CN115233741A - Temporary filling construction method for diaphragm wall joint - Google Patents

Temporary filling construction method for diaphragm wall joint Download PDF

Info

Publication number
CN115233741A
CN115233741A CN202211007855.8A CN202211007855A CN115233741A CN 115233741 A CN115233741 A CN 115233741A CN 202211007855 A CN202211007855 A CN 202211007855A CN 115233741 A CN115233741 A CN 115233741A
Authority
CN
China
Prior art keywords
bag
filling
pressure
filling bag
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211007855.8A
Other languages
Chinese (zh)
Inventor
彭威
段昌恒
李常钦
郭克诚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Qiancheng Pile Work Technology Co ltd
Original Assignee
Wuhan Qiancheng Pile Work Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Qiancheng Pile Work Technology Co ltd filed Critical Wuhan Qiancheng Pile Work Technology Co ltd
Priority to CN202211007855.8A priority Critical patent/CN115233741A/en
Publication of CN115233741A publication Critical patent/CN115233741A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/08Sinking workpieces into water or soil inasmuch as not provided for elsewhere
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/20Restraining of underground water by damming or interrupting the passage of underground water by displacing the water, e.g. by compressed air
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Soil Sciences (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

The invention discloses a temporary filling construction method for a diaphragm wall joint, which comprises the following steps: a. and (3) pore-forming detection: b. and (3) filling bag installation: arranging square timbers at two sides of a guide wall in the tank body, placing the filling bag into the tank body, ensuring that the height difference between the top of the filling bag and the ground is within plus 1 meter and minus 0.5 meter, simultaneously ensuring that the filling bag is exposed out of the liquid level, and when the top of the filling bag exceeds 1 meter, using a special frame for hoisting, and ensuring that the filling bag is in a natural vertical state; c. connecting pipelines: communicating the water source, the complete set of loading monitoring equipment and the filling bag through pipelines; d. fill bladder loading and monitoring. The invention has the advantages of simple structure, high strength, strong operability and good filling effect.

Description

Temporary filling construction method for diaphragm wall joint
Technical Field
The invention relates to the field of diaphragm wall construction. More particularly, the invention relates to a temporary filling construction method for a diaphragm wall joint.
Background
Along with the scarcity of land resources in rapid development of urban construction, ground buildings need to be continuously extended towards the underground, the underground diaphragm wall is one of the preferred processes of the underground construction, the treatment of joint gaps in the construction of the underground diaphragm wall is an important link and quality control difficulty, and the temporary filling of wall joints and the sealing and water prevention after the construction are one of key control targets in the construction process.
The temporary filling of the traditional diaphragm wall construction joint adopts a throwing and filling sand bag or a steel joint box; the sand bag is simple and quick to throw and fill, but the sand and soil and the manpower are large in demand, long in time consumption and high in cost; the steel joint box is good in filling effect, but is complex to operate, and the filling depth is limited.
Disclosure of Invention
The invention aims to provide a temporary filling construction method for a diaphragm wall joint, which has the advantages of simple structure, high strength, strong operability and good filling effect.
The technical scheme adopted by the invention for solving the technical problem is as follows: a temporary filling construction method for a diaphragm wall joint comprises the following steps:
a. and (3) pore-forming detection:
b. filling bag installation: arranging square timbers at two sides of a guide wall in the tank body, placing the filling bag into the tank body, ensuring that the height difference between the top of the filling bag and the ground is within plus 1 meter and minus 0.5 meter, simultaneously ensuring that the filling bag is exposed out of the liquid level, and when the top of the filling bag exceeds 1 meter, using a special frame to lift the filling bag, and ensuring that the filling bag is in a natural vertical state;
c. connecting pipelines: communicating the water source, the complete set of loading monitoring equipment and the filling bag through pipelines;
d. filling capsule loading and monitoring:
d1. adding the filling bag to rated capacity water and rated working pressure, then statically loading for 5-15 minutes, wherein the pressure drop is 150-200Kpa, and pouring concrete can be carried out after the pressure does not drop linearly;
d2. during the concrete pouring process: when the pressure in the filling bag reaches the early warning pressure, slowing down the discharging speed;
when the pressure in the filling bag reaches the high-pressure alarm pressure, the concrete pouring is immediately stopped, and when the pressure value returns to the rated working pressure, the concrete pouring or the concrete intermittent pouring is started.
Preferably, step a includes:
a1. performing hole collapse and perpendicularity scanning on the joint space of the tank body by using an ultrasonic probe hole, ensuring that the perpendicularity in the left and right directions is 5 per thousand, and smoothly putting the filling bag to the bottom;
a2. the hole detector is used for passing detection, so that no sharp object damages the filling bag and the filling bag is smoothly put down, and the super-excavation is carried out for 0.6-0.8 m;
a3. carrying out depth detection by using a plumb bob to ensure that a sand bag of 0.5-5 m is filled at the bottom of the joint;
a4. and detecting the specific gravity of the slurry in the tank to ensure that the specific gravity of the slurry is within 1.2.
Preferably, when the thickness between the guide walls in the tank body is 0.6-1.5 m, the diameter of the filling bag is 0.6-1.5 m.
Preferably, the filling bag consists of an inner layer, a middle layer and an outer layer, the inner layer is a liquid rubber coating, the middle layer is a polyester and aramid fiber mixed layer, the outer layer is a wear-resistant rubber coating, and the total thickness of the filling bag is 1.8-3cm.
Preferably, the set of loading monitoring equipment comprises loading equipment, data acquisition equipment and monitoring equipment;
the loading equipment comprises a water storage bag, a water pump, an electromagnetic valve and a quick water connection pipe; the water storage bag is connected with the filling bag through a quick water connection pipe, and a water pump and an electromagnetic valve are installed on the quick water connection pipe;
the data acquisition equipment comprises a pressure sensor and a flowmeter, the flowmeter is arranged on the quick water pipe, and the pressure sensor is arranged at the top in the filling bag;
the monitoring equipment comprises a microcomputer processor and an acousto-optic alarm group; and the audible and visual alarm, the flowmeter and the pressure sensor are all connected with the microcomputer processor.
Preferably, the method further comprises a step e of unloading the program:
after concrete is poured for 4-8 hours and is initially set after inspection, the concrete can be connected with drainage equipment to open a valve for drainage, and continuous drainage is needed once during drainage;
and (3) discharging by using a water meter during drainage, when the residual amount of water in the filling bag is not more than 500 kilograms and can not be drawn out, lifting the bag by using a crane, wherein the bag must be lifted within 2 hours after the pressure of the bag is released to prevent the bag from collapsing and burying, the surface of the bag is slowly washed by using water, the appearance is checked to be damaged or not, and the bag is folded and packaged on the spot after being lifted out.
Preferably, in the step d 2:
when the pressure in the filling bag reaches the low-pressure early warning value range, observing whether the pressure in the bag is linearly reduced within a set time, and starting the standby bag if the pressure in the bag is linearly reduced;
when the pressure in the filling bag reaches a low-pressure alarm value, the standby bag is started.
The invention at least comprises the following beneficial effects: the temporary filling construction method for the underground diaphragm wall joint has the advantages of simple structure, high strength, strong operability and good filling effect. The construction is carried out by adopting the filling bag, the pressure and the capacity are controllable, the construction efficiency is high, and local materials can be used.
Additional advantages, objects, and features of the invention will be set forth in part in the description which follows and in part will become apparent to those having ordinary skill in the art upon examination of the following or may be learned from practice of the invention.
Drawings
FIG. 1 is a schematic view of a fill bladder installation of the present invention;
FIG. 2 is a plan view of the fill bag of the present invention installed flat on the ground;
FIG. 3 is a diagram showing the effect of grooving process using the present invention.
Description of reference numerals: 1 guide wall, 2 square timber, 3 filling bags and 4 lifting ropes.
Detailed Description
The present invention will now be described more fully hereinafter with reference to the accompanying drawings. Those skilled in the art will be able to implement the invention based on these teachings. Before describing the present invention in detail with reference to the accompanying drawings, it is to be noted that: the technical solutions and features provided in the present invention in the respective sections including the following description may be combined with each other without conflict.
Moreover, the embodiments of the present invention described in the following description are generally only some embodiments of the present invention, and not all embodiments. Therefore, all other embodiments obtained by a person of ordinary skill in the art based on the embodiments of the present invention without any creative effort shall fall within the protection scope of the present invention.
The invention is further described in detail with reference to the accompanying drawings and implementation, and the specific implementation process is as follows:
as shown in fig. 1 to 3, the invention provides a temporary filling construction method for a diaphragm wall joint, which comprises the following steps:
a. and (3) pore-forming detection:
b. the filling bag 3 is installed: the square timbers 2 are arranged on two sides of the guide wall 1 in the groove body, the square timbers 2 are connected through the lifting ropes 4, the filling bag 3 is placed in the groove body, the height difference between the top of the filling bag 3 and the ground is ensured to be within plus 1 meter and minus 0.5 meter, meanwhile, the liquid level of the filling bag 3 is ensured to be exposed, when the top of the filling bag 3 exceeds 1 meter, a special frame is required to be used for lifting, and the filling bag 3 is ensured to be in a natural vertical state;
c. connecting pipelines: communicating pipelines among a water source, the complete set of loading monitoring equipment and the filling bag 3;
d. filling capsule 3 loading and monitoring:
d1. adding the filling bag 3 to rated capacity water and rated 200Kpa working pressure, then statically loading for 5-15 minutes, and pouring concrete after the pressure drop is 150-200Kpa and the pressure does not drop linearly;
d2. during the concrete pouring process: when the pressure in the filling bag 3 reaches the early warning pressure of 250Kpa, slowing down the discharging speed;
when the pressure in the filling bag 3 reaches the high-pressure alarm pressure of 300Kpa, the concrete pouring is immediately stopped, and when the pressure value returns to the rated working pressure of about 200Kpa, the concrete pouring or the concrete intermittent pouring is started.
Step a comprises the following steps:
a1. performing hole collapse and perpendicularity scanning on the joint space of the tank body by using an ultrasonic probe hole, ensuring that the perpendicularity in the left and right directions is 5 thousandths, and smoothly putting the filling bag 3 to the bottom;
a2. the hole detector is used for passing detection, so that no sharp object damages the filling bag 3 and the filling bag 3 is smoothly put down, and the super-excavation is carried out for 0.6-0.8 m;
a3. carrying out depth detection by using a plumb bob to ensure that a sand bag of 0.5-5 m is filled at the bottom of the joint;
a4. and detecting the specific gravity of the slurry in the tank to ensure that the specific gravity of the slurry is within 1.2.
The technical scheme can also comprise the following technical details so as to better realize the technical effects: when the thickness between the guide walls 1 in the tank body is 0.6-1.5 m, the diameter of the filling bag 3 is 0.6-1.5 m.
Figure BDA0003809634250000041
The technical scheme can also comprise the following technical details so as to better realize the technical effects: the filling bag 3 is composed of an inner layer, a middle layer and an outer layer, the inner layer is a liquid rubber coating and serves as a sealing inner container, the middle layer is a polyester and aramid fiber mixed layer and serves as a stress framework layer, the outer layer is a wear-resistant rubber coating, the total thickness of the filling bag 3 is 1.8-3cm, and the sealing inner container can be regularly checked and replaced to ensure safety.
The technical scheme can also comprise the following technical details so as to better realize the technical effects: the set of loading monitoring equipment comprises loading equipment, data acquisition equipment and monitoring equipment;
the loading equipment comprises a water storage bag, a water pump, an electromagnetic valve and a quick water connection pipe; the water storage bag is connected with the filling bag 3 through a quick water connection pipe, and a water pump and an electromagnetic valve are installed on the quick water connection pipe;
the data acquisition equipment comprises a pressure sensor and a flowmeter, the flowmeter is arranged on the quick water pipe, and the pressure sensor is arranged at the top in the filling bag 3 and used for detecting the pressure in the bag in real time and the working state of the bag;
the monitoring equipment comprises a remote terminal, a microcomputer processor and an acousto-optic alarm group; and the audible and visual alarm, the flowmeter and the pressure sensor are all connected with the microcomputer processor.
In the scheme, real-time monitoring pressure signals acquired by the sensor are transmitted to the microcomputer processor, the normal working pressure is 150-250Kpa, a yellow light of the audible and visual alarm higher than 250Kpa is on, the audible and visual alarm works together to remind field operators of paying attention to pressure to control the concrete pouring speed, a red light lower than 150Kpa is on, and the audible and visual alarm works together to remind operators of paying close attention to pressure change to prepare for emergency.
Pressure and flow signals monitored and collected by the field pressure sensor are converted by the microcomputer processor and transmitted to the remote terminal through the RTU, and when early warning and alarming values are achieved, personnel with related operation and management authorities are notified through telephones, short messages, weChats and the like, and data cannot be tampered and permanently kept.
The technical scheme can also comprise the following technical details so as to better realize the technical effects: further comprising step e, uninstalling the program:
after concrete is poured for 4-8 hours and is initially set after inspection, the concrete can be connected with drainage equipment to open a valve for drainage, and continuous drainage is needed once during drainage;
and (3) measuring and discharging by using a water meter during drainage, lifting the bag by using a crane when the allowance of water in the filling bag 3 is not more than 500 kilograms and the bag cannot be drawn out, lifting the bag within 2 hours after the pressure of the bag is released to prevent the bag from collapsing and burying, slowly washing the surface of the bag by using water while checking whether the appearance is damaged or not, and folding and packaging on the spot after the bag is lifted out.
When the capsule is pulled out, the weight of the capsule is required to be less than 10 tons, and the capsule is lifted under the command of a safety worker when the weight of the capsule is more than 10 tons, and the capsule is washed while being lifted.
The technical scheme can also comprise the following technical details so as to better realize the technical effects: in the step d 2:
when the pressure in the filling bag 3 reaches the low-pressure early warning value range, observing whether the pressure in the bag is linearly reduced within a set time, and starting the standby bag if the pressure in the bag is linearly reduced;
when the pressure in the filling bag 3 reaches a low-pressure alarm value, the standby bag is started.
In the embodiment, whether the low-pressure early warning value is 150-100Kpa or not is linearly reduced (within 10 minutes), and emergency measures are immediately taken when the low-pressure early warning value is less than 100Kpa, and the standby bag is started.
By contrast, for the construction of walls with the thickness of 1.2 meters and the depth of 40 meters, the construction method has the advantages that the construction time is less than 1.5 hours, the cost is lower than 5000 yuan/time, the water source is sufficient, and the method is environment-friendly, rapid and free of turbulent flow. The construction is carried out by adopting the traditional sandbag, the construction time is 3-6 hours, the cost is 6000-8000 yuan/time, a field, sand and manpower are needed, and the problems of occupied land, time consumption and sandbag residue and pump blockage exist. The construction is carried out by adopting the steel joint box, the construction time is less than 1.5 hours, the equipment cost is 30-50 ten thousands, the depth is limited, and the pulling depth is high.
While embodiments of the invention have been described above, it is not limited to the applications set forth in the description and the embodiments, which are fully applicable to various fields of endeavor for which the invention may be embodied with additional modifications as would be readily apparent to those skilled in the art, and the invention is therefore not limited to the details given herein and to the embodiments shown and described without departing from the generic concept as defined by the claims and their equivalents.

Claims (7)

1. A temporary filling construction method for a diaphragm wall joint is characterized by comprising the following steps:
a. and (3) pore-forming detection:
b. and (3) filling bag installation: arranging square timbers at two sides of a guide wall in the tank body, placing the filling bag into the tank body, ensuring that the height difference between the top of the filling bag and the ground is within plus 1 meter and minus 0.5 meter, simultaneously ensuring that the filling bag is exposed out of the liquid level, and when the top of the filling bag exceeds 1 meter, using a special frame to lift the filling bag, and ensuring that the filling bag is in a natural vertical state;
c. connecting pipelines: communicating the water source, the complete set of loading monitoring equipment and the filling bag through pipelines;
d. filling capsule loading and monitoring:
d1. adding the filling bag to rated capacity water and rated working pressure, then statically loading for 5-15 minutes, wherein the pressure drop is 150-200Kpa, and pouring concrete can be carried out after the pressure does not drop linearly;
d2. during the concrete pouring process: when the pressure in the filling bag reaches the early warning pressure, slowing down the discharging speed;
when the pressure in the filling bag reaches the high-pressure alarm pressure, the concrete pouring is immediately stopped, and when the pressure value returns to the rated working pressure, the concrete pouring or the intermittent concrete pouring is started.
2. The temporary filling construction method of the diaphragm wall joint according to claim 1, wherein the step a comprises:
a1. performing hole collapse and perpendicularity scanning on the joint space of the tank body by using an ultrasonic probe hole, ensuring that the perpendicularity in the left and right directions is 5 per thousand, and smoothly putting the filling bag to the bottom;
a2. the hole detector is used for passing detection, so that no sharp object damages the filling bag and the filling bag is smoothly put down, and the super-excavation is carried out for 0.6-0.8 m;
a3. carrying out depth detection by using a plumb bob to ensure that a sand bag of 0.5-5 m is filled at the bottom of the joint;
a4. and detecting the specific gravity of the slurry in the tank to ensure that the specific gravity of the slurry is within 1.2.
3. The temporary filling construction method of the underground diaphragm wall joint as claimed in claim 1, wherein the diameter of the filling bag is 0.6-1.5 m when the thickness between the guide walls in the groove body is 0.6-1.5 m.
4. The temporary filling construction method of the ground wall joint according to claim 1, wherein the filling bag is composed of an inner layer, a middle layer and an outer layer, the inner layer is a liquid rubber coating, the middle layer is a polyester and aramid mixed layer, the outer layer is a wear-resistant rubber coating, and the total thickness of the filling bag is 1.8-3cm.
5. The temporary filling construction method for the underground diaphragm wall joint according to claim 1, wherein the complete set of loading monitoring equipment comprises loading equipment, data acquisition equipment and monitoring equipment;
the loading equipment comprises a water storage bag, a water pump, an electromagnetic valve and a quick water connection pipe; the water storage bag is connected with the filling bag through a quick water connection pipe, and a water pump and an electromagnetic valve are installed on the quick water connection pipe;
the data acquisition equipment comprises a pressure sensor and a flowmeter, the flowmeter is arranged on the quick water pipe, and the pressure sensor is arranged at the top in the filling bag;
the monitoring equipment comprises a microcomputer processor and an acousto-optic alarm group; and the audible and visual alarm, the flowmeter and the pressure sensor are all connected with the microcomputer processor.
6. A temporary filling construction method of a diaphragm wall joint according to claim 1, further comprising a step e of unloading a program:
after concrete is poured for 4-8 hours and is initially set after inspection, the concrete can be connected with drainage equipment to open a valve for drainage, and continuous drainage is needed once during drainage;
and (3) discharging by using a water meter during drainage, when the residual amount of water in the filling bag is not more than 500 kilograms and can not be drawn out, lifting the bag by using a crane, wherein the bag must be lifted within 2 hours after the pressure of the bag is released to prevent the bag from collapsing and burying, the surface of the bag is slowly washed by using water, the appearance is checked to be damaged or not, and the bag is folded and packaged on the spot after being lifted out.
7. A temporary filling construction method of a diaphragm wall joint according to claim 1, wherein in the step d 2:
when the pressure in the filling bag reaches the low-pressure early warning value range, observing whether the pressure in the bag is linearly reduced within a set time, and starting a standby bag if the pressure in the bag is linearly reduced;
when the pressure in the filling bag reaches a low-pressure alarm value, the standby bag is started.
CN202211007855.8A 2022-08-22 2022-08-22 Temporary filling construction method for diaphragm wall joint Pending CN115233741A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211007855.8A CN115233741A (en) 2022-08-22 2022-08-22 Temporary filling construction method for diaphragm wall joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211007855.8A CN115233741A (en) 2022-08-22 2022-08-22 Temporary filling construction method for diaphragm wall joint

Publications (1)

Publication Number Publication Date
CN115233741A true CN115233741A (en) 2022-10-25

Family

ID=83681376

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211007855.8A Pending CN115233741A (en) 2022-08-22 2022-08-22 Temporary filling construction method for diaphragm wall joint

Country Status (1)

Country Link
CN (1) CN115233741A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116770813A (en) * 2023-06-19 2023-09-19 中铁一局集团(广州)建设工程有限公司 Perpendicularity adjusting structure for prefabricated underground continuous wall installation process and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004285801A (en) * 2003-03-25 2004-10-14 Kumagai Gumi Co Ltd Water cut off joining method and structure between members
CN104278697A (en) * 2014-10-31 2015-01-14 姜兆礼 Mud sac for sealing end space of underground continuous wall
CN110424374A (en) * 2019-08-29 2019-11-08 深圳中科研人工智能大数据有限公司 Flexible liquid capsule and packing method for diaphram wall header space packing
CN111155511A (en) * 2020-02-19 2020-05-15 武汉速安达建筑橡塑制品有限公司 Multi-cabin diaphragm wall joint construction filling bag and construction method
CN111997095A (en) * 2020-07-15 2020-11-27 武汉速安达建筑橡塑制品有限公司 Construction method for underground diaphragm wall construction by bag-in-bag filling technology
CN212896425U (en) * 2020-05-20 2021-04-06 安徽太基建设工程股份有限公司 Slurry bag for filling underground diaphragm wall
CN214832581U (en) * 2020-12-30 2021-11-23 中地君豪高科股份有限公司 Device for preventing concrete from flowing around during construction of underground garbage waste water partition underground diaphragm wall

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004285801A (en) * 2003-03-25 2004-10-14 Kumagai Gumi Co Ltd Water cut off joining method and structure between members
CN104278697A (en) * 2014-10-31 2015-01-14 姜兆礼 Mud sac for sealing end space of underground continuous wall
CN110424374A (en) * 2019-08-29 2019-11-08 深圳中科研人工智能大数据有限公司 Flexible liquid capsule and packing method for diaphram wall header space packing
CN111155511A (en) * 2020-02-19 2020-05-15 武汉速安达建筑橡塑制品有限公司 Multi-cabin diaphragm wall joint construction filling bag and construction method
CN212896425U (en) * 2020-05-20 2021-04-06 安徽太基建设工程股份有限公司 Slurry bag for filling underground diaphragm wall
CN111997095A (en) * 2020-07-15 2020-11-27 武汉速安达建筑橡塑制品有限公司 Construction method for underground diaphragm wall construction by bag-in-bag filling technology
CN214832581U (en) * 2020-12-30 2021-11-23 中地君豪高科股份有限公司 Device for preventing concrete from flowing around during construction of underground garbage waste water partition underground diaphragm wall

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116770813A (en) * 2023-06-19 2023-09-19 中铁一局集团(广州)建设工程有限公司 Perpendicularity adjusting structure for prefabricated underground continuous wall installation process and construction method thereof
CN116770813B (en) * 2023-06-19 2024-01-26 中铁一局集团(广州)建设工程有限公司 Perpendicularity adjusting structure for prefabricated underground continuous wall installation process and construction method thereof

Similar Documents

Publication Publication Date Title
CN105239563B (en) A kind of supporting rotary drilling rig dry method pore-creating filling pile structure of grouting behind shaft or drift lining and construction method
CN106018736B (en) Urban Underground pipeline seepage triggers the experimental rig of surface collapse
CN115233741A (en) Temporary filling construction method for diaphragm wall joint
CN111155511A (en) Multi-cabin diaphragm wall joint construction filling bag and construction method
CN206038341U (en) Test device of simulation tunnel internal water pressure
CN110528596A (en) A kind of static loading experiment construction technology and detection method based on self-balancing technology
CN110258658A (en) The leakage anticipation of diaphram wall and the construction method of processing
CN209669949U (en) A kind of cisten mechanism and load test device for load test
CN103510549B (en) A kind of method to set up of the pressure relief device for structures anti-floating
CN112647533A (en) Construction system and construction method for preventing slurry leakage in jacket foundation pile by pile-first method
CN114108656A (en) Construction method of foundation pit support
CN117626947A (en) Construction method of rotary drilling bored concrete pile
CN107764232A (en) A kind of measuring system and its construction, measuring method for wearing river shield tunnel riverbed vertical deformation
CN209760241U (en) Electric grouting system
CN111980035A (en) Pipeline construction method by air bubble mixed light soil backfilling method
CN209686465U (en) A kind of load test system using water tank as loading system
CN116695715A (en) Inflatable fore shaft pipe and construction method thereof applied to underground diaphragm wall
CN110672347A (en) Substitution method for carrying out load test on large crane
CN210049299U (en) Civil engineering static test is with intelligent ballast device
CN207258458U (en) Rail tanker sweeps bottom device
CN211922592U (en) Multi-cabin ground is wall even and is connected construction and pack bag
CN113981958A (en) Method for plugging karst cave of mechanical pore-forming cast-in-place pile
CN217870633U (en) Temporary filling bag system for I-steel joint of diaphragm wall
CN209669947U (en) A kind of foldable water tank and load test device
CN103512808A (en) Hydraulic pressure resistance property detection platform for mine waterproof type escape capsule

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination