CN211774575U - Assembled core tube structure - Google Patents

Assembled core tube structure Download PDF

Info

Publication number
CN211774575U
CN211774575U CN201922216272.6U CN201922216272U CN211774575U CN 211774575 U CN211774575 U CN 211774575U CN 201922216272 U CN201922216272 U CN 201922216272U CN 211774575 U CN211774575 U CN 211774575U
Authority
CN
China
Prior art keywords
core tube
cast
sleeves
shear walls
glue injection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922216272.6U
Other languages
Chinese (zh)
Inventor
程美涛
徐巍
许梦雅
臧海宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201922216272.6U priority Critical patent/CN211774575U/en
Application granted granted Critical
Publication of CN211774575U publication Critical patent/CN211774575U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to an assembled core section of thick bamboo structure. The assembled core tube structure comprises a plurality of core tube units which are sequentially stacked, and each core tube unit comprises four shear walls, edge members, grouting sleeves and glue injection sleeves. The shear walls are sequentially and adjacently arranged to form a cylindrical structure, and the edge members are filled between the shear walls; the grouting sleeves are arranged on the shear walls, and the shear walls of the adjacent core tube units are connected through the grouting sleeves; the glue injection sleeve is arranged on the edge component, and the edge components of the adjacent core tube units are connected through the glue injection sleeve. The prefabricated core tube structure is high in prefabrication rate and convenient to manufacture, and construction quality is guaranteed at the same time.

Description

Assembled core tube structure
Technical Field
The utility model relates to an assembly type structure field especially relates to an assembled core section of thick bamboo structure.
Background
For the increasingly developed building market in China, the defects of a cast-in-place structure system tend to be obvious. In the face of these problems, the success experience of the building industrialization in foreign countries is combined, and the wave of the assembly type building industrialization is lifted in the building industry in China, so that the development of the assembly type building industrialization enters a brand-new era, and the great change of the production mode in the building field is promoted.
The fabricated building is a building which is formed by transferring a large amount of field operation work in the traditional construction mode to a factory, processing and manufacturing building components and accessories (such as floor slabs, wall slabs, stairs, balconies and the like) in the factory, transporting the components and accessories to a building construction site, and assembling and installing the components and the accessories on the site in a reliable connection mode. The prefabricated building mainly comprises a prefabricated concrete structure, a steel structure, a modern wood structure building and the like, and is a representative of a modern industrial production mode due to the adoption of standardized design, factory production, assembly construction, informatization management and intelligent application.
However, as the prefabricated building is developed vigorously, the requirements for the prefabricated rate of the single body are continuously increased, the prefabricated edge components are complicated in deepened design, the factory manufacturing is troublesome, and the field installation is difficult. Therefore, in order to improve the monomer prefabrication rate, facilitate factory manufacturing and ensure the construction quality, the design of an assembled sleeve connection core tube structure system has become a technical problem to be solved urgently in the industry.
SUMMERY OF THE UTILITY MODEL
In view of the above, there is a need to provide an assembled core tube structure with high monomer prefabrication rate, convenient manufacturing and guaranteed construction quality.
An assembled core barrel structure comprising a plurality of sequentially stacked core barrel units, the core barrel units comprising:
the four shear walls are sequentially and adjacently arranged to form a cylindrical structure;
the edge members are filled between the shear walls;
the grouting sleeves are arranged on the shear walls, and the shear walls of the adjacent core tube units are connected through the grouting sleeves;
and the glue injection sleeves are arranged on the edge components, and the edge components of the adjacent core tube units are connected through the glue injection sleeves.
In one embodiment, the edge member comprises a precast segment and a cast in place segment, the cast in place segment being located at both ends of the precast segment.
In one embodiment, the number of the cast-in-place sections is two, the glue injection sleeve is arranged in one cast-in-place section, and the connecting steel bar is arranged in the other cast-in-place section.
In one embodiment, a corner region is formed between adjacent shear walls, and the edge member is located in the corner region and matches the shape of the corner region.
In one embodiment, an inner formwork is arranged on the side surface of the cast-in-place section, which is close to the cylindrical structure.
In one embodiment, an external formwork is arranged on the side surface of the cast-in-place section, which is far away from the cylindrical structure.
In one embodiment, the shear wall is further provided with a plurality of embedded steel bars, and the embedded steel bars and the grouting sleeves are respectively located at two opposite ends of the shear wall.
In one embodiment, the location of the embedded steel bars on the shear wall corresponds to the location of the grout sleeve on the shear wall.
In one embodiment, the number of the grouting sleeves is multiple, and the grouting sleeves are uniformly arranged along the length direction of the shear wall.
Above-mentioned assembled core section of thick bamboo structure, shear force wall can be whole prefabricated to realize the connection of shear force wall in the core section of thick bamboo unit from top to bottom through grout sleeve, edge component passes through the connection of edge component in the core section of thick bamboo unit from top to bottom of injecting glue sleeve realization. Compared with the traditional shear wall, the four shear walls of the assembled core tube structure can be integrally prefabricated on site and then directly hoisted, so that the prefabrication rate and the construction speed of an assembled building are improved. In addition, the edge members are connected through the glue injection sleeve, so that the connection of the shear walls in the adjacent core tube units and the connection of the edge members can be completed at one time, and the construction efficiency is improved. Therefore, the prefabricated core tube structure is high in prefabrication rate and convenient to manufacture, and construction quality is guaranteed at the same time.
Drawings
FIG. 1 is a formal diagram of a core barrel unit of an assembled core barrel structure of an embodiment;
FIG. 2 is a cross-sectional view A-A of the fabricated core barrel construction of FIG. 1;
fig. 3 is a B-B sectional view of the fabricated core barrel structure shown in fig. 1.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
The utility model discloses an assembled core section of thick bamboo structure specially adapted has the frame construction or the core section of thick bamboo structure of elevator, will combine the attached drawing to carry out the detailed description to the present case below.
As shown in fig. 1 to 3, the fabricated core tube structure of an embodiment includes a plurality of core tube units 1 stacked in sequence, and the core tube units 1 include four shear walls 10, edge members 20, grouting sleeves 12, and glue injection sleeves 22. The shear walls 10 are sequentially and adjacently arranged to form a cylindrical structure, and the edge members 20 are filled between the shear walls 10; the grouting sleeves 12 are arranged on the shear walls 10, and the shear walls 10 of the adjacent core barrel units 1 are connected through the grouting sleeves 12; the glue injection sleeve 22 is disposed on the edge member 20, and the edge members 20 of the adjacent core barrel units 1 are connected through the glue injection sleeve 22.
According to the needs of construction, assembled core section of thick bamboo structure can set to different heights, generally, core section of thick bamboo structure can include a plurality of core section of thick bamboo units 1, with a plurality of core section of thick bamboo units 1 from the bottom up range upon range of formation core section of thick bamboo structure in proper order. For ease of illustration, fig. 1 shows only one core barrel unit 1.
As shown in fig. 2 and 3, the core tube unit 1 includes four shear walls 10, and the four shear walls 10 are sequentially arranged adjacently to form a tube-shaped structure. As shown in fig. 1, the shear wall 10 includes first and second oppositely disposed ends. Wherein, the first end is provided with embedded steel bar 14, and the second end is provided with grout sleeve 12. When the upper and lower core tube units 1 are assembled, the embedded steel bars 14 of the upper core tube unit 1 can be inserted into the grouting sleeve 12 of the lower core tube unit 1. And then grouting material is injected into the grouting sleeve 12, and when the grouting material is solidified, the connection of the upper core barrel unit 1 and the lower core barrel unit 1 is realized. The shear wall 10 is connected by the grouting sleeve 12, construction is simple and convenient, and no additional formwork is required on site.
