CN211713564U - Sponge permeable pavement with rainwater collection and guiding functions - Google Patents

Sponge permeable pavement with rainwater collection and guiding functions Download PDF

Info

Publication number
CN211713564U
CN211713564U CN201922263866.2U CN201922263866U CN211713564U CN 211713564 U CN211713564 U CN 211713564U CN 201922263866 U CN201922263866 U CN 201922263866U CN 211713564 U CN211713564 U CN 211713564U
Authority
CN
China
Prior art keywords
layer
rainwater
plain concrete
area
plastic blind
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922263866.2U
Other languages
Chinese (zh)
Inventor
韩君
谢爱华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Landscape Design Institute Co ltd
Original Assignee
Suzhou Institute Of Landscape Architecture Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Institute Of Landscape Architecture Design Co ltd filed Critical Suzhou Institute Of Landscape Architecture Design Co ltd
Priority to CN201922263866.2U priority Critical patent/CN211713564U/en
Application granted granted Critical
Publication of CN211713564U publication Critical patent/CN211713564U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a sponge permeable pavement for rainwater collection and guide, which comprises a tamped plain soil layer, a graded gravel layer is laid above the tamped plain soil layer, a main plain concrete layer is arranged above the graded gravel layer, a single-layer bidirectional steel bar is arranged in the main plain concrete layer, a drainage ditch area is arranged on one side of the main plain concrete layer along the length direction, plastic blind ditch pipes are arranged in the drainage ditch area along the length direction, a geotextile layer is wrapped outside the plastic blind ditch pipes, a gravel buffer layer and a natural stone exposed aggregate permeable concrete surface layer are sequentially arranged above the main plain concrete layer, one side of the graded gravel layer is provided with a rainwater garden foundation area and a rainwater garden water accumulation area, a plurality of overflow ports which are arranged at equal intervals are communicated between the plastic blind ditch pipes and the rainwater garden foundation area, and through the mode, the utility model can effectively achieve the effect of collecting, purifying and recycling of rainwater on the pavement, the cost is lower, is convenient for construct.

Description

Sponge permeable pavement with rainwater collection and guiding functions
Technical Field
The utility model relates to a road surface drainage technical field especially relates to a sponge permeable pavement of direction is collected to rainwater.
Background
The modern people generally advocate ecological landscape construction, the proposal of sponge city and rain flood management concept require that the low-influence development mode is adopted in the city development and construction process, the rainwater is collected, and the initial rainwater containing high-concentration nitrogen and phosphorus is discharged after being purified, so that the pollution to underground water is reduced.
The permeable pavement is an important technical measure of sponge cities and is widely applied to sidewalks, squares, non-motor vehicle lanes of municipal roads and the like, and the permeable pavement can enable rainwater to quickly seep downwards, reduce road surface runoff, relieve urban drainage pressure and improve pavement skid resistance; however, the traditional permeable pavement can only meet the requirement of direct infiltration of rainwater, and cannot be collected, purified and recycled, so that a pavement structure system which can realize rainwater infiltration and can be collected and recycled is urgently needed.
SUMMERY OF THE UTILITY MODEL
The utility model discloses the main technical problem who solves provides a sponge permeable pavement of direction is collected to rainwater, can effectively reach the effect that the purification was recycled in the collection of road surface rainwater, and the cost is lower, the construction of being convenient for.
In order to solve the technical problem, the utility model discloses a technical scheme be: the sponge permeable pavement comprises a rammed plain soil layer, a graded broken stone layer is laid above the rammed plain soil layer, a main plain concrete layer is arranged above the graded broken stone layer, a single-layer bidirectional steel bar is arranged in the main plain concrete layer, a drainage ditch area is arranged on one side of the main plain concrete layer along the length direction, plastic blind ditch pipes are arranged in the drainage ditch area along the length direction, a geotextile layer is wrapped outside the plastic blind ditch pipes, a broken stone buffer layer and a natural stone exposed aggregate permeable concrete surface layer are sequentially arranged above the main plain concrete layer, a rainwater garden foundation area and a rainwater garden water accumulation area are arranged on one side of the graded broken stone layer, and a plurality of overflow ports which are arranged at equal intervals are communicated between the plastic blind ditch pipes and the rainwater garden foundation area.
Preferably, a plain concrete cushion layer is arranged between the drainage ditch area and the graded gravel layer, and the plastic blind ditch pipe is arranged above the plain concrete cushion layer.
Preferably, the plain concrete cushion layer has a gradient of 2.5 to 3.5 percent along the extension direction of the plastic blind ditch pipe.
Preferably, the main plain concrete layer is C30 plain concrete and has a thickness of 100-120 mm.
Preferably, the thickness of the graded broken stone layer is 200-250 mm.
The utility model has the advantages that: the utility model provides a pair of sponge permeable pavement of direction is collected to rainwater can effectively infiltrate the rainwater on road surface on the spot, obtains to collect the purpose of purifying and recycling, and the construction is simple and convenient, has good industrial applicability.
Drawings
Fig. 1 is a schematic structural view of a rainwater collection and guiding sponge permeable pavement of the present invention;
the parts in the drawings are numbered as follows:
1. tamping a plain soil layer; 2. grading a crushed stone layer; 3. a main plain concrete layer; 4. a single layer of bidirectional rebar; 5. a drain area; 6. a plastic blind ditch pipe; 7. a geotextile layer; 8. a macadam buffer layer; 9. natural stone exposed aggregate permeable concrete surface layer; 10. a rain garden foundation area; 11. a rainwater garden catchment area; 12. an overflow port;
13. and (4) a plain concrete cushion layer.
Detailed Description
The following detailed description of the preferred embodiments of the present invention will be provided in conjunction with the accompanying drawings, so as to enable those skilled in the art to more easily understand the advantages and features of the present invention, and thereby define the scope of the invention more clearly and clearly.
As shown in figure 1, the sponge permeable pavement for rainwater collection and guiding comprises a rammed plain soil layer 1, a graded gravel layer 2 is laid above the rammed plain soil layer 1, the preferred thickness of the graded gravel layer 2 is 200-250 mm, the transition effect of leveling and supporting an upper main plain concrete structure is achieved above the rammed plain soil structure, the structural strength of the pavement is enhanced, and good water permeability and diffusion stress are achieved.
As shown in fig. 1, after the graded broken stone structure is laid, erecting a formwork and pouring a main plain concrete layer 3, wherein the main plain concrete layer 3 is preferably C30 plain concrete with a thickness of 100-120 mm and is used for providing adaptive base support strength; the structure can provide enough supporting strength, but if the toughness of structure is not enough, the cracked phenomenon of settlement may produce, consequently in order to guarantee the toughness and the intensity of structure simultaneously, prevents to subside the fracture problem, is provided with single-deck two-way reinforcing bar 4 in main plain concrete layer 3, and the diameter of reinforcing bar can be selected to 8 ~ 10mm, interval 200 mm.
As shown in fig. 1, a drainage channel area 5 is arranged on one side of a main plain concrete layer 3 along the length direction, plastic blind channel pipes 6 are arranged in the drainage channel area 5 along the length direction, the plastic blind channel pipe structure takes thermoplastic synthetic resin as a main raw material and is modified, thin plastic filaments are extruded out through a nozzle in a hot melting state, and the extruded plastic filaments are welded on nodes through a forming device to form a three-dimensional net-shaped structure.
As shown in fig. 1, in order to filter the rainwater and the silt contained in the road, a geotextile layer 7 is coated outside the plastic blind ditch pipe 6, and the rainwater which permeates is firstly filtered by the geotextile layer 7 and then permeates into the plastic blind ditch pipe 6 to be guided and collected. A plain concrete cushion layer 13 is arranged between the drainage ditch area 5 and the graded crushed stone layer 2, the plastic blind ditch pipe 6 is arranged above the main plain concrete layer 3, and in order to further improve the diversion and collection effect, the plain concrete cushion layer 13 is in a gradient of 2.5-3.5% along the extension direction of the plastic blind ditch pipe 6 by utilizing the flow direction of water flow.
As shown in fig. 1, a broken stone buffer layer 8 and a natural stone exposed aggregate water permeable concrete surface layer 9 are sequentially arranged above the main concrete layer 3, the natural stone exposed aggregate water permeable concrete surface structure has porosity, high water permeability is realized, water can easily pass through, and the broken stone buffer structure is used for assisting in transferring buffer and supporting pavement load and simultaneously permeating rainwater. One side of the graded gravel layer 2 is provided with a rainwater garden foundation area 10 and a rainwater garden ponding area 11, a plurality of overflow ports 12 which are distributed at equal intervals are communicated between the plastic blind ditch pipe 6 and the rainwater garden foundation area 10, rainwater collected by the plastic blind ditch pipe 6 is discharged into the rainwater garden foundation area 10 through the overflow ports 12, the root system in the garden can effectively purify the rainwater, and the purified water is discharged into the rainwater garden ponding area 11 to be recycled in other aspects.
The above only is the embodiment of the present invention, not limiting the patent scope of the present invention, all the equivalent structures or equivalent processes that are used in the specification and the attached drawings or directly or indirectly applied to other related technical fields are included in the patent protection scope of the present invention.

Claims (5)

1. The utility model provides a sponge permeable pavement of direction is collected to rainwater which characterized in that: the rainwater garden soil layer comprises a rammed plain soil layer (1), a graded broken stone layer (2) is laid above the rammed plain soil layer (1), a main plain concrete layer (3) is arranged above the graded broken stone layer (2), a single-layer bidirectional steel bar (4) is arranged in the main plain concrete layer (3), a drainage ditch area (5) is arranged on one side of the main plain concrete layer (3) along the length direction, plastic blind ditch pipes (6) are arranged in the drainage ditch area (5) along the length direction, a geotextile layer (7) covers the plastic blind ditch pipes (6), a gravel buffer layer (8) and a natural stone exposed aggregate water permeable concrete surface layer (9) are sequentially arranged above the main plain concrete layer (3), a rainwater garden foundation area (10) and a rainwater garden water accumulation area (11) are arranged on one side of the graded broken stone layer (2), and a plurality of overflow ports (12) which are arranged at equal intervals are communicated and arranged between the plastic blind ditch pipes (6) and the rainwater garden foundation area (10) .
2. The sponge permeable pavement for collecting and guiding rainwater according to claim 1, which is characterized in that: a plain concrete cushion layer (13) is arranged between the drainage ditch region (5) and the graded gravel layer (2), and the plastic blind ditch pipe (6) is arranged above the plain concrete cushion layer (13).
3. The sponge permeable pavement for collecting and guiding rainwater according to claim 2, which is characterized in that: the plain concrete cushion layer (13) is 2.5% -3.5% of gradient along the extension direction of the plastic blind ditch pipe (6).
4. The sponge permeable pavement for collecting and guiding rainwater according to claim 1, which is characterized in that: the main plain concrete layer (3) is C30 plain concrete and has a thickness of 100-120 mm.
5. The sponge permeable pavement for collecting and guiding rainwater according to claim 1, which is characterized in that: the thickness of the graded broken stone layer (2) is 200-250 mm.
CN201922263866.2U 2019-12-17 2019-12-17 Sponge permeable pavement with rainwater collection and guiding functions Active CN211713564U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922263866.2U CN211713564U (en) 2019-12-17 2019-12-17 Sponge permeable pavement with rainwater collection and guiding functions

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922263866.2U CN211713564U (en) 2019-12-17 2019-12-17 Sponge permeable pavement with rainwater collection and guiding functions

Publications (1)

Publication Number Publication Date
CN211713564U true CN211713564U (en) 2020-10-20

Family

ID=72817874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922263866.2U Active CN211713564U (en) 2019-12-17 2019-12-17 Sponge permeable pavement with rainwater collection and guiding functions

Country Status (1)

Country Link
CN (1) CN211713564U (en)

Similar Documents

Publication Publication Date Title
CN205420946U (en) Novel ecology that prevents surface gathered water road structure of permeating water
CN204849520U (en) Road drainage system
CN211621076U (en) Sponge city permeable pavement
CN106087647A (en) A kind of urban road rain water collecting system
CN205171305U (en) Bituminous paving with drainage structures
CN110438914A (en) Water tank culvert and its construction method are crossed on soft soil foundation
CN207062672U (en) A kind of permeable pavement structure
CN202627166U (en) Novel water-discharging ecological zone for town road
CN212247917U (en) Combined box culvert for drainage of building site
CN210797145U (en) Noise-reduction drainage polymer modified porous concrete pavement structure
CN211713564U (en) Sponge permeable pavement with rainwater collection and guiding functions
CN203866664U (en) Permeable concrete pavement system with permeation and drainage guide pipes
CN110924257A (en) Municipal road, pouring template for construction of municipal road and construction method of pouring template
CN216474335U (en) A foundation structure for installing night light ceramic tile that permeates water
CN215329163U (en) Structure of combined sponge city system for sidewalk and green belt
CN214459302U (en) Ecological structure beneficial to pavement of road surface and purification of water quality of road surface drainage
CN210238171U (en) Pedestrian and vehicle road in park
CN211688840U (en) Concrete structure permeates water
CN211447157U (en) Sponge urban rainwater drainage system
CN210065466U (en) Runoff pollution control ecological filter ditch
CN210140780U (en) Anti-clogging ecological permeable box culvert
CN217711049U (en) Prefabricated infiltration ditch that permeates water suitable for sponge city pavement
CN113136765B (en) Water-retaining purifying drainage sidewalk
CN219059637U (en) Permeable pavement
CN215593563U (en) Pavement permeable structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 202 Xujiang Road, Suzhou, Jiangsu Province

Patentee after: Suzhou Landscape Design Institute Co.,Ltd.

Address before: 202 Xujiang Road, Suzhou, Jiangsu Province

Patentee before: SUZHOU INSTITUTE OF LANDSCAPE ARCHITECTURE DESIGN CO.,LTD.

CP01 Change in the name or title of a patent holder