CN211951709U - Support hanger for comprehensive pipeline - Google Patents

Support hanger for comprehensive pipeline Download PDF

Info

Publication number
CN211951709U
CN211951709U CN201922231560.9U CN201922231560U CN211951709U CN 211951709 U CN211951709 U CN 211951709U CN 201922231560 U CN201922231560 U CN 201922231560U CN 211951709 U CN211951709 U CN 211951709U
Authority
CN
China
Prior art keywords
base
bearing
gallows
rod
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922231560.9U
Other languages
Chinese (zh)
Inventor
易平
张寿俊
陈金海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Lide Intelligent Technology Co.,Ltd.
Original Assignee
Nanjing Aomi Intelligent Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Aomi Intelligent Technology Co ltd filed Critical Nanjing Aomi Intelligent Technology Co ltd
Priority to CN201922231560.9U priority Critical patent/CN211951709U/en
Application granted granted Critical
Publication of CN211951709U publication Critical patent/CN211951709U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a synthesize pipe and use a gallows belongs to a gallows technical field, the base below is fixed with the bracing piece, the bracing piece is two, forms with second carrier bar fixed connection structure, the fixed orifices is used for installing the carrier bar and strengthens the device, the carrier bar is hollow cuboid, be equipped with respectively on the carrier bar side and bear the fixed orifices, bear the fixed orifices and bear the fixed orifices one-to-one, be equipped with spacing hole on the second carrier bar to the side of going up and down, install firm device and second gallows on the spacing hole, firm device cross section is the U-shaped, and the lower extreme is equipped with the screw pole, the second gallows is the rectangle frame, strengthen the device and include second base, lead screw, third base, top pipe and lower pipe, this synthesize pipe is with a gallows, simple structure, the flexibility is strong.

Description

Support hanger for comprehensive pipeline
Technical Field
The utility model belongs to the technical field of a gallows, concretely relates to comprehensive pipeline is with a gallows.
Background
The pipeline is synthesized a gallows will be in the installation engineering with the drainage, warm and lead to, electric, the gallows of each specialty such as fire control is synthesized and is in the same place, and the planning design is coordinated, integrates into a unified gallows system, is favorable to practicing thrift the cost, accelerates the construction progress, improves the impression quality to furthest saves space, and current problem exists in the flexibility, can not satisfy the needs of different pipe diameters, lacks to some extent in stability.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a synthesize a gallows for pipeline to the solution can not adapt to different pipe diameters and poor stability's problem.
In order to achieve the above object, the utility model provides a following technical scheme: a supporting and hanging frame for a comprehensive pipeline comprises a base, wherein two supporting rods are fixed below the base, is fixedly connected with a second bearing rod to form a structure, the supporting rod is a cuboid with a hollow inner part, one opening of the supporting rod is in a T shape, two symmetrical side surfaces are provided with symmetrical fixing holes, the fixing holes are used for installing the bearing rod and the reinforcing device, the bearing rod is a hollow cuboid, the bearing fixing holes are respectively arranged on the side surfaces of the bearing rod, the bearing fixing holes correspond to the bearing fixing holes one by one, the upper and lower side surfaces of the second bearing rod are provided with at least two limiting holes, the number of the limiting holes is even, the diameter of the limiting holes is 2/3 of the side length of the bearing rod, the limiting holes are provided with a firming device and a second hanging bracket, the cross section of the fastening device is U-shaped, a screw rod is arranged at the lower end of the fastening device, and the second hanging bracket is a rectangular frame.
Strengthen the device and include second base, lead screw, third base, top pipe and lower pipe, be equipped with adjusting nut on the lead screw for adjust the distance of connecting between upper pipe and the lower pipe, the third base is simultaneously fixed in on the fixed orifices of the one end other end of lower pipe through the bolt fastening in bracing piece.
Preferably, the upper side face of the second hanging bracket is provided with at least two limiting connecting holes, the limiting connecting holes are connected to the limiting holes, and the lower side face of the second hanging bracket is provided with limiting holes for installing a fastening device.
Preferably, the number of the mounting holes of the base and the second base is at least two
Preferably, the support rod and the second hanger have the same side length.
Preferably, the outer diameter of the bearing rod is matched with the inner diameter of the opening side of the supporting rod.
Preferably, a buffer pad is arranged between the carrying rod and the pipeline.
The utility model discloses a technological effect and advantage: the support and hanger for the comprehensive pipeline is simple in structure and strong in flexibility, and can be installed according to different pipe diameters in field installation through the preset limiting holes;
strengthen the device and include second base, lead screw, third base, top pipe and below pipe through setting up, be equipped with adjusting nut on the lead screw for adjust the distance of connecting between the pipe of upper side and the below, adjust the length of strengthening the device according to the needs of field installation, increase the stability of gallows.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a side view of the present invention;
FIG. 3 is a structural view of a second carrier bar of the present invention;
fig. 4 is a structural diagram of the carrier bar of the present invention.
In the figure: 1-support rod, 2-base, 3-reinforcing device, 4-bearing rod, 5-fixing hole, 6-second bearing rod, 7-firm device, 8-second hanger, 31-second base, 32-screw rod, 33-third base, 34-upper tube, 35-lower tube, 61-limiting hole, 41-bearing fixing hole and 81-limiting connecting hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The utility model provides a support hanger for integrated pipeline as shown in the figure, which comprises a base 2, wherein a support rod 1 is fixed under the base 2, two support rods 1 are arranged and are fixedly connected with a second bearing rod 6 to form a structure, the support rod 1 is a cuboid with a hollow inner part and a T-shaped opening, two symmetrical fixing holes 5 are arranged on two symmetrical side faces, the fixing holes 5 are used for installing the bearing rods 4 and the reinforcing devices 3, the bearing rods 4 are hollow cuboids, bearing fixing holes 41 are respectively arranged on two side faces of the bearing rods 4, a buffer cushion is arranged between the bearing rods 4 and the pipeline, the bearing fixing holes 41 and the fixing holes 5 are in one-to-one correspondence, limiting holes 61 are arranged on the upper side face and the lower side face of the second bearing rod 6, the number of the limiting holes 61 is at least two, the limiting holes 61 are even numbers, the diameter of the limiting holes 61 is 2/3 of the side length 4 of the bearing rods, a firm device 7 and a second hanger, the cross section of the fixing device 7 is U-shaped, the lower end of the fixing device is provided with a screw rod, the second hanging bracket 8 is a cuboid frame, the side surface of the second hanging bracket 8 is provided with limiting connecting holes 81, the number of the limiting connecting holes 81 is at least two, the connecting holes are connected to the limiting holes 61, and the lower side surface of the second hanging bracket 8 is provided with the limiting holes 61 for installing the fixing device 7.
Reinforcing apparatus 3 includes second base 31, the lead screw 32, third base 33, upper pipe 34 and lower pipe 35, be equipped with adjusting nut on the lead screw 32, a connection distance for adjusting between upper pipe 34 and the lower pipe 35, third base 33 one side is fixed in lower pipe 35 one end, the another side passes through the bolt fastening on the fixed orifices 5 of bracing piece 1, the mounting hole of base 2 and second base 31 is two at least, the side length homogeneous phase of bracing piece 1 and second gallows 8, the external diameter of carrier bar 4 and the internal diameter phase-match of bracing piece 1 opening side.
The working principle is as follows: this comprehensive pipeline is with a gallows, be fixed in the wall body base 2 earlier, set up the position that carrier bar 4 selected fixed orifices 5 according to erectting the pipeline, according to the size of pipe diameter, select suitable firm device 7 size on the second carrier bar 6, and install in spacing hole 61, install second gallows 8 as required again, after the piping erection is accomplished, be fixed in the wall body second base 31 of reinforcing means 3 on, third base 33 is fixed in on the suitable fixed orifices 5 of bracing piece 1, accommodate the length of lead screw 32, it is fixed firm to make the gallows.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (6)

1. The utility model provides a synthesize a gallows for pipeline, includes base (2), its characterized in that: the supporting rods (1) are fixed below the base (2), the two supporting rods (1) are fixedly connected with a second bearing rod (6) to form a structure, the supporting rods (1) are hollow cuboids, one side of each supporting rod is opened in a T shape, symmetrical fixing holes (5) are formed in two symmetrical side faces, the fixing holes (5) are used for installing the bearing rods (4) and the reinforcing devices (3), the bearing rods (4) are hollow cuboids, bearing fixing holes (41) are respectively formed in two side faces of each bearing rod (4), the bearing fixing holes (41) correspond to the fixing holes (5) one by one, limiting holes (61) are formed in the upper side face and the lower side face of the second bearing rod (6), the number of the limiting holes (61) is at least two, the number of the limiting holes is even, the diameter of each side length of each limiting hole (61) is 2/3 of each bearing rod (4), and a firming device (7) and a second hanging bracket (8) are installed on each limiting hole (61), the cross section of the fastening device (7) is U-shaped, a screw rod is arranged at the lower end of the fastening device, and the second hanging bracket (8) is a cuboid frame; strengthen device (3) and include second base (31), lead screw (32), third base (33), top pipe (34) and lower pipe (35), be equipped with adjusting nut on lead screw (32) for adjust the distance of connection between upper pipe (34) and lower pipe (35), third base (33) one side is fixed in lower pipe (35) one end, and the another side passes through the bolt fastening on fixed orifices (5) of bracing piece (1).
2. The support and hanger assembly for integrated piping of claim 1, wherein: the side is equipped with spacing connecting hole (81) on second gallows (8), spacing connecting hole (81) quantity is two at least to connect in spacing hole (61), second gallows (8) downside is equipped with spacing hole (61) for install solid device (7).
3. The support and hanger assembly for integrated piping of claim 1, wherein: the number of the mounting holes of the base (2) and the second base (31) is at least two.
4. The support and hanger assembly for integrated piping of claim 1, wherein: the side lengths of the support rod (1) and the second hanging bracket (8) are the same.
5. The support and hanger assembly for integrated piping of claim 1, wherein: the outer diameter of the bearing rod (4) is matched with the inner diameter of the opening side of the support rod (1).
6. The support and hanger assembly for integrated piping of claim 1, wherein: and a buffer cushion is arranged between the bearing rod (4) and the pipeline.
CN201922231560.9U 2019-12-13 2019-12-13 Support hanger for comprehensive pipeline Active CN211951709U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922231560.9U CN211951709U (en) 2019-12-13 2019-12-13 Support hanger for comprehensive pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922231560.9U CN211951709U (en) 2019-12-13 2019-12-13 Support hanger for comprehensive pipeline

Publications (1)

Publication Number Publication Date
CN211951709U true CN211951709U (en) 2020-11-17

Family

ID=73175088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922231560.9U Active CN211951709U (en) 2019-12-13 2019-12-13 Support hanger for comprehensive pipeline

Country Status (1)

Country Link
CN (1) CN211951709U (en)

Similar Documents

Publication Publication Date Title
CN106764048B (en) The method that air hose installation is carried out using self-locking type wind pipe hanger
CN211951709U (en) Support hanger for comprehensive pipeline
CN208982781U (en) Air hose mounting bracket in truss
CN210374024U (en) Intelligent air conditioner easy to assemble
CN215484886U (en) Adjustable strutting arrangement for building
CN209876443U (en) Fan hanger
CN212775988U (en) Pipeline gallows installation device
CN210567278U (en) Windproof type monitoring mounting rack for expressway
CN208603629U (en) A kind of fixed device of basis installation of embedded parts
CN207245046U (en) A kind of guardrail
CN205583579U (en) Easily line cable frame of installation establishes crane span structure
CN217737521U (en) Adjustable mounting rack for mounting air conditioner
CN214626280U (en) Hanging bracket
CN219755716U (en) Bidirectional-support single-water-pipe-side longitudinal anti-seismic support and hanger
CN210372343U (en) Suspension type comprehensive support and hanger
CN212897607U (en) Tower type supporting truss
CN214999823U (en) Sliding support for steam blowing transverse pipe of unit
CN212507419U (en) Template stabilising arrangement for construction
CN214834668U (en) Ultra-long support device of all-steel climbing frame
CN209457278U (en) The suspension and support and spherical net rack structure roofing of spherical net rack structure roofing
CN213546551U (en) Pole is embraced to portal frame
CN216406186U (en) Adjustable supporting device for blocking template of pay-off hole
CN219755545U (en) Multi-water pipe combined lateral anti-seismic bracket
CN103343645B (en) A kind of vehicle-mounted removable communication tower
CN210195311U (en) Safety rope fixing support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: Room 2006 and 2008, science and technology center, Nanjing Olympic Sports Center, 222 Jiangdong Middle Road, Jianye District, Nanjing City, Jiangsu Province, 210000

Patentee after: Nanjing Lide Intelligent Technology Co.,Ltd.

Address before: Room 2006 and 2008, science and technology center, Nanjing Olympic Sports Center, 222 Jiangdong Middle Road, Jianye District, Nanjing City, Jiangsu Province, 210000

Patentee before: Nanjing Aomi Intelligent Technology Co.,Ltd.

CP01 Change in the name or title of a patent holder