In the present embodiment, the number of the grouting sleeves 12 is plural, and the plural grouting sleeves 12 are arranged along the length direction of the shear wall 10. Correspondingly, the number of the embedded steel bars 14 is also multiple, and the embedded steel bars 14 and the grouting sleeves 12 are respectively located at two opposite ends of the shear wall 10. The embedded steel bars 14 and the grouting sleeves 12 are used for connecting adjacent core tube units 1, and the embedded steel bars and the grouting sleeves correspond to each other in arrangement positions on the shear wall 10, so that the core tube units 1 can be conveniently assembled, and the construction efficiency is improved.
With continued reference to fig. 1 and 2, the shear wall 10 is shaped like a rectangular parallelepiped, and four shear walls 10 are disposed adjacent to each other in sequence to form a cavity shaped like a rectangular parallelepiped. Because the shear walls 10 have a certain thickness, an included angle region exists between the adjacent shear walls 10. Correspondingly, in the present embodiment, the number of the corner regions is 4. The edge member 20 is located in the angled region and matches the shape of the angled region to ensure the integrity of the appearance of the core barrel unit 1. In the present embodiment, the edge member 20 has an L-shape, and two side edges thereof are respectively used for connecting with the adjacent shear walls 10.
In this embodiment, the edge member 20 includes a prefabricated section 200 and a cast-in-place section 202, the cast-in-place section 202 is located at two ends of the prefabricated section 200, and the glue injection sleeve 22 is disposed on the cast-in-place section 202. The number of cast-in-place sections 202 is two, and the two cast-in-place sections 202 are respectively located at two opposite ends of the prefabricated section 200. During actual construction, the precast segment 200 can be precast, and the cast-in-place segment 202 is a post-cast area. After the shear walls 10 of the upper core tube unit 1 and the lower core tube unit 1 are assembled, the prefabricated sections 200 of the edge members 20 are arranged in the included angle area, then cast-in-situ sections 202 of the edge members 20 are formed by casting, the glue injection sleeves 22 and the reserved steel bars 24 are respectively arranged on the two cast-in-situ sections 202, then the reserved steel bars 24 of the upper core tube unit 1 are inserted into the glue injection sleeves 22 of the lower core tube unit 1, and the connection of the edge members 20 is completed. Wherein, the reserved steel bar 24 and the glue injection sleeve 22 are cast in situ in the cast-in-place section 202 and are formed at one time.
The connection mode of the reserved steel bars 24 of the cast-in-place section 202 of the edge member 20 is the connection mode of the glue injection sleeve 22. The glue injection sleeve 22 differs from the grout sleeve 12 by: (1) the glue injection space is small, the steel bars with the same diameter are connected, and the outer diameter of the glue injection sleeve 22 is smaller than that of the grouting sleeve 12. (2) The glue injection sleeve 22 has only one grouting opening, and the slurry is discharged from two ends of the glue injection sleeve 22. (3) Resin sizing material is used to replace grouting material.
As shown in FIG. 2, in this embodiment, an interior formwork 30 is provided in the cast-in-place section 202 adjacent to the side of the tubular structure. Because the cast-in-place section 202 is fabricated in situ, the inner mold shell 30 may function as a formwork. Further, in this embodiment, the cast-in-place section 202 is provided with an external formwork on the side far away from the tubular structure. Likewise, the outer mold shell may also function as a template. Wherein the inner mold shell 30 and the outer mold shell are set before the cast-in-place section 202 is poured. In other embodiments, no exterior form can be provided when used for transverse connection of the core tubular structural edge members 20.
Compared with the traditional shear wall 10, the assembled core tube structure can be integrally prefabricated, can be directly hoisted on site, and has the construction speed improved by more than three times. Meanwhile, the edge members 20 are connected by the glue injection sleeves 22, so that the construction method is optimized, the construction period is shortened, 50% of labor cost can be saved, the connection of the steel bars in the cast-in-place area and the pouring of concrete are completed at one time, and the construction efficiency is improved. Therefore, the assembled core tube structure can improve the monomer prefabrication rate, can also enable the site to be less in modeling and free of modeling, can save 50% of labor cost and 40% of construction period, reduces the collision of reinforcing steel bars at nodes, is convenient for site construction, improves the construction efficiency and ensures the construction quality.
An application and construction method of the fabricated core tube structure will be described below, and the application and construction method of the fabricated core tube structure includes the following steps:
step one, prefabricating the shear wall 10 integrally to form a cylindrical structure, wherein the shear wall 10 is provided with a grouting sleeve 12. Four shear walls 10 are sequentially arranged adjacently to form a cylindrical structure, and the upper core barrel unit 1 and the lower core barrel unit 1 are connected through a grouting sleeve 12.
Step two, prefabricating edge members 20, and filling the edge members 20 between the shear walls 10 to form a core tube unit 1; wherein the edge member 20 is provided with a glue injection sleeve 22. The edge members 20 comprise prefabricated sections 200 and cast-in-place sections 202, the cast-in-place sections 202 are respectively located at two opposite ends of the prefabricated sections 200, the glue injection sleeves 22 are arranged on the cast-in-place sections 202, and the edge members 20 of the upper core barrel unit 1 and the lower core barrel unit 1 are connected through the glue injection sleeves 22.
And step three, laminating the core tube units 1, connecting the upper shear wall 10 and the lower shear wall 10 through the grouting sleeve 12, and connecting the upper edge member 20 and the lower edge member 20 through the glue injection sleeve 22. The connection between the upper and lower adjacent core tube units 1 is completed through the grouting sleeve 12 and the glue injection sleeve 22.
And fourthly, injecting grouting material into the grouting sleeve 12 and injecting glue stock into the glue injection sleeve 22 to finish the construction of the assembled core tube structure.
The application construction method of the assembled core tube structure is simple in steps, convenient for field construction, beneficial to improving the construction efficiency and capable of guaranteeing the construction quality.
The technical features of the embodiments described above may be arbitrarily combined, and for the sake of brevity, all possible combinations of the technical features in the embodiments described above are not described, but should be considered as being within the scope of the present specification as long as there is no contradiction between the combinations of the technical features.
The above-mentioned embodiments only represent some embodiments of the present invention, and the description thereof is specific and detailed, but not to be construed as limiting the scope of the present invention. It should be noted that, for those skilled in the art, without departing from the spirit of the present invention, several variations and modifications can be made, which are within the scope of the present invention. Therefore, the protection scope of the present invention should be subject to the appended claims.

Claims (9)

1. An assembled core tube structure, characterized in that core tube structure includes a plurality of core tube units that stack up in proper order, core tube unit includes:
the four shear walls are sequentially and adjacently arranged to form a cylindrical structure;
the edge members are filled between the shear walls;
the grouting sleeves are arranged on the shear walls, and the shear walls of the adjacent core tube units are connected through the grouting sleeves;
and the glue injection sleeves are arranged on the edge components, and the edge components of the adjacent core tube units are connected through the glue injection sleeves.
2. The fabricated core barrel structure of claim 1, wherein the rim member comprises a prefabricated section and a cast-in-place section, the cast-in-place section being located at both ends of the prefabricated section.
3. The fabricated core tube structure of claim 2, wherein the number of the cast-in-place sections is two, one of the cast-in-place sections is provided with the glue injection sleeve, and the other cast-in-place section is provided with a reserved steel bar.
4. The fabricated core barrel structure of claim 1, wherein adjacent shear walls form an angle-clip region therebetween, the edge member being located in the angle-clip region and matching the shape of the angle-clip region.
5. The fabricated core tubular structure of claim 2, wherein an inner formwork is provided at a side of the cast-in-place section adjacent to the tubular structure.
6. The fabricated core tubular structure of claim 5, wherein an exterior formwork is provided on a side of the cast-in-place section remote from the tubular structure.
7. The assembled core tube structure of claim 1, wherein the shear wall is further provided with a plurality of embedded steel bars, and the embedded steel bars and the grouting sleeves are respectively located at two opposite ends of the shear wall.
8. The fabricated core barrel structure of claim 7, wherein the position of the embedded rebar on the shear wall corresponds to the position of the grout sleeve on the shear wall.
9. The fabricated core tube structure of claim 1, wherein the number of the grout sleeve is plural, and the plurality of grout sleeves are uniformly arranged along a length direction of the shear wall.
CN201922216272.6U 2019-12-12 2019-12-12 Assembled core tube structure Active CN211774575U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922216272.6U CN211774575U (en) 2019-12-12 2019-12-12 Assembled core tube structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922216272.6U CN211774575U (en) 2019-12-12 2019-12-12 Assembled core tube structure

Publications (1)

Publication Number Publication Date
CN211774575U true CN211774575U (en) 2020-10-27

Family

ID=72980885

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922216272.6U Active CN211774575U (en) 2019-12-12 2019-12-12 Assembled core tube structure

Country Status (1)

Country Link
CN (1) CN211774575U (en)

Similar Documents

Publication Publication Date Title
CN213233888U (en) Assembled partial cavity shear wall and connecting node
CN110453810A (en) Insulation construction integration composite wallboard
CN112942562A (en) Fabricated structure and construction method thereof
CN211774575U (en) Assembled core tube structure
CN209686711U (en) Prefabricated laminated superposed column, reinforced column and assembled architecture body
CN110778024A (en) Laminated concrete prefabricated column, connecting structure and construction method thereof
CN110847374A (en) Assembly type core tube structure and application construction method thereof
CN211200927U (en) Laminated concrete prefabricated column and connecting structure
CN213805964U (en) Single-face superposed L-shaped prefabricated part node
CN210798044U (en) Wallboard in prefabricated of assembly type structure
CN111980203A (en) Prefabricated part and connecting structure and method for upper and lower prefabricated parts
CN1510230B (en) Member for cast-in-situ steel reinforced concrete
CN109057159A (en) Prefabricated laminated superposed column, assembled architecture body and assembled architecture body method of construction
KR200400855Y1 (en) Half slab having hollow structure
CN212534856U (en) Prefabricated cavity stair
CN216195752U (en) Integrated prefabricated shear wall structure with decorative structure
CN213509048U (en) Single-face superposed prefabricated part node
CN218522010U (en) Prefabricated wall structure in integrated building
CN217601854U (en) Prefabricated even roof beam of easy die stripping and coincide even roof beam of constituteing thereof
CN216239270U (en) Assembled rectangular opening component and connecting node of assembled rectangular opening component and superposed beam slab
CN216195997U (en) Precast beam component with integrated decorative structure
CN212001568U (en) Windowsill structure and mold
CN100593059C (en) Cast-in-situ concrete hollow slab
KR100517373B1 (en) Wall Structure Using Tapered Hollow Precast Concrete Pannel and Constructing Method thereof
JP3011080B2 (en) How to make a caisson skeleton

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant