CN211691578U - Safety protection shed for building construction - Google Patents

Safety protection shed for building construction Download PDF

Info

Publication number
CN211691578U
CN211691578U CN201922368576.4U CN201922368576U CN211691578U CN 211691578 U CN211691578 U CN 211691578U CN 201922368576 U CN201922368576 U CN 201922368576U CN 211691578 U CN211691578 U CN 211691578U
Authority
CN
China
Prior art keywords
pipe
safety protection
pipe section
building construction
water pumping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922368576.4U
Other languages
Chinese (zh)
Inventor
卢必友
杨俊峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Chengye Construction & Engineering Co ltd
Original Assignee
Chongqing Chengye Construction & Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Chengye Construction & Engineering Co ltd filed Critical Chongqing Chengye Construction & Engineering Co ltd
Priority to CN201922368576.4U priority Critical patent/CN211691578U/en
Application granted granted Critical
Publication of CN211691578U publication Critical patent/CN211691578U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model discloses a safety protection shed for building construction, which comprises a support column, an anti-smashing layer beam and a marking frame, wherein the upper end of the anti-smashing layer beam is detachably connected; the marking frame is enclosed around the beam of the anti-smashing layer; a spraying dust-settling device is arranged at the edge of the lower end of the marking frame; the spraying dust-settling device comprises a water tank, a water pumping pipe, a PVC surrounding pipe and a spray head; the lower end of the water pumping pipe extends into the water tank, and a water pump is connected to the water pumping pipe; the upper end of the water pumping pipe is connected with the PVC surrounding pipe; the PVC surrounding pipe is detachably arranged around the lower edge of the marking frame; the spray head is arranged at the lower part of the PVC surrounding pipe; the upper parts of the support columns on the two sides are connected through a side wall plate component; the side coaming is rotatably arranged below the spray head; the utility model discloses the technical scheme who takes has solved because building site's raise dust is big, builds the safety protection canopy in building site and also is mostly open structure, and the raise dust of building site influences the workman's that is just working or has a rest problem in the protection canopy easily.

Description

Safety protection shed for building construction
Technical Field
The utility model relates to a construction equipment technical field, concretely relates to safety protection canopy for construction.
Background
During construction at a building construction site, a plurality of unsafe factors often exist at the construction site, and in the construction process, woodworking construction is often needed, such as manufacturing of a concrete pouring template, manufacturing of a frame plate and the like, and steel bar processing is also needed, such as welding and bending of the steel bars. The above construction operations are generally performed near a building, and in the construction process of the building, objects falling from the air are possible to cause personal injury to constructors at any time. Therefore, construction operations such as carpentry and reinforcing steel bars are carried out on the construction site, and a safety protection shed must be built to protect constructors. Sometimes, a safety protection shed is also built for the construction workers to have a temporary rest; simultaneously building site's raise dust is big, builds the safety protection canopy also for open structure at building site, and the raise dust of building site influences the workman's that is working or have a rest problem in protecting the canopy easily.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a safety protection canopy for construction solves because building site's raise dust is big, builds also most for open structure at the safety protection canopy in construction site, and the raise dust in construction site influences the workman's that is just working or has a rest problem in the protection canopy easily.
In order to solve the technical problem, the utility model adopts the following technical scheme: a safety protection shed for building construction comprises support columns, anti-smashing layer cross beams and a marking frame, wherein the upper ends of the support columns are detachably connected with the anti-smashing layer cross beams; the marking frame is enclosed around the beam of the anti-smashing layer; a spraying dust-settling device is arranged at the edge of the lower end of the marking frame; the spraying dust-settling device comprises a water tank, a water pumping pipe, a PVC surrounding pipe and a spray head; the lower end of the water pumping pipe extends into the water tank, and a water pump is connected to the water pumping pipe; the upper end of the water pumping pipe is connected with the PVC surrounding pipe; the PVC surrounding pipe is detachably arranged around the lower edge of the marking frame; the spray head is arranged at the lower part of the PVC surrounding pipe; the upper parts of the support columns on the two sides are connected through a side wall plate component; the side coaming is rotatably arranged below the spray head;
the PVC enclosing pipe comprises a first pipe section, a second pipe section, a third pipe section and a fourth pipe section which are sequentially communicated end to end; one side of the fourth pipe section is connected with a connector; the connector is connected with the water pumping pipe;
the first pipe section, the second pipe section, the third pipe section and the fourth pipe section are respectively fixed on the lower edge of the marking frame through pipe hoop assemblies; the water pumping pipe is connected with the supporting column through a pipe hoop component;
the side wall plate component comprises a mounting cross beam and a rotating plate; the rotating plate is hinged with the mounting cross beam through a hinge;
the lower end of the rotating plate is provided with a drainage part; a diversion trench is processed on the surface of the drainage part; a clamping rib extends downwards from the lower end of the drainage part;
a guardrail is arranged below the rotating plate; the upper surface of the guardrail is provided with a clamping groove corresponding to the clamping rib;
the rotating plate is provided with a handle groove; the handle groove penetrates through the rotating plate;
a handle is rotatably arranged in the handle groove; the two ends of the handle are hinged with the two ends of the handle groove.
Compared with the prior art, the beneficial effects of the utility model are one of following at least:
1. the spraying dust-settling device can spray water mist to the periphery from the upper part of the protection shed, and water drops absorb dust particles in the air around the protection shed and fall along with the water drops, so that the dust around the protection shed is reduced, and the comfort level of workers who are in construction and rest in the protection shed is improved;
2. the water pumping pipe pumps water from the water tank and sends the water into the PVC surrounding pipe, the PVC surrounding pipe is arranged around the protection shed in a circle, water can form a channel in the PVC surrounding pipe, then the water is sprayed out from a spray head at the bottom of the PVC surrounding pipe through water pressure and is sprayed from the top to the periphery of the protection shed, and dust can be reduced from all directions;
3. through side wall plate unit connection between the support column of both sides, side wall plate unit is favorable to improving the protective effect of protection canopy, the side wall plate rotates and sets up in the shower nozzle below, can overturn as required in a flexible way and open, when opening the shower nozzle water spray, also can open the outside upset of side wall plate, the water droplet of having adsorbed the dust falls the back, through the side wall plate landing to the protection canopy outside subaerial, after avoiding spraying water smoke, be favorable to hindering in the water smoke trickles into the protection canopy, influence construction and rest.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a side view of the present invention.
FIG. 3 is a schematic structural diagram of a PVC bustle pipe.
Fig. 4 is a schematic view of a rotating plate structure.
In the drawings: 1. a support pillar; 2. the beam of the anti-smashing layer; 3. marking a frame; 4. a water tank; 5. a water pumping pipe; 6, PVC surrounding pipes; 7. a spray head; 8. a side wall panel assembly; 9. a first tube section; 10. a second tube section; 11. a third tube section; 12. a fourth tube section; 13. a connector; 14. a rotating plate; 15. a drainage part; 16. a diversion trench; 17. clamping ribs; 18. a guardrail; 19. a handle slot; 20. a handle.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Example 1: as shown in fig. 1 to 4, a safety protection shed for building construction comprises a support column 1, an anti-smashing layer beam 2 and a marking frame 3, wherein the upper end of the anti-smashing layer beam 2 is detachably connected; the marking frame is enclosed around the anti-smashing layer beam 2; a spraying dust-settling device is arranged at the edge of the lower end of the marking frame; the spraying dust-settling device comprises a water tank 4, a water pumping pipe 5, a PVC surrounding pipe 6 and a spray head 7; the lower end of the water pumping pipe 5 extends into the water tank 4, and the water pumping pipe 5 is connected with a water pump; the upper end of the water pumping pipe 5 is connected with a PVC surrounding pipe 6; the PVC surrounding pipe 6 is detachably arranged around the lower edge of the marking frame; the spray head 7 is arranged at the lower part of the PVC surrounding pipe 6; the upper parts of the support columns 1 on the two sides are connected through a side wall plate component 8; the side coaming is rotatably arranged below the spray head 7; in the embodiment, the water pump adopts the model of a conventional submersible pump and is electrically connected to an external power supply; any water pump with reasonable model and structure can be selected according to the requirement; in this embodiment, the nozzle 7 is a conventional nozzle 7, and any nozzle 7 with a reasonable structure and connection mode can be selected as required.
