CN211850832U - Constructional column concrete casting template - Google Patents

Constructional column concrete casting template Download PDF

Info

Publication number
CN211850832U
CN211850832U CN202020462422.1U CN202020462422U CN211850832U CN 211850832 U CN211850832 U CN 211850832U CN 202020462422 U CN202020462422 U CN 202020462422U CN 211850832 U CN211850832 U CN 211850832U
Authority
CN
China
Prior art keywords
pouring
constructional column
plate
baffle
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020462422.1U
Other languages
Chinese (zh)
Inventor
丁晓
武飞彦
黄高明
卫国庆
王宁宁
刘越
贾鹏
张志利
翟卓恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi First Construction Group Co Ltd
Original Assignee
Shanxi First Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi First Construction Group Co Ltd filed Critical Shanxi First Construction Group Co Ltd
Priority to CN202020462422.1U priority Critical patent/CN211850832U/en
Application granted granted Critical
Publication of CN211850832U publication Critical patent/CN211850832U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a constructional column concrete pouring template, which comprises a constructional column template, wherein one side of the top of the constructional column template is provided with a pouring plate, the pouring plate is in an inverted triangle shape, one side of the top of the constructional column template is provided with a pouring gate, the pouring plate is rotationally connected with a baffle, one side of the baffle is provided with a screw, the back of the pouring plate is provided with a 16mm round hole, a rocking handle with the diameter of 16mm is arranged at the round hole, after the pouring is completed, the rocking handle is rotated to drive the screw to rotate, the screw rotates to drive a support rod to rotate, the screw enters the pouring plate while rotating, the screw pushes a push plate to move, the push plate moves to push the baffle to rotate, the baffle extrudes the concrete to form an inverted triangle-shaped pouring block, after the concrete is initially solidified, the convex concrete is chiseled by workers, only the workers need to chive the convex concrete at the top of the baffle, and the concrete, the material is saved, the chiseling concrete is less, and the labor is saved.

Description

Constructional column concrete casting template
Technical Field
The utility model relates to a building field especially relates to a constructional column concrete placement template.
Background
The constructional column is characterized in that in order to enhance the integrity and stability of a building, a reinforced concrete constructional column is arranged in a wall body of a multi-layer brick-concrete structure building and is connected with each layer of ring beam to form a space frame capable of resisting bending and shearing, and the constructional column is an effective measure for preventing a house from collapsing. The arrangement positions of the constructional columns are at four corners of the outer wall, the joints of the cross walls and the outer longitudinal walls at staggered layers, two sides of a larger hole, the joints of the inner wall and the outer wall of a large room, and the like. In addition, the number of layers of the house is different, the earthquake intensity is different, and the setting requirements of the constructional columns are different.
This application improves under prior art, and among the prior art, a similar structure of falling triangle can often be pour to the constructional column when pouring, and the current inverted triangle that forms after pouring the completion is often great, and the concrete that needs to pick the chisel is more, is not convenient for pick the chisel, extravagant manpower.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a constructional column concrete casting template.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a constructional column concrete placement template, includes the constructional column template, constructional column template top one side is installed and is pour the board, the shape of pouring the board is for falling three horn shapes, the pouring gate has been seted up near one side of pouring the board on constructional column template top, and pours the board and be linked together with the pouring gate, it is connected with the baffle to pour the inboard rotation, one side butt that the constructional column template was kept away from to the baffle has the push pedal, one side rotation that the baffle was kept away from to the push pedal is connected with the ball, the one side welding that the ball stretched out the push pedal of ball has branch, the one end welding that the ball was kept away from to branch has the screw rod with pour board threaded connection, the one end welding that branch was kept.
As a further description of the above technical solution: the baffle bottom fixedly connected with connecting axle, the connecting axle inner wall rotates and is connected with and pours board inner wall fixed mounting's pivot.
As a further description of the above technical solution: pour board bottom inner wall and pass through iron nail fixed mounting and have the packing that rotates with the connecting axle to be connected, first arc recess has been seted up at the packing top, and first arc recess and connecting axle looks adaptation, pour the inboard wall and seted up second arc recess, and second arc recess and connecting axle looks adaptation.
As a further description of the above technical solution: pour the fixed plate that the board both sides were installed the symmetric distribution through the iron nail, and the fixed plate passes through the iron nail with the constructional column template and fixes, two sets of the mounting panel with pour the board butt is installed to one side below that the fixed plate is close to each other.
As a further description of the above technical solution: the mounting panel top is provided with the inclined plane, and the inclined plane gradient is the same with the gradient of pouring the board hypotenuse, the inclined plane at mounting panel top with pour the board butt, the mounting panel passes through the iron nail with the constructional column template and fixes.
As a further description of the above technical solution: the mounting panel both sides are provided with the fixture block of symmetric distribution through the cutting, the fixed plate is close to one side of mounting panel seted up with the draw-in groove, and draw-in groove and fixture block looks adaptation.
The utility model discloses following beneficial effect has:
1. when the utility model is used for pouring, concrete is poured towards one side of the baffle close to the constructional column template, the concrete enters the constructional column template through the pouring gate after being guided by the baffle, pouring is carried out, a 16mm round hole is formed on the back surface of the pouring plate, a nut with the aperture of 16mm is welded at the round hole, a rocking handle with the diameter of 16mm is installed, after pouring is completed, the rocking handle is rotated to drive the screw rod to rotate, the screw rod rotates to drive the supporting rod to rotate, the screw rod simultaneously enters the pouring plate, the screw rod pushes the push plate to move, the push plate moves to push the baffle to rotate, the baffle extrudes the concrete to form an inverted triangular pouring block, convex concrete is chiseled after the concrete is initially solidified, at the moment, only a worker is needed to chiseling the convex concrete at the top of the baffle, the concrete bench after pouring is smaller than before, materials are saved, less concrete is removed and chiseled, and labor is saved.
2. The utility model discloses in pour board bottom butt mounting panel, the mounting panel top sets up the inclined plane and pours the board butt, and the mounting panel both sides are fixed with the fixed plate through draw-in groove, fixture block and iron nail, and the fixed plate passes through the iron nail and pours board, constructional column template fixed, and the installation of being convenient for is pour board and each subassembly, is convenient for install and use.
Drawings
Fig. 1 is a schematic structural view of a constructional column concrete casting template provided by the invention;
fig. 2 is an enlarged schematic structural view of a point a in fig. 1 according to the present invention;
FIG. 3 is a side view of a structural column concrete cast slab as set forth in the present invention;
fig. 4 is an enlarged schematic structural view of the position B in fig. 3 according to the present invention;
fig. 5 is an enlarged schematic structural diagram of the position C of fig. 1 in the present invention.
Illustration of the drawings:
1-constructional column template, 2-pouring gate, 3-pouring plate, 4-baffle, 5-screw, 6-mounting plate, 7-connecting shaft, 8-rotating shaft, 9-filling block, 10-fixing plate, 11-clamping groove, 12-clamping block, 13-supporting rod, 14-ball and 15-push plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention; the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance, and furthermore, unless otherwise explicitly stated or limited, the terms "mounted," "connected," and "connected" are to be construed broadly and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1-5, the utility model provides a constructional column concrete casting template, including constructional column template 1, pouring plate 3 is installed to constructional column template 1 top one side, pouring plate 3's shape is the shape of falling triangle, pouring gate 2 has been seted up to the one side that the constructional column template 1 top is close to pouring plate 3, and pouring plate 3 is linked together with pouring gate 2, pouring plate 3 internal rotation is connected with baffle 4, baffle 4 is kept away from constructional column template 1 one side butt joint push pedal 15, push pedal 15 is kept away from baffle 4 one side rotation and is connected with ball 14, ball 14 stretches out one side of push pedal 15 and welds branch 13, the screw rod 5 with pouring plate 3 threaded connection is welded to the one end welding that branch 14 was kept away from to branch 13, the handle is welded to the one end welding that branch 13 was kept away from to screw rod 5, and the handle adopts old and useless reinforcing bar to make, baffle 4 makes, the screw 5 and each component thereof are convenient for driving the baffle 4 to rotate for forming the inverted triangle;
referring to fig. 1 and 2, in the application, the bottom of the baffle 4 is fixedly connected with a connecting shaft 7, the inner wall of the connecting shaft 7 is rotatably connected with a rotating shaft 8 fixedly mounted with the inner wall of the pouring plate 3, and the connecting shaft 7 and the rotating shaft 8 facilitate the rotation of the baffle 4;
referring to fig. 1 and 2, in the application, a filling block 9 rotatably connected with a connecting shaft 7 is fixedly mounted on the inner wall of the bottom of a pouring plate 3 through an iron nail, a first arc-shaped groove is formed in the top of the filling block 9 and is matched with the connecting shaft 7, a second arc-shaped groove is formed in the inner wall of the pouring plate 3 and is matched with the connecting shaft 7, the filling block 9 prevents the inner wall of the bottom of the pouring plate 3 from entering concrete, and meanwhile, the baffle 4 is convenient to rotate;
referring to fig. 1, 2 and 3, in the present application, fixing plates 10 are symmetrically arranged on two sides of a pouring plate 3 through iron nails, the fixing plates 10 are fixed with a constructional column formwork 1 through the iron nails, a mounting plate 6 abutting against the pouring plate 3 is arranged below one side of each two groups of fixing plates 10 close to each other, and the fixing plates 10 and the mounting plate 6 facilitate fixing the pouring plate 3 with the constructional column formwork 1;
referring to fig. 2, in the application, an inclined plane is arranged at the top end of the mounting plate 6, the inclination of the inclined plane is the same as that of the inclined edge of the pouring plate 3, the inclined plane at the top of the mounting plate 6 is abutted to the pouring plate 3, the mounting plate 6 and the constructional column formwork 1 are fixed through iron nails, and the inclined plane at the top of the mounting plate 6 is convenient for the mounting plate 6 to extrude the pouring plate 3, so that the infirm fixation between the pouring plate 3 and the constructional column formwork 1 is avoided;
referring to fig. 3 and 4, in the application, the fixture blocks 12 are symmetrically distributed on two sides of the mounting plate 6 by cutting, and the fixture groove 11 is formed in one side of the fixing plate 10 close to the mounting plate 6, and the fixture groove 11 is matched with the fixture block 12, so that the mounting plate 6 and the fixing plate 10 can be conveniently mounted.
The working principle is as follows:
in the application, when pouring, concrete is poured towards one side of a baffle 4 close to a constructional column template 1, the concrete enters the constructional column template 1 through a pouring gate 2 after being guided by the baffle 4, pouring is carried out, a 16mm round hole is formed in the back of a pouring plate 3, a nut with the diameter of 16mm is welded at the round hole, a rocking handle with the diameter of 16mm is installed, after pouring is completed, the rocking handle is rotated to drive a screw rod 5 to rotate, the screw rod 5 rotates to drive a supporting rod 13 to rotate, the screw rod 5 simultaneously enters the pouring plate 3 when rotating, the screw rod 5 pushes a push plate 15 to move, the push plate 15 moves to push the baffle 4 to rotate, the baffle 4 extrudes the concrete to form an inverted triangular pouring block, convex concrete is chiseled after the concrete is initially solidified, at the moment, a worker only needs to chive the convex concrete at the top of the baffle 4, so that a poured concrete platform is smaller than before, the material is saved, the picking and chiseling concrete is less, and the labor is saved;
in this application, pour 3 bottom butt mounting panels 6 of board, 6 tops of mounting panel set up the inclined plane and pour 3 butts of board, and 6 both sides of mounting panel are fixed with fixed plate 10 through draw-in groove 11, fixture block 12 and iron nail, and fixed plate 10 is fixed through iron nail and pouring board 3, constructional column template 1, and the installation of being convenient for is pour board 3 and each subassembly, is convenient for install and use.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (6)

1. A constructional column concrete casting template, includes constructional column template (1), its characterized in that: the structure column formwork comprises a structure column formwork (1), wherein a pouring plate (3) is installed on one side of the top of the structure column formwork (1), the pouring port (2) is formed in one side, close to the pouring plate (3), of the top end of the structure column formwork (1), the pouring plate (3) is communicated with the pouring port (2), a baffle (4) is connected in the pouring plate (3) in a rotating mode, a push plate (15) abuts against one side, far away from the structure column formwork (1), of the baffle (4), a ball (14) is connected in the rotating mode of one side, far away from the baffle (4), of the push plate (15), a support rod (13) is welded on one side, extending out of the push plate (15), of the support rod (13), a screw rod (5) in threaded connection with the pouring plate (3) is welded on one end, far away from the support rod (13), and the rocking handle is made of waste steel bars.
2. A constructional column concrete casting template as defined in claim 1 wherein: baffle (4) bottom fixedly connected with connecting axle (7), connecting axle (7) inner wall rotates and is connected with and pours pivot (8) of board (3) inner wall fixed mounting.
3. A constructional column concrete casting template as defined in claim 1 wherein: pour board (3) bottom inner wall through iron nail fixed mounting have with connecting axle (7) rotate packing block (9) of being connected, first arc recess has been seted up at packing block (9) top, and first arc recess and connecting axle (7) looks adaptation, pour board (3) inner wall and seted up second arc recess, and second arc recess and connecting axle (7) looks adaptation.
4. A constructional column concrete casting template as defined in claim 1 wherein: pour board (3) both sides and install symmetric distribution's fixed plate (10) through the iron nail, and fixed plate (10) are fixed through the iron nail with constructional column template (1), and are two sets of one side below that fixed plate (10) are close to each other is installed and is pour mounting panel (6) of board (3) butt.
5. A constructional column concrete casting template as defined in claim 4 wherein: the mounting panel (6) top is provided with the inclined plane, and the inclined plane gradient is the same with the gradient of pouring board (3) hypotenuse, the inclined plane at mounting panel (6) top with pour board (3) butt, mounting panel (6) are fixed through the iron nail with constructional column template (1).
6. A constructional column concrete casting template as defined in claim 4 wherein: mounting panel (6) both sides are provided with fixture block (12) of symmetric distribution through the cutting, one side that fixed plate (10) are close to mounting panel (6) seted up with draw-in groove (11), and draw-in groove (11) and fixture block (12) looks adaptation.
CN202020462422.1U 2020-04-02 2020-04-02 Constructional column concrete casting template Active CN211850832U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020462422.1U CN211850832U (en) 2020-04-02 2020-04-02 Constructional column concrete casting template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020462422.1U CN211850832U (en) 2020-04-02 2020-04-02 Constructional column concrete casting template

Publications (1)

Publication Number Publication Date
CN211850832U true CN211850832U (en) 2020-11-03

Family

ID=73144631

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020462422.1U Active CN211850832U (en) 2020-04-02 2020-04-02 Constructional column concrete casting template

Country Status (1)

Country Link
CN (1) CN211850832U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117325282A (en) * 2023-11-30 2024-01-02 山西一建集团有限公司 Bearing wall pouring forming device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117325282A (en) * 2023-11-30 2024-01-02 山西一建集团有限公司 Bearing wall pouring forming device
CN117325282B (en) * 2023-11-30 2024-03-12 山西一建集团有限公司 Bearing wall pouring forming device

Similar Documents

Publication Publication Date Title
CN108908662B (en) Chiseling-free construction mold for prefabricated hollow slab beam
CN211850832U (en) Constructional column concrete casting template
CN109024987A (en) Construction method is poured after a kind of toilet shear wall
CN214144112U (en) Accurate positioning and connecting device for beam column PC component
CN212534738U (en) Truss floor plate
CN112049454B (en) Concrete floor structure with foam concrete
CN211974330U (en) Combined building pouring template for constructional engineering
CN108979145B (en) Template assembly structure with aluminum die assembly
CN208702139U (en) A kind of construction template structure of toilet wall
CN214656398U (en) Cast-in-place beam box template fixing device
CN110725542A (en) Concrete building aluminum formwork structure installation system and construction method
CN218875852U (en) Processing device for prestressed laminated slab
CN216658365U (en) Roofing splayed corner prefabricate design mould
CN206233578U (en) Inner corner trim reinforcing template and its formwork system
CN214272907U (en) Shear wall root reinforcing and plugging mechanism
CN215168091U (en) Bracing fixed knot constructs and aluminum alloy template bracing device
CN217840867U (en) Steel form for construction of constructional column at junction of longitudinal and transverse walls of house
CN214739885U (en) Constructional column pouring mold
CN214925372U (en) Girder mould
CN215630964U (en) Precast concrete superimposed sheet
CN217000864U (en) Secondary structure constructional column formwork supporting dustpan opening device
CN219772730U (en) Double-column pier climbing formwork inner side template
CN219952769U (en) Multifunctional building ash shovel device
CN220840824U (en) Prestressed concrete goose-shaped roof plate mould system
CN215212327U (en) Sandwich plate supports pole setting base device with adjustable angle

Legal Events

Date Code Title Description
GR01 Patent grant