CN211775632U - Movable operating platform for roof structure - Google Patents

Movable operating platform for roof structure Download PDF

Info

Publication number
CN211775632U
CN211775632U CN202020103510.2U CN202020103510U CN211775632U CN 211775632 U CN211775632 U CN 211775632U CN 202020103510 U CN202020103510 U CN 202020103510U CN 211775632 U CN211775632 U CN 211775632U
Authority
CN
China
Prior art keywords
roof
flange plate
placing base
article placing
guide rails
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020103510.2U
Other languages
Chinese (zh)
Inventor
孙芃
曲龙
李一响
青治勇
石江林
张鑫
周洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202020103510.2U priority Critical patent/CN211775632U/en
Application granted granted Critical
Publication of CN211775632U publication Critical patent/CN211775632U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model provides a portable operation platform for roof structure, include: the article placing device comprises an article placing base, wherein two opposite ends of the article placing base are respectively provided with an upright post, the upright posts at the two ends of the article placing base oppositely extend to form a supporting arm, and the bottom of the supporting arm is provided with a first roller; the two guide rails are arranged below a cross beam of the roof, sliding grooves along the length direction of the guide rails are formed in the guide rails, and the first rollers at the two ends of the article placing base are arranged in the sliding grooves of the two guide rails in a sliding manner in a one-to-one correspondence manner; and the traction equipment comprises a guy cable and a guy cable rolling device, the guy cable rolling device is arranged on the guide rail, the first end of the guy cable is connected with the upright post, and the second end of the guy cable is connected with the guy cable rolling device. The utility model provides a when the room lid structure to the too high floor of headroom carries out high altitude construction operation, traditional high altitude construction operation measure has construction cycle length, problem with high costs.