The spraying dust-settling device can spray water mist to the periphery from the upper part of the protection shed, and water drops absorb dust particles in the air around the protection shed and fall along with the water drops, so that the dust around the protection shed is reduced, and the comfort level of workers who are in construction and rest in the protection shed is improved; the water is pumped up from the water tank 4 by the water pumping pipe 5 and is sent into the PVC enclosing pipe 6, the PVC enclosing pipe 6 is arranged around the protection shed in a circle, water can form a passage in the PVC enclosing pipe 6, then the water is sprayed out from the spray head 7 at the bottom of the PVC enclosing pipe 6 through water pressure and is sprayed from the top to the periphery of the protection shed, and dust can be reduced from all directions; the support columns 1 on two sides are connected through the side wall plate assembly 8, the side wall plate assembly 8 is favorable for improving the protection effect of the protection shed, the side wall plate is rotated and arranged below the spray head 7, the side wall plate can be flexibly turned and opened as required, when the spray head 7 is opened to spray water, the side wall plate can also be turned and opened outwards, after water drops adsorbing dust fall down, the side wall plate slides to the ground outside the protection shed, after water mist spraying is avoided, water mist is favorably prevented from being splashed into the protection shed, and construction and rest are influenced.
The PVC surrounding pipe 6 comprises a first pipe section 9, a second pipe section 10, a third pipe section 11 and a fourth pipe section 12 which are sequentially communicated end to end; one side of the fourth pipe section 12 is connected with a connector 13; the connector 13 is connected with the water pumping pipe 5; in the embodiment, the PVC enclosing pipe 6 comprises a first pipe section 9, a second pipe section 10, a third pipe section 11 and a fourth pipe section 12 which are sequentially connected end to end, so that the PVC enclosing pipe 6 can be assembled on site when a protective shed is built on site, and the PVC enclosing pipe 6 can be conveniently disassembled and recycled after construction is finished; in the embodiment, the first pipe section 9, the second pipe section 10, the third pipe section 11 and the fourth pipe section 12 are communicated through the connector 13, so that water pumped from the water pumping pipe 5 can pass through the connector and can be sprayed out from the spray head 7; the fourth pipe section 12 is provided with a connector 13 for facilitating connection with the suction pipe 5.
The first pipe section 9, the second pipe section 10, the third pipe section 11 and the fourth pipe section 12 are respectively fixed on the lower edge of the marking frame through pipe hoop assemblies; the water pumping pipe 5 is connected with the supporting column 1 through a pipe hoop component; in the embodiment, the pipe hoop assembly adopts a conventional steel buckle type pipe hoop, and the pipeline is fixed through two hook and loop structures which are connected in a rotating mode; the first pipe section 9, the second pipe section 10, the third pipe section 11 and the fourth pipe section 12 are detachably connected with the marking frame through pipe hoops, so that the disassembly and the assembly are convenient, and the stability in the water spraying process is facilitated; the pumping pipe 5 is connected with the support column 1, so that the working stability of the pumping pipe 5 is facilitated.
The side wall plate assembly 8 comprises a mounting cross beam (not shown in the figure) and a rotating plate 14; the rotating plate 14 is hinged with the mounting cross beam through a hinge; in the embodiment, the mounting beam is arranged below the anti-smashing layer beam 2; the rotating plate 14 and the mounting cross beam are connected through a conventional hinge piece, in the embodiment, the hinge piece with the fixed rotating angle is selected, so that the rotating plate 14 can support a certain angle after rotating for a certain angle, and water is guided to the outer side of the protective shed conveniently. In this embodiment, the mounting beam is located inside the designation frame 3.
The lower end of the rotating plate is provided with a drainage part 15; a diversion trench 16 is processed on the surface of the drainage part 15; a clamping rib 17 extends downwards from the lower end of the drainage part 15; drainage portion 15 can further improve the drainage effect, is favorable to reducing the inside injection of water smoke to the protection canopy, is favorable to improving the comfort level of operation workman in the protection canopy.
A guardrail 18 is arranged below the rotating plate 14; the upper surface of the guardrail 18 is provided with a clamping groove corresponding to the clamping rib 17; in this embodiment, the guard rail 18 can further protect the interior of the shelter, and the guard rail 18 includes a mounting frame and a blocking net; the draw-in groove sets up on the installing frame upper surface, because with card muscle 17 activity joint, when not opening rotor plate 14, can fix rotor plate 14 through draw-in groove and card muscle 17, be favorable to improving the stability of structure.
The rotating plate 14 is provided with a handle groove 19; the handle groove 19 penetrates through the rotating plate 14; the handle groove 19 formed in the rotation plate 14 in this embodiment penetrates the rotation plate 14, and facilitates pulling the handle 20 in the handle groove 19 from both side surfaces of the rotation plate 14.
A handle 20 is rotatably arranged in the handle groove 19; two ends of the handle 20 are hinged with two ends of the handle groove 19; in this embodiment, the handle 20 is solid and is matched with the handle groove 19, and the two ends of the handle 20 and the two ends of the handle groove 19 can be realized by arranging a conventional shaft pin piece, so that the handle 20 can be flexibly turned over on the surfaces of the two sides of the rotating plate 14, and an operator can stand outside the protective shed or in the protective shed to pull the handle 20, and then pull the rotating plate 14 open.
Although the invention has been described herein with reference to a number of illustrative embodiments thereof, it should be understood that numerous other modifications and embodiments can be devised by those skilled in the art that will fall within the spirit and scope of the principles of this invention. More specifically, various variations and modifications are possible in the component parts and/or arrangements of the subject combination arrangement within the scope of the disclosure, the drawings and the appended claims. In addition to variations and modifications in the component parts and/or arrangements, other uses will also be apparent to those skilled in the art.

Claims (8)

1. A safety protection shed for building construction comprises support columns (1), anti-smashing layer cross beams (2) and a marking frame (3), wherein the upper ends of the support columns are detachably connected with the anti-smashing layer cross beams (2); the marking frame (3) is enclosed and blocked around the anti-smashing layer beam (2); the method is characterized in that: a spraying dust-settling device is arranged at the edge of the lower end of the marking frame (3); the spraying dust-settling device comprises a water tank (4), a water pumping pipe (5), a PVC surrounding pipe (6) and a spray head (7); the lower end of the water pumping pipe (5) extends into the water tank (4), and a water pump is connected to the water pumping pipe (5); the upper end of the water pumping pipe (5) is connected with a PVC surrounding pipe (6); the PVC surrounding pipe (6) is detachably arranged around the lower edge of the marking frame (3); the spray head (7) is arranged at the lower part of the PVC surrounding pipe (6); the upper parts of the supporting columns (1) at the two sides are connected through a side wall plate component (8); the side wall plate is rotatably arranged below the spray head (7).
2. The safety protection shed for building construction according to claim 1, characterized in that: the PVC enclosing pipe (6) comprises a first pipe section (9), a second pipe section (10), a third pipe section (11) and a fourth pipe section (12) which are sequentially communicated end to end; one side of the fourth pipe section (12) is connected with a connector (13); the connector (13) is connected with the water pumping pipe (5).
3. The safety protection shed for building construction according to claim 2, characterized in that: the first pipe section (9), the second pipe section (10), the third pipe section (11) and the fourth pipe section (12) are respectively fixed on the lower edge of the marking frame (3) through pipe hoop assemblies; the water pumping pipe (5) is connected with the supporting column (1) through a pipe hoop component.
4. The safety protection shed for building construction according to claim 1, characterized in that: the side wall plate component (8) comprises a mounting cross beam and a rotating plate (14); the rotating plate (14) is hinged with the mounting cross beam through a hinge.
5. The safety protection shed for building construction according to claim 4, characterized in that: the lower end of the rotating plate (14) is provided with a drainage part (15); a diversion trench (16) is processed on the surface of the drainage part (15); the lower end of the drainage part (15) extends downwards to form a clamping rib (17).
6. The safety protection shed for building construction according to claim 5, characterized in that: a guardrail (18) is arranged below the rotating plate (14); the upper surface of the guardrail (18) is provided with a clamping groove corresponding to the clamping rib (17).
7. The safety protection shed for building construction according to claim 4, characterized in that: a handle (20) groove (19) is arranged on the rotating plate (14); the groove (19) of the handle (20) penetrates through the rotating plate (14).
8. The safety protection shed for building construction according to claim 7, characterized in that: the handle (20) is rotatably arranged in the handle (20) groove (19); two ends of the handle (20) are hinged with two ends of the handle (20) groove (19).
CN201922368576.4U 2019-12-25 2019-12-25 Safety protection shed for building construction Expired - Fee Related CN211691578U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922368576.4U CN211691578U (en) 2019-12-25 2019-12-25 Safety protection shed for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922368576.4U CN211691578U (en) 2019-12-25 2019-12-25 Safety protection shed for building construction

Publications (1)

Publication Number Publication Date
CN211691578U true CN211691578U (en) 2020-10-16

Family

ID=72794577

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922368576.4U Expired - Fee Related CN211691578U (en) 2019-12-25 2019-12-25 Safety protection shed for building construction

Country Status (1)

Country Link
CN (1) CN211691578U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114950044A (en) * 2022-06-02 2022-08-30 陈通军 Dustproof device and dustproof method for road construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114950044A (en) * 2022-06-02 2022-08-30 陈通军 Dustproof device and dustproof method for road construction
CN114950044B (en) * 2022-06-02 2023-09-29 新疆丝路光普建设工程有限公司 Dustproof device and dustproof method for road construction

Similar Documents

Publication Publication Date Title
CN211691578U (en) Safety protection shed for building construction
CN106013774B (en) A kind of sliding formwork flexibility platform device for being suitble to dispatch
CN108162203A (en) A kind of metope perforating device with spraying function
CN113338704A (en) Urban highway environment-friendly construction device and construction method
CN216664943U (en) Safety protection frame
CN214615300U (en) Scaffold for construction
CN109577624A (en) Frame-shear structure scaffold system and construction method
CN108722737A (en) A kind of wood strip finishing coat machine
CN213104640U (en) Flange drilling processing circulation cleaning device
CN214613632U (en) Guardrail device of cast-in-place box girder and cast-in-place box girder
CN212262726U (en) Dust absorbing device for machining
CN215926890U (en) Protection canopy for building engineering
CN209034636U (en) A kind of wood strip finishing coat machine
CN218853851U (en) Fixed automatic spraying device for climbing frame
CN215594873U (en) Building construction protection platform
CN212129988U (en) Novel building is climbed and is sprayed device
CN220814835U (en) Construction platform for upright post
CN218308706U (en) Ancient building timber structure three proofings lacquer construction spraying device
CN219943318U (en) Paint spraying tool for bicycle frame machining
CN218360263U (en) Paint spraying equipment for surface of umbrella rib
CN213898038U (en) Gate-type scaffold for construction
CN218522350U (en) Regularization steel bar shed
CN211164591U (en) Concrete tower is rail guard for section of thick bamboo mould
CN107956504A (en) One kind moves liftable high pressure and catches dirt spraying device
CN216787909U (en) Rail guard is used in construction of quick detach formula building engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201016

Termination date: 20211225