CN212003047U - Geological survey is with rig balancing unit - Google Patents

Geological survey is with rig balancing unit Download PDF

Info

Publication number
CN212003047U
CN212003047U CN202020421295.0U CN202020421295U CN212003047U CN 212003047 U CN212003047 U CN 212003047U CN 202020421295 U CN202020421295 U CN 202020421295U CN 212003047 U CN212003047 U CN 212003047U
Authority
CN
China
Prior art keywords
drilling platform
rig
screw rod
drilling
balancing unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020421295.0U
Other languages
Chinese (zh)
Inventor
王贵轩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020421295.0U priority Critical patent/CN212003047U/en
Application granted granted Critical
Publication of CN212003047U publication Critical patent/CN212003047U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a rig balancing unit is used in geological survey, including drilling platform, install the rig body on drilling platform and set up on drilling platform and correspond the drill way of rig body drill bit, four side equipartitions of drilling platform have the card frame, and card frame facial make-up is equipped with through spliced pole interconnect between a plurality of support columns and the support column, all is equipped with first screw hole in the spliced pole, and first screw hole female connection has the screw rod, and the backup pad has all been installed to the bottom of screw rod, and the top of screw rod has been installed and has been revolved the board. Can move the maintenance with the card frame to each side position of drilling platform, do benefit to and adjust the backup pad position, make it can support relatively more flat subaerial, rotatory board of revolving, the screw rod is rotatory downwards in the screw hole, contacts each backup pad ground at last for drilling platform steadily places subaerial, through the support of this kind of balancing unit to ground of different side positions.

Description

Geological survey is with rig balancing unit
Technical Field
The utility model belongs to the technical field of the geology reconnaissance, concretely relates to drilling rig balancing unit for geology reconnaissance.
Background
In the geological exploration process, a drilling machine is needed to drill an exploration area so as to sample underground rock and soil, and then inspection analysis is carried out.
Present medium-sized rig of geological survey, the downside is drilling platform, the last rig that has flexible drill bit of installing of drilling platform, the last drill way that still sets up corresponding rig drill bit of drilling platform, a drill bit for the rig wears out drilling platform and drills into the underground, because some regional ground is not flat, drilling platform places this subaerial time unstability, when the drill bit is drilled into the underground down, when the drill bit runs into harder stratum, drilling platform's unstability, rock when leading to drill bit drilling stratum easily, the drill bit is easy to be cracked, thereby the loss is great, current mode, fill up into the stone with drilling platform's bottom surface and the gapped region of ground cooperation, can not rock with guarantee drilling platform, the weak point of existence has: due to the complexity of the ground, it is temporarily difficult to find a matched stone block to be padded under the drilling platform, and when the drilling platform is actually placed on the uneven ground, the balance of the drilling platform is difficult to effectively ensure.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a rig balancing unit is used in geological survey to solve among the prior art and actually place drilling platform when uneven subaerial, be difficult to effectively ensure the problem of its equilibrium.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a geological survey is with rig balancing unit, includes drilling platform, installs the rig body on drilling platform and sets up on drilling platform and correspond the drill way of rig body drill bit, four side equipartitions of drilling platform have the card frame, card frame facial make-up is equipped with through spliced pole interconnect between a plurality of support columns and the support column, all be equipped with first screw hole in the support column, first screw hole female connection has the screw rod, the backup pad has all been installed to the bottom of screw rod, the top of screw rod has been installed and has been revolved the board.
Preferably, the supporting column is of a square column structure.
Preferably, the lower surface of the supporting plate is uniformly provided with anti-skid protrusions which are of a hemispherical structure.
Preferably, the clamping frame is of a U-shaped plate structure and is inserted into the drilling platform, the clamping frame is provided with second threaded holes, the second threaded holes are in threaded connection with bolts, positioning grooves are evenly formed in the four sides of the upper surface of the drilling platform, and the bolts are inserted into the positioning grooves.
Compared with the prior art, the beneficial effects of the utility model are that:
first, the clamping frame can be moved and retained to all side positions of the drilling platform, and the position of the supporting plate can be adjusted conveniently, so that the supporting plate can be supported on relatively flat ground.
The second, rotatory board of revolving, the screw rod is rotatory downwards in the threaded hole, contacts each backup pad ground at last for drilling platform steadily places subaerial, and this kind of balancing unit through different side positions is to the support on ground, has solved and has actually placed drilling platform when uneven subaerial, is difficult to effectively ensure its equilibrium's problem.
Drawings
Fig. 1 is a schematic front view of the present invention;
FIG. 2 is a partially cut-away front view of the present invention;
fig. 3 is a schematic top view of the present invention;
fig. 4 is a top view partially sectional schematic view of the present invention.
In the figure: the drilling platform comprises a drilling platform 1, a drilling machine body 2, a drilling opening 3, a clamping frame 4, a supporting column 5, a connecting column 6, a first threaded hole 7, a screw rod 8, a supporting plate 9, an anti-skid protrusion 10, a rotating plate 11, a second threaded hole 12, a bolt 13 and a positioning groove 14.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1, fig. 2, fig. 3 and fig. 4, the present invention provides a technical solution: the utility model provides a rig balancing unit is used in geological survey, including drilling platform 1, install rig body 2 on drilling platform 1 and set up on drilling platform 1 and correspond the drill hole 3 of rig body 2 drill bit, four side equipartitions of drilling platform 1 have card frame 4, card frame 4 is U template structure, four sides of drilling platform 1 all set up two card frames 4, card frame 4 facial make-up is equipped with between a plurality of support columns 5 and the support column 5 through 6 interconnect of spliced pole, transversely set up three support column 5 on every card frame 4, support column 5 and spliced pole 6 are founding an organic whole.
Referring to fig. 1, 2, 3 and 4, the support column 5 is a square column structure, the support column 5 is internally provided with a first threaded hole 7, the first threaded hole 7 is arranged at the central position of the connecting column 6, the first threaded hole 7 is in threaded connection with a screw 8, the bottom of the screw 8 is provided with a support plate 9, the support plate 9 is a circular plate structure, the lower end of the screw 8 is welded and connected with the central position of the upper surface of the support plate 9, the lower surface of the support plate 9 is uniformly provided with anti-skidding protrusions 10, the anti-skidding protrusions 10 and the support plate 9 are integrated by fusion casting, the arrangement of the anti-skidding protrusions 10 increases the matching resistance between the lower surface of the support plate 9 and the ground, the support plate 9 is not easy to slide when supported on the ground, the anti-skidding protrusions 10 are of a hemispherical structure, the top of the screw 9 is provided with a rotary plate 11, the rotary plate 11 is a circular plate, inner wall sliding contact drilling platform 1 of card frame 4 all is equipped with second screw hole 12 on the card frame 4, and second screw hole 12 sets up the upper surface central point who puts at card frame 4, and second screw hole 12 threaded connection bolt 13, the equipartition has constant head tank 14 on four sides of drilling platform 1's upper surface, and constant head tank 14 is circular groove structure, and when bolt 13 screw in constant head tank 14 was interior, had stabilized card frame 4 at drilling platform 1 position, bolt 13 inserts constant head tank 14.
The utility model discloses when concrete implementation: before the drilling platform is used, a plurality of workers can stand on four sides of the drilling platform 1 respectively, a leveling disc is placed on the upper surface of the drilling platform 1, the drilling platform 1 is lifted upwards, a supporting plate 9 is separated from the ground upwards, a bolt 13 is rotated, the bolt 13 is rotated upwards to go out of a positioning groove 14, a clamping frame 4 is moved to each side position of the drilling platform 1 until the lower surface of the supporting plate 9 can correspond to the relatively flat ground, the bolt 13 corresponds to the corresponding positioning groove 14, the bolt 13 is rotated reversely, the bolt 13 is rotated into the positioning groove 14, the position of the clamping frame 4 on the drilling platform 1 is stabilized, the height of each side position on the drilling platform 1 is properly adjusted, central air bubbles of the leveling disc flow into a central scale mark, a rotary plate 11 is rotated to enable a screw rod 8 to rotate downwards in a threaded hole 7, finally, each supporting plate 9 is contacted with the ground, the drilling platform 1 is stably placed on the ground, and the ground is, the balance of the drilling operation process of the drilling machine can be effectively guaranteed. The problem of drilling equipment operation in-process, the drill bit receives the reverse impact direction of harder stone to be difficult to ensure, and original pad income stone also can both be filled up in each position of four sides basically, and stability will be enough strong can, three or four supports although can balanced support, but receive the not strong technical problem of balanced guarantee nature of harder stone impact back.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. The utility model provides a geological survey is with rig balancing unit, includes drilling platform (1), install rig body (2) on drilling platform (1) and set up drilling opening (3) on drilling platform (1) and corresponding rig body (2) drill bit, its characterized in that: clamping frames (4) are evenly distributed on four sides of the drilling platform (1), a plurality of supporting columns (5) are arranged on the clamping frames (4) in an assembled mode, the supporting columns (5) are connected with one another through connecting columns (6), first threaded holes (7) are formed in the supporting columns (5), threaded screws (8) are connected into the first threaded holes (7) in an inner threaded mode, supporting plates (9) are installed at the bottoms of the screws (8), and rotating plates (11) are installed at the tops of the screws (8).
2. A drill rig counterbalance arrangement for geological surveying according to claim 1, wherein: the support column (5) is of a square column structure.
3. A drill rig counterbalance arrangement for geological surveying according to claim 1, wherein: the lower surface of the supporting plate (9) is uniformly provided with anti-skid protrusions (10), and the anti-skid protrusions (10) are of a hemispherical structure.
4. A drill rig counterbalance arrangement for geological surveying according to claim 1, wherein: the clamp frame (4) is of a U-shaped plate structure, the clamp frame (4) is inserted into the drilling platform (1), second threaded holes (12) are formed in the clamp frame (4), the second threaded holes (12) are in threaded connection with bolts (13), positioning grooves (14) are evenly distributed in four sides of the upper surface of the drilling platform (1), and the bolts (13) are inserted into the positioning grooves (14).
CN202020421295.0U 2020-03-28 2020-03-28 Geological survey is with rig balancing unit Expired - Fee Related CN212003047U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020421295.0U CN212003047U (en) 2020-03-28 2020-03-28 Geological survey is with rig balancing unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020421295.0U CN212003047U (en) 2020-03-28 2020-03-28 Geological survey is with rig balancing unit

Publications (1)

Publication Number Publication Date
CN212003047U true CN212003047U (en) 2020-11-24

Family

ID=73421816

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020421295.0U Expired - Fee Related CN212003047U (en) 2020-03-28 2020-03-28 Geological survey is with rig balancing unit

Country Status (1)

Country Link
CN (1) CN212003047U (en)

Similar Documents

Publication Publication Date Title
CN210918867U (en) Drilling rig for geological survey
CN213902934U (en) Geological exploration tool
CN211042775U (en) Sampler for geological environment monitoring
CN212003047U (en) Geological survey is with rig balancing unit
CN214330523U (en) Simple drilling device for geological mineral exploration
CN112483007A (en) Drilling equipment for resource exploration
CN215332807U (en) Geological exploration drilling device
CN214697693U (en) Portable geological survey device
CN214741128U (en) Drilling device for underground water resource observation
CN116104417A (en) Balance equipment for geological survey drilling machine
CN214793870U (en) Geotechnical sampling device for constructional engineering investigation
CN112482991B (en) Roofbolter with geology recognition function
CN219692722U (en) A mapping equipment support frame for geological exploration
CN112796293A (en) Rig carries static sounding survey equipment
CN112664136A (en) Drilling platform for geological exploration
CN215931333U (en) Geological exploration sampling device
CN220504937U (en) Mineral geological investigation rig
CN214145483U (en) High-efficient probing device of geological survey
CN213181560U (en) Water flooding core clamping device
CN217738709U (en) Mining geological exploration is with electronic rotation type sampler
CN220504967U (en) Drill rod bracket of horizontal directional drilling machine
CN214394840U (en) Drilling machine for civil construction
CN215860023U (en) Pneumatic drilling machine for geological exploration hydraulic engineering
CN217089957U (en) Geological exploration device suitable for different topography
CN221038118U (en) Geological investigation corer

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Wang Guixuan

Inventor after: Hu Maomao

Inventor after: Hu Jun

Inventor before: Wang Guixuan

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201124