CN211898801U - Connection form between current drainage ditch and inspection well - Google Patents

Connection form between current drainage ditch and inspection well Download PDF

Info

Publication number
CN211898801U
CN211898801U CN202020380681.XU CN202020380681U CN211898801U CN 211898801 U CN211898801 U CN 211898801U CN 202020380681 U CN202020380681 U CN 202020380681U CN 211898801 U CN211898801 U CN 211898801U
Authority
CN
China
Prior art keywords
inspection
current situation
inspection well
well
inspection shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020380681.XU
Other languages
Chinese (zh)
Inventor
方刚
楼少华
唐颖栋
吕权伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN202020380681.XU priority Critical patent/CN211898801U/en
Application granted granted Critical
Publication of CN211898801U publication Critical patent/CN211898801U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model relates to a connection form between current situation escape canal and inspection shaft. The utility model aims at providing a simple structure, construction convenience, the lower current situation escape canal of cost and the connected form between the inspection shaft. The technical scheme of the utility model is that: the utility model provides a connection form between current situation escape canal and inspection shaft which characterized in that: a bottom inspection well is arranged between the current situation drainage ditch and the current situation inspection well, a water inlet communicated with the current situation drainage ditch is formed in the side wall of the upper portion of the bottom inspection well, a water outlet is formed in the side wall of the middle portion of the bottom inspection well and communicated with a water inlet in the side wall of the current situation inspection well through a communicating pipe, and the water inlet of the current situation inspection well and the water outlet in the bottom inspection well are located at the same elevation or are slightly lower than the water outlet in the bottom inspection well. The utility model is suitable for a municipal administration water supply and drainage field.

Description

Connection form between current drainage ditch and inspection well
Technical Field
The utility model relates to a connection form between current situation escape canal and inspection shaft. Is suitable for the field of municipal water supply and drainage.
Background
Common drainage ditches can be divided into open ditches, cover plate ditches and closed ditches according to the section form, wherein the open ditches are drainage ditches without ditch cover plates except for the water dispersion slope of the outer wall of the house, and can quickly and organically guide ground water and rainwater to a downstream pipeline. The cover plate ditch reduces the entry of sundries by adding the cover plate above the open ditch on the premise of ensuring that water and rainwater on the road surface can enter the ditch. The blind ditch is a ditch buried under the ground to guide water flow, and can be generally connected with a downstream municipal drainage system due to the fact that covering soil with a certain thickness is arranged right above the blind ditch.
The open ditch or the cover ditch has the condition that the open ditch or the cover ditch cannot be connected in the same direction when being connected to a downstream drainage system because the surface of the open ditch or the cover ditch is not covered with soil. At this time, a certain modification is needed before the drainage ditch is accessed into the inspection well. The common practice in the prior art is to arrange a floor drain at the end of the drainage ditch and connect the drainage pipe with the downstream inspection well. The connection form is easy to generate clogging at the grate of the floor drain, waste is easy to decay at the floor drain, and a pipeline at the downstream of the floor drain is usually smaller than a water passing section of an upstream water outlet, so that the water body overflowing capacity is seriously influenced.
Chinese patent publication No. CN 206635915U discloses a connection structure between an open drain ditch and a drain pipe, the connection structure is a linking pipe with an opening on a side wall of a non-section of the open drain ditch, a grate is arranged at the opening of the linking pipe, the direction of the linking pipe is consistent with the direction of the open drain ditch, the drain pipe is inserted into the tail end of the linking pipe, and the drain pipe and the inner wall of the tail end of the linking pipe are sealed and fixed by waterproof mortar. This prior art can realize the separation of solid waste and water, but because pipeline and open drain ditch are the form of following the way and connecing, downstream pipeline earthing can't satisfy the requirement, when needs cross pavement or road, the connecting pipe is damaged by the influence of ground load easily in the in-service use, and seals through waterproof mortar between drain pipe and the terminal inner wall of adapter pipe and fix insecure.
Disclosure of Invention
The to-be-solved technical problem of the utility model is: to the problem that exists, provide a simple structure, construction convenience, the lower current situation escape canal of cost and the connected form between the inspection shaft.
The utility model adopts the technical proposal that: the utility model provides a connection form between current situation escape canal and inspection shaft which characterized in that: a bottom inspection well is arranged between the current situation drainage ditch and the current situation inspection well, a water inlet communicated with the current situation drainage ditch is formed in the side wall of the upper portion of the bottom inspection well, a water outlet is formed in the side wall of the middle portion of the bottom inspection well and communicated with a water inlet in the side wall of the current situation inspection well through a communicating pipe, and the water inlet of the current situation inspection well and the water outlet in the bottom inspection well are located at the same elevation or are slightly lower than the water outlet in the bottom inspection well.
And the water outlet of the bottom falling inspection well is 0.3-0.5 m higher than the bottom of the bottom falling inspection well.
And when the two ends of the communicating pipe are connected with the bottom-falling inspection well and the current situation inspection well, the communicating pipe is sealed and fixed by a waterproof sleeve.
And a stainless steel grating is arranged at the water outlet of the falling bottom inspection well.
The spacing between the bars of the stainless steel grating is 30 mm.
And sealing the communicating pipe by adopting a reinforced concrete square bag.
The minimum thickness of the soil above the communicating pipe is 0.7 m.
The communicating pipe is obliquely and downwards obliquely arranged from the bottom-falling inspection well end to the current-situation inspection well end, and the gradient is 3 per thousand.
The well lid is all equipped with at the bottom of falling inspection shaft and current situation inspection shaft top, and the well inner wall that corresponding inspection shaft is pressed close to the well lid is arranged, is equipped with the cat ladder that corresponds corresponding well lid in bottom of falling inspection shaft and current situation inspection shaft.
The current situation escape canal coats and is stamped the apron.
The utility model has the advantages that: the utility model discloses a set up the inspection shaft that falls at the bottom, filth and sewage separation in the escape canal, the filth deposits in the inspection shaft bottom that falls at the bottom, and sewage then flows from the connecting pipe of inspection shaft lateral wall that falls at the bottom to the stainless steel grid that accessible mouth of pipe department set up carries out the separation of solid waste and water.
The utility model discloses well pipeline does not have the elbow design, has avoided among the prior art tiny precipitate of elbow department of floor drain pipe to pile up the phenomenon, has enlarged the rivers section of pipeline, makes sewage discharge more smoothly.
The utility model discloses adopt waterproof sleeve pipe to seal fixedly when china communicating pipe is connected with the wall of a well, can ensure the leakproofness.
The utility model discloses can't be in the same direction as connecing when advancing the current situation inspection shaft in the current situation escape canal, adopt and fall to the ground the inspection shaft switching, reduce the connecting pipe elevation simultaneously, make its buried depth increase, can effectively avoid the pipeline when crossing pavement or road, the connecting pipe receives the ground load influence and is damaged.
Drawings
Fig. 1 is a schematic plan view of an embodiment.
Fig. 2 is a sectional view of fig. 1 through 1.
Fig. 3 is a cross-sectional view 2-2 of fig. 1.
1. A current drainage ditch; 2. a cover plate; 3. a bottom-falling inspection well; 4. a well cover; 5. a stainless steel grating; 6. a communicating pipe; 7. a waterproof sleeve; 8. a current situation inspection well; 9. the ladder is climbed.
Detailed Description
As shown in fig. 1 to 3, the present embodiment is a connection form between a current drainage ditch and an inspection well, and includes a current drainage ditch, a bottom inspection well and a current inspection well, wherein the current drainage ditch is covered with a cover plate to form a cover plate ditch, and the end of the cover plate ditch is connected to the upper part of the bottom inspection well; a water inlet communicated with the cover plate ditch is formed in the side wall of the upper part of the bottom falling inspection well, and a water outlet is formed in the side wall of the middle part of the bottom falling inspection well; the current drainage ditch is provided with a water inlet on the side wall of the middle part and a water outlet on the side wall of the lower part.
In this example, the water inlet of the present drainage ditch is slightly lower than the water outlet of the bottoming inspection well, and the water outlet of the bottoming inspection well is communicated with the water inlet of the present drainage ditch through a communication pipe. When the communicating pipe is connected with the bottom-falling inspection well and the current situation inspection well, the communicating pipe is sealed and fixed by a waterproof sleeve, so that the sealing performance can be ensured.
In this embodiment, the water outlet of the falling-bottom inspection well is provided with a stainless steel grating, the distance between the grating bars is 30mm, and the solid waste entering the current inspection well is filtered, so that the solid waste entering the current inspection well is greatly reduced, and the operation efficiency of the current pipe network system is improved.
In the embodiment, the communicating pipes are obliquely and downwards obliquely arranged from the end of the falling inspection well to the end of the current inspection well, and the gradient is 3 per thousand, so that the normal flow of water flow is facilitated. The soil covering thickness of the communicating pipe 6 is 0.7m, if the soil covering thickness of the communicating pipe 6 is limited by current conditions, the requirement of the lowest soil covering of 0.7m cannot be met, the burial depth can be properly reduced, and the pipeline is encapsulated in a reinforced concrete square bag mode, so that the ground load bearing capacity of the pipeline is improved.
The distance between the bottom of the floor inspection well and the water outlet on the side wall of the floor inspection well can be 0.3m, 0.4m or 0.5m, and the appropriate height can be selected according to the actual conditions such as the depth, the flow rate, the solid dirt content and the like of the current drainage ditch.
This embodiment all is equipped with the well lid at end inspection shaft and current situation inspection shaft top in the falling, and the well lid is pressed close to the well inner wall arrangement of corresponding inspection shaft, is equipped with the cat ladder that corresponds corresponding well lid in end inspection shaft and the current situation inspection shaft, and when the deposit reached certain thickness in the inspection shaft, opened the well lid, the people can clear up and overhaul bottom down.
When rivers process current situation escape canal to the inspection shaft that falls to the bottom in this embodiment, along with the large granule solid waste that rivers got into deposits in inspection shaft low portion that falls to the bottom because of the action of gravity, water then discharges into current situation inspection shaft behind communicating pipe from inspection shaft middle part lateral wall that falls to the bottom.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. The utility model provides a connection form between current situation escape canal and inspection shaft which characterized in that: a bottom inspection well is arranged between the current situation drainage ditch and the current situation inspection well, a water inlet communicated with the current situation drainage ditch is formed in the side wall of the upper portion of the bottom inspection well, a water outlet is formed in the side wall of the middle portion of the bottom inspection well and communicated with a water inlet in the side wall of the current situation inspection well through a communicating pipe, and the water inlet of the current situation inspection well and the water outlet in the bottom inspection well are located at the same elevation or are slightly lower than the water outlet in the bottom inspection well.
2. The form of connection between a presence gutter and an inspection shaft of claim 1, wherein: and the water outlet of the bottom falling inspection well is 0.3-0.5 m higher than the bottom of the bottom falling inspection well.
3. The form of connection between a presence gutter and an inspection shaft of claim 1, wherein: and when the two ends of the communicating pipe are connected with the bottom-falling inspection well and the current situation inspection well, the communicating pipe is sealed and fixed by a waterproof sleeve.
4. The form of connection between a presence gutter and an inspection shaft of claim 1, wherein: and a stainless steel grating is arranged at the water outlet of the falling bottom inspection well.
5. The form of connection between a presence gutter and an inspection shaft of claim 4, wherein: the spacing between the bars of the stainless steel grating is 30 mm.
6. The form of connection between a presence gutter and an inspection shaft of claim 1, wherein: and sealing the communicating pipe by adopting a reinforced concrete square bag.
7. The form of connection between a presence gutter and an inspection shaft of claim 1, wherein: the minimum thickness of the soil above the communicating pipe is 0.7 m.
8. A form of connection between a presence gutter and an inspection shaft according to claim 1 or 6 or 7, characterised in that: the communicating pipe is obliquely and downwards obliquely arranged from the bottom-falling inspection well end to the current-situation inspection well end, and the gradient is 3 per thousand.
9. The form of connection between a presence gutter and an inspection shaft of claim 1, wherein: the well lid is all equipped with at the bottom of falling inspection shaft and current situation inspection shaft top, and the well inner wall that corresponding inspection shaft is pressed close to the well lid is arranged, is equipped with the cat ladder that corresponds corresponding well lid in bottom of falling inspection shaft and current situation inspection shaft.
10. The form of connection between a presence gutter and an inspection shaft of claim 1, wherein: the current situation escape canal coats and is stamped the apron.
CN202020380681.XU 2020-03-23 2020-03-23 Connection form between current drainage ditch and inspection well Active CN211898801U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020380681.XU CN211898801U (en) 2020-03-23 2020-03-23 Connection form between current drainage ditch and inspection well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020380681.XU CN211898801U (en) 2020-03-23 2020-03-23 Connection form between current drainage ditch and inspection well

Publications (1)

Publication Number Publication Date
CN211898801U true CN211898801U (en) 2020-11-10

Family

ID=73269567

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020380681.XU Active CN211898801U (en) 2020-03-23 2020-03-23 Connection form between current drainage ditch and inspection well

Country Status (1)

Country Link
CN (1) CN211898801U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112443029A (en) * 2020-11-25 2021-03-05 中国电建集团华东勘测设计研究院有限公司 Bypass type drainage pipeline inspection well structure and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112443029A (en) * 2020-11-25 2021-03-05 中国电建集团华东勘测设计研究院有限公司 Bypass type drainage pipeline inspection well structure and construction method thereof

Similar Documents

Publication Publication Date Title
KR101039196B1 (en) Keeping treatment system for primary stage rainwater using the water-storage tank
CN211421194U (en) Green ecological self-drainage anti-floating device for sloping field building
CN102635157B (en) Siphoning type rainwater drainage and recovery system
CN211898801U (en) Connection form between current drainage ditch and inspection well
CN209556088U (en) Gutter inlet for intercepting initial rainwater based on buoy
CN207582618U (en) A kind of pump discharges into water system
CN216275516U (en) Novel protective facility for dam back slope
CN212837009U (en) Water retaining and draining device for garage
CN211447019U (en) Basement bottom plate structure
CN210976044U (en) Wall-mounted micro drainage pump station for sewage interception engineering
CN209144648U (en) A kind of bridge drainage collection system
CN204001140U (en) The one gradient formula transformer station raceway groove drainage system that catchments
KR101151090B1 (en) Keeping treatment system for primary stage rainwater using the water-storage tank
CN216552309U (en) Open caisson for rural sewage pipe network distribution of rain and sewage
CN214245994U (en) Lower floor blowdown upper rainwater ground overflow formula rain sewage diversion system
CN217500474U (en) Point source pollution treatment equipment for river and lake sewage discharge outlet
CN215290378U (en) Underground spring water taking structure
CN205348376U (en) Cellular -type sewage is collected and is discharged well automatically convenient to make compost
CN219863185U (en) Drainage pipe network structure capable of preventing sewage from flowing backward
CN212053507U (en) Rain and sewage diversion drainage device combined with roof siphon drainage
CN219653889U (en) Prefabricated pump station of integration
CN1087052C (en) Building method of sewerage system capable of preventing odor from diffusing and draining water
CN217233590U (en) Double-layer drainage ditch structure of tunnel
CN215630565U (en) Sewage intercepting device
CN217734284U (en) Rainwater overflow device