CN211922592U - Multi-cabin ground is wall even and is connected construction and pack bag - Google Patents

Multi-cabin ground is wall even and is connected construction and pack bag Download PDF

Info

Publication number
CN211922592U
CN211922592U CN202020185110.0U CN202020185110U CN211922592U CN 211922592 U CN211922592 U CN 211922592U CN 202020185110 U CN202020185110 U CN 202020185110U CN 211922592 U CN211922592 U CN 211922592U
Authority
CN
China
Prior art keywords
bag
pressure
filling
outer bag
water inlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020185110.0U
Other languages
Chinese (zh)
Inventor
陈凯
翟世鸿
杨钊
赵焜
柴成荣
刘泽明
姜兆礼
鲍高强
吴宁
田良健
易再德
吴忠良
罗曼
吴鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Speed Anderson Rubber Products Co ltd
Original Assignee
Wuhan Speed Anderson Rubber Products Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Speed Anderson Rubber Products Co ltd filed Critical Wuhan Speed Anderson Rubber Products Co ltd
Priority to CN202020185110.0U priority Critical patent/CN211922592U/en
Application granted granted Critical
Publication of CN211922592U publication Critical patent/CN211922592U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model discloses a many cabins ground is wall joint construction and is filled bag even, fill the bag and include outer bag and locate the outer bag in the inflation bag, a plurality of inflation bags pass through communicating pipe series connection and install in outer bag, separate into a plurality of sealed cabins with outer bag internal partitioning, fill the bag top and install water inlet and outlet valve in water inlet department, pressure sensor is still installed at the top, the bottom is installed the blowoff valve in water outlet department. The filling bag only releases pressure in a single cabin even if a certain cabin is damaged, and because the two ends of the pressure release section are firmly clamped by the expansion bag, most of concrete can still be prevented from flowing around, and the filling effect of other cabins is not influenced; the expansion bag is small in size and strong in bearing capacity, original whole bag bearing pressure is changed into segmented bearing pressure after segmentation, and reliability is improved. The filling bag is used for construction filling of the construction joint space of the underground diaphragm wall, is widely used for replacing traditional processes of sand throwing bags, locking pipes, joint boxes and the like, and has the advantages of simple and rapid construction, low cost, cyclic use and the like.

Description

Multi-cabin ground is wall even and is connected construction and pack bag
Technical Field
The utility model relates to an underground continuous wall construction technical field, concretely relates to many cabins ground is wall joint construction and is filled bag even.
Background
With the acceleration of urbanization construction, urban land resources are scarce, and a large amount of building space needs to extend underground, particularly rail transit, large shopping malls, office buildings, parking lots and the like; the underground continuous wall is one of the most suitable construction schemes for underground space construction, and has the advantages of high construction speed, stable quality, good safety and reasonable cost; the construction of the underground continuous wall is generally carried out by constructing a groove with certain width and depth according to the design requirement through a double-wheel milling or grooving machine, and the width is generally 3-6 meters; reinforced concrete is poured to form an underground wall, the underground wall is formed by connecting the walls one by one, in order to prevent the water leakage of a joint between the walls, the joint of the underground continuous wall generally adopts a cross-shaped steel embedded part to form a concave-convex construction groove, the concave-convex groove is firstly filled with a sand bag, a guide pipe and a joint box during each construction, the filler is withdrawn after concrete is solidified to form a water-stop groove for the next wall, the most mature filling measure or sand bag is used, the bagging and throwing filling accumulation of one construction needs more than 10 persons for 1 day, a large amount of mechanical throwing matching wastes time and labor; there are also steel boxes, which lock the tubes but are limited in depth.
The inside and outside mechanisms and construction units research the underground continuous wall joint filling construction technology:
the authorization notice number is CN104278697B, the slurry bag for sealing and filling the space of the underground continuous wall head is vulcanized by rubber and fiber reinforced layers, the section of the slurry bag is trapezoidal slurry entering and exiting at the bottom, and the like; in actual use, design defects are completely exposed, the slurry bag is formed by vulcanizing rubber and a fiber reinforced layer, the underground continuous wall reinforcement cage is extruded to displace along with the increase of pressure due to elastic deformation after pressurization, the concrete flows around after the pressure of the bag body is small, and the concrete flows into a space to be filled; slurry is opened when entering and exiting the lower tank through a bottom valve and is closed when falling into the bottom, the operation is inconvenient in practical operation, the sealing is not tight, and a bag cannot be taken out after the concrete flows around, so that the reinforcement cage of the next wall cannot be installed according to the designed position due to the concrete flows around, a subsequent joint leaks water, huge cost treatment and project progress delay are taken afterwards, and serious hidden danger is left;
although the flexible liquid bag filled in the end space of the underground continuous wall with the application publication number of CN110424374A/CN110424375A adopts a multilayer structure, the design is that a vulcanized layer is added to a Kevlar liner, according to the specification, the Kevlar liner only has the functions of increasing strength, resisting abrasion and tearing, and the outer layer is still made of rubber and fiber, rubber cord fabric or rubber, fiber and cord fabric; in the actual use process, the friction and the pressure of the bag are mainly between the outer surface and the wall of the bag, the Kevlar is arranged in the bag and cannot achieve the expected strength, wear resistance and tear resistance effects, the supporting component is arranged in the bag, the operation difficulty is increased, and the stress state and the stress degree between the bag and the supporting component are difficult to master; the pouring speed provided in the scheme can not exceed 6 m/h, and the construction time of a wall with the depth of 40 m is increased by 2-4 times compared with the original wall; the alarm pressure is 2.6 kg, the general volume of the filling bag is 10-100 cubic, the actual instantaneous pressure reaches more than 4 kg, and the design and processing materials of the bag are required to be high.
The traditional rubber bag of the scheme is integrally vulcanized and formed after the cord or cord fabric is bonded and formed by frictioning, the bearing capacity is the friction force caused by mutual bonding of materials, the material is bonded more thickly when the pressure is higher, the operation is more inconvenient, and the construction effect is greatly influenced by elastic deformation.
The construction procedure of the underground continuous wall comprises the steps of firstly excavating a deep groove in the ground by using grooving equipment according to design, placing a reinforcement cage, and then pouring concrete, wherein the groove wall is rough and sharp on the surface after grooving is carried out under complicated geological conditions, holes are collapsed, the local size is uneven, and the like, and the strength, the rigidity and the flexibility during folding and unfolding are required during the construction of filling bags; the strength of the bag can withstand the impact pressure of the co-friction extrusion of the inner wall of the underground continuous wall and the reinforcement cage under the complex geological conditions and the pouring of concrete. As the slurry wall protection process is adopted, the slurry density is about 1.2, pressure difference exists when water is used in the bag, according to theoretical calculation and field actual experience, the pressure difference of 0.2 kilogram per 10 meters, 0.8 kilogram is needed for a 40-meter wall to keep internal and external balance pressure, the bag does not float upwards, and 1 kilogram of working pressure is added, so that the pressure in the 40-meter bag is added to 2 kilograms to be a safe initial working value, the field actual casting speed of the underground continuous wall concrete is generally 10-20 cubic meters per hour, the instantaneous pressure generated in the actual casting and pipe drawing process exceeds 4 kilograms, and the material has certain strength; the rigidity of the capsule requires very low elastic deformation of the capsule, and new requirements are put forward on materials and processing modes; the bag is required to have good flexibility when the filling space is required to be narrow, the bag is convenient to fold into a smaller size to enter and exit the space, the I-steel 630 multiplied by 250 at the end part of the reinforcement cage is taken as an example of an 800 underground continuous wall, the general size of the I-steel plus overexcavation space is only 630 multiplied by 500, adverse factors are not considered, and the bag cannot be placed when the size is too large;
firstly, it is determined that filling the joint space of the underground diaphragm wall by using a filling bag instead of other methods is a good scheme, but according to the requirements of the field, the diameter of the filling bag is between 0.6 and 1.5 meters, the length of an outer bag is between 20 and 120 meters, the volume of the outer bag is between 10 and 100 cubes, the working pressure is more than 4 kilograms, the strict requirements on the filling bag are provided, and the following problems need to be solved when the filling bag of the underground diaphragm wall joint is successfully used:
1) firstly, the quality of the filling bag is 100 percent reliable, the construction time is shortened compared with the original scheme, and the construction cost is comparable to the original cost;
2) the influence of various complex working conditions such as rough and sharp object on the surface of the wall of the groove, hole collapse, bottom sludge accumulation and the like on the safety and installation of the capsule due to the size and verticality deviation after the joint space of the underground continuous wall is grooved can be overcome;
3) the bladder has a sufficiently high pressure bearing capacity and a relatively long and stable service life;
4) the operation is simple and practical, and the installation and the removal are convenient and quick;
5) a complete safety detection scheme and construction process are required.
SUMMERY OF THE UTILITY MODEL
The utility model provides a many cabins ground is wall joint construction and is filled bag separates into a plurality of independent sealed cabins at the inside inflation bag of outer bag through establishing ties with the outer bag, and then improves the reliability.
In order to achieve the above object, the utility model adopts the following technical scheme:
the utility model provides a many cabins ground is wall joint construction and is filled bag even, includes outer bag and locates the inflation bag in the outer bag, and is a plurality of the inflation bag is installed in outer bag through communicating pipe series connection, with outer bag internal partitioning to become a plurality of sealed cabins, fill the bag top and install water inlet and outlet valve in water inlet department, pressure sensor is still installed at the top, and the blowoff valve is installed in water outlet department in the bottom.
Preferably, a feed-through pipe is arranged in the expansion bag, the feed-through pipe penetrates through two side walls of the expansion bag and is sealed with the expansion bag, an electromagnetic valve is mounted at the top of the feed-through pipe, and the initial pressure of the expansion bag is greater than 1.5 times of the working pressure of the outer bag.
Preferably, install detachable digital display screen and audible-visual annunciator on the filling bag, digital display screen and audible-visual annunciator and pressure sensor electric connection.
Preferably, the water inlet and outlet valve comprises an outer bag water inlet and outlet valve and an expansion bag water inlet and outlet valve which are respectively arranged at the top of the outer bag and the top of the expansion bag, and the blowoff valve comprises an outer bag blowoff valve and an expansion bag blowoff valve which are respectively arranged at the bottom of the outer bag and the bottom of the expansion bag.
Preferably, the outer bag comprises an inner container and a framework layer, the framework layer is sleeved outside the inner container, two ends of the framework layer are connected with the inner container through flange groups, a reinforcing layer and a shaping steel sand bag are respectively arranged at the top and the bottom between the inner container and the framework layer, and a wear-resistant coating is coated on the outer side of the framework layer.
Preferably, the inner container is provided with a hoisting screw, and the hoisting screw penetrates through the reinforcing layer and the framework layer and extends to the outside of the filling bag.
Preferably, the inner container is made of PVC coated cloth or TPU coated cloth; the framework layer is woven into an annular tube by adopting a braided tube or a braided belt in a criss-cross manner; the wear-resistant coating is made of polyurea.
Preferably, the flange group comprises a water inlet and outlet flange group arranged at the top of the outer bag and a sewage discharge flange group arranged at the bottom of the outer bag, the water inlet and outlet flange group is provided with an outer bag water inlet and outlet valve and an expansion bag water inlet and outlet valve, and the sewage discharge flange group is provided with an outer bag sewage discharge valve and an expansion bag sewage discharge valve.
Due to the structure, the beneficial effects of the utility model reside in that:
1. the multi-cabin diaphragm wall joint construction filling bag and the construction method are used for construction filling of underground diaphragm wall construction joint spaces, widely used for replacing traditional processes of sand throwing bags, locking pipes, joint boxes and the like, and have the advantages of simplicity and rapidness in construction, low cost, recycling and the like;
2. the filling bag is divided into a plurality of independent sealed cabins, so that only a single cabin is used for pressure relief even if a certain cabin is damaged, and as the two ends of the pressure relief section are firmly clamped by the expansion bag, most of concrete can still be prevented from flowing around, the filling effect of other cabins is not influenced, and the safety and reliability of the filling bag are further improved; the expansion bag has small volume and strong bearing capacity, changes the original whole bag bearing pressure into the segmental bearing pressure after segmenting, is similar to the working principle of rails and sleepers, is matched with the casting side pressure and impact force curve in the concrete casting process, reduces the requirement of the whole material and further improves the reliability;
3. the outer bag is multilayer structure, and the function is clear, and especially the skeleton layer uses current super large diameter to weave the pipe, wholly weaves existing intensity and closely knit degree, can effectively prevent the puncture again, and its self rated pressure can reach 4 kilograms, and burst pressure reaches 9 kilograms, provides factor of safety more than 2 times for the bag, and simultaneously, the removable scheme of inner bag can guarantee the safe handling and effective reduce cost of product.
Drawings
