-section, reduce the slope, the unsuitable situation of length that the level attaches wall member standard festival can not appear.
Drawings
The technology of the present invention will be further described in detail with reference to the accompanying drawings and detailed description:
fig. 1 is a front view of a column of the present invention;
fig. 2 is a side view of the column of the present invention;
fig. 3 is a schematic view of the column of the present invention installed on a building with gradually changed cross-section.
Reference numerals:
1-a first plate body;
2-a second plate body;
3-erecting a rod; 31-a positioning hole;
4-adjusting the connecting piece; 41-jack; 42-a positioning member; 43-connecting the fixing hole; 401 — a first end plate; 402-a second end plate; 403-a connecting rod;
5-a cross bar;
6-gradual change section building;
7-standard section of horizontal wall-attached rod;
8-a pull rod.
Detailed Description
The conception, specific structure and technical effects of the present invention will be described clearly and completely with reference to the accompanying drawings and embodiments, so as to fully understand the objects, aspects and effects of the present invention. It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The same reference numbers will be used throughout the drawings to refer to the same or like parts.
It should be noted that, unless otherwise specified, when a feature is referred to as being "fixed" or "connected" to another feature, it may be directly fixed or connected to the other feature or indirectly fixed or connected to the other feature. Furthermore, the description of the upper, lower, left, right, etc. used in the present invention is only relative to the mutual positional relationship of the components of the present invention in the drawings.
Referring to fig. 1 to 3, the column of the attached lifting scaffold for the gradual-change cross-section building comprises a first plate body 1, a second plate body 2, a plurality of vertical rods 3 and an adjusting connecting piece 4 for installing a standard knot 7 of a horizontal wall-attached rod piece.
The first plate body 1 and the second plate body 2 are arranged in parallel to each other so as to be connected with a building up and down stably.
The vertical rods 3 are parallel to each other, two ends of each vertical rod 3 are fixedly connected with the first plate body 1 and the second plate body 2 respectively, and the length of each vertical rod 3 is larger than or equal to the floor height of the building 6 with the gradually-changed cross section so as to connect building structures of upper and lower floors. In particular, the length of the upright 3 is 4-6m or 8-10 m. More specifically, the length of the upright stanchion 3 is 4.5m or 9m to adapt to the section change of a single-layer standard building or the section change of a two-layer standard building.
The adjusting connecting piece 4 is arranged between the upright rods 3 and can be adjusted up and down along the upright rods 3, and the adjusting connecting piece 4 is provided with a connecting and fixing hole 43 which is used for being fixedly connected with the standard knot 7 of the horizontal wall-attached rod piece.
Based on above-mentioned structure, the length of pole setting 3 is equal to or greater than the floor height of gradual change cross section building 6, can connect the building with the upper and lower both ends of stand, installs in variable cross section department to fill variable cross section's sunken, and can connect horizontal wall member standard festival 7 through adjusting connecting piece 4, owing to filled variable cross section's sunken, reduce the slope, the unsuitable condition of length of horizontal wall member standard festival 7 can not appear. In the installation fixed in-process of stand, it is firm to need to use pull rod 8 to carry out the tractive usually, and pull rod 8 has two kinds usually, and one kind is length-adjustable, and one kind is length-fixed, because adjustment connecting piece 4 can adjust from top to bottom, therefore this scheme can enough be applicable to adjustable pull rod 8, also can be applicable to the pull rod 8 of fixed length.
A plurality of positioning holes 31 are equidistantly formed in the upright rod 3, positioning pieces 42 used for being inserted into the positioning holes 31 for positioning are arranged on the adjusting connecting piece 4, and insertion holes 41 for the positioning pieces 42 to penetrate through are formed in the adjusting connecting piece 4. The up-and-down position adjustment of the adjusting connector 4 is realized by means of the positioning hole 31 and the positioning member 42, and the positioning member 42 can be a bolt or a bolt.
In particular, the uprights 3 are divided into two groups, two uprights 3 per group, i.e. all uprights 3 are supplied with 4.
The adjusting link 4 includes a first end plate 401, a second end plate 402, and a connecting rod 403. The first end plate 401 and the second end plate 402 are parallel and are respectively located at two sides of the upright stanchions 3, the connecting rod 403 is inserted between the two groups of upright stanchions 3, two ends of the connecting rod 403 are respectively fixedly connected with the first end plate 401 and the second end plate 402, and the length of the first end plate 401 and the length of the second end plate 402 are both greater than the width between the left group of upright stanchions 3 and the right group of upright stanchions 3; the coupling fixing holes 43 are provided on the first and second end plates 401 and 402. Two sets of pole setting 3 about promptly will adjust connecting piece 4 through connecting rod 403 spacing for adjust connecting piece 4 can not remove about, because the length of first end plate 401 and second end plate 402 is greater than the width between the pole setting 3 again, adjust connecting piece 4 also can't the back-and-forth movement, so, it only can reciprocate and adjust. Wherein, pole setting 3 is square pipe, and it is more convenient to carry on spacingly to adjusting connecting piece 4. The connecting rod 403 may be a split bolt.
Preferably, in order to enhance the connection strength between the vertical rods 3, the upright post further comprises a plurality of cross rods 5 arranged between two adjacent vertical rods 3, and two ends of each cross rod 5 are respectively and fixedly connected with the adjacent vertical rods 3.
Other contents of the stand of the attached lifting scaffold for the gradual change cross-section building refer to the prior art, and are not repeated herein.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the present invention in any way, so that any modification, equivalent change and modification made by the technical spirit of the present invention to the above embodiments do not depart from the technical solution of the present invention, and still fall within the scope of the technical solution of the present invention.

Claims (7)

1. An upright post of an attached lifting scaffold for a gradual-change cross-section building is characterized by comprising a first plate body, a second plate body, a plurality of upright posts and an adjusting connecting piece for installing standard sections of horizontal wall-attached rod pieces;
the first plate body and the second plate body are arranged in parallel;
the vertical rods are parallel to each other, two ends of each vertical rod are fixedly connected with the first plate body and the second plate body respectively, and the length of each vertical rod is greater than or equal to the floor height of the building with the gradually-changed section;
the adjusting connecting piece is arranged between the upright rods and can be adjusted up and down along the upright rods, and the adjusting connecting piece is provided with a connecting and fixing hole for fixedly connecting with the standard section of the horizontal wall-attached rod piece.
2. The mast of an attached lifting scaffold for progressive section buildings according to claim 1, characterized in that: the pole setting is last the equidistance to be equipped with a plurality of locating holes, be equipped with on the regulation connecting piece be used for with the setting element of locating hole grafting location, be equipped with on the regulation connecting piece and supply the setting element to pass on the jack spare.
3. The mast of an attached lifting scaffold for progressive section buildings according to claim 1, characterized in that: the upright posts are divided into two groups;
the adjusting connecting piece comprises a first end plate, a second end plate and a connecting rod;
the first end plate and the second end plate are parallel and are respectively positioned at two sides of the upright stanchions, the connecting rod is inserted between the two groups of upright stanchions, two ends of the connecting rod are respectively and fixedly connected with the first end plate and the second end plate, and the length of the first end plate and the length of the second end plate are both larger than the width between the left group of upright stanchions and the right group of upright stanchions; the connecting and fixing holes are formed in the first end plate and the second end plate.
4. The mast of an attached lifting scaffold for progressive section buildings according to claim 1, characterized in that: the vertical rod fixing device is characterized by further comprising a plurality of cross rods arranged between every two adjacent vertical rods, and the two ends of each cross rod are fixedly connected with the adjacent vertical rods respectively.
5. The mast of an attached lifting scaffold for progressive section buildings according to claim 1, characterized in that: the upright stanchion is a square tube.
6. The mast of an attached lifting scaffold for progressive section buildings according to claim 1, characterized in that: the length of the vertical rod is 4-6m or 8-10 m.
7. The mast of an attached lifting scaffold for progressive section buildings according to claim 6, characterized in that: the length of the vertical rod is 4.5m or 9 m.
CN202020641131.9U 2020-04-24 2020-04-24 A stand that is used for inserted lift scaffold of gradual change cross-section building Active CN212129871U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020641131.9U CN212129871U (en) 2020-04-24 2020-04-24 A stand that is used for inserted lift scaffold of gradual change cross-section building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020641131.9U CN212129871U (en) 2020-04-24 2020-04-24 A stand that is used for inserted lift scaffold of gradual change cross-section building

Publications (1)

Publication Number Publication Date
CN212129871U true CN212129871U (en) 2020-12-11

Family

ID=73690745

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020641131.9U Active CN212129871U (en) 2020-04-24 2020-04-24 A stand that is used for inserted lift scaffold of gradual change cross-section building

Country Status (1)

Country Link
CN (1) CN212129871U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727113A (en) * 2020-12-29 2021-04-30 上海建工四建集团有限公司 System for increasing construction top-lifting cantilever end attached wall by using standard knot and installation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727113A (en) * 2020-12-29 2021-04-30 上海建工四建集团有限公司 System for increasing construction top-lifting cantilever end attached wall by using standard knot and installation method

Similar Documents

Publication Publication Date Title
CN214531117U (en) Assembled steel construction house module connection structure
CN212129871U (en) A stand that is used for inserted lift scaffold of gradual change cross-section building
CN211057625U (en) Prefabricated pier stud of assembled installation aligning device
CN216276816U (en) Connecting assembly for hanging frame of building machine
CN212506008U (en) Fast-assembling guardrail
CN210117915U (en) Single-floor climbing frame and climbing system
CN218976174U (en) Electric power construction crossing frame
CN211473311U (en) Movable adjustable tower
CN111021702A (en) Lifting scaffold unit
CN213571537U (en) Bridge safety device
CN210152410U (en) Stereotyping protective barrier suitable for soft foundation rapid construction
CN215564254U (en) Scaffold frame that construction was used
CN219992538U (en) Subway large-span columnless transfer station arched roof optimization structure
CN212176545U (en) Wall-attached guide seat for creeping formwork
CN218733096U (en) Multi-purpose combination cable testing bridge of side slope
CN216276815U (en) Connecting assembly for hanging frame of building machine
CN216275246U (en) High-strength bracket for bent cap construction
CN219177355U (en) Clamping assembly for gantry connecting frame
CN221001858U (en) Construction operation platform
CN218581177U (en) Stair braced system
CN214495334U (en) Construction elevator auxiliary stay device
CN217232601U (en) Combined upright post for climbing overhead layer
CN218346734U (en) Building wall frame for building construction of house wall surface
CN219548303U (en) Scaffold for civil engineering construction
CN216240384U (en) Operation platform assembly with ladder stand suitable for steel structure high altitude installation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant