CN211899576U - Operation platform for construction of inclined curtain wall structure - Google Patents

Operation platform for construction of inclined curtain wall structure Download PDF

Info

Publication number
CN211899576U
CN211899576U CN202020448797.2U CN202020448797U CN211899576U CN 211899576 U CN211899576 U CN 211899576U CN 202020448797 U CN202020448797 U CN 202020448797U CN 211899576 U CN211899576 U CN 211899576U
Authority
CN
China
Prior art keywords
curtain wall
construction
wall structure
guide
box body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020448797.2U
Other languages
Chinese (zh)
Inventor
方建鹏
周春海
姜捷奇
花定兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Sanxin Technology Development Co ltd
Original Assignee
Shenzhen Sanxin Technology Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Sanxin Technology Development Co ltd filed Critical Shenzhen Sanxin Technology Development Co ltd
Priority to CN202020448797.2U priority Critical patent/CN211899576U/en
Application granted granted Critical
Publication of CN211899576U publication Critical patent/CN211899576U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an operation platform is used in slope curtain wall construction, top gallows including bottom mount and at least one, the top gallows sets up in the top of slope curtain wall construction, the bottom mount set up in the bottom of slope curtain wall construction, top gallows below is provided with the operation box of liftable, the operation box through hang heavy rope with top gallows connects, slope curtain wall construction one side parallel arrangement has the guide cable, the guide cable is worn to locate the operation box and with hang heavy rope parallel arrangement. The guide cable and the inclined curtain wall structure are arranged in parallel, so that the distance between the operation box body and the inclined curtain wall structure can be kept unchanged when the operation box body is lifted, the operation box body is started, the operation box body is lifted upwards, the guide cable limits the running track of the operation box body, the inclined lifting of the operation platform for construction of the inclined curtain wall structure is realized, and the installation requirement of the inclined curtain wall structure (or other special-shaped curtain wall structures) is met.

Description

Operation platform for construction of inclined curtain wall structure
Technical Field
The utility model relates to a building curtain construction technical field, more specifically say and indicate an operation platform is used in slope curtain wall construction.
Background
The construction of building curtain wall requires workers to operate in the high-altitude outdoor, and generally has two construction measures: scaffold and hanging flower basket. The scaffold can be set up according to the physique of curtain, strong adaptability. But the scaffold also has the shortcoming such as the expense is high, occupy the place, and the hanging flower basket is used nimble, and the expense is lower relatively, does not occupy the place, does not hinder other work kind constructions, therefore the hanging flower basket also uses very generally. However, the conventional gondola has a significant disadvantage compared to the scaffold: the scaffold can be basically suitable for curtain walls with all shapes, and the common hanging basket has poor adaptability to curtain walls with complex shapes, such as inclined curtain walls. Because the common hanging basket can only be vertically lifted, the distance between the hanging basket and the inclined curtain wall (or other special-shaped curtain walls) cannot be guaranteed to be unchanged during lifting, the distance cannot meet the requirement, and workers cannot perform curtain wall installation operation in the hanging basket. Therefore, the common hanging basket cannot meet the installation requirement of the inclined curtain wall (or other special-shaped curtain walls).
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome prior art not enough, provide an operation platform is used in slope curtain wall construction.
In order to achieve the above purpose, the utility model adopts the following technical scheme: the utility model provides an operation platform is used in slope curtain wall construction, includes bottom mount and at least one top gallows, the top gallows sets up in the top of slope curtain wall construction, the bottom mount set up in the bottom of slope curtain wall construction, top gallows below is provided with the operation box of liftable, the operation box through hang heavy rope with top gallows connects, slope curtain wall construction one side parallel arrangement has the guide cable, the guide cable wear to locate the operation box and with hang heavy rope parallel arrangement.
The further technical scheme is as follows: the bottom mount with the bottom of slope curtain wall construction is connected fixedly, be equipped with fixed pulley on the mount of bottom, slope curtain wall construction rear is provided with hand block, the direction cable is walked around fixed pulley is connected with hand block, through hand block adjusts the tensile force of direction cable is in order to adjust the operation box with the distance of the wall of slope curtain wall construction.
The further technical scheme is as follows: the operation box body includes case body and at least one power direction subassembly, the power direction subassembly includes motor and direction locating part, the direction locating part set up in the top of case body, the top of direction locating part is equipped with guide pulley and hoisting pulley, guide pulley is used for placing the guide rope, hoisting pulley is used for placing the lifting rope, the motor with the lifting rope is connected.
The further technical scheme is as follows: the lifting pulley is arranged in front of the guide pulley.
The further technical scheme is as follows: the guide limiting part is fixedly connected with the box body through a bolt.
The further technical scheme is as follows: the top gallows with slope curtain structure top is connected fixedly, just top gallows one end is connected fixedly with main part roofing steel construction, and the other end is equipped with preceding pulley and back pulley respectively, preceding pulley is used for hanging the hoisting rope, the back pulley is used for hanging the direction cable.
The further technical scheme is as follows: and one end of a top hanging bracket connected with the main roof steel structure is provided with two connecting parts, namely a front connecting part and a rear connecting part, the front connecting part is a semicircular supporting steel part, and the rear connecting part is fixedly connected with the main roof steel structure through a hoop.
The further technical scheme is as follows: the operation platform for the construction of the inclined curtain wall structure is provided with a safety rope, a safety lock is arranged on an operation box body, the upper end of the safety rope is fixedly connected with the main roof steel structure, and the lower end of the safety rope is connected with the safety lock.
The further technical scheme is as follows: the power direction subassembly is two, and two the power direction subassembly set up in the both sides of case body.
The further technical scheme is as follows: the number of the top hanging brackets is two, and the two top hanging brackets are arranged above the side of the box body.
Compared with the prior art, the utility model beneficial effect be: the utility model relates to an operation platform is used in slope curtain wall construction sets up the top gallows through the top at slope curtain wall construction, sets up the bottom mount through the bottom at slope curtain wall construction, through the operation box that sets up the liftable below the gallows at the top, the operation box is through hanging heavy rope and top gallows connection, through slope curtain wall construction one side parallel arrangement guide cable, the guide cable is worn to locate the operation box and with hanging heavy rope parallel arrangement. The guide cable plays a role in presetting a lifting track of the operation box body, the guide cable is arranged in parallel with the inclined curtain wall structure, so that the distance between the operation box body and the inclined curtain wall structure can be kept unchanged when the operation box body is lifted, the operation box body is started, the operation box body is lifted upwards, the guide cable limits the running track of the operation box body, the inclined lifting of the operation platform for construction of the inclined curtain wall structure is realized, and the installation requirement of the inclined curtain wall structure (or other special-shaped curtain wall structures) is met.
The foregoing is a summary of the present invention, and other objects, features and advantages of the present invention will be apparent from the following detailed description of the preferred embodiments, which is provided for the purpose of illustration and understanding of the present invention.
Drawings
FIG. 1 is a schematic view of an operating platform for construction of an inclined curtain wall structure;
FIG. 2 is a schematic view of an operating box;
FIG. 3 is a front view of the guide stop;
fig. 4 is a front view of the top hanger.
Reference numerals
1. A bottom mount; 11. fixing the pulley; 2. a top hanger; 21. a front pulley; 22. a rear pulley; 23. a front connecting part; 24. a rear connection portion; 3. an inclined curtain wall structure; 31. a chain block; 4. operating the box body; 41. a box body; 42. a motor; 43. a guide limit piece; 431. a guide pulley; 432. a lifting pulley; 5. hoisting a weight rope; 6. a guide cable; 7. a safety cord; 8. main part roofing steel construction.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention will be described in further detail with reference to the accompanying drawings and the following detailed description.
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by those skilled in the art without creative efforts belong to the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and to simplify the description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore should not be construed as limiting the present invention.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless specifically limited otherwise.
In the present invention, unless otherwise expressly specified or limited, the terms "mounted," "connected," and "secured" are to be construed broadly and can, for example, be connected or detachably connected or integrated; can be mechanically or electrically connected; either directly or indirectly through intervening media, either internally or in any other relationship. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
In the present disclosure, unless expressly stated or limited otherwise, the first feature "on" or "under" the second feature may comprise direct contact between the first and second features, or may comprise contact between the first and second features not directly. Also, the first feature being "on," "above" and "over" the second feature includes the first feature being directly on and obliquely above the second feature, or merely indicating that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature includes the first feature being directly under and obliquely below the second feature, or simply meaning that the first feature is at a lesser elevation than the second feature.
In the description herein, references to the description of the term "one embodiment," "some embodiments," "an example," "a specific example," or "some examples," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above should not be understood to necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples. Furthermore, various embodiments or examples described in this specification can be combined and combined by one skilled in the art.
As shown in fig. 1 to 4, an operation platform for construction of an inclined curtain wall structure comprises a bottom fixing frame 1 and at least one top hanging frame 2, wherein the top hanging frame 2 is arranged at the top of the inclined curtain wall structure 3, the bottom fixing frame 1 is arranged at the bottom of the inclined curtain wall structure 3, a liftable operation box body 4 is arranged below the top hanging frame 2, the operation box body 4 is connected with the top hanging frame 2 through a lifting rope 5, a guide rope 6 is arranged on one side of the inclined curtain wall structure 3 in parallel, and the guide rope 6 penetrates through the operation box body 4 and is arranged in parallel with the lifting rope 5. The guide cable 6 plays a role in presetting a lifting track for the operation box body 4, the guide cable 6 is arranged in parallel with the inclined curtain wall structure 3, so that the distance between the operation box body 4 and the inclined curtain wall structure 3 is kept unchanged when the operation box body is lifted, the operation box body 4 is started, the operation box body 4 is lifted upwards, the guide cable 6 limits the running track of the operation box body 4, the inclined lifting of the operation platform for construction of the inclined curtain wall structure 3 is realized, and the installation requirement of the inclined curtain wall structure 3 (or other special-shaped curtain wall structures) is met.
Specifically, as shown in fig. 1, the bottom fixing frame 1 is fixedly connected to the bottom of the inclined curtain wall structure 3, the bottom fixing frame 1 is provided with a fixed pulley 11, the rear of the inclined curtain wall structure 3 is provided with a manual block 31, the guide cable 6 bypasses the fixed pulley 11 and is connected with the manual block 31, and the tension of the guide cable 6 is adjusted by the manual block 31 to adjust the distance between the operation box 4 and the wall surface of the inclined curtain wall structure 3. During operation, the tension force of the guide cable 6 is controlled through the hand-operated block 31, so that the distance between the operation box body 4 and the wall surface of the inclined curtain wall structure 3 is controlled, and a worker can conveniently carry out curtain wall installation operation.
Specifically, as shown in fig. 2, the operation box 4 includes a box body 41 and at least one power guide assembly, the power guide assembly includes a motor 42 and a guide limiting member 43, the guide limiting member 43 is disposed above the box body 41, a guide pulley 431 and a lifting pulley 432 are disposed on the top of the guide limiting member 43, the guide pulley 431 is used for placing the guide rope 6, the lifting pulley 432 is used for placing the lifting rope 5, and the motor 42 is connected with the lifting rope 5. When the motor 42 is activated, the operating box 4 moves along the trajectory of the guide cable 6 via the guide pulley 431. The inclined lifting is realized, and the installation requirement of the inclined curtain wall structure 3 is met.
Specifically, as shown in fig. 2 to 3, the lifting pulley 432 is provided in front of the guide pulley 431. The lifting pulley 432 is even behind the guide pulley 431 so that the operating case 4 does not interfere with both during the lifting.
Specifically, as shown in fig. 2, the guide stoppers 43 are fixed to the box body 41 by bolting. The connecting device is connected and fixed in a bolt connecting mode, the connection is reliable, and the operation is simple.
Specifically, as shown in fig. 1 and 4, the top hanger 2 is fixedly connected to the top of the inclined curtain wall structure 3, one end of the top hanger 2 is fixedly connected to the main roof steel structure 8, and the other end of the top hanger 2 is provided with a front pulley 21 and a rear pulley 22 respectively, the front pulley 21 is used for hanging the lifting rope 5, and the rear pulley 22 is used for hanging the guide rope 6.
Specifically, as shown in fig. 1 and 4, two connecting portions, namely a front connecting portion 23 and a rear connecting portion 24, are arranged at one end of the top hanger 2 connected to the main roof steel structure 8, the front connecting portion 23 is a semicircular supporting steel member, and the rear connecting portion 24 is fixedly connected to the main roof steel structure 8 through a hoop.
Specifically, steel structures such as the semicircular supporting steel piece and the hoop are made of Q235 steel and subjected to hot dip galvanizing treatment.
Specifically, as shown in fig. 1 and 2, the operation platform for the construction of the inclined curtain wall structure is provided with a safety rope 7, the operation box body 4 is provided with a safety lock, the upper end of the safety rope 7 is fixedly connected with a main roof steel structure 8, and the lower end of the safety rope is connected with the safety lock. By arranging the safety rope 7 and the safety lock, the safety of operators can be guaranteed, and the safety of measures is improved.
Specifically, the number of the guide cables 6 corresponds to the number of the power guide assemblies, and the number of the power guide assemblies is two, and the two power guide assemblies are disposed on two sides of the box body 41. The two power guide assemblies run synchronously and keep the same lifting speed, so that the operation box body 4 is more stable in the lifting process.
Specifically, the number of the top hangers 2 is two, and the two top hangers 2 are disposed laterally above the box body 41. The rear pulleys 22 provided on the two top spreaders 2 can be used to suspend the two guide ropes 6 and the front pulleys 21 can be used to suspend the two hoist ropes 5, which provides the advantage of making the operating box 4 more stable when lifted.
Specifically, the bottom fixing frame 1 is fixed on the bottom surface through a steel plate and a bolt, and is firmly connected.
Specifically, the guide rope 6, the sling rope 5 and the safety rope 7 are all steel wire ropes.
Specifically, the operation platform for the construction of the inclined curtain wall structure can be applied to the construction of curtain walls with various inclination angles, and can be used for selecting steel wire ropes with different diameters through calculation and checking and also can be suitable for the requirements of construction operation boxes 4 with different sizes and different construction loads.
Specifically, this operation platform is used in slope curtain wall construction is fixed in main part roofing steel construction 8 through top gallows 2, and fixed pulley 11 is fixed in ground, and the back pulley 22 of guide cable 6 upper end string in top gallows 2 passes the guide pulley 431 that sets up on operation box 4 in the middle of, and the lower extreme passes fixed pulley 11 and is connected with hand hoist 31. The upper end of the lifting rope 5 is hung on the front pulley 21 of the top hanging frame 2, and the middle of the lifting rope passes through the lifting pulley 432 and then is connected with the motor 42. The tensile force of guide cable 6 is controlled through hand block 31 during operation to the distance of control platform case body 41 and slope curtain wall structure curtain wall face makes things convenient for the workman to carry out the curtain installation operation. The safety lock is arranged in the operation box body 4, the lower end of the safety rope 7 penetrates through the safety lock, and the upper end of the safety rope is hung on the main roof steel structure 8, so that the safety of operators is guaranteed, and the safety of measures is improved.
Compared with the prior art, the utility model relates to an operation platform is used in slope curtain wall construction sets up the top gallows through the top at slope curtain wall construction, sets up the bottom mount through the bottom at slope curtain wall construction, through the operation box that sets up the liftable below the gallows at the top, and the operation box is through hanging heavy rope and top gallows connection, through slope curtain wall construction one side parallel arrangement guide cable, and the guide cable is worn to locate the operation box and is hung heavy rope parallel arrangement with hanging. The guide cable plays a role in presetting a lifting track of the operation box body, the guide cable is arranged in parallel with the inclined curtain wall structure, so that the distance between the operation box body and the inclined curtain wall structure can be kept unchanged when the operation box body is lifted, the operation box body is started, the operation box body is lifted upwards, the guide cable limits the running track of the operation box body, the inclined lifting of the operation platform for construction of the inclined curtain wall structure is realized, and the installation requirement of the inclined curtain wall structure (or other special-shaped curtain wall structures) is met.
The technical content of the present invention is further described by the embodiments only, so that the reader can understand it more easily, but the embodiments of the present invention are not limited thereto, and any technical extension or re-creation according to the present invention is protected by the present invention. The protection scope of the present invention is subject to the claims.

Claims (10)

1. The utility model provides an operation platform is used in slope curtain wall construction, its characterized in that, includes bottom mount and at least one top gallows, the top gallows sets up in the top of slope curtain wall construction, the bottom mount set up in the bottom of slope curtain wall construction, top gallows below is provided with the operation box of liftable, the operation box through the hoisting rope with top gallows connects, slope curtain wall construction one side parallel arrangement has the guide cable, the guide cable wear to locate the operation box and with hoisting rope parallel arrangement.
2. The operating platform for the construction of the inclined curtain wall structure according to claim 1, wherein the bottom fixing frame is fixedly connected with the bottom of the inclined curtain wall structure, a fixed pulley is arranged on the bottom fixing frame, a manual block is arranged behind the inclined curtain wall structure, the guide cable is connected with the manual block by bypassing the fixed pulley, and the tension of the guide cable is adjusted by the manual block so as to adjust the distance between the operating box body and the wall surface of the inclined curtain wall structure.
3. The operation platform for the construction of the inclined curtain wall structure according to claim 2, wherein the operation box body comprises a box body and at least one power guide assembly, the power guide assembly comprises a motor and a guide limiting part, the guide limiting part is arranged above the box body, a guide pulley and a lifting pulley are arranged at the top of the guide limiting part, the guide pulley is used for placing the guide rope, the lifting pulley is used for placing the lifting rope, and the motor is connected with the lifting rope.
4. The inclined curtain wall structure construction work platform of claim 3, wherein the lifting pulley is arranged in front of the guide pulley.
5. The operation platform for the construction of the inclined curtain wall structure according to claim 3, wherein the guide limiting piece is fixedly connected with the box body through a bolt.
6. The operation platform for the construction of the inclined curtain wall structure as claimed in claim 4, wherein the top hanging bracket is fixedly connected with the top of the inclined curtain wall structure, one end of the top hanging bracket is fixedly connected with a main roof steel structure, the other end of the top hanging bracket is respectively provided with a front pulley and a rear pulley, the front pulley is used for hanging the lifting rope, and the rear pulley is used for hanging the guide rope.
7. The operation platform for the construction of the inclined curtain wall structure according to claim 6, wherein one end of the top hanging bracket connected with the main roof steel structure is provided with two connecting parts, namely a front connecting part and a rear connecting part, the front connecting part is a semicircular supporting steel part, and the rear connecting part is fixedly connected with the main roof steel structure through a hoop.
8. The operation platform for the construction of the inclined curtain wall structure as claimed in claim 7, wherein a safety rope is arranged on the operation platform for the construction of the inclined curtain wall structure, a safety lock is arranged on the operation box body, the upper end of the safety rope is fixedly connected with the steel structure of the main roof, and the lower end of the safety rope is connected with the safety lock.
9. The operation platform for the construction of the inclined curtain wall structure according to claim 3, wherein the number of the power guide assemblies is two, and the two power guide assemblies are arranged on two sides of the box body.
10. The inclined operation platform for curtain wall structure construction as claimed in claim 9, wherein the number of the top hangers is two, and the two top hangers are disposed laterally above the box body.
CN202020448797.2U 2020-03-31 2020-03-31 Operation platform for construction of inclined curtain wall structure Active CN211899576U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020448797.2U CN211899576U (en) 2020-03-31 2020-03-31 Operation platform for construction of inclined curtain wall structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020448797.2U CN211899576U (en) 2020-03-31 2020-03-31 Operation platform for construction of inclined curtain wall structure

Publications (1)

Publication Number Publication Date
CN211899576U true CN211899576U (en) 2020-11-10

Family

ID=73274958

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020448797.2U Active CN211899576U (en) 2020-03-31 2020-03-31 Operation platform for construction of inclined curtain wall structure

Country Status (1)

Country Link
CN (1) CN211899576U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111287440A (en) * 2020-03-31 2020-06-16 深圳市三鑫科技发展有限公司 Operation platform for construction of inclined curtain wall structure
CN115977366A (en) * 2022-11-21 2023-04-18 中建深圳装饰有限公司 Operating platform suitable for inverted curtain wall and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111287440A (en) * 2020-03-31 2020-06-16 深圳市三鑫科技发展有限公司 Operation platform for construction of inclined curtain wall structure
CN115977366A (en) * 2022-11-21 2023-04-18 中建深圳装饰有限公司 Operating platform suitable for inverted curtain wall and construction method

Similar Documents

Publication Publication Date Title
CN211899576U (en) Operation platform for construction of inclined curtain wall structure
CN213537070U (en) Make things convenient for hanging of curtain installation to send device
CN213011574U (en) Rapid unhooking device and hoisting mechanism
CN111287440A (en) Operation platform for construction of inclined curtain wall structure
CN210029743U (en) Lifting appliance for high-rise prefabricated composite slab construction
CN115947240A (en) Hoisting machine lifting device
CN217054278U (en) Fixing structure for mounting cornice inclined roof hanging basket
CN215291554U (en) Slant traction guide rope lock device
CN213085125U (en) Elevator shaft traction rotary telescopic construction elevator
CN214935294U (en) H-shaped steel beam hoisting assembly for steel structure construction
CN211569866U (en) Hoist for PC component convenient to adjust assembly dimension
CN2213146Y (en) Adjustable lift sub for lifting steel plate
CN206636185U (en) The treadle of false work of laborsaving assembly pulley is installed
CN205294671U (en) Device of falling roof beam
CN217837981U (en) Lifting device of wind turbine generator and wind turbine generator
CN212608991U (en) Rear-mounted slideway slot hoisting device
CN211775639U (en) Embedded plate type hanging basket mounting structure
CN217102693U (en) Container type glass curtain wall hoisting equipment
CN212101608U (en) Steel construction hoist and mount protector
CN221590352U (en) Electric hanging basket support type hanging mechanism
CN215711070U (en) Lifting appliance for passenger car body and workshop production line
CN221165732U (en) Electromechanical device installs auxiliary device
CN214527791U (en) Be applied to hoist device of parapet
CN219194305U (en) Hoist and mount self-traction ware and lifting device