CN211773894U - Prefabricated formula work well is salvageed to cable - Google Patents

Prefabricated formula work well is salvageed to cable Download PDF

Info

Publication number
CN211773894U
CN211773894U CN201922500609.6U CN201922500609U CN211773894U CN 211773894 U CN211773894 U CN 211773894U CN 201922500609 U CN201922500609 U CN 201922500609U CN 211773894 U CN211773894 U CN 211773894U
Authority
CN
China
Prior art keywords
cable
opposite
work well
opposite plates
plates
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922500609.6U
Other languages
Chinese (zh)
Inventor
纪沛辰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201922500609.6U priority Critical patent/CN211773894U/en
Application granted granted Critical
Publication of CN211773894U publication Critical patent/CN211773894U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a prefabricated working well for cable emergency repair, which comprises two opposite plates arranged along the cable laying direction and positioned at two sides of a cable, the top and the bottom of the opposite plates are respectively provided with a plurality of fixed brackets for connecting the two opposite plates, each fixed bracket is detachably connected with the two opposite plates, when the cable rush-repair prefabricated working well is used, a plurality of fixed brackets are laid at the bottom of an excavation site, then two opposite plates are arranged on the fixed brackets along the cable arrangement direction, two fixing supports are arranged at the top of the cable support, the fixing support at the top and the fixing support at the bottom are used for firmly fixing the two opposite plates, so that the two opposite plates are assembled into a working well at an excavation place, therefore, the construction speed of the working well is greatly improved, the cable rush-repair power restoration time is shortened, the construction cost is reduced, and the cable rush-repair prefabricated working well is used in the field of cable rush-repair.

Description

Prefabricated formula work well is salvageed to cable
Technical Field
The utility model is used for the cable field of salvageing especially relates to a prefabricated formula work well is salvageed to cable.
Background
When the cable breaks down due to long-time operation or influence of other factors, the power supply emergency repair department can rush to the site for troubleshooting and emergency repair, digging cable ditches or protective pipes under sidewalks at various suspicious fault points, performing accurate test and confirmation again, after the fault points are confirmed to be correct, expanding the emergency repair working surface immediately, manufacturing a cable intermediate joint, recovering power supply after the test is qualified, according to the power supply specification, a cable working well must be built at the cable intermediate joint so as to ensure the safe operation of the cable, and in the prior art, the construction of most cable working wells adopts the modes of brick laying and on-site formwork erecting pouring, not only the construction speed is slow and the power restoration time is prolonged, and moreover, a large amount of labor cost and construction cost are consumed, the flatness is poor, the quality is unstable, and meanwhile, the construction period is also easily influenced by factors such as seasonal weather, and the like, so that urban road traffic jam is seriously caused.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve one of the technical problem who exists among the prior art at least, provide a prefabricated formula work well is salvageed to cable, it can improve work well construction speed by a wide margin for the cable is salvageed and is recovered the electric time, reduces construction cost.
The utility model provides a technical scheme that its technical problem adopted is: the utility model provides a prefabricated formula work well is salvageed to cable, its mainly includes and sets up and lie in two riser on cable both sides along the cable laying direction, the top and the bottom of riser all are equipped with a plurality of two of connections the fixed bolster of riser, each the fixed bolster and two the connection can be dismantled to the riser.
Preferably, the top of the opposite plate is provided with two fixing supports, and the two fixing supports are respectively located at two ends of the opposite plate.
Preferably, the bottom of the opposite plate is provided with three fixing supports, one of which is arranged in the middle of the opposite plate, and the other two of which are respectively arranged at two ends of the opposite plate.
Preferably, both ends of the fixed support are provided with bumps, and the top and the bottom of the opposite plate are provided with clamping grooves matched with the bumps.
Preferably, the device also comprises a cover plate, and two sides of the cover plate are lapped on the tops of the two opposite plates.
Preferably, the cover plate is provided with a plurality of cover plates, and each cover plate is spliced between the two fixing supports.
Preferably, the tops of the two opposite plates are respectively provided with an avoiding groove for clamping two ends of the cover plate.
Preferably, a plurality of cable brackets perpendicular to the opposite plates are installed in the two opposite plates.
Preferably, the cable supports are sequentially arranged from top to bottom.
One of the above technical solutions has at least one of the following advantages or beneficial effects: this prefabricated formula work well is salvageed to cable is when using, lay a plurality of fixed bolsters in the bottom in excavation place, then install two opposite plates on the fixed bolster along the direction that the cable was arranged, two fixed bolsters of top installation at the cable support, the fixed bolster at top and the fixed bolster of bottom are used for firmly fixing two opposite plates, make two opposite plates assemble out the work well in the excavation place, thereby improve the construction speed of work well by a wide margin, accelerate the cable and salvage the repowerage time, and the construction cost is reduced.
Drawings
The present invention will be further explained with reference to the accompanying drawings:
fig. 1 is a schematic structural diagram of an embodiment of the present invention;
FIG. 2 is a cross-sectional view taken at A-A of FIG. 1;
FIG. 3 is a cross-sectional view taken at B-B of FIG. 1;
fig. 4 is a side view of the alignment plate of the present invention.
Detailed Description
This section will describe in detail the embodiments of the present invention, preferred embodiments of the present invention are shown in the attached drawings, which are used to supplement the description of the text part of the specification with figures, so that one can intuitively and vividly understand each technical feature and the whole technical solution of the present invention, but they cannot be understood as the limitation of the protection scope of the present invention.
In the present invention, if there is a description of directions (up, down, left, right, front and back), it is only for convenience of description of the technical solution of the present invention, and it is not intended to indicate or imply that the technical features indicated must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present invention.
In the utility model, the meaning of a plurality of is one or more, the meaning of a plurality of is more than two, and the meaning of more than two is understood as not including the number; the terms "above", "below", "within" and the like are understood to include the instant numbers. In the description of the present invention, if there is any description of "first" and "second" only for the purpose of distinguishing technical features, it is not to be understood as indicating or implying relative importance or implicitly indicating the number of indicated technical features or implicitly indicating the precedence of the indicated technical features.
In the present invention, unless otherwise explicitly defined, the terms "set", "install", "connect", and the like are to be understood in a broad sense, and for example, may be directly connected or may be indirectly connected through an intermediate medium; can be fixedly connected, can also be detachably connected and can also be integrally formed; may be mechanically coupled, may be electrically coupled or may be capable of communicating with each other; either as communication within the two elements or as an interactive relationship of the two elements. The technical skill in the art can reasonably determine the specific meaning of the above words in the present invention by combining the specific contents of the technical solution.
Referring to fig. 2, an embodiment of the present invention provides a prefabricated working well for cable emergency repair, which mainly includes two opposite plates 1 disposed along a cable laying direction and located at two sides of a cable, wherein a plurality of fixing brackets 2 connecting the two opposite plates 1 are disposed at the top and bottom of the opposite plates 1, each fixing bracket 2 is detachably connected to the two opposite plates 1, during use, a plurality of fixing brackets 2 are disposed at the bottom of an excavation site, then the two opposite plates 1 are mounted on the fixing brackets 2 along the cable laying direction, two fixing brackets 2 are also mounted at the top of the cable bracket, the fixing bracket 2 at the top and the fixing bracket 2 at the bottom are used for firmly fixing the two opposite plates 1, and then a gap between the opposite plates 1 and a roadbed is backfilled and compacted, so that the two opposite plates 1 form a working well inside the excavation site, and the working well can greatly increase a construction speed, the cable repair and restoration time is shortened, and the construction cost is effectively reduced.
Referring to fig. 1 and 2, the top of the opposite plate 1 is provided with two fixing supports 2, the two fixing supports 2 are respectively located at two ends of the opposite plate 1, and the two fixing supports 2 form a fixing plane at the top end of the opposite plate 1, so that the opposite plate 1 can be fixed, and the materials spent on fixing the opposite plate 1 can be effectively saved.
In addition, the bottom of counterpoint board 1 is equipped with three fixed bolster 2, and one of them is established at the middle part of counterpoint board 1, and two are established respectively at the both ends of counterpoint board 1, and the fixed bolster 2 at both ends can be fixed counterpoint board 1, and middle fixed bolster 2 can be more firm with two connection of counterpoint board 1, prevents to take place to become flexible between two counterpoint boards 1.
Referring to fig. 2, the both ends of fixed bolster 2 all are equipped with lug 21, the top and the bottom of counterpiece board 1 all be equipped with lug 21 assorted draw-in groove 11, when using, with the lug 21 embedding of fixed bolster 2 inside the draw-in groove 11 of counterpiece board 1, draw-in groove 11 can be with 2 chucking of fixed bolster on counterpiece board 1, and draw-in groove 11 adopts the draw-in groove 11 of full enclosure, can effectively avoid lug 21 to take place to remove in draw-in groove 11 inside like this, prevent that the working well from appearing not hard up.
Referring to fig. 1 and 3, the cable rush-repair prefabricated working well further comprises a cover plate 5, two sides of the cover plate 5 are lapped on the tops of the two opposite plates 1, and after the working well is constructed, the cover plate 5 is covered on the tops of the opposite plates 1 to play a role in closing a well mouth.
Referring to fig. 1, in some embodiments, a plurality of cover plates 5 are arranged, each cover plate 5 is spliced between two fixing supports 2, when a well bottom needs to be accessed, the well bottom can be directly accessed only by opening any one of the cover plates 5, and time cost and labor cost for opening and closing the well head are effectively saved.
Refer to fig. 3, fig. 4, the top of two riser 1 all is equipped with the groove 12 of dodging of card holding apron 5 both ends, apron 5 lid is when riser 1's top, the both ends of apron 5 are all taken on two riser 1 dodge groove 12, dodge groove 12 and play the effect spacing to apron 5, avoid apron 5 to cover take place relative slip because of the exogenic action after riser 1's top, of course, except carrying on spacingly through dodging groove 12, can also set up buckle part and carry on spacingly to apron 5, it is specific, set up bellied fastener at riser 1's top, the both ends of apron 5 set up with fastener complex hole site, when placing apron 5, aim at the hole site of apron 5 and carry out the coordination to the bellied fastener in riser 1 top and place, thereby play the effect of fixed apron 5.
Referring to fig. 2, fig. 3, install in two riser 1 with riser 1 vertically a plurality of cable support 4, in the use, cable support 4 is used for laying the cable, avoids the cable to be disorderly crisscross to bring unnecessary trouble for maintenance work, and in addition, cable support 4 also can avoid cable intermediate head direct contact ground, effectively improves cable intermediate head's life.
Referring to fig. 2 and 3, the cable holders 4 are sequentially arranged from top to bottom, so that the cables are arranged more orderly, and subsequent overhaul and maintenance are facilitated.
The invention is not limited to the above embodiments, and those skilled in the art can make equivalent modifications or substitutions without departing from the spirit of the invention, and such equivalent modifications or substitutions are included in the scope defined by the claims of the present application.

Claims (9)

1. The utility model provides a prefabricated formula work well is salvageed to cable which characterized in that: the cable laying device comprises two opposite plates which are arranged along the cable laying direction and are positioned on two sides of a cable, wherein a plurality of fixing supports for connecting the two opposite plates are arranged at the top and the bottom of each opposite plate, and each fixing support is detachably connected with the two opposite plates.
2. The prefabricated work well for cable repair according to claim 1, wherein: the top of the opposite plate is provided with two fixing supports which are respectively positioned at two ends of the opposite plate.
3. The prefabricated work well for cable repair according to claim 1, wherein: the bottom of the opposite plate is provided with three fixed supports, one of the fixed supports is arranged in the middle of the opposite plate, and the two fixed supports are respectively arranged at two ends of the opposite plate.
4. The prefabricated work well for cable repair according to claim 3, wherein: the two ends of the fixed support are both provided with a convex block, and the top and the bottom of the opposite plate are both provided with a clamping groove matched with the convex block.
5. The prefabricated work well for cable repair according to claim 1, wherein: the two opposite vertical plates are arranged on the two sides of the cover plate.
6. The prefabricated work well for cable repair according to claim 5, wherein: the cover plate is provided with a plurality of cover plates, and each cover plate is spliced between the two fixing supports.
7. The prefabricated work well for cable repair according to claim 6, wherein: the tops of the two opposite plates are respectively provided with an avoiding groove for clamping the two ends of the cover plate.
8. The prefabricated work well for cable repair according to claim 1, wherein: and a plurality of cable brackets which are vertical to the opposite plates are arranged in the two opposite plates.
9. The prefabricated work well of cable rush-repair of claim 8, characterized in that: and the cable supports are sequentially arranged from top to bottom.
CN201922500609.6U 2019-12-31 2019-12-31 Prefabricated formula work well is salvageed to cable Active CN211773894U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922500609.6U CN211773894U (en) 2019-12-31 2019-12-31 Prefabricated formula work well is salvageed to cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922500609.6U CN211773894U (en) 2019-12-31 2019-12-31 Prefabricated formula work well is salvageed to cable

Publications (1)

Publication Number Publication Date
CN211773894U true CN211773894U (en) 2020-10-27

Family

ID=72890630

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922500609.6U Active CN211773894U (en) 2019-12-31 2019-12-31 Prefabricated formula work well is salvageed to cable

Country Status (1)

Country Link
CN (1) CN211773894U (en)

Similar Documents

Publication Publication Date Title
CN211773894U (en) Prefabricated formula work well is salvageed to cable
CN211898414U (en) Combined type supporting construction for building
CN205419600U (en) A base steel construction for constructing tower crane base accurate positioning installation
CN216689447U (en) Slope protection protector for civil engineering
CN213775393U (en) Temporary operation platform for tunnel support based on cantilever excavator
CN211945660U (en) Multi-connected cable pulley capable of freely adjusting angle
CN211524347U (en) Safety protective guard for road repair
CN104229615A (en) Mechanical lifting appliance for cable trench covers of substation and switching station
CN218216439U (en) Novel composite cable protection pipe
CN210380148U (en) Assembly type building machine electric pipeline installation connecting device
CN202972186U (en) Cable support
CN107882513A (en) A kind of integrated drill background apparatus
CN218291459U (en) Combined ground rail for workshop
CN216109968U (en) New energy automobile has charging parking stall of direction function
CN214125419U (en) Underground traffic construction service supervision and management system
CN217651815U (en) Foundation pit supporting structure in shaft construction
CN218624265U (en) Composite geomembrane applied to tunnel engineering
CN220233747U (en) Inside line arrangement device of power equipment
CN216699457U (en) A road surface excavation cable protection device for telecom engineering construction
CN204823548U (en) Elevator hauler overhauls platform
CN221029924U (en) Spliced flood prevention slope protection
CN219420158U (en) Easy-to-overhaul cable bridge with classified placement function
CN219586564U (en) Bridge bent cap construction support
CN219908956U (en) Foundation pit supporting device with adjustable
CN216783287U (en) Fill electric pile with monitoring function

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant