CN211815597U - Fixing sleeve for bridge engineering cable - Google Patents

Fixing sleeve for bridge engineering cable Download PDF

Info

Publication number
CN211815597U
CN211815597U CN202020193275.2U CN202020193275U CN211815597U CN 211815597 U CN211815597 U CN 211815597U CN 202020193275 U CN202020193275 U CN 202020193275U CN 211815597 U CN211815597 U CN 211815597U
Authority
CN
China
Prior art keywords
wall
connecting block
clamp
cable
screw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020193275.2U
Other languages
Chinese (zh)
Inventor
张伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020193275.2U priority Critical patent/CN211815597U/en
Application granted granted Critical
Publication of CN211815597U publication Critical patent/CN211815597U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a bridge engineering is fixed sleeve pipe for cable, including bridge body, cable body, ground tackle body and clamp, the double-screw bolt is installed to bridge body upper end outer wall one side, double-screw bolt one side outer wall is provided with the connecting block, first screw has been seted up to connecting block lower extreme outer wall one side, double-screw bolt one side outer wall is provided with the stopper, the spacing groove has been seted up to connecting block upper end outer wall one side, the connecting block runs through spacing groove one side outer wall and installs ground tackle body, ground tackle body upper end outer wall one side is provided with the cable body, the sleeve pipe body has been cup jointed to cable body one side outer wall, sleeve pipe body one side outer wall is provided with the clamp, the clamp deviates from sleeve. The utility model discloses a set up connecting block, stopper and ground tackle body, reached the effect of being convenient for install the cable body, improved cable body installation effectiveness, improved the equipment practicality.

Description

Fixing sleeve for bridge engineering cable
Technical Field
The utility model relates to a sleeve pipe technical field specifically is a bridge engineering is fixed sleeve pipe for cable.
Background
Bridge engineering refers to the working process of bridge surveying, designing, constructing, maintaining, detecting and the like, and the science and engineering technology for researching the process, and is a branch of civil engineering, a cable is a main bearing structure of a suspension bridge, a cable-stayed bridge and an arch suspension bridge, and in the prior art, in order to ensure the safety of the bridge and the cable structure, the cable needs to be subjected to anticorrosion protection.
Through the massive search, the typical sleeve pipe for bridge cables disclosed as CN204151680U of publication number of the puncture positioning device in the prior art is found, the landscape effect of the cable bridge is effectively improved, meanwhile, the cable is protected, the structure is economical and simple, the assembly and disassembly are convenient, and the cable is easy to overhaul and maintain.
Traditional cable body protects through the sleeve pipe body, avoids the cable body to receive rainwater erosion, improves the life of cable body, and nevertheless cable body installation steps are comparatively complicated, and the installation effectiveness is lower, and sleeve pipe body mounting structure stability is not enough.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a bridge engineering is fixed sleeve for cable possesses the advantage that improves the installation effectiveness and improve sleeve pipe body mounting structure stability, has solved the lower and unstable problem of sleeve pipe body mounting structure of installation effectiveness.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a bridge engineering is fixed sleeve pipe for cable, includes bridge body, cable body, ground tackle body and clamp, the double-screw bolt is installed to bridge body upper end outer wall one side, double-screw bolt one side outer wall is provided with the connecting block, double-screw bolt one side outer wall is provided with the stopper, the spacing groove has been seted up to connecting block upper end outer wall one side, the connecting block runs through spacing groove one side outer wall and installs the ground tackle body, ground tackle body upper end outer wall one side is provided with the cable body, cable body one side outer wall has cup jointed the sleeve pipe body, sleeve pipe body one side outer wall is provided with the clamp, the clamp deviates from sleeve pipe body.
Preferably, a first screw hole is formed in one side of the outer wall of the lower end of the connecting block, and the connecting block is meshed with the stud through the first screw hole.
Preferably, a rubber pad is fixed on one side of the outer wall of the upper end of the limiting block in a laminating manner, and the outer wall of the upper end of the rubber pad is connected with the upper end of the inner wall of the connecting block.
Preferably, a nut is installed on the outer wall of one side of the connecting block.
Preferably, the supporting shoe deviates from clamp one side outer wall and has seted up the second screw, the inside threaded connection of second screw has the bolt, the bolt runs through second screw one end outer wall and the clamp department of meeting.
Preferably, the clamp deviates from one section of outer wall of the supporting block and is arranged inside the supporting block, and the clamp is sleeved outside the sleeve body.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model discloses a set up the connecting block, stopper and ground tackle body, the effect of being convenient for install the cable body has been reached, during the installation, through the manual connecting block of taking, and place in the double-screw bolt upper end, the manual spanner that takes of staff rotates the nut, the connecting block is followed and is rotated, and mesh mutually through first screw and double-screw bolt, when relative movement takes place for the connecting block, the purpose of extrusion stopper has been reached, guarantee inside the stopper controlled position connecting block, and guaranteed cable body installation stability through the meshing force, cable body installation efficiency has been improved, the equipment practicality has been improved.
2. The utility model discloses a set up supporting shoe, bolt and clamp, reached the effect of fixed sleeving body, the manual clamp of taking of staff to make the clamp cup joint with the sleeve pipe body outside, the clamp has reached the purpose of fixed sleeving body, the manual spanner of taking of staff rotates the bolt, the bolt takes place relative movement through the second screw, when the bolt contacts with the inside clamp of supporting shoe, has reached the purpose of fixed clamp, has guaranteed clamp job stabilization nature, has improved the equipment practicality.
Drawings
Fig. 1 is a schematic view of the structure of the present invention;
fig. 2 is a schematic top view of the cable body structure of the present invention;
fig. 3 is an enlarged schematic view of the structure a in fig. 2 according to the present invention.
In the figure: 1. a bridge body; 11. a stud; 12. connecting blocks; 13. a first screw hole; 14. a limiting block; 15. An anchor body; 16. a limiting groove; 17. a rubber pad; 18. a nut; 2. a cable body; 21. a sleeve body; 22. clamping a hoop; 23. a support block; 24. a second screw hole; 25. and (4) bolts.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1 to fig. 3, the present invention provides an embodiment: the utility model provides a bridge engineering is fixed sleeve pipe for cable, includes bridge body 1, cable body 2, ground tackle body 15 and clamp 22, and double-screw bolt 11 is installed to 1 upper end outer wall one side of bridge body, and 11 one side outer walls of double-screw bolt are provided with connecting block 12. The outer wall of one side of the connecting block 12 is provided with a nut 18. A first screw hole 13 is formed in one side of the outer wall of the lower end of the connecting block 12, and the connecting block 12 is meshed with the stud 11 through the first screw hole 13. The engagement force ensures the connection stability between the connecting block 12 and the stud 11. The outer wall of one side of the stud 11 is provided with a limiting block 14, one side of the outer wall of the upper end of the limiting block 14 is fixedly attached with a rubber pad 17, and the outer wall of the upper end of the rubber pad 17 is connected with the upper end of the inner wall of the connecting block 12. Rubber pad 17 has guaranteed the sealed purpose of spacing groove 16, avoids the rainwater to get into first screw 13 inside, avoids the inside phenomenon of rustting that takes place of first screw 13, has improved equipment utility life, has improved the equipment practicality. Limiting groove 16 is seted up to connecting block 12 upper end outer wall one side, and connecting block 12 runs through limiting groove 16 one side outer wall and installs ground tackle body 15. During the installation, through the manual connecting block 12 of taking to place in double-screw bolt 11 upper end, the manual spanner that takes of staff rotates nut 18, and connecting block 12 follows the rotation, and meshes with double-screw bolt 11 mutually through first screw 13, when connecting block 12 takes place relative movement, has reached the purpose of extrusion stopper 14, guarantees that stopper 14 is controlled to be located inside connecting block 12, and has guaranteed 2 installation stability of cable body through the engaging force, has improved 2 installation effectiveness of cable body, has improved the equipment practicality.
One side of the outer wall of the upper end of the anchorage device body 15 is provided with a cable body 2. The anchor body 15 achieves the purpose of connecting the cable bodies 2. The outer wall of one side of the cable body 2 is sleeved with a sleeve body 21, and the outer wall of one side of the sleeve body 21 is provided with a hoop 22. The clamp 22 achieves the purpose of fixing the sleeve body 21, and ensures the connection stability of the sleeve body 21 and the cable body 2. The outer wall of the clamp 22 at the side away from the sleeve body 21 is provided with a supporting block 23. The hoop 22 deviates from a section of outer wall of the supporting block 23 and is arranged inside the supporting block 23, and the hoop 22 is sleeved outside the sleeve body 21. The supporting shoe 23 deviates from clamp 22 one side outer wall and has seted up second screw 24, and the inside threaded connection of second screw 24 has bolt 25, and bolt 25 runs through second screw 24 one end outer wall and clamp 22 junction mutually. The manual clamp 22 of taking of staff to make clamp 22 cup joint with the sleeve pipe body 21 outside, clamp 22 has reached the purpose of fixed sleeve pipe body 21, the manual spanner that takes of staff rotates bolt 25, and bolt 25 takes place relative movement through second screw 24, when bolt 25 and the contact of the inside clamp 22 of supporting shoe 23, has reached the purpose of fixed clamp 22, has guaranteed clamp 22 job stabilization nature, has improved the equipment practicality.
The working principle is as follows: during the installation, through the manual connecting block 12 of taking to place in double-screw bolt 11 upper end, the manual spanner that takes of staff rotates nut 18, and connecting block 12 follows the rotation, and meshes with double-screw bolt 11 mutually through first screw 13, when connecting block 12 takes place relative movement, has reached the purpose of extrusion stopper 14, guarantees that stopper 14 is controlled to be located inside connecting block 12, and has guaranteed 2 installation stability of cable body through the engaging force, has improved 2 installation effectiveness of cable body, has improved the equipment practicality.
The manual clamp 22 of taking of staff to make clamp 22 cup joint with the sleeve pipe body 21 outside, clamp 22 has reached the purpose of fixed sleeve pipe body 21, the manual spanner that takes of staff rotates bolt 25, and relative movement takes place for bolt 25 through second screw 24, when bolt 25 and the contact of the inside clamp 22 of supporting shoe 23, has reached the purpose of fixed clamp 22, has guaranteed clamp 22 job stabilization nature, has improved the equipment practicality.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides a bridge engineering is fixed sleeve pipe for cable, includes bridge body (1), cable body (2), ground tackle body (15) and clamp (22), its characterized in that: double-screw bolt (11) are installed to bridge body (1) upper end outer wall one side, double-screw bolt (11) one side outer wall is provided with connecting block (12), double-screw bolt (11) one side outer wall is provided with stopper (14), spacing groove (16) have been seted up to connecting block (12) upper end outer wall one side, connecting block (12) run through spacing groove (16) one side outer wall and install ground tackle body (15), ground tackle body (15) upper end outer wall one side is provided with cable body (2), sleeve pipe body (21) have been cup jointed to cable body (2) one side outer wall, sleeve pipe body (21) one side outer wall is provided with clamp (22), clamp (22) deviate from sleeve pipe body (21) one side outer wall and install supporting shoe (23.
2. The fixing sleeve for the bridge engineering cable according to claim 1, wherein: first screw hole (13) have been seted up to connecting block (12) lower extreme outer wall one side, and connecting block (12) mesh mutually through first screw hole (13) and double-screw bolt (11).
3. The fixing sleeve for the bridge engineering cable according to claim 1, wherein: a rubber pad (17) is fixedly attached to one side of the outer wall of the upper end of the limiting block (14), and the outer wall of the upper end of the rubber pad (17) is connected with the upper end of the inner wall of the connecting block (12).
4. The fixing sleeve for the bridge engineering cable according to claim 1, wherein: and a nut (18) is arranged on the outer wall of one side of the connecting block (12).
5. The fixing sleeve for the bridge engineering cable according to claim 1, wherein: supporting shoe (23) deviate from clamp (22) one side outer wall and seted up second screw (24), second screw (24) internal thread is connected with bolt (25), bolt (25) run through second screw (24) one end outer wall and clamp (22) department of meeting.
6. The fixing sleeve for the bridge engineering cable according to claim 1, wherein: the clamp (22) deviates from one section of outer wall of the supporting block (23) and is arranged inside the supporting block (23), and the clamp (22) is sleeved outside the sleeve body (21).
CN202020193275.2U 2020-02-21 2020-02-21 Fixing sleeve for bridge engineering cable Expired - Fee Related CN211815597U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020193275.2U CN211815597U (en) 2020-02-21 2020-02-21 Fixing sleeve for bridge engineering cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020193275.2U CN211815597U (en) 2020-02-21 2020-02-21 Fixing sleeve for bridge engineering cable

Publications (1)

Publication Number Publication Date
CN211815597U true CN211815597U (en) 2020-10-30

Family

ID=72999070

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020193275.2U Expired - Fee Related CN211815597U (en) 2020-02-21 2020-02-21 Fixing sleeve for bridge engineering cable

Country Status (1)

Country Link
CN (1) CN211815597U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113216398A (en) * 2021-04-26 2021-08-06 北京建筑大学 T-shaped three-stay-rod cable dome structure and implementation method thereof
CN113324134A (en) * 2021-04-26 2021-08-31 广东竣崑建设有限公司 Beam slab levelness detection device for engineering construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113216398A (en) * 2021-04-26 2021-08-06 北京建筑大学 T-shaped three-stay-rod cable dome structure and implementation method thereof
CN113324134A (en) * 2021-04-26 2021-08-31 广东竣崑建设有限公司 Beam slab levelness detection device for engineering construction

Similar Documents

Publication Publication Date Title
CN211815597U (en) Fixing sleeve for bridge engineering cable
CN102304959A (en) Color steel roof panel clamp
CN102787597B (en) Multi-cable recyclable anchor cable head connecting device
CN213087522U (en) Civil engineering strutting arrangement
CN212614804U (en) Novel mining anchor rope of cavity slip casting
CN212316970U (en) Foundation pile with protective structure
CN220550462U (en) Corrugated steel concrete composite structure
CN217204548U (en) Protection architecture and drainage shaft
CN216689423U (en) Foundation pit supporting device convenient to install
CN217079513U (en) Dry-hanging stone pendant with adjustable
CN215368097U (en) Reverse-hanging honeycomb composite stone installation system
CN211151350U (en) Jumper splicing sleeve of overhead power transmission line
CN202644529U (en) Multi-cable recoverable anchor cable head connecting device
CN212715502U (en) Inclined hook head bolt and angle iron tie assembly
CN214033336U (en) High-efficient mounting structure of bridge steel construction
CN217999150U (en) Electric power iron tower base of adjustable installation
CN219888943U (en) Stable connection structure of municipal engineering water supply and drainage pipeline
CN214304715U (en) Parallel outer holding joint assembly
CN217000889U (en) Wisdom building site is with high formwork anti-collapse mechanism
CN214576215U (en) Standardized protection for near-edge opening
CN215807217U (en) Channel steel structure for anti-seismic support
CN215759779U (en) Wall connecting device
CN220954109U (en) Assembled building coincide module
CN217028899U (en) Assembling structure of prefabricated pipe jacking pipe joint
CN215253452U (en) Connection mounting structure for steel frame building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201030

CF01 Termination of patent right due to non-payment of annual fee