CN211774506U - Building assembled prefab balcony structure - Google Patents

Building assembled prefab balcony structure Download PDF

Info

Publication number
CN211774506U
CN211774506U CN201922015743.7U CN201922015743U CN211774506U CN 211774506 U CN211774506 U CN 211774506U CN 201922015743 U CN201922015743 U CN 201922015743U CN 211774506 U CN211774506 U CN 211774506U
Authority
CN
China
Prior art keywords
hoisting
groove
balcony structure
steel bars
embedded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922015743.7U
Other languages
Chinese (zh)
Inventor
陈梅娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Dingang Building Materials Industry Co Ltd
Original Assignee
Jiangsu Dingang Building Materials Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Dingang Building Materials Industry Co Ltd filed Critical Jiangsu Dingang Building Materials Industry Co Ltd
Priority to CN201922015743.7U priority Critical patent/CN211774506U/en
Application granted granted Critical
Publication of CN211774506U publication Critical patent/CN211774506U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a building assembled prefab balcony structure, include: the steel bar pre-buried hoisting device comprises a body, pre-buried steel bars and a hoisting groove; a plurality of embedded steel bars are embedded in the body; the hoisting groove has been seted up on the sun mesa of body, and one of them embedded bar exposes at the middle part of hoisting inslot portion, the utility model discloses a to the improvement of a building assembled prefab balcony structure, have simple structure, connect simple and conveniently, the operation is convenient, is convenient for hang and dismantle, lifts by crane efficient advantage, thereby effectual solution the utility model provides a problem and not enough.

Description

Building assembled prefab balcony structure
Technical Field
The utility model relates to a prefabricated building element technical field, more specifically the theory that says so especially relates to a building assembled prefab balcony structure.
Background
In the assembly type building, the prefabricated balcony is produced in a factory, transported to a construction site, and then is hoisted by a sling and butted with a floor slab when prefabricated building components for assembly type construction are assembled, and the joint of the prefabricated balcony and the floor slab is poured and filled to form an integral structure.
The current prefabricated balcony is comparatively inconvenient during hoist and mount, influences the construction progress.
In view of the above, the present invention provides a structure of a prefabricated balcony, which is designed to solve the problems and improve the practical value.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building assembled prefab balcony structure to it is comparatively inconvenient when solving the current prefabricated balcony hoist and mount that proposes in the above-mentioned background art, influences the problem and the not enough of construction progress.
In order to achieve the above object, the utility model provides a building assembled prefab balcony structure is reached by following specific technological means:
a building assembly type prefabricated component balcony structure, comprising: the steel bar pre-buried hoisting device comprises a body, pre-buried steel bars and a hoisting groove; a plurality of embedded steel bars are embedded in the body; a hoisting groove is formed in the male table surface of the body, and one of the embedded steel bars is exposed in the middle of the interior of the hoisting groove.
As a further optimization of this technical scheme, the utility model relates to a building assembled prefab balcony structure the hoist and mount groove overlooks and is the long circle, and the hoist and mount groove is the rectangular array mode and is provided with everywhere.
As the further optimization of this technical scheme, the utility model relates to a building assembled prefab balcony structure the centre of a circle connecting wire of the long circular form of hoist and mount groove is 90 degrees cross arrangement with embedded bar.
As a further optimization of the technical scheme, the utility model relates to a building assembled prefab balcony structure the tank bottom of hoist and mount groove sets up to 10-30mm apart from the distance of embedded bar.
Because of above-mentioned technical scheme's application, compared with the prior art, the utility model have the following advantage:
1. the utility model discloses a set up the hoist and mount groove of long circular form, and one of them embedded bar exposes at the inside middle part of hoist and mount groove, be convenient for through the embedded bar expose the part at the hoist and mount inslot come with the couple hookup of lifting by crane equipment, simple and convenient when connecting, the efficiency of lifting by crane is high.
2. The utility model discloses a centre of a circle connecting wire that sets up the long circular form of hoist and mount groove is 90 degrees cross arrangement with pre-buried reinforcing bar for it is comparatively convenient when the couple of equipment of lifting by crane of the operation of hoist and mount inslot, be favorable to the hanging and the dismantlement of couple, the efficient that lifts by crane.
3. The utility model discloses a to the improvement of a building assembled prefab balcony structure, have simple structure, connect simple and conveniently, the operation is convenient, is convenient for hang and dismantle, lifts by crane efficient advantage, thereby effectual solution the utility model discloses the problem that proposes in background art one with not enough.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this application, are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification. In the drawings:
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic top view of the present invention;
fig. 3 is a schematic side view of the cross-sectional structure of the present invention.
In the figure: body 1, embedded steel bar 2, hoist and mount groove 3.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
It is to be noted that, in the description of the present invention, "a plurality" means two or more unless otherwise specified; the terms "upper", "lower", "left", "right", "inner", "outer", "front", "rear", "head", "tail", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are merely for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention.
Meanwhile, in the description of the present invention, unless otherwise explicitly specified or limited, the terms "connected" and "connected" should be interpreted broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; the connection can be mechanical connection or electrical connection; may be directly connected or indirectly connected through an intermediate. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1 to 3, the present invention provides a specific technical implementation of the fabricated prefabricated balcony structure:
a building assembly type prefabricated component balcony structure, comprising: the steel bar hoisting device comprises a body 1, embedded steel bars 2 and hoisting grooves 3; a plurality of embedded steel bars 2 are embedded in the body 1; the male table surface of the body 1 is provided with a hoisting groove 3, and one of the embedded steel bars 2 is exposed in the middle of the inside of the hoisting groove 3.
Specifically, referring to fig. 2, the lifting groove 3 is in an oblong shape in a top view, and the lifting groove 3 is arranged at four positions in a rectangular array manner.
Specifically, referring to fig. 2, the circle center connecting line of the oblong shape of the hoisting groove 3 and the embedded steel bar 2 are arranged in a 90-degree crossing manner, so that the hook of the hoisting equipment can swing in the hoisting groove 3, the hook of the hoisting equipment can be operated in the hoisting groove conveniently, the hanging and detaching of the hook are facilitated, and the hoisting efficiency is high.
Specifically, referring to fig. 3, the distance between the bottom of the hoisting groove 3 and the embedded steel bar 2 is set to be 10-30mm, so that the hook of the hoisting equipment can smoothly pass through the bottom of the embedded steel bar 2.
The method comprises the following specific implementation steps:
the hook of the hoisting equipment is inserted into the hoisting groove 3 and penetrates through the bottom of the embedded steel bar 2, so that the hook of the hoisting equipment and the part of the embedded steel bar 2 exposed in the hoisting groove 3 are hooked with the hook, the hoisting equipment is hoisted after connection is finished, and after the body 1 and the wall body of the building are assembled, the hoisting groove 3 is poured and filled with concrete.
In summary, the following steps: according to the building assembly type prefabricated part balcony structure, the long circular hoisting groove is formed, one embedded steel bar is exposed in the middle of the inside of the hoisting groove, so that the embedded steel bar can be conveniently hooked with a hook of hoisting equipment through the part of the embedded steel bar exposed in the hoisting groove, the connection is simple and convenient, and the hoisting efficiency is high; the circle center connecting line of the oblong shape of the hoisting groove is arranged to be crossed with the embedded steel bars at 90 degrees, so that the operation of the hook of the hoisting equipment in the hoisting groove is more convenient, the hanging and the dismounting of the hook are facilitated, and the hoisting efficiency is high; the utility model discloses a to the improvement of a building assembled prefab balcony structure, have simple structure, connect simple and conveniently, the operation is convenient, is convenient for hang and dismantles, lifts by crane efficient advantage, thereby effectual solution the utility model provides a problem and not enough.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. A building assembly type prefabricated component balcony structure, comprising: the steel bar hoisting device comprises a body (1), embedded steel bars (2) and hoisting grooves (3); the method is characterized in that: a plurality of embedded steel bars (2) are embedded in the body (1); the hanging groove (3) is formed in the sun table surface of the body (1), and one of the embedded steel bars (2) is exposed in the middle of the interior of the hanging groove (3).
2. A building fabricated balcony structure as claimed in claim 1, wherein: the overlooking is long circular in the hoisting groove (3), and the hoisting groove (3) is arranged at four positions in a rectangular array mode.
3. A building fabricated balcony structure as claimed in claim 1 or 2, wherein: the circle center connecting line of the oblong shape of the hoisting groove (3) and the embedded steel bars (2) are arranged in a 90-degree crossed manner.
4. A building fabricated balcony structure as claimed in claim 1, wherein: the distance between the bottom of the hoisting groove (3) and the embedded steel bars (2) is set to be 10-30 mm.
CN201922015743.7U 2019-11-21 2019-11-21 Building assembled prefab balcony structure Expired - Fee Related CN211774506U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922015743.7U CN211774506U (en) 2019-11-21 2019-11-21 Building assembled prefab balcony structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922015743.7U CN211774506U (en) 2019-11-21 2019-11-21 Building assembled prefab balcony structure

Publications (1)

Publication Number Publication Date
CN211774506U true CN211774506U (en) 2020-10-27

Family

ID=72963297

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922015743.7U Expired - Fee Related CN211774506U (en) 2019-11-21 2019-11-21 Building assembled prefab balcony structure

Country Status (1)

Country Link
CN (1) CN211774506U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114562022A (en) * 2022-03-23 2022-05-31 张雪利 Prefabricated balcony slab of assembled and hoisting structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114562022A (en) * 2022-03-23 2022-05-31 张雪利 Prefabricated balcony slab of assembled and hoisting structure
CN114562022B (en) * 2022-03-23 2022-10-14 张雪利 Prefabricated balcony slab of assembled and hoisting structure

Similar Documents

Publication Publication Date Title
CN102328881B (en) Device and method for hoisting entire oversized steel reinforcement cage in one step
CN211774506U (en) Building assembled prefab balcony structure
CN202544468U (en) Drawbar-type electrical steel tubular rod
CN209244222U (en) A kind of basket type builder's jack
CN208072990U (en) CONSTRUCTION OPERATIONS platform
CN215287688U (en) Civil engineering construction building templates lifts by crane clamping device
CN217627175U (en) Steel reinforcement cage hoisting tool
CN102777036A (en) Air reverse mechanical joint construction method of super-long vertical reinforcement cage
CN215558413U (en) Lifting sling for rectangular culvert sections
CN203187370U (en) Inner mast hoisting device
CN212957625U (en) Prefabricated brick moulding bed
CN210127053U (en) Concrete lifting device for building construction
CN210067423U (en) Aluminum alloy template hangs mould system
CN215797924U (en) Hoist for hoisting outer mold of prefabricated box girder
CN201132732Y (en) Prefabricated element slings
CN218371213U (en) A hoisting structure for concrete pipe section
CN211622271U (en) Prefabricated post connection structure of assembled and prefabricated post
CN104291225A (en) Non-dragging independent mast device for hoisting rigid steel pile
CN216426495U (en) Hoist and mount compensating beam
CN205772948U (en) Super High Core Walls Structure soil dead man
CN215290762U (en) Integrated hoisting building inner wall
CN212924070U (en) Lifting appliance structure
CN213651603U (en) Simple hoisting device
CN217838064U (en) Auxiliary pipeline installation device
CN218201745U (en) Hoisting device for prefabricated pi-shaped beam plate of caisson

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201027

Termination date: 20211121