CN215253452U - Connection mounting structure for steel frame building - Google Patents

Connection mounting structure for steel frame building Download PDF

Info

Publication number
CN215253452U
CN215253452U CN202121814075.5U CN202121814075U CN215253452U CN 215253452 U CN215253452 U CN 215253452U CN 202121814075 U CN202121814075 U CN 202121814075U CN 215253452 U CN215253452 U CN 215253452U
Authority
CN
China
Prior art keywords
connecting pipe
steel frame
vice
pipe
fixing bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121814075.5U
Other languages
Chinese (zh)
Inventor
王月明
杨立勋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202121814075.5U priority Critical patent/CN215253452U/en
Application granted granted Critical
Publication of CN215253452U publication Critical patent/CN215253452U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The utility model discloses a steelframe building is with connecting mounting structure, including main connecting pipe, first vice connecting pipe, the vice connecting pipe of second, steelframe pipe, spacing dish, first gasket and first protection casing. The utility model has the advantages that: first pair connecting pipe, it is provided with the fixed orifices to run through on the vice connecting pipe of second, first fixing bolt runs through the fixed orifices, and it is connected with the nut to twist on first fixing bolt, make the staff can be with main connecting pipe and first pair connecting pipe as required, the whole length of connecting between the vice connecting pipe of second constitution carries out the regulation of certain degree, first pair connecting pipe, the lateral wall tail end of the vice connecting pipe of second is provided with the arc notch, run through in the notch and be provided with the fixed slot, binding clip is connected with the second gasket on the second fixing bolt, the second gasket is the arc and equals with the radian of arc notch, make the staff can be through bar fixed slot with steel frame pipe and first pair connecting pipe, the fixed length between the vice connecting pipe of second finely tunes.

Description

Connection mounting structure for steel frame building
Technical Field
The utility model relates to a connect mounting structure specifically is a steel frame building is with connecting mounting structure, belongs to and connects mounting structure technical field.
Background
The steel structure building is a neotype building system, and steel construction building compares traditional concrete building, has replaced reinforced concrete with steel sheet or shaped steel, and intensity is higher, and the shock resistance is better to because the component can batch production preparation, field erection, therefore the time limit for a project that significantly reduces, because in steel frame building, need use connection structure to connect the steel pipe and form a unified overall framework, consequently, then need a steel frame building with connecting mounting structure.
However, most of the existing connection mounting structures have various problems:
1) most of the existing connecting and mounting structures are not provided with telescopic connecting rods, so that the overall length between the steel pipe and the connecting structure cannot be adjusted to a certain degree according to needs;
2) the existing connection mounting structure is mostly not provided with a sealing structure, so that rainwater can flow into the mounting structure, and the inside corrosion of the mounting structure is damaged.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a connection mounting structure for steelframe building just lies in for the solution problem.
The utility model discloses a following technical scheme realizes above-mentioned purpose: a connection mounting structure for steel frame construction, comprising:
the connecting mechanism is composed of a main connecting pipe, a first auxiliary connecting pipe and a second auxiliary connecting pipe, a cylindrical cavity is arranged in the main connecting pipe in a penetrating mode, and the first auxiliary connecting pipe and the second auxiliary connecting pipe which are equal in outer diameter lamp and smaller than the cavity in the main connecting pipe are symmetrically connected and fixed at two ends of the main connecting pipe in a left-right mode;
and the fixing mechanism is composed of a first fixing bolt, the fixing mechanism is fixed on the connecting mechanism, and the first fixing bolt vertically penetrates through the connecting part of the main connecting pipe, the first auxiliary connecting pipe and the second auxiliary connecting pipe.
As a further aspect of the present invention: run through on first vice connecting pipe, the vice connecting pipe of second and be provided with the fixed orifices, the fixed orifices is the equidistance formula and is provided with six groups, and two upper and lower fixed orifices constitute a set of, and first fixing bolt runs through the fixed orifices to it is connected with the nut to twist on first fixing bolt.
As a further aspect of the present invention: the sealing plug is characterized in that steel frame pipes are connected in the inner cavities of the first auxiliary connecting pipe and the second auxiliary connecting pipe, first gaskets are filled in gaps among the steel frame pipes, the first auxiliary connecting pipe and the second auxiliary connecting pipe, and the sealing plug is connected in a fixing hole exposed in the external environment in a screwing mode.
As a further aspect of the present invention: the lateral wall tail end of first pair connecting pipe, the vice connecting pipe of second is provided with the arc notch, runs through in the notch and is provided with the fixed slot, is symmetrical formula setting from top to bottom in the fixed slot to vertical through connection has second fixing bolt in the fixed slot, and the binding clip is connected with the second gasket on the second fixing bolt, and the second gasket is the arc and equals with the radian of arc notch.
As a further aspect of the present invention: the tail end of first pair connecting pipe, the vice connecting pipe of second is fixed with the spacing dish, and all series connection has first protection casing on first pair connecting pipe, the vice connecting pipe of second, and series connection has the second protection casing on the steel frame pipe, and first protection casing, second protection casing are detachable to twist and twist the locking.
The utility model has the advantages that:
1) fixing holes are arranged on the first auxiliary connecting pipe and the second auxiliary connecting pipe in a penetrating manner, six groups of fixing holes are arranged in an equidistant manner, the upper fixing hole and the lower fixing hole form one group, the first fixing bolt penetrates through the fixing holes and is screwed and connected with a nut on the first fixing bolt, so that a worker can adjust the overall length formed by connecting the main connecting pipe with the first auxiliary connecting pipe and the second auxiliary connecting pipe to a certain degree according to needs;
2) arc-shaped notches are formed in the tail ends of the side walls of the first auxiliary connecting pipe and the second auxiliary connecting pipe, fixing grooves are formed in the notches in a penetrating mode, the upper portions and the lower portions of the fixing grooves are symmetrically arranged, a second fixing bolt is vertically connected in the fixing grooves in a penetrating mode, a second gasket is connected to a binding clip on the second fixing bolt, the second gasket is arc-shaped and equal to the radian of the arc-shaped notches, so that a worker can finely adjust the fixed length between the steel frame pipe and the first auxiliary connecting pipe and between the steel frame pipe and the second auxiliary connecting pipe through the strip-shaped fixing grooves, and the second fixing bolt is isolated from the first auxiliary connecting pipe and the second auxiliary connecting pipe through the second gasket, and the first auxiliary connecting pipe and the second auxiliary connecting pipe are prevented from being abraded when the second fixing bolt is screwed;
3) the inner cavities of the first auxiliary connecting pipe and the second auxiliary connecting pipe are connected with a steel frame pipe, a first gasket is filled in a gap between the steel frame pipe and the first auxiliary connecting pipe and between the steel frame pipe and the second auxiliary connecting pipe, a sealing plug is screwed and connected in a fixing hole exposed in the external environment, the inner cavities of the first auxiliary connecting pipe and the second auxiliary connecting pipe are isolated from the external environment, and rainwater is prevented from entering the cavities to cause corrosion damage inside the first auxiliary connecting pipe and the second auxiliary connecting pipe;
4) the tail end of first pair connecting pipe, the vice connecting pipe of second is fixed with the spacing dish, and all series connection has first protection casing on first pair connecting pipe, the vice connecting pipe of second, and series connection has the second protection casing on the steel frame pipe, and first protection casing, second protection casing are detachable to twist and twist the locking, twist soon through first protection casing, second protection casing and twist and connect and form a unified whole, make the junction between vice connecting pipe and the steel frame pipe can keep apart with external environment, prevent the junction corrosion.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a schematic view of the first protective cover and the second protective cover of the present invention;
fig. 3 is an enlarged schematic view of the auxiliary connecting pipe of the present invention.
In the figure: 1. the main connecting pipe, 2, first auxiliary connecting pipe, 3, the vice connecting pipe of second, 4, steel frame pipe, 5, spacing dish, 6, first gasket, 7, first protection casing, 8, second protection casing, 9, first fixing bolt, 10, fixed orifices, 11, sealing plug, 12, fixed slot, 13, second gasket and 14, second fixing bolt.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example one
Referring to fig. 1 to 3, a connecting and mounting structure for steel frame building includes:
the connecting mechanism is composed of a main connecting pipe 1, a first auxiliary connecting pipe 2 and a second auxiliary connecting pipe 3, a cylindrical cavity is arranged in the main connecting pipe 1 in a penetrating mode, and the first auxiliary connecting pipe 2 and the second auxiliary connecting pipe 3 which are equal to each other in outer diameter lamps and smaller than the cavity in the main connecting pipe 1 are connected and fixed at two ends of the main connecting pipe 1 in a left-right symmetrical mode;
and the fixing mechanism is composed of a first fixing bolt 9, the fixing mechanism is fixed on the connecting mechanism, and the first fixing bolt 9 vertically penetrates through the joint of the main connecting pipe 1 and the first auxiliary connecting pipe 2 and the second auxiliary connecting pipe 3.
The embodiment of the utility model provides an in, run through on first pair connecting pipe 2, the vice connecting pipe 3 of second and be provided with fixed orifices 10, fixed orifices 10 are the equidistance formula and are provided with six groups, and two upper and lower fixed orifices 10 constitute a set of, and first fixing bolt 9 runs through fixed orifices 10 to it is connected with the nut to twist on first fixing bolt 9, makes the staff can carry out the regulation of certain degree with the whole length of being connected the constitution between main connecting pipe 1 and first pair connecting pipe 2, the vice connecting pipe 3 of second as required.
In the embodiment of the present invention, the lateral wall tail end of the first pair of connecting pipes 2, the second pair of connecting pipes 3 is provided with an arc-shaped notch, a fixing groove 12 is penetratingly disposed in the notch, the fixing groove 12 is symmetrically disposed up and down, and a second fixing bolt 14 is vertically penetratingly connected to the fixing groove 12, a second gasket 13 is connected to a binding clip on the second fixing bolt 14, the second gasket 13 is arc-shaped and is equal to the arc of the arc-shaped notch, so that a worker can finely adjust the fixed length between the steel frame pipe 4 and the first pair of connecting pipes 2 through the bar-shaped fixing groove 12, and finely adjust the fixed length between the second pair of connecting pipes 3, and isolate the second fixing bolt 14 from the first pair of connecting pipes 2 and the second pair of connecting pipes 3 through the second gasket 13, thereby preventing the first pair of connecting pipes 2 and the second pair of connecting pipes 3 from being worn when the second fixing bolt 14 is rotated.
Example two
Referring to fig. 1 to 3, a connecting and mounting structure for steel frame building includes:
the connecting mechanism is composed of a main connecting pipe 1, a first auxiliary connecting pipe 2 and a second auxiliary connecting pipe 3, a cylindrical cavity is arranged in the main connecting pipe 1 in a penetrating mode, and the first auxiliary connecting pipe 2 and the second auxiliary connecting pipe 3 which are equal to each other in outer diameter lamps and smaller than the cavity in the main connecting pipe 1 are connected and fixed at two ends of the main connecting pipe 1 in a left-right symmetrical mode;
and the fixing mechanism is composed of a first fixing bolt 9, the fixing mechanism is fixed on the connecting mechanism, and the first fixing bolt 9 vertically penetrates through the joint of the main connecting pipe 1 and the first auxiliary connecting pipe 2 and the second auxiliary connecting pipe 3.
The embodiment of the utility model provides an in, be connected with steel frame pipe 4 in the inside cavity of first pair connecting pipe 2, the vice connecting pipe of second 3, steel frame pipe 4 and first pair connecting pipe 2, space department between the vice connecting pipe of second 3 fills has first gasket 6, it is connected with sealing plug 11 to twist in the fixed orifices 10 exposed in external environment soon, with first pair connecting pipe 2, the inside cavity and the external environment of the vice connecting pipe of second 3 keep apart, prevent that the rainwater from getting into in the cavity, cause first pair connecting pipe 2, the inside corrosion of the vice connecting pipe of second 3 damages.
In the embodiment of the present invention, the end of the first pair of connection pipes 2 and the second pair of connection pipes 3 is fixed with the limiting disc 5, and the first protective cover 7 is connected in series to the first pair of connection pipes 2 and the second pair of connection pipes 3, the second protective cover 8 is connected in series to the steel frame pipe 4, the first protective cover 7 and the second protective cover 8 are detachably screwed and locked, and the first protective cover 7 and the second protective cover 8 are screwed and connected to form a unified whole, so that the joint between the pair of connection pipes and the steel frame pipe 4 can be isolated from the external environment, and the joint is prevented from being corroded.
The working principle is as follows: when the connecting and mounting structure is used, the overall length between the first auxiliary connecting pipe 2 and the second auxiliary connecting pipe 3 and the main connecting pipe 1 is adjusted according to needs, the first fixing bolt 9 penetrates through the fixing hole 10 to be locked, then the fixing hole 10 exposed in the external environment is screwed and sealed through the sealing plug 11, then the steel frame pipe 4 is inserted into the inner cavities of the first auxiliary connecting pipe 2 and the second auxiliary connecting pipe 3, the steel frame pipe 4 is screwed and locked with the first auxiliary connecting pipe 2 and the second auxiliary connecting pipe 3 through the second fixing bolt 14, and finally the first protective cover 7 and the second protective cover 8 are screwed and butted with each other.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (5)

1. The utility model provides a connection mounting structure for steel frame building which characterized in that includes:
the connecting mechanism is composed of a main connecting pipe (1), a first auxiliary connecting pipe (2) and a second auxiliary connecting pipe (3), a cylindrical cavity is arranged in the main connecting pipe (1) in a penetrating mode, and the first auxiliary connecting pipe (2) and the second auxiliary connecting pipe (3) which are equal in outer diameter lamp and smaller than the cavity in the main connecting pipe (1) are connected and fixed at two ends of the main connecting pipe (1) in a left-right symmetrical mode;
the fixing mechanism is composed of a first fixing bolt (9), the fixing mechanism is fixed on the connecting mechanism, and the first fixing bolt (9) vertically penetrates through the connecting position of the main connecting pipe (1) and the first auxiliary connecting pipe (2) and the second auxiliary connecting pipe (3).
2. The connection and installation structure for the steel frame building according to claim 1, wherein: run through on first vice connecting pipe (2), the vice connecting pipe of second (3) and be provided with fixed orifices (10), fixed orifices (10) are the equidistance formula and are provided with six groups, and two upper and lower fixed orifices (10) constitute a set of, and fixed orifices (10) are run through in first fixing bolt (9) to it is connected with the nut to twist on first fixing bolt (9).
3. The connection and installation structure for steel frame construction according to claim 1 or 2, wherein: be connected with steel frame pipe (4) in the inside cavity of first vice connecting pipe (2), the vice connecting pipe of second (3), the space department between steel frame pipe (4) and first vice connecting pipe (2), the vice connecting pipe of second (3) is filled has first gasket (6), exposes in fixed orifices (10) of external environment and twists soon to be connected with sealing plug (11).
4. The connection and installation structure for the steel frame building according to claim 1, wherein: the lateral wall tail end of first pair connecting pipe (2), the vice connecting pipe of second (3) is provided with the arc notch, runs through in the notch and is provided with fixed slot (12), and fixed slot (12) are symmetrical formula setting from top to bottom to vertical through connection has second fixing bolt (14) in fixed slot (12), and the binding clip is connected with second gasket (13) on second fixing bolt (14), and second gasket (13) are the arc and equal with the radian of arc notch.
5. The connection and installation structure for the steel frame building according to claim 1, wherein: the tail end of first pair connecting pipe (2), the vice connecting pipe of second (3) is fixed with limiting disc (5), and all series connection has first protection casing (7) on first pair connecting pipe (2), the vice connecting pipe of second (3), and series connection has second protection casing (8) on steel frame pipe (4), and first protection casing (7), second protection casing (8) are detachable to twist and twist the locking.
CN202121814075.5U 2021-08-05 2021-08-05 Connection mounting structure for steel frame building Active CN215253452U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121814075.5U CN215253452U (en) 2021-08-05 2021-08-05 Connection mounting structure for steel frame building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121814075.5U CN215253452U (en) 2021-08-05 2021-08-05 Connection mounting structure for steel frame building

Publications (1)

Publication Number Publication Date
CN215253452U true CN215253452U (en) 2021-12-21

Family

ID=79496896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121814075.5U Active CN215253452U (en) 2021-08-05 2021-08-05 Connection mounting structure for steel frame building

Country Status (1)

Country Link
CN (1) CN215253452U (en)

Similar Documents

Publication Publication Date Title
CN209817101U (en) Novel square steel tube column beam connected node
CN210658937U (en) Wall structure of prefabricated building
CN215253452U (en) Connection mounting structure for steel frame building
CN210420908U (en) Highway assembled box culvert
CN112196585B (en) Anchor-shotcreting latticed shell supporting system for coal mine tunnel
CN211774645U (en) Assembled concrete building connection structure
CN210263402U (en) Arc single-layer latticed shell structure for large-scale steel structure building
CN211369314U (en) Building guardrail for civil engineering convenient to concatenation
CN201447769U (en) Cross type column beam
CN210737796U (en) Connection structure of prefabricated building
CN216475625U (en) Assembled heat preservation wall assembly structure
CN211080306U (en) Precast concrete piping lane
CN213952285U (en) U-shaped combined concrete prefabricated box culvert
CN211572259U (en) Grouting sleeve for grouting construction
CN218092197U (en) Novel connecting piece for reinforcing steel structure
CN211079892U (en) Safety protection blocking net for bridge
CN217735254U (en) High-efficient heat dissipation aluminum alloy ex-trusions
CN217517890U (en) Curtain wall structure with high installation accuracy
CN219796475U (en) Novel corrosion-resistant pipeline
CN215594365U (en) Node connecting structure of prefabricated concrete structure
CN214884506U (en) Three-net built-in composite heat insulation system
CN213329468U (en) Assembled building node with excellent anti-seismic performance
CN220050010U (en) Copper smelting integral casting heat preservation copper chute
CN213562331U (en) Shaft coupling shell convenient to dismantle