FIG. 1 is a schematic structural view of a multi-cabin underground continuous wall joint filling bag according to an embodiment of the present invention;
FIG. 2 is a schematic structural view of the present invention when a filling bag is used for the construction of the joint space of the underground diaphragm wall;
FIG. 3 is a schematic structural view of a second multi-cabin underground continuous wall joint filling bag according to an embodiment of the present invention;
FIG. 4 is a schematic top view of a multi-cabin underground continuous wall joint filling bag according to an embodiment of the present invention;
FIG. 5 is a schematic bottom structure view of a second multi-cabin underground continuous wall joint filling bag according to an embodiment of the present invention;
FIG. 6 is a structural layout diagram of the skeleton layer of the multi-cabin underground continuous wall joint filling bag according to the second embodiment of the present invention;
fig. 7 is a schematic cross-sectional view of the carcass layer of a second multi-cabin underground diaphragm wall joint filling capsule according to an embodiment of the present invention.
Detailed Description
The first embodiment is as follows:
as shown in figures 1 and 2, the embodiment provides a multi-cabin underground continuous wall joint filling bag, the diameter of the filling bag is 0.6-1.5 meters and the length of the filling bag is 20-120 meters according to actual needs on site, and most of the filling bag has the dimensions of 0.8 meter and 1 meter, and the length of the filling bag is 30-60 meters.
The filling bag includes outer bag 1 and locates the inflation bag 2 in outer bag 1, and is a plurality of inflation bag 2 installs in outer bag 1 through communicating pipe 3 series connection, with 1 internal partitioning of outer bag a plurality of sealed cabins 11, filling bag top is installed into water inlet and outlet valve in water inlet department, and pressure sensor 4 is still installed (can be dismantled) at the top, and the blowoff valve is installed in water outlet department in the bottom.
In the present embodiment, the outer bag 1 is a single-layer bag. The expansion bag 2 in the outer bag 1 is installed in series through the communicating pipe 3 at a certain interval, and the outer bag 1 is divided into a plurality of sealed cabins 11, so that when one cabin 11 goes wrong, other cabins are not affected, and the work can be continued.
The inflation bag 2 is internally provided with a feed-through pipe 21, the feed-through pipe 21 penetrates through two side walls of the inflation bag 2 and is sealed with the inflation bag 2, the top of the feed-through pipe 21 is provided with an electromagnetic valve 22, the valve is in a normally closed state when the electromagnetic valve 22 works, and the initial pressure of the inflation bag 2 is 1.5 times greater than the working pressure of the outer bag 1.
Install detachable digital display screen and audible-visual annunciator 5 on the filling bag, digital display screen and audible-visual annunciator 5 and pressure sensor 4 electric connection. The digital display screen and the audible and visual alarm 5 can be arranged on the bag, can also be arranged integrally with the water pump, and can be connected with a main controller 10 of the control system or can be arranged independently.
The water inlet and outlet valve comprises an outer bag water inlet and outlet valve 51 and an expansion bag water inlet and outlet valve 52 which are respectively arranged at the top of the outer bag 1 and the top of the expansion bag 2, and the blow-down valve comprises an outer bag blow-down valve 53 and an expansion bag blow-down valve 54 which are respectively arranged at the bottom of the outer bag 1 and the bottom of the expansion bag 2. Residual sewage in the outer bag 1 of the filling bag is discharged through an outer bag water discharge valve 51, residual sewage in the expansion bag 2 is discharged through an expansion bag water discharge valve 52, the two valves both use electromagnetic valves, and plugs can be used for replacing the electromagnetic valves to plug under special conditions.
The construction method for filling the space of the diaphragm wall joint by applying the filling bag of the embodiment comprises the following steps:
s1, filling bag pressure loading: after technical bottom crossing and construction preparation are well made, a filling bag is hung in a hole to be constructed in a joint space of an underground continuous wall and is subjected to pressure loading, water inlet and outlet valves (an outer bag water inlet and outlet valve 51 and an expansion bag water inlet and outlet valve 52) at the top of the bag are connected with a water pump 6, the water pump 6 is connected with an external water source (a water storage bag 7), the water pump 6 is used for respectively injecting water into an outer bag 1 and an expansion bag 2, the water sequentially enters each expansion bag 2 through a communicating pipe 3, a flow meter 8 is installed on an outlet pipeline of the water pump 6, and the flow meter 8 is connected with a main controller 10 of an external control system and is used for carrying out capacity and pressure;
s2, pressure monitoring of the filling bag: the pressure sensor 4, the digital display screen and the acousto-optic alarm 5 are respectively connected with the main controller 10 and the remote monitoring terminal 13, the pressure sensor 4 collects the pressure of the outer bag 1 and the pressure of the expansion bag 2 in real time and transmits the pressure to the main controller 10 and/or the remote monitoring terminal 13, pressure state parameters of the filled bag are displayed and recorded, and when the pressure of the filled bag reaches a preset value, the main controller 10 and/or the remote monitoring terminal 13 controls the digital display screen and the acousto-optic alarm 5 to give an acousto-optic alarm;
s3, filling bag pressure unloading: after the concrete of the underground diaphragm wall is poured for 4-8 hours, and after the concrete is initially set by probe detection, firstly, the expansion bag 2 is decompressed, the expansion bag 2 is discharged for 5-10 minutes, then the outer bag 1 is discharged, water in the filling bag is naturally discharged under the internal and external pressure difference, mud is supplemented to the space outside the bag, the water yield is detected by using a flowmeter 8 during water discharge, the bag is hoisted to a hole, residual sewage is discharged through a drain valve (an outer bag drain valve 53 and an expansion bag drain valve 54), when the residual water is within 0.5 ton, the bag can be lifted by using a crane, and the surface of the bag is slowly flushed by water for packaging.
Wherein, the technical background content in step S1 includes:
(1) key control objective
1) Detecting the groove depth and the groove width of the underground continuous wall joint by using a hole detector, and detecting the verticality and hole collapse condition by using ultrasonic waves;
2) the water inlet and outlet capacity of the filling bag is monitored, so that shortage and excess are prevented;
3) the prepressurization pressure of the expansion capsule is 3 kilograms;
the pre-pressure value of the outer bag of the filling bag is 2 kilograms;
the pre-pressure value of the outer bag is 2-3 kg, and concrete is strictly forbidden to be poured before the pre-pressure value is not reached;
the early warning pressure value of the outer bag is 3-4 kilograms, and when the early warning pressure value is reached, the discharging speed is slowed down;
when the alarm pressure value of the outer bag is more than 4 kilograms and the alarm pressure value is reached, the concrete pouring is immediately stopped, and when the pressure value is reduced to about 3 kilograms, the concrete pouring or the concrete intermittent pouring is started;
(2) controlling the concrete pouring speed to be 10-20 m/h;
(3) after the concrete pouring is finished for 4-8 hours, the pressure can be released after the initial setting of the concrete is determined by probe detection.
The construction preparation work in step S1 specifically includes:
(1) equipment bill of materials: the underground continuous wall joint filling bag is used for loading monitoring equipment, spare tool parts and filling material backup in a complete set;
(2) checking the state of the equipment:
1) when the capsule is continuously used, only the appearance inspection of the filling capsule is needed; when the device is not used for a long time, firstly, safety detection, internal and external pressure detection and internal pressure detection are carried out, and after the internal pressure is loaded to 2 kilograms and static pressure for 2 hours, the pressure is not less than 1.8 kilograms (the pressure drop is not more than 10 percent), the device is qualified; carrying out external pressure detection in a local external pressure mode until the pressure is not less than 3.6 kg (the pressure drop is not less than 10%) after the pressure is 4 kg and static pressure is carried out for 2 hours, thus the product is qualified;
2) the complete set of loading monitoring equipment 12 and the safety control suite are subjected to an electrified operation test;
3) the quick water receiving pipe group 14 and the matching connecting pieces need to be subjected to pressure maintaining tests, and the quantity and the appearance are checked;
4) the water and electricity connection position and safety inspection are carried out to ensure that the water source supply capacity is 20-40 cubic meters per hour and the power supply capacity is more than 10 kilowatts;
5) a reserve of alternative fill material is made to ensure that there is ready material when the fill bag is not in use.
(3) And (3) pore-forming detection:
1) carrying out hole collapse and verticality scanning on the joint space by using ultrasonic hole probing to know the actual situation in the hole;
2) detecting by using a hole detector, ensuring that no sharp object damages the capsule and the capsule is smoothly put down, and ensuring that the perimeter of a rectangular space is less than or equal to 5-50 cm of the perimeter of the filled capsule;
3) carrying out depth detection by using a plumb bob to ensure that a sand bag 9 with the height of 0.5-5 m is filled at the bottom of the joint;
4) detecting the specific gravity by using a mud hydrometer to ensure that the density of the mud is about 1.2 of the design specification;
(4) filling bladder installation
1) The bottom of the bag is filled with a sand bag 9 with the height of 0.5-5 m.
2) Hoisting the filling bag into a hole to be constructed of the underground continuous wall;
3) the height between the top of the bag and the ground is ensured to be within +0.5 m and-1 m, the liquid level at the top of the bag is ensured to leak, the part of the top which exceeds the top is required to be lifted by using a special frame, and the bag is ensured to be in a natural vertical state.
(5) Pipe connection
(1) Communicating pipelines among a water source (a water storage bag), the complete set of loading monitoring equipment 12 and the filling bag;
(2) and (5) experimentally pressurizing to check the smoothness and the tightness of the pipeline.
(6) Monitoring connections
1) Checking whether a power supply of the pressure acquisition and transmission system is normal;
2) and (5) experimentally pressurizing to check the smoothness and the tightness of the pipeline.
(7) Bladder fill volume and pressure settings
Calculating and detecting basis of the volume in the capsule:
1) calculating the volume according to the overall dimension of the capsule, and taking the volume as a loading basis to prevent shortage and excess;
2) the inlet and outlet flow meter is arranged on the pipeline of the quick water receiving pipe set 14 of the bag, and the inlet and outlet flow rate is counted by using the flow meter to detect the state.
The safe pressure basis of the filling bag is the pressure difference between the inside and the outside of the bag, the working pressure, the concrete pouring side pressure and the safe storage pressure
1) Pressure difference between the inside and the outside of the capsule: the specific gravity of the slurry outside the bag is about 1.2, and the water inside the bag is 1, so that the internal and external pressure difference can be increased along with the increase of the depth;
2) working pressure: in order to keep the bag to have certain rigidity, certain pressure is required, and a large number of experiments prove that 1-1.5 kilograms of pressure is most suitable;
3) concrete pouring side pressure: the generated lateral pressure and the force generated by pulling and inserting the concrete pouring guide pipe;
4) safe reserve pressure: reserving 1 time of safety factor;
5) a pressure sensor 4 is mounted on top of the filled bladder for real time sensing of the pressure within the bladder.
The bag filling and watering process in step S1 includes:
(1) firstly, pressurizing the expansion bag 2 to 3 kilograms of pressure;
(2) then the outer bag 1 is pressurized to 2 kilograms of pressure;
(3) the outer bag 1 is pressurized to 2 kilograms and then statically loaded for 15 minutes before concrete can be poured.
The remote monitoring terminal 13 in the step S2 includes a mobile phone, a tablet computer, and software on a computer, the pressure acquired by the field pressure sensor 4 is monitored, the flow signal is transmitted to the remote monitoring terminal 13 through conversion and an RTU, the remote monitoring terminal 13 monitors and records, the monitoring value is set to be consistent with the field, and when the early warning and alarm value is reached, the personnel with the related operation and management authority is notified through a phone call, a short message, a WeChat, and the like, and the data cannot be tampered and permanently retained.
The sound-light alarm in step S2 specifically includes:
the field digital display screen and the remote monitoring terminal 13 synchronously display the real-time pressure values of the outer bag 1 and the expansion bag 2, and the audible and visual alarm 5 acts according to the set pressure value;
the pre-pressure value of the expansion bag 2 is 3 kg;
the pre-pressure value of the outer bag 1 of the filling bag is 2 kg;
when the pressure value of the outer bag of the filling bag is 2-3 kg, the indicator light is green, and normal pouring can be carried out;
when the pressure value of the outer bag of the filling bag reaches 3-4 kilograms, the indicating lamp is displayed to be yellow, and meanwhile, an alarm sound is sounded to remind that the concrete pouring speed is slowed down;
when the pressure value of the outer bag of the filling bag is more than 4 kilograms, the indicating lamp displays red, simultaneously sounds an alarm, immediately stops pouring concrete, and starts pouring concrete or intermittently pours concrete when the pressure value drops to 3 kilograms.
The multi-cabin diaphragm wall joint construction filling bag and the multi-cabin diaphragm wall joint construction method are used for construction filling of the diaphragm wall construction joint space, are widely used for replacing traditional processes of sand throwing bags, locking pipes, joint boxes and the like, and have the advantages of simplicity and rapidness in construction, low cost, recycling and the like;
the filling bag is divided into a plurality of independent sealed cabins, so that only a single cabin is used for pressure relief even if a certain cabin is damaged, and as the two ends of the pressure relief section are firmly clamped by the expansion bag, most of concrete can still be prevented from flowing around, the filling effect of other cabins is not influenced, and the safety and reliability of the filling bag are further improved; the expansion bag has small volume and strong bearing capacity, changes the original whole bag bearing pressure into the segmental bearing pressure after segmentation, is similar to the working principle of rails and sleepers in shape, is consistent with the casting side pressure and impact force curve in the concrete casting process, reduces the requirement of the whole material and further improves the reliability.
Example two:
basically the same as the first embodiment, except that:
as shown in fig. 3 to 7, the outer bag 1 includes an inner container 101 and a framework layer 102, the framework layer 102 is sleeved outside the inner container 101, two ends of the framework layer 102 are connected with the inner container 101 through flange sets, a reinforcing layer 103 and a shaped steel sandbag 104 are respectively installed at the top and the bottom between the inner container 101 and the framework layer 102, and an abrasion-resistant coating 105 is coated on the outer side of the framework layer 102.
The shaped steel sand bag 104 is positioned between the liner 101 and the framework layer 102 and is uniformly annularly arranged along the inner wall of the framework layer 102, the shaped steel sand bag 104 is formed by quilting two pieces of high-strength cloth into a continuous cylindrical pocket with the diameter of 2-6 cm, iron sand is arranged in the pocket, and the pocket is 1.5-3 m long; because the bag is softer and the buoyancy of the bottom of the groove is large, the bottom of the shaped steel grit bag 104 keeps certain shape, rigidity and weight when being used for placing the bag downwards, the bag is favorably placed downwards smoothly, and the bottom weight and the buoyancy keep the bag in a natural vertical state in the groove.
The inner container 101 is provided with a hoisting screw 108, the hoisting screw 108 penetrates through the reinforcing layer 103 and the framework layer 102 and extends to the outside of the filling capsule, and the hoisting screw 108 is provided with a gasket 109.
The inner container 101 is made of PVC coated cloth or TPU coated cloth; the framework layer 102 is made of braided tubes (as shown in fig. 3) or is made of braided belts into annular tubes in a criss-cross manner (as shown in fig. 6 and 7, the framework layer 102 is processed into an annular outer layer by a radial braided belt 1022 and then spirally wound with a weft braided belt 1021, and the weft braided belt 1021 can be installed in a layer inside and outside the radial braided belt 1022); the wear-resistant coating 105 is made of polyurea.
The flange group comprises a water inlet and outlet flange group 106 arranged at the top of the outer bag 1 and a sewage discharge flange group 107 arranged at the bottom, an outer bag water inlet and outlet valve 51 and an expansion bag water inlet and outlet valve 52 are installed on the water inlet and outlet flange group 106, an outer bag sewage discharge valve 53 and an expansion bag sewage discharge valve 54 are installed on the sewage discharge flange group 107, a power line of the valves is installed on the inner wall of the framework layer 102 in advance, and an aviation plug is led out from the top of the filling bag to connect a control power supply (safety inspection before construction finds that the power supply has problems, and the electromagnetic valve can be detached and plugged by.
The water inlet and outlet flange group 106 and the sewage discharge flange group 107 are both composed of four flanges (111, 112, 113 and 114), the diameter of the water inlet and outlet flange group 106 is between 300 and 500 mm, and the diameter of the sewage discharge flange group 107 is between 150 and 200 mm. The end parts of the liner 101 and the framework layer 102 are coaxially and laminated and mounted, and are fixedly connected through a water inlet and outlet flange group 106 and bolts (115, 116 and 117), the flanges 111 and 112 clamp the liner 101 oppositely, the bolts (115 and 117) fix the liner 101, the flanges (112, 113 and 114) clamp the end part of the framework layer 102 and the end part of the reinforcement layer 103 oppositely, and the bolts (116 and 117) fix the framework layer 102 and the reinforcement layer 103.
The filling bag of this embodiment, outer bag are multilayer structure, and the function is distinct, and especially the skeleton layer uses current super large diameter to weave the pipe, wholly weaves existing intensity and closely knit degree, can effectively prevent the puncture again, and its self rated pressure can reach 4 kilograms, and burst pressure reaches 9 kilograms, provides factor of safety more than 2 times for the bag, and simultaneously, the removable scheme of inner bag can guarantee the safe handling and the effective reduce cost of product.
The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention, and various modifications and changes will occur to those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (8)