Description

Movable operating platform for roof structure
Technical Field
The utility model relates to a construction technical field, concretely relates to portable operation platform for roof structure.
Background
In conventional construction works, high-altitude construction work is usually performed on floors with excessively high clearance, such as a courtyard, a hall, a commercial dome, a house roof, and the like, by taking measures such as scaffold erection, temporary support, and the like. However, the traditional measures have the problems of long construction period and high cost.
SUMMERY OF THE UTILITY MODEL
In order to overcome the defects in the prior art, a movable operating platform for a roof structure is provided so as to solve the problems of long construction period and high cost of the traditional overhead construction measures when the overhead construction work is carried out on the roof structure of a floor with too high clearance.
To achieve the above object, there is provided a mobile operation platform for a roof structure, comprising:
the article placing device comprises an article placing base, wherein two opposite ends of the article placing base are respectively provided with an upright post, the upright posts at the two ends of the article placing base oppositely extend to form a supporting arm, and the bottom of the supporting arm is provided with a first roller;
the two guide rails are arranged below a cross beam of the roof, sliding grooves along the length direction of the guide rails are formed in the guide rails, and the first rollers at the two ends of the article placing base are arranged in the sliding grooves of the two guide rails in a sliding manner in a one-to-one correspondence manner; and
traction equipment, including cable and roll cable device, roll cable device install in on the guide rail, the first end of cable connect in the stand, the second end of cable connect in roll cable device.
Furthermore, the roof is rectangular, the guide rail is arranged along the width direction of the roof, and the object placing base is arranged along the length direction of the roof.
Further, the outside at the edge of putting the thing base is connected with many cantilever beams, and keeping away from of many cantilever beams the one end of putting the thing base is connected with the connecting rod, it is equipped with the guardrail to erect on the connecting rod, the guardrail is located the below of guide rail.
Furthermore, a platform plate is paved on the object placing base and the plurality of cantilever beams.
Further, the crossbeam is shaped steel girder, the guide rail includes first web and first flange board, the upside of first web connect in shaped steel girder, first flange board connect in the downside of first web, the upper surface of first flange board forms the spout.
Furthermore, the roof is a concrete floor, the cross beam is a concrete beam, two sides of the concrete beam are respectively provided with a suspender, the top end of the suspender is connected to the floor, a supporting section steel spans below the concrete beam, the bottom end of the suspender is connected to the supporting section steel, and the guide rail is arranged at the bottom of the supporting section steel.
Further, the guide rail includes second flange plate, third flange plate and connect in the second flange plate with second web between the third flange plate, the second flange plate connect in the bottom of supporting shaped steel, the upper surface of third flange plate forms the spout.
Furthermore, a second roller is mounted on the end face of one end, far away from the upright post, of the supporting arm, and the second roller abuts against the second web.
The beneficial effects of the utility model reside in that, the utility model discloses a portable operation platform for roof structure through installing the guide rail in the crossbeam below of roof, will put the first gyro wheel on the stand at the both ends of thing base again and smoothly locate the spout, utilizes the pulling equipment pulling to put the thing base for put the thing base and stop in the construction station of treating of roof below. The utility model discloses a portable operation platform for room lid structure can be according to the size of job site building structure size at any time adjustment platform, can reduce the waste of material at a plurality of operating mode recycles of a plurality of projects to, the platform dismouting is convenient, the multiplex kind demand when satisfying high altitude construction.
Drawings
Fig. 1 is a schematic structural view of a mobile operation platform for a roof structure according to a first embodiment of the present invention.
Fig. 2 is a top view of a mobile operation platform for a roof structure according to a first embodiment of the present invention.
Fig. 3 is a schematic structural diagram of a column according to a first embodiment of the present invention.
Fig. 4 is a schematic structural view of a guide rail according to a first embodiment of the present invention.
Fig. 5 is a schematic structural view of a support arm according to a first embodiment of the present invention.
Fig. 6 is a schematic structural view of a guide rail according to a second embodiment of the present invention.
Detailed Description
The following description of the embodiments of the present invention is provided for illustrative purposes, and other advantages and effects of the present invention will be readily apparent to those skilled in the art from the disclosure herein. The present invention can also be implemented or applied through other different specific embodiments, and various details in the present specification can be modified or changed based on different viewpoints and applications without departing from the spirit of the present invention.
First embodiment
Fig. 1 is the utility model discloses a portable operation platform's for roof structure structural structure of first embodiment structural schematic diagram, fig. 2 are the utility model discloses a portable operation platform's for roof structure's for first embodiment plan view, fig. 3 are the utility model discloses the structural schematic diagram of the stand of first embodiment, fig. 4 are the utility model discloses the structural schematic diagram of the guide rail of first embodiment, fig. 5 are the utility model discloses the structural schematic diagram of the supporting arm of first embodiment.
Referring to fig. 1 to 5, the utility model provides a portable operation platform for roof structure, include: the article placing base 1, two guide rails 2 and traction equipment.
Specifically, two opposite ends of the placement base 1 are respectively provided with an upright post 11. Support arms 12 are formed to extend opposite to the vertical posts 11 at both ends of the placement base 1. The bottom of the support arm 12 is fitted with a first roller 13. The number of the guide rails is at least two. The two guide rails 2 are installed below the cross member 4 of the roof 3. The guide rail 2 is formed with a slide groove along the longitudinal direction of the guide rail 2. The first rollers 13 at the two ends of the article placing base 1 are arranged in the sliding grooves of the two guide rails 2 in a sliding manner in a one-to-one correspondence manner.
The traction equipment comprises a traction cable and a cable winding device. The rope winding device is mounted on the guide rail 2. The first end of the cable is connected to the upright post 11 and the second end of the cable is connected to the cable winder.
In this embodiment, the rope reeling device is a winch.
The utility model discloses a portable operation platform for roof structure through installing the guide rail in the crossbeam below of roof, will put the first gyro wheel on the stand at the both ends of thing base again and smoothly locate the spout, utilizes the pulling equipment pulling to put the thing base for put the thing base and stop in the waiting construction station of roof below. The utility model discloses a portable operation platform for room lid structure can be according to the size of job site building structure size at any time adjustment platform, can reduce the waste of material at a plurality of operating mode recycles of a plurality of projects to, the platform dismouting is convenient, the multiplex kind demand when satisfying high altitude construction.
The utility model discloses a portable operation platform for room lid structure installs and dismantles conveniently to be convenient for the transportation deposit, improved the conveying efficiency, reduced and deposited the area.
Specifically, roof 3 is the rectangle, and guide rail 2 sets up along the width direction of roof 3, puts thing base 1 and sets up along the length direction of roof 3. Furthermore, the length of the object placing base is matched with that of the roof. The operating space of constructors is provided through the storage base, the storage base is pulled to a station to be constructed by the aid of the pulling device, and the constructors can construct the roof structure at any position of the storage base.
In the present embodiment, a plurality of cantilever beams 15 are connected to the outside of the edge of the placement base 1 in order to further expand the operation space. A plurality of cantilever beams 15 are arranged along the edge of the object placing base at intervals. One end of the plurality of cantilever beams 15 far away from the article placing base 1 is connected with a connecting rod 16. A guardrail 17 is vertically arranged on the connecting rod 16. The guard rail 17 is located below the guide rail 2.
In this embodiment, be formed with the breach on the guardrail, constructor can put the thing base through this breach business turn over.
As a preferred embodiment, a platform plate is laid on the base 1 and the cantilever beams 15. In the drawings, the platform plate and the pulling device are shown.
In the present embodiment, the cross beam 4 is a steel section beam. The guide rail 2 comprises a first web 21 and a first flange plate 22. The upside of first web is connected in shaped steel girder steel. The first flange plate is connected to the underside of the first web. The upper surface of the first flange plate forms a chute.
Specifically, the section steel girder is I-shaped steel. The guide rail is inverted T-shaped steel. First web welded connection is in shaped steel girder steel bottom. The upper surface of the first flange plate 22 is connected with a track slot plate, and one side of the track slot plate, which is far away from the first web plate, is formed with a limiting raised edge to prevent the first roller from sliding out of the sliding groove. The limiting warping edge is arranged along the length direction of the first flange plate.
In order to improve the structural strength of the guide rail, the first web plate is positioned in the middle of the first flange plate, and a reinforcing plate is connected between one side of the first web plate, which is far away from the sliding chute, and the upper surface of the first flange plate; the bottom of shaped steel girder and the one side that is close to the spout of first web are connected in the backup pad to strengthen the anti side torsional strength of girder steel.
The storage base is of a steel frame structure and comprises a main beam and a secondary beam. The main beam and the secondary beam are both formed steel. The length of the main beam is 12100mm, and the length of the secondary beam is 1040 mm. Each upright post is connected with the guide rail through a supporting arm, and a bull-eye wheel assembly is arranged at the bottom of each supporting arm. The bull's eye wheel assembly includes first gyro wheel and second gyro wheel. The first idler wheel is a main bull's eye wheel, and the second idler wheel is an auxiliary bull's eye wheel. Each bull eye wheel component comprises a main bull eye wheel and an auxiliary bull eye wheel, the model of the main bull eye wheel is SP-60, and the movement of the storage base is realized; the auxiliary bull's eye wheel model is SP-30, and the contraposition thing base is spacing, guarantees to put the thing base and can not take place to derail in the removal process. Each pair of bull's eye wheel assemblies is disposed in a support arm.
The stand distributes in the four corners of putting the thing base to with put the thing base and pass through high strength bolt and connect, the length of stand is 1040 mm. The stand is erect and is located on the girder, is connected with the angle steel bracing between stand and the girder to consolidate.
In order to make the movement of the object placing base smoother and smoother, the end surface of one end of the supporting arm 12 far away from the upright post 11 is provided with a second roller 14. The second roller 14 abuts against the first web 21.
Second embodiment
The present embodiment is different from the first embodiment in that: the roof is a concrete floor 3 'and the cross beam is a concrete beam 4'. The mounting structures for mounting the guide rails below the cross member are different.
In this embodiment, as shown in fig. 6, the concrete beam 4 'is provided with hanger rods 31' on both sides thereof, respectively. The top end of the boom 31 'is connected to the floor 3'. Supporting section steel 41 ' is spanned below the concrete beam, and the bottom ends of the two suspension rods 31 ' are connected to the supporting section steel 41 '. The guide rail 2 is mounted to the bottom of the support section steel 41'.
In this embodiment, the guide rail comprises a second flange plate 21 ', a third flange plate 23 ', and a second web 22 ' connected between the second flange plate 21 ' and the third flange plate 23 '. The second flange plate 21 ' is connected to the bottom of the support section steel 41 ', and the upper surface of the third flange plate 23 ' forms a slide groove.
The end face of the end of the support arm 12 ' remote from the upright 11 ' is fitted with a second roller 14 which abuts against a second web 22 '.
In order to make the object placing base move more smoothly and smoothly, the end surface of one end of the supporting arm 12 'far away from the upright post 11' is provided with a second roller. The second roller abuts against the second web 22'.
In the concrete structure building, a supporting steel beam with the specification of H200mm multiplied by 10mm multiplied by 200mm is arranged above a concrete beam at intervals of 500mm on a concrete floor, a supporting section steel 4 'with the specification of H500mm multiplied by 200mm multiplied by 10mm multiplied by 16mm is hung below the corresponding position below the concrete beam, and a long screw rod with the diameter of 30mm penetrates through the concrete floor to connect the supporting steel beam with a flange of the supporting section steel 4'. The guide rail is welded on the supporting section steel 4 ', and the second flange plate 21 ' of the guide rail is connected with the lower flange of the supporting section steel 4 ' above by a high-strength bolt with the diameter of phi 30 mm. All the specifications of other parts, the specifications of the guide rail, the installation mode of the guide rail and the like are the same as those of the first embodiment under the working condition, and the connection modes of all the parts are all in bolt connection, so that the platform is convenient to disassemble and assemble, and the cyclic utilization of all the parts of the platform is realized.
It should be noted that the structure, ratio, size and the like shown in the drawings attached to the present specification are only used for matching with the content disclosed in the specification, so as to be known and read by those skilled in the art, and are not used for limiting the limit conditions that the present invention can be implemented, so that the present invention has no technical essential meaning, and any structure modification, ratio relationship change or size adjustment should still fall within the scope that the technical content disclosed in the present invention can cover without affecting the efficacy and the achievable purpose of the present invention. Meanwhile, the terms such as "upper", "lower", "left", "right", "middle" and "one" used in the present specification are for convenience of description, and are not intended to limit the scope of the present invention, and changes or adjustments of the relative relationship thereof may be made without substantial technical changes, and the present invention is also regarded as the scope of the present invention.
The present invention has been described in detail with reference to the embodiments shown in the drawings, and those skilled in the art can make various modifications to the present invention based on the above description. Therefore, certain details of the embodiments should not be construed as limitations of the present invention, which are intended to be limited only by the scope of the appended claims.

Claims (8)

1. A mobile operations platform for roof structures, comprising:
the article placing device comprises an article placing base, wherein two opposite ends of the article placing base are respectively provided with an upright post, the upright posts at the two ends of the article placing base oppositely extend to form a supporting arm, and the bottom of the supporting arm is provided with a first roller;
the two guide rails are arranged below a cross beam of the roof, sliding grooves along the length direction of the guide rails are formed in the guide rails, and the first rollers at the two ends of the article placing base are arranged in the sliding grooves of the two guide rails in a sliding manner in a one-to-one correspondence manner; and
traction equipment, including cable and roll cable device, roll cable device install in on the guide rail, the first end of cable connect in the stand, the second end of cable connect in roll cable device.
2. The mobile operator platform for a roof structure of claim 1, wherein said roof is rectangular, said rail is disposed along a width direction of said roof, and said storage base is disposed along a length direction of said roof.
3. The movable operating platform for a roof structure as recited in claim 1, wherein a plurality of cantilever beams are connected to the outer side of the edge of the object placing base, one ends of the plurality of cantilever beams, which are far away from the object placing base, are connected with connecting rods, guard rails are vertically arranged on the connecting rods, and the guard rails are located below the guide rails.
4. The mobile operations platform for roof structures of claim 3, wherein platform plates are paved on the object placing base and the plurality of cantilever beams.
5. The mobile operator platform for a roof structure of claim 1, wherein said cross beam is a steel section beam, said guide rail comprises a first web and a first flange plate, an upper side of said first web is connected to said steel section beam, said first flange plate is connected to a lower side of said first web, and an upper surface of said first flange plate forms said sliding groove.
6. The mobile operation platform for a roof structure of claim 1, wherein the roof is a concrete floor, the cross beam is a concrete beam, suspension rods are respectively arranged on two sides of the concrete beam, the top ends of the suspension rods are connected to the floor, a supporting section steel spans under the concrete beam, the bottom ends of the suspension rods are connected to the supporting section steel, and the guide rail is mounted at the bottom of the supporting section steel.
7. The mobile operator platform for a roof structure of claim 6, wherein the rail comprises a second flange plate, a third flange plate, and a second web connected between the second flange plate and the third flange plate, the second flange plate being connected to a bottom of the supporting section steel, an upper surface of the third flange plate forming the runner.
8. A mobile operator platform for a roof structure according to claim 7, wherein the end face of the end of the support arm remote from the uprights is fitted with a second roller which abuts against the second web.
CN202020103510.2U 2020-01-17 2020-01-17 Movable operating platform for roof structure Active CN211775632U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020103510.2U CN211775632U (en) 2020-01-17 2020-01-17 Movable operating platform for roof structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020103510.2U CN211775632U (en) 2020-01-17 2020-01-17 Movable operating platform for roof structure

Publications (1)

Publication Number Publication Date
CN211775632U true CN211775632U (en) 2020-10-27

Family

ID=72893871

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020103510.2U Active CN211775632U (en) 2020-01-17 2020-01-17 Movable operating platform for roof structure

Country Status (1)

Country Link
CN (1) CN211775632U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236610A (en) * 2020-01-17 2020-06-05 中国建筑第八工程局有限公司 Lower hanging type mobile operation platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236610A (en) * 2020-01-17 2020-06-05 中国建筑第八工程局有限公司 Lower hanging type mobile operation platform

Similar Documents

Publication Publication Date Title
CN108729354B (en) Downstream bridge movable formwork and construction method thereof
CN107447973B (en) Unilateral suspension type air mobile steel platform
CN111236610A (en) Lower hanging type mobile operation platform
CN211775632U (en) Movable operating platform for roof structure
CN204139569U (en) Sliding scaffold
CN210216163U (en) Self-supporting cantilever formwork support system
KR20110014341A (en) Tower ctane wall bracing with a safety fence
CN102815606B (en) Device for realizing operation of mobile tower crane on structural floor and construction method
CN204754160U (en) Rail mounted removes work platform
CN112252741A (en) Full-rail crane for super high-rise unit curtain wall and installation and use method thereof
CN206554524U (en) A kind of construction discharging platform
CN210439081U (en) Magnetic suspension type platform
CN203257106U (en) Multifunctional power-driven walking type walking system
CN213356779U (en) Overweight steel column translation transportation installation device
JPH06272389A (en) Temporary unloading stage
CN212101770U (en) Double-rail device convenient to install and detach quickly and used for hoisting curtain wall unit plate
CN210794552U (en) Net rack color steel plate profiling rapid conveying device
CN108545621A (en) A kind of precast stand slab hanging apparatus
CN212532065U (en) Gantry crane capable of being used in different height difference places
CN212151231U (en) A general protection platform of floor for construction elevator
CN211890720U (en) Support frame for mounting corrugated plate
CN108755419B (en) Construction platform for hoisting bridge shock-proof steel stop block and installation method
CN211711873U (en) Rail mounted is used for hoist and mount traction system of transportation
JP2007247301A (en) Construction system for scaffolding
CN215714661U (en) Device for installing steel truss girder cable carrying channel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant