Prior art keywords
pipe
connecting pipe
filling machine
filling
conveyor belt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020159616.4U
Other languages
Chinese (zh)
Inventor
杨前卫
马姗姗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xi'an Oriental Dairy Co ltd
Original Assignee
Xi'an Oriental Dairy Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xi'an Oriental Dairy Co ltd filed Critical Xi'an Oriental Dairy Co ltd
Priority to CN202020159616.4U priority Critical patent/CN211969942U/en
Application granted granted Critical
Publication of CN211969942U publication Critical patent/CN211969942U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Containers And Plastic Fillers For Packaging (AREA)

Abstract

本实用新型公开了一种高速枕灌装机除水装置,涉及灌装设备的技术领域。其技术要点是:包括灌装机本体,灌装机本体包括依次连接的上袋结构、灌装机构、以及热封机构,热封机构的出料口连接有传送带,传送带通过支撑架固定于地面,传送带上侧设有固定架,固定架的下表面连接有连接管,连接管通过第一连接件连接有若干出风管,连接管一端通过第二连接件连接于风机且连接管另一端封闭设置。通过设置的传送带,传送带上固定连接的固定架,以及固定架下侧连接的连接管,通过连接管上设置的风机对包装袋表面的水雾进行吹干,避免了在装箱过程中因包装袋表面存在水分而破坏包装箱,提高了工作效率,节省了成本。

Figure 202020159616

The utility model discloses a water removing device for a high-speed pillow filling machine, which relates to the technical field of filling equipment. The technical points are: including a filling machine body, the filling machine body includes an upper bag structure, a filling mechanism, and a heat-sealing mechanism connected in sequence, the discharge port of the heat-sealing mechanism is connected with a conveyor belt, and the conveyor belt is fixed on the ground through a support frame The upper side of the conveyor belt is provided with a fixing frame, the lower surface of the fixing frame is connected with a connecting pipe, the connecting pipe is connected with a number of air outlet pipes through the first connecting piece, one end of the connecting pipe is connected to the fan through the second connecting piece, and the other end of the connecting pipe is closed set up. Through the set conveyor belt, the fixed frame fixedly connected on the conveyor belt, and the connecting pipe connected to the lower side of the fixed frame, the water mist on the surface of the packaging bag is blown dry by the fan set on the connecting pipe, so as to avoid the problems caused by packaging during the packing process. The presence of moisture on the surface of the bag damages the packaging box, which improves work efficiency and saves costs.

Figure 202020159616

Description

一种高速枕灌装机除水装置A high-speed pillow filling machine water removal device

技术领域technical field

本实用新型涉及灌装设备的技术领域,更具体地说,它涉及一种高速枕灌装机除水装置。The utility model relates to the technical field of filling equipment, in particular to a water removing device for a high-speed pillow filling machine.

背景技术Background technique

液体饮品软体包装袋的灌装作业常采用灌装机来完成,灌装机通常包括上袋机构、灌注机构和热封机构。上袋机构将包装袋送到灌注机构后,灌注机构完成灌注,再由热封机构封装后进入下一流程,在热封的过程中会喷淋水雾对包装袋热封后进行冷却,但是在装箱时会因为包装袋上的水雾将包装箱打湿,容易损坏包装箱。The filling operation of liquid beverage soft packaging bags is often completed by a filling machine, which usually includes a bag-loading mechanism, a filling mechanism and a heat-sealing mechanism. After the bag loading mechanism sends the packaging bag to the perfusion mechanism, the perfusion mechanism completes the perfusion, and then encapsulates it by the heat sealing mechanism and enters the next process. During the heat sealing process, water mist will be sprayed to cool the packaging bag after heat sealing, but When packing, the packing box will be wet due to the water mist on the packing bag, which is easy to damage the packing box.

在公开号为CN207713385U的中国实用新型专利公开了一种液体灌装机。包括机座,机座上设有料缸、调压装置、压力表、脚踏开关、选择开关、急停开关,料缸上连接有三通阀,三通阀的上下两端分别设有出料软管和进料软管,机座上还设有支架杆,支架杆上设有灌装头总成,灌装头总成包括灌装气缸、灌装三通导管和灌装长导管,灌装气缸设置在灌装三通导管顶部,灌装气缸的活塞杆设置在灌装三通导管内部,活塞杆与灌装三通导管顶壁伸缩连接处密封,活塞杆末端设有活塞开关,灌装三通导管侧部开口与出料软管密封连接,灌装长导管顶部与灌装三通导管螺纹连接,灌装长导管底部设有第一灌装支管和第二灌装支管,第一灌装支管、第二灌装支管均与灌装长导管底部连通,第一灌装支管、第二灌装支管均与灌装长导管底部连通处设有截流阀门,截流阀门为铁片板,铁片板底部与内部管壁铰接,且铁片板与管壁直径相适应,灌装三通导管上还设有支撑架,支撑架底部两侧分别设有第一电磁铁和第二电磁铁,第一电磁铁和第二电磁铁上分别缠绕有第一线圈和第二线圈,机座内部设有电池、总开关和保护电阻,机座外壁设有第一开关和第二开关,第一开关与第一线圈通过导线串联连接,第二开关与第二线圈通过导线串联连接,电池通过导线与总开关、保护电阻串联连接,第一开关与第二开关并联连接,第一线圈与第二线圈通过并联连接。灌装时,首先给第二线圈通电,使第二电磁铁带有磁性,将铁片板吸靠在第二灌装支管处,将第二灌装支管的灌装通道封闭,第一灌装支管的灌装通道接通,用第一灌装支管对容器进行液体灌装,将另一个等待灌装的容器置于第二灌装支管底部对齐。待第一灌装支管底部的容器快装满后,再给第二线圈断电,第一线圈通电,使第一电磁铁带有磁性,将铁片板吸靠在第一灌装支管处,将第一灌装支管的灌装通道封闭,第二灌装支管的灌装通道接通,再对第二灌装支管底部的容器进行灌装。再对第二灌装支管底部的容器进行灌装过程中,第一灌装支管内残留的液体会滴落到第一灌装支管底部的容器内,然后再将装满液体的容器封口,将新的空瓶容器再次放置到第一灌装支管底部,等待第二灌装支管底部的容器灌装完成在进行灌装。A Chinese utility model patent with publication number CN207713385U discloses a liquid filling machine. Including the machine base, the machine base is equipped with a material cylinder, a pressure regulating device, a pressure gauge, a foot switch, a selector switch, and an emergency stop switch, and a three-way valve is connected to the material cylinder. Tube and feeding hose, a bracket rod is also provided on the machine base, and a filling head assembly is arranged on the bracket rod. The filling head assembly includes a filling cylinder, a filling three-way conduit and a filling long conduit. The cylinder is set at the top of the filling tee duct, the piston rod of the filling cylinder is set inside the filling tee duct, the telescopic connection between the piston rod and the top wall of the filling tee duct is sealed, the end of the piston rod is provided with a piston switch, and the filling The side opening of the three-way conduit is sealed with the discharge hose, the top of the filling long conduit is threadedly connected to the filling three-way conduit, and the bottom of the long filling conduit is provided with a first filling branch pipe and a second filling branch pipe. The filling branch pipe and the second filling branch pipe are connected with the bottom of the long filling pipe, and the first filling branch pipe and the second filling branch pipe are connected with the bottom of the long filling pipe. The bottom of the sheet plate is hinged with the inner pipe wall, and the iron sheet plate is adapted to the diameter of the pipe wall. A support frame is also provided on the filling tee conduit, and a first electromagnet and a second electromagnet are respectively provided on both sides of the bottom of the support frame. The first electromagnet and the second electromagnet are respectively wound with a first coil and a second coil, a battery, a main switch and a protection resistor are arranged inside the base, and a first switch and a second switch are arranged on the outer wall of the base. The first switch It is connected in series with the first coil through wires, the second switch is connected in series with the second coil through wires, the battery is connected in series with the main switch and the protection resistor through wires, the first switch is connected in parallel with the second switch, and the first coil and the second coil are connected in series by connecting in parallel. When filling, first energize the second coil to make the second electromagnet with magnetism, suck the iron plate against the second filling branch pipe, close the filling channel of the second filling branch pipe, and the first filling The filling channel of the branch pipe is connected, the container is filled with liquid by the first filling branch pipe, and another container waiting to be filled is placed at the bottom of the second filling branch pipe to align. After the container at the bottom of the first filling branch pipe is almost full, power off the second coil, and the first coil is energized, so that the first electromagnet is magnetic, and the iron plate is sucked against the first filling branch pipe. The filling channel of the first filling branch pipe is closed, the filling channel of the second filling branch pipe is connected, and then the container at the bottom of the second filling branch pipe is filled. During the filling process of the container at the bottom of the second filling branch pipe, the residual liquid in the first filling branch pipe will drip into the container at the bottom of the first filling branch pipe, and then the container filled with liquid is sealed to seal the container. The new empty bottle container is placed at the bottom of the first filling branch pipe again, waiting for the container at the bottom of the second filling branch pipe to be filled before filling.

上述装置通过第一灌装支管与第二灌装支管的循环使用,有效的避免了更换容器的时间段灌装液体的泄漏,而且不会造成时间的浪费,提高了灌装效率,但是仍然不能解决包装袋的水雾损坏包装箱。The above-mentioned device effectively avoids the leakage of the filling liquid during the time period when the container is replaced through the cyclic use of the first filling branch pipe and the second filling branch pipe, and does not waste time and improves the filling efficiency, but still cannot Solve the water mist of the packaging bag to damage the packaging box.

实用新型内容Utility model content

本实用新型的目的在于提供一种高速枕灌装机除水装置,通过设置的传送带,传送带上固定连接的固定架,以及固定架下侧连接的连接管,通过连接管上设置的风机对包装袋表面的水雾进行吹干,避免了在装箱过程中因包装袋表面存在水分而破坏包装箱,提高了工作效率,节省了成本。The purpose of this utility model is to provide a water removing device for a high-speed pillow filling machine, through the conveyor belt provided, the fixed frame fixedly connected on the conveyor belt, and the connecting pipe connected to the lower side of the fixed frame, the packaging is removed by the fan set on the connecting pipe. The water mist on the surface of the bag is blown dry, which avoids damage to the packaging box due to the presence of moisture on the surface of the packaging bag during the packing process, improves work efficiency and saves costs.

为实现上述目的,本实用新型提供了如下技术方案:To achieve the above object, the utility model provides the following technical solutions:

一种高速枕灌装机除水装置,包括灌装机本体,所述灌装机本体包括依次连接的上袋结构、灌装机构、以及热封机构,所述热封机构的出料口连接有传送带,所述传送带通过支撑架固定于地面,所述传送带上侧设有固定架,所述固定架的下表面连接有连接管,所述连接管通过第一连接件连接有若干出风管,所述连接管一端通过第二连接件连接于风机且所述连接管另一端封闭设置。A water removal device for a high-speed pillow filling machine, comprising a filling machine body, wherein the filling machine body comprises an upper bag structure, a filling mechanism, and a heat-sealing mechanism that are connected in sequence, and the discharge port of the heat-sealing mechanism is connected to There is a conveyor belt, the conveyor belt is fixed on the ground through a support frame, a fixed frame is arranged on the upper side of the conveyor belt, and the lower surface of the fixed frame is connected with a connecting pipe, and the connecting pipe is connected with a number of air outlet pipes through the first connecting piece , one end of the connecting pipe is connected to the fan through a second connecting piece, and the other end of the connecting pipe is closed.

通过采用上述技术方案,通过设置的传送带,传送带上固定连接的固定架,以及固定架下侧连接的连接管,通过连接管上设置的风机对包装袋表面的水雾进行吹干,避免了在装箱过程中因包装袋表面存在水分而破坏包装箱,提高了工作效率,节省了成本。By adopting the above technical solution, the water mist on the surface of the packaging bag is blown dry by the fan set on the connecting pipe through the conveyor belt provided, the fixed frame fixedly connected on the conveyor belt, and the connecting pipe connected to the lower side of the fixed frame, avoiding the need for air-conditioning. During the packing process, the packing box is damaged due to the presence of moisture on the surface of the packing bag, which improves the work efficiency and saves the cost.

进一步的,所述固定架的上表面开设有若干相互平行的条形孔,所述连接管的上表面设有至少两个固定块,所述固定块贯穿所述条形孔且远离所述连接管一端置于所述固定架上侧,所述固定块远离所述连接管一端连接有挡块,所述挡块与所述固定块螺纹连接。Further, the upper surface of the fixing frame is provided with a plurality of mutually parallel bar-shaped holes, and the upper surface of the connecting pipe is provided with at least two fixing blocks, and the fixing blocks pass through the bar-shaped holes and are away from the connection. One end of the pipe is placed on the upper side of the fixing frame, and one end of the fixing block away from the connecting pipe is connected with a stopper, and the stopper is threadedly connected with the fixing block.

通过采用上述技术方案,设置的固定块可以将连接管固定在固定架上方便对传送带上的包装袋进行吹风,而设置的条形孔方便移动固定块的位置,进而移动连接管的位置,适用于更多的不同规格的包装袋,提高了装置的适用性。By adopting the above technical solution, the fixed block can fix the connecting pipe on the fixed frame to facilitate the blowing of the packaging bags on the conveyor belt, and the strip-shaped hole is convenient to move the position of the fixed block, and then the position of the connecting pipe, which is suitable for It can be used in more packaging bags of different specifications, which improves the applicability of the device.

进一步的,所述第二连接件为金属定型软管。Further, the second connecting piece is a metal shaped hose.

通过采用上述技术方案,第二连接件设置为金属定型软管可以方便对通过改变第二连接件的形状,来对风机的位置进行调节,可以将风机放在一个不会影响操作者的位置,提高了工作效率,同时节省了空间利用率。By adopting the above technical solution, setting the second connecting piece as a metal shaped hose can facilitate the adjustment of the position of the fan by changing the shape of the second connecting piece, and the fan can be placed in a position that will not affect the operator, Improve work efficiency and save space utilization.

进一步的,所述第一连接件包括与所述连接管连接的固定管,还包括倾斜管,所述倾斜管一端连接于固定管且另一端连接于出风管,所述倾斜管的轴线延长线与所述固定管的轴线延长线之间存在夹角且不重合。Further, the first connecting piece includes a fixed pipe connected with the connecting pipe, and also includes an inclined pipe, one end of the inclined pipe is connected to the fixed pipe and the other end is connected to the air outlet pipe, and the axis of the inclined pipe is extended. There is an included angle between the line and the extension line of the axis of the fixed tube and are not coincident.

通过采用上述技术方案,设置的倾斜管与固定管能够将改变出风的方向将正面吹风变为侧吹,能够使风吹的更加均匀,提高了蒸发的效率。By adopting the above technical solution, the provided inclined pipe and fixed pipe can change the direction of the air blowing from the front to the side blowing, which can make the air blow more evenly and improve the efficiency of evaporation.

进一步的,所述固定管上套设有从动轮,所述固定架一侧设有电机,所述电机的输出端套接有主动轮,所述主动轮与所述从动轮通过链条啮合连接。Further, a driven wheel is sleeved on the fixing tube, a motor is installed on one side of the fixing frame, a driving wheel is sleeved at the output end of the motor, and the driving wheel and the driven wheel are meshed and connected by a chain.

通过采用上述技术方案,通过设置的主动轮以及从动轮,通过链条连接,再通过电机驱动,增大了出风管的覆盖面积,提高了吹干的效率。By adopting the above technical scheme, the provided driving wheel and the driven wheel are connected by a chain, and then driven by a motor, so that the coverage area of the air outlet pipe is increased, and the drying efficiency is improved.

进一步的,所述倾斜管为金属定型软管。Further, the inclined tube is a metal shaped hose.

通过采用上述技术方案,倾斜管设置为金属定型软管方便去调节角度,进而可以吹到不同的角度,从而提高了吹干的效率。By adopting the above technical solution, the inclined tube is set as a metal shaped hose to facilitate the adjustment of the angle, so that it can be blown to different angles, thereby improving the drying efficiency.

进一步的,所述固定架沿所述传送带传动方向分为若干段,若干段相互拼接。Further, the fixing frame is divided into several sections along the driving direction of the conveyor belt, and the several sections are spliced with each other.

通过采用上述技术方案,设置成拼接段,可以根据实际需要的长度来选取合适的长度进行使用,节省了材料,从而降低了成本。By adopting the above-mentioned technical scheme and setting it as a splicing section, a suitable length can be selected and used according to the actual required length, which saves materials and thus reduces costs.

进一步的,所述固定架的拼接处设有密封垫。Further, a sealing gasket is provided at the splicing part of the fixing frame.

通过采用上述技术方案,设置的密封垫可以降低拼接处的漏风。By adopting the above technical solution, the provided sealing gasket can reduce the air leakage at the splicing part.

与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the present utility model are:

(1)通过采用上述技术方案,通过设置的传送带,传送带上固定连接的固定架,以及固定架下侧连接的连接管,通过连接管上设置的风机对包装袋表面的水雾进行吹干,避免了在装箱过程中因包装袋表面存在水分而破坏包装箱,提高了工作效率,节省了成本;(1) By adopting the above technical solution, the water mist on the surface of the packaging bag is blown dry by the fan set on the connecting pipe through the conveyor belt set, the fixed frame fixedly connected on the conveyor belt, and the connecting pipe connected to the lower side of the fixed frame, It avoids the damage of the packing box due to the presence of moisture on the surface of the packing bag during the packing process, improves the work efficiency and saves the cost;

(2)通过采用上述技术方案,设置的固定块可以将连接管固定在固定架上方便对传送带上的包装袋进行吹风,而设置的条形孔方便移动固定块的位置,进而移动连接管的位置,适用于更多的不同规格的包装袋,提高了装置的适用性。(2) By adopting the above technical solution, the fixed block can fix the connecting pipe on the fixed frame to facilitate the blowing of the packaging bag on the conveyor belt, and the strip hole is convenient to move the position of the fixed block, thereby moving the connecting pipe. The position is suitable for more bags of different specifications, which improves the applicability of the device.

附图说明Description of drawings

图1为本实用新型整体结构示意图;1 is a schematic diagram of the overall structure of the present utility model;

图2为本实用新型部分结构示意图;Fig. 2 is a partial structural representation of the utility model;

图3为连接管与出风管的连接示意图。FIG. 3 is a schematic diagram of the connection between the connecting pipe and the air outlet pipe.

附图标记:1、上袋结构;2、灌装机构;3、热封机构;4、传送带;5、支撑架;6、固定架;7、连接管;8、第一连接件;81、固定管;82、倾斜管;9、出风管;10、第二连接件;11、条形孔;12、固定块;13、挡块;14、从动轮;15、主动轮;16、电机;17、链条;18、密封垫;19、风机。Reference numerals: 1. Upper bag structure; 2. Filling mechanism; 3. Heat sealing mechanism; 4. Conveyor belt; 5. Supporting frame; 6. Fixing frame; 7. Connecting pipe; Fixed pipe; 82, inclined pipe; 9, air outlet pipe; 10, second connecting piece; 11, strip hole; 12, fixed block; 13, stop block; 14, driven wheel; 15, driving wheel; 16, motor ; 17, chain; 18, gasket; 19, fan.

具体实施方式Detailed ways

下面结合附图和实施例,对本实用新型进行详细描述。The present utility model will be described in detail below with reference to the accompanying drawings and embodiments.

如图1、图2和图3所示,为本实用新型所披露的一种高速枕灌装机除水装置,包括灌装机本体,灌装机本体包括依次连接的上袋结构1、灌装机构2、以及热封机构3,热封机构3的出料口连接有传送带4,传送带4通过支撑架5固定于地面,传送带4上侧设有固定架6,固定架6的下表面连接有连接管7,连接管7通过第一连接件8连接有若干出风管9,连接管7一端通过第二连接件10连接于风机19且连接管7另一端封闭设置。通过设置的传送带4,传送带4上固定连接的固定架6,以及固定架6下侧连接的连接管7,通过连接管7上设置的风机19对包装袋表面的水雾进行吹干,避免了在装箱过程中因包装袋表面存在水分而破坏包装箱,提高了工作效率,节省了成本。As shown in Figure 1, Figure 2 and Figure 3, it is a water removal device for a high-speed pillow filling machine disclosed by the utility model, comprising a filling machine body, and the filling machine body comprises an upper bag structure 1 connected in sequence, a filling machine The mounting mechanism 2 and the heat sealing mechanism 3, the discharge port of the heat sealing mechanism 3 is connected with the conveyor belt 4, the conveyor belt 4 is fixed on the ground through the support frame 5, the upper side of the conveyor belt 4 is provided with a fixing frame 6, and the lower surface of the fixing frame 6 is connected There is a connecting pipe 7. The connecting pipe 7 is connected with several air outlet pipes 9 through the first connecting piece 8. One end of the connecting pipe 7 is connected to the fan 19 through the second connecting piece 10, and the other end of the connecting pipe 7 is closed. Through the conveyor belt 4 provided, the fixed frame 6 fixedly connected on the conveyor belt 4, and the connecting pipe 7 connected to the lower side of the fixed frame 6, the water mist on the surface of the packaging bag is blown dry by the fan 19 set on the connecting pipe 7, so as to avoid During the packing process, the packing box is damaged due to the presence of moisture on the surface of the packing bag, which improves the work efficiency and saves the cost.

如图2和图3所示,固定架6的上表面开设有若干相互平行的条形孔11,连接管7的上表面设有至少两个固定块12,固定块12贯穿条形孔11且远离连接管7一端置于固定架6上侧,固定块12远离连接管7一端连接有挡块13,挡块13与固定块12螺纹连接。设置的固定块12可以将连接管7固定在固定架6上方便对传送带4上的包装袋进行吹风,而设置的条形孔11方便移动固定块12的位置,进而移动连接管7的位置,适用于更多的不同规格的包装袋,提高了装置的适用性。第二连接件10为金属定型软管。第二连接件10设置为金属定型软管可以方便对通过改变第二连接件10的形状,来对风机19的位置进行调节,可以将风机19放在一个不会影响操作者的位置,提高了工作效率,同时节省了空间利用率。第一连接件8包括与连接管7连接的固定管81,还包括倾斜管82,倾斜管82一端连接于固定管81且另一端连接于出风管9,倾斜管82的轴线延长线与固定管81的轴线延长线之间存在夹角且不重合。设置的倾斜管82与固定管81能够将改变出风的方向将正面吹风变为侧吹,能够使风吹的更加均匀,提高了蒸发的效率。固定管81上套设有从动轮14,固定架6一侧设有电机16,电机16的输出端套接有主动轮15,主动轮15与从动轮14通过链条17啮合连接。主动轮15与从动轮14均为链轮,链条17图中用皮带示意。通过设置的主动轮15以及从动轮14,通过链条17连接,再通过电机16驱动,增大了出风管9的覆盖面积,提高了吹干的效率。倾斜管82为金属定型软管。倾斜管82设置为金属定型软管方便去调节角度,进而可以吹到不同的角度,从而提高了吹干的效率。As shown in FIG. 2 and FIG. 3 , the upper surface of the fixing frame 6 is provided with a plurality of mutually parallel bar-shaped holes 11 , the upper surface of the connecting pipe 7 is provided with at least two fixing blocks 12 , and the fixing blocks 12 pass through the bar-shaped holes 11 and One end away from the connecting pipe 7 is placed on the upper side of the fixing frame 6 , and one end of the fixing block 12 away from the connecting pipe 7 is connected with a stopper 13 , and the stopper 13 is threadedly connected with the fixing block 12 . The set fixing block 12 can fix the connecting pipe 7 on the fixing frame 6 to facilitate the blowing of the packaging bag on the conveyor belt 4, and the set strip hole 11 is convenient to move the position of the fixing block 12, and then move the position of the connecting pipe 7, It is suitable for more packaging bags of different specifications, which improves the applicability of the device. The second connector 10 is a metal shaped hose. The setting of the second connecting piece 10 as a metal shaped hose can facilitate the adjustment of the position of the fan 19 by changing the shape of the second connecting piece 10 . Work efficiency while saving space utilization. The first connecting piece 8 includes a fixed pipe 81 connected with the connecting pipe 7, and also includes an inclined pipe 82. One end of the inclined pipe 82 is connected to the fixed pipe 81 and the other end is connected to the air outlet pipe 9. The axis extension of the inclined pipe 82 is connected to the fixed pipe 82. There is an included angle between the extension lines of the axis of the pipe 81 and do not coincide. The provided inclined pipe 82 and the fixed pipe 81 can change the direction of the air blowing from the front side to the side blowing, which can make the wind blow more uniformly and improve the efficiency of evaporation. A driven wheel 14 is sleeved on the fixed tube 81 , a motor 16 is installed on one side of the fixing frame 6 , and the output end of the motor 16 is sleeved with a driving wheel 15 . Both the driving wheel 15 and the driven wheel 14 are sprockets, and the chain 17 is indicated by a belt in the figure. The provided driving wheel 15 and the driven wheel 14 are connected by the chain 17 and then driven by the motor 16 to increase the coverage area of the air outlet 9 and improve the drying efficiency. The inclined tube 82 is a metal shaped hose. The inclined tube 82 is set as a metal shaped hose for easy adjustment of the angle, so that it can be blown to different angles, thereby improving the drying efficiency.

如图1所示,固定架6沿传送带4传动方向分为若干段,若干段相互拼接。设置成拼接段,可以根据实际需要的长度来选取合适的长度进行使用,节省了材料,从而降低了成本。固定架6的拼接处设有密封垫18。设置的密封垫18可以降低拼接处的漏风。As shown in FIG. 1 , the fixing frame 6 is divided into several sections along the transmission direction of the conveyor belt 4 , and the several sections are spliced with each other. It is set as a splicing section, and an appropriate length can be selected and used according to the actual required length, which saves materials and thus reduces costs. A gasket 18 is provided at the splicing part of the fixing frame 6 . The provided sealing gasket 18 can reduce the air leakage at the joint.

以上所述仅是本实用新型的优选实施方式,本实用新型的保护范围并不仅局限于上述实施例,凡属于本实用新型思路下的技术方案均属于本实用新型的保护范围。应当指出,对于本技术领域的普通技术人员来说,在不脱离本实用新型原理前提下的若干改进和润饰,这些改进和润饰也应视为本实用新型的保护范围。The above are only the preferred embodiments of the present invention, and the protection scope of the present invention is not limited to the above-mentioned embodiments, and all technical solutions that belong to the idea of the present invention belong to the protection scope of the present invention. It should be pointed out that for those skilled in the art, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.

Claims (8)

1. The utility model provides a high-speed pillow liquid filling machine water trap, includes the liquid filling machine body, the liquid filling machine body is including last bag structure (1), filling mechanism (2) and heat-seal mechanism (3) that connect gradually, its characterized in that, the discharge gate of heat-seal mechanism (3) is connected with conveyer belt (4), conveyer belt (4) are fixed in ground through support frame (5), conveyer belt (4) upside is equipped with mount (6), the lower surface of mount (6) is connected with connecting pipe (7), connecting pipe (7) are connected with a plurality of play tuber pipes (9) through first connecting piece (8), connecting pipe (7) one end is passed through second connecting piece (10) and is connected in fan (19) just connecting pipe (7) other end seals the setting.
2. The water removing device for the high-speed pillow filling machine according to claim 1, wherein a plurality of strip-shaped holes (11) which are parallel to each other are formed in the upper surface of the fixing frame (6), at least two fixing blocks (12) are arranged on the upper surface of the connecting pipe (7), the fixing blocks (12) penetrate through the strip-shaped holes (11), one end of each fixing block (12) far away from the connecting pipe (7) is arranged on the upper side of the fixing frame (6), one end of each fixing block (12) far away from the connecting pipe (7) is connected with a stop block (13), and the stop block (13) is in threaded connection with the fixing blocks (12).
3. A high speed pillow filler de-watering device according to claim 1, characterised in that the second connector (10) is a metal profile hose.
4. The water removing device for the high-speed pillow filling machine according to claim 3, wherein the first connecting member (8) comprises a fixed pipe (81) connected with the connecting pipe (7), and further comprises an inclined pipe (82), one end of the inclined pipe (82) is connected to the fixed pipe (81) and the other end of the inclined pipe is connected to the air outlet pipe (9), and an included angle is formed between an axis extension line of the inclined pipe (82) and an axis extension line of the fixed pipe (81) and the included angle is not coincident with the axis extension line of the inclined pipe (82).
5. The water removing device of the high-speed pillow filling machine according to claim 4, wherein a driven wheel (14) is sleeved on the fixed pipe (81), a motor (16) is arranged on one side of the fixed frame (6), an output end of the motor (16) is sleeved with a driving wheel (15), and the driving wheel (15) is meshed with the driven wheel (14) through a chain (17).
6. The high speed pillow filler de-watering apparatus of claim 4 wherein the angled tube (82) is a metal forming hose.
7. A high speed pillow filler de-watering device according to claim 1, characterized in that the holder (6) is divided into sections in the direction of the conveyor belt (4) drive, which sections are joined to each other.
8. A water removal device for a high-speed pillow filler according to claim 7, characterized in that a sealing gasket (18) is provided at the joint of the fixing frame (6).
CN202020159616.4U 2020-02-10 2020-02-10 A high-speed pillow filling machine water removal device Expired - Fee Related CN211969942U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020159616.4U CN211969942U (en) 2020-02-10 2020-02-10 A high-speed pillow filling machine water removal device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020159616.4U CN211969942U (en) 2020-02-10 2020-02-10 A high-speed pillow filling machine water removal device

Publications (1)

Publication Number Publication Date
CN211969942U true CN211969942U (en) 2020-11-20

Family

ID=73372495

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020159616.4U Expired - Fee Related CN211969942U (en) 2020-02-10 2020-02-10 A high-speed pillow filling machine water removal device

Country Status (1)

Country Link
CN (1) CN211969942U (en)

Similar Documents

Publication Publication Date Title
CN207209929U (en) Bottled Yoghourt bottle placer based on Pneumatic time-delay control
CN207191620U (en) One kind pumping heat sealing machine
CN104176305B (en) A kind of full-automatic fruit bag machine
CN211969942U (en) A high-speed pillow filling machine water removal device
CN105841462A (en) Water removing device for packaging foam
CN218858840U (en) A multifunctional bag opening device for prefabricated bags
CN113562247B (en) Efficient food processing packing apparatus
CN206307735U (en) A kind of parcel automatic material-absorbing device
CN113826975B (en) Be used for clothing production to load device with organic velvet
CN210592618U (en) Full-automatic powder heat seal air exhaust device
CN208761031U (en) A kind of packing machine is with removing adhesive dispenser
CN211845052U (en) Vacuum-pumping system of vacuum packaging machine
CN209209174U (en) Full-automatic clapper type bag clamping mechanism
CN206478990U (en) A kind of leak detection automatic air-drying equipment of aerosol products
CN203698777U (en) Food sealer
CN203819581U (en) Paper adhesive tape sealing heating device of bag feeding machine
CN221070997U (en) Plastic soft bottle filling and sealing machine
CN220363545U (en) Integral packer for temperature sensor
CN206537592U (en) Sealing machine for powdery material packaging bag
CN211224443U (en) Novel packaged food storage device
CN221954698U (en) Aluminum profile bagging machine
CN214766565U (en) Dispensing mechanism of dispenser
CN217865134U (en) A kind of sealing equipment for tea bag production
CN106628718B (en) Freeze leak stoppage tool and technique
JP3604419B2 (en) Bag sealing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201120