1. The utility model provides a capsule is filled in construction of many cabins ground wall joint which characterized in that: including outer bag and the inflation bag of locating in the outer bag, it is a plurality of the inflation bag passes through communicating pipe series connection and installs in the outer bag, separates into a plurality of sealed cabins with outer bag internal partitioning, fill the bag top and install water inlet and outlet valve in water inlet department, pressure sensor is still installed at the top, and the blowoff valve is installed in water outlet department in the bottom.
2. The multi-cabin diaphragm wall joint construction filling bag of claim 1, wherein: the expansion bag is internally provided with a feed-through pipe, the feed-through pipe penetrates through two side walls of the expansion bag and is sealed with the expansion bag, the top of the feed-through pipe is provided with an electromagnetic valve, and the initial pressure of the expansion bag is 1.5 times greater than the working pressure of the outer bag.
3. The multi-cabin diaphragm wall joint construction filling bag of claim 1, wherein: install detachable digital display screen and audible-visual annunciator on the filling bag, digital display screen and audible-visual annunciator and pressure sensor electric connection.
4. The multi-cabin diaphragm wall joint construction filling bag of claim 1, wherein: the water inlet and outlet valve comprises an outer bag water inlet and outlet valve and an expansion bag water inlet and outlet valve which are respectively arranged at the top of the outer bag and the top of the expansion bag, and the blowoff valve comprises an outer bag blowoff valve and an expansion bag blowoff valve which are respectively arranged at the bottom of the outer bag and the bottom of the expansion bag.
5. The multi-cabin diaphragm wall joint construction infill bag of claim 4, wherein: the outer bag comprises an inner container and a framework layer, the framework layer is sleeved outside the inner container, two ends of the framework layer are connected with the inner container through flange groups, a reinforcing layer and a shaping steel sandbag are respectively installed at the top and the bottom between the inner container and the framework layer, and a wear-resistant coating is coated on the outer side of the framework layer.
6. The multi-cabin diaphragm wall joint construction filling bag of claim 5, wherein: and the hoisting screws are arranged on the inner container, penetrate through the reinforcing layer and the framework layer and extend to the outside of the filling bag.
7. The multi-cabin diaphragm wall joint construction filling bag of claim 5, wherein: the inner container is processed by adopting PVC coated cloth or TPU coated cloth; the framework layer is woven into an annular tube by adopting a braided tube or a braided belt in a criss-cross manner; the wear-resistant coating is made of polyurea.
8. The multi-cabin diaphragm wall joint construction filling bag of claim 5, wherein: the flange group comprises a water inlet and outlet flange group arranged at the top of the outer bag and a sewage discharge flange group arranged at the bottom of the outer bag, an outer bag water inlet and outlet valve and an expansion bag water inlet and outlet valve are mounted on the water inlet and outlet flange group, and an outer bag sewage discharge valve and an expansion bag sewage discharge valve are mounted on the sewage discharge flange group.
CN202020185110.0U 2020-02-19 2020-02-19 Multi-cabin ground is wall even and is connected construction and pack bag Active CN211922592U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020185110.0U CN211922592U (en) 2020-02-19 2020-02-19 Multi-cabin ground is wall even and is connected construction and pack bag

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020185110.0U CN211922592U (en) 2020-02-19 2020-02-19 Multi-cabin ground is wall even and is connected construction and pack bag

Publications (1)

Publication Number Publication Date
CN211922592U true CN211922592U (en) 2020-11-13

Family

ID=73350173

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020185110.0U Active CN211922592U (en) 2020-02-19 2020-02-19 Multi-cabin ground is wall even and is connected construction and pack bag

Country Status (1)

Country Link
CN (1) CN211922592U (en)

Similar Documents

Publication Publication Date Title
CN111155511A (en) Multi-cabin diaphragm wall joint construction filling bag and construction method
CN104763436B (en) A kind of push-bench method of reseptance under high hydraulic pressure complex geological condition and device
CN101013073B (en) Method and device for testing hydraulic pressure of cast-in-place reinforced concrete water delivery pipe
CN109630803B (en) Pipeline repairing device, system and method
CN108548763A (en) Slip casting reinforcing body stability threedimensional model pilot system and method under erosion and seepage effect
CN110926727B (en) Water closing test method for plastic drainage pipeline in rural domestic sewage collection project
CN112482395A (en) Construction method of cast-in-situ bored pile and inner support supporting structure of rail transit station
CN114135249A (en) Reusable and automatic pressure supplementing gas extraction drilling and sealing system and working method thereof
CN211922592U (en) Multi-cabin ground is wall even and is connected construction and pack bag
CN114458856A (en) Device and method for repairing water-carrying structure of in-service pipeline
CN115233741A (en) Temporary filling construction method for diaphragm wall joint
CN114108656A (en) Construction method of foundation pit support
CN113803089A (en) Artificial surrounding rock construction process for treating collapsed cavity of tunnel
CN107764232A (en) A kind of measuring system and its construction, measuring method for wearing river shield tunnel riverbed vertical deformation
CN209760241U (en) Electric grouting system
CN117626947A (en) Construction method of rotary drilling bored concrete pile
CN113187493A (en) Control method for preventing negative ring duct piece from floating upwards in steel sleeve of shield tunneling machine
CN116357391A (en) Air bag type hard rock stratum compressed air energy storage chamber structure
CN116695715A (en) Inflatable fore shaft pipe and construction method thereof applied to underground diaphragm wall
CN206608211U (en) A kind of temporary blocking device speedily carried out rescue work for shield tunnel water leak accident
CN103512808A (en) Hydraulic pressure resistance property detection platform for mine waterproof type escape capsule
CN209839469U (en) Pocket-shaped water plugging device for drainage pipeline
CN210194598U (en) Foundation support engineering ground is wall construction joint case device even
CN113981958A (en) Method for plugging karst cave of mechanical pore-forming cast-in-place pile
CN217870633U (en) Temporary filling bag system for I-steel joint of diaphragm wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant