CN211689968U - Bridge maintenance construction facility - Google Patents

Bridge maintenance construction facility Download PDF

Info

Publication number
CN211689968U
CN211689968U CN201922241525.5U CN201922241525U CN211689968U CN 211689968 U CN211689968 U CN 211689968U CN 201922241525 U CN201922241525 U CN 201922241525U CN 211689968 U CN211689968 U CN 211689968U
Authority
CN
China
Prior art keywords
fixedly connected
plate
bridge
shaped
backup pad
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922241525.5U
Other languages
Chinese (zh)
Inventor
胡萍凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Sanzu Road And Bridge Engineering Co ltd
Original Assignee
Guangzhou Shenxue Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Shenxue Construction Engineering Co ltd filed Critical Guangzhou Shenxue Construction Engineering Co ltd
Priority to CN201922241525.5U priority Critical patent/CN211689968U/en
Application granted granted Critical
Publication of CN211689968U publication Critical patent/CN211689968U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a bridge maintenance technical field just discloses a bridge maintenance construction facility, including U-shaped case and backup pad, two fixed plates of backup pad right side top fixedly connected with, the one end fixedly connected with U-shaped board of backup pad is kept away from to the fixed plate, there is the motor at the left top of backup pad through overhanging fixed mounting of board, the right side threaded connection of backup pad has the hob. This bridge maintenance construction facility, through setting up the U-shaped case, can let pedestrian or vehicle normally pass, through setting up the floating gate, keep apart bridge construction position, through setting up the motor, the hob, lagging and interior concave type handle, when the construction operation is accomplished and is about to be under construction to the left side on bridge the right, starter motor, make the hob rotate, it moves to drive the lagging, make the U-shaped case also move right, hold interior concave type handle, make the floating gate move left, pedestrian or vehicle's normal passage has been ensured, and the construction position has been transformed, and also facilitate the use.

Description

Bridge maintenance construction facility
Technical Field
The utility model relates to a bridge maintenance technical field specifically is a bridge maintenance construction facility.
Background
The bridge is generally erected on rivers, lakes and seas to enable vehicles, pedestrians and other structures to pass smoothly, in order to adapt to the modern high-speed developed traffic industry, the bridge is also extended to be erected to span mountain ranges, unfavorable geology or meet other traffic needs to enable the bridge to pass more conveniently, in the bridge construction or maintenance process, the safest method is to seal the bridge, but the bridge can greatly influence the trip of people, the normal passing of the pedestrians or vehicles is obstructed, if semi-closed and semi-constructed operation is carried out, potential safety hazards can be caused to the pedestrians or vehicles, the existing bridge maintenance and construction facilities cannot be used for safe construction and normal passing of the pedestrians and vehicles at the same time, and the existing bridge maintenance and construction facilities cannot be used flexibly and are inconvenient.
Disclosure of Invention
Solves the technical problem
The utility model provides a not enough to prior art, the utility model provides a bridge maintenance construction facility possesses can safe construction, can let advantages such as pedestrian and vehicle normal current again, has solved and can not compromise can safe construction and let pedestrian and vehicle normal current, the problem that can not use in a flexible way moreover.
Technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: a bridge maintenance construction facility comprises a U-shaped box and a supporting plate, wherein the top of the right side of the supporting plate is fixedly connected with two fixed plates, one ends of the fixed plates, far away from the supporting plate, are fixedly connected with a U-shaped plate, the top of the left side of the supporting plate is fixedly provided with a motor through an extending plate, the right side of the supporting plate is in threaded connection with a spiral rod, the top of the U-shaped box is fixedly connected with a sleeve plate, the sleeve plate is in threaded connection with the surface of the spiral rod through a threaded hole, the insides of the two fixed plates are respectively provided with a first chute, the insides of the two first chutes are respectively and movably connected with a first roller, the bottoms of the first rollers are fixedly connected with a movable door through a connecting rod, the front side and the back side of the movable door are respectively and fixedly connected with an inward concave handle, the tops, the supporting plate and the U-shaped plate are fixedly connected with springs on the opposite sides, and the other ends of the springs are fixedly connected with buffer plates.
Preferably, the left end of the screw rod penetrates through the right side of the support plate, extends to the outside of the support plate, and is rotatably connected with the output shaft of the motor.
Preferably, the number of the second rollers is four, every two second rollers form a group, and one ends of the second rollers, which are close to the spiral rods, are fixedly connected with the front and the back of the U-shaped box respectively.
Preferably, two the inside of fixed plate all is seted up flutedly, the recess is located first spout under, the inside swing joint of side surface and recess of connecting rod.
Preferably, the top wall of the U-shaped box is fixedly connected with ten street lamps, every five street lamps form a group, and the distance between every two adjacent street lamps in each group is equal.
Preferably, two the equal fixedly connected with warning light in one side that the fixed plate carried on the back mutually.
Preferably, the top of the U-shaped plate is provided with a clamping groove, the bottom of the clamping groove is fixedly connected with a bearing seat, and the inside of the bearing seat is rotatably connected with the right end of the screw rod.
Compared with the prior art, the utility model provides a bridge maintenance construction facility possesses following beneficial effect:
this bridge maintenance construction facility, through setting up the U-shaped case, can let pedestrian or vehicle normally pass, through setting up the floating gate, keep apart bridge construction position, the current safety of pedestrian or vehicle has been ensured, through setting up the motor, the hob, the lagging, first gyro wheel and interior concave type handle, when bridge right construction operation is accomplished and is about to be under construction to the left side, starter motor, make the hob rotate, it moves to drive the lagging right, make the U-shaped case also move right, hold interior concave type handle, make the floating gate move left, make the construction position kept apart, pedestrian or vehicle can normally pass in the U-shaped case that moves to the right simultaneously, and even the construction position has been changeed, also can use in a flexible way.
This bridge maintenance construction facilities through setting up second gyro wheel and second spout for the U-shaped case can remove more in a flexible way, through setting up spring and buffer board, prevents the collision between U-shaped case and U-shaped board and the backup pad, has strengthened this bridge maintenance construction facilities's practicality.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a top view of the present invention;
FIG. 3 is a schematic diagram of the fixing plate structure of the present invention;
fig. 4 is a schematic view of the U-shaped plate structure of the present invention.
Wherein: 1. a U-shaped box; 2. a support plate; 3. a fixing plate; 4. a U-shaped plate; 5. a motor; 6. a screw rod; 7. sheathing; 8. a threaded hole; 9. a first chute; 10. a first roller; 11. a movable door; 12. a concave-shaped handle; 13. a groove; 14. a second chute; 15. a second roller; 16. a spring; 17. a buffer plate; 18. a street lamp; 19. a warning light; 20. and a bearing seat.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, a bridge maintenance and construction facility comprises a U-shaped box 1 and a supporting plate 2, wherein a pedestrian or a vehicle can normally pass through the U-shaped box 1, two fixing plates 3 are fixedly connected to the top of the right side of the supporting plate 2, a U-shaped plate 4 is fixedly connected to one end of the fixing plate 3 away from the supporting plate 2, a motor 5 is fixedly mounted on the top of the left side of the supporting plate 2 through an extending plate, a screw rod 6 is connected to the right side of the supporting plate 2 through a thread, the left end of the screw rod 6 penetrates through the right side of the supporting plate 2 and extends to the outside of the supporting plate 2, and is rotatably connected to an output shaft of the motor 5, a sleeve plate 7 is fixedly connected to the top of the U-shaped box 1, the sleeve plate 7 is connected to the surface of the screw rod 6 through a thread hole 8, first chutes 9 are respectively formed in the two fixing plates 3, the quantity of the first idler wheels 10 is two, the bottom of the first idler wheel 10 is fixedly connected with a movable door 11 through a connecting rod, the construction position of the bridge is isolated through arranging the movable door 11, the passing safety of pedestrians or vehicles is ensured, the front surface and the back surface of the movable door 11 are both fixedly connected with an inward concave handle 12, through arranging a motor 5, a spiral rod 6, a sleeve plate 7, a U-shaped box 1, the movable door 11, the first idler wheel 10 and the inward concave handle 12, when the construction operation is completed on the right side of the bridge and the construction operation is about to be carried out on the left side, the motor 5 is started, the spiral rod 6 is rotated to drive the sleeve plate 7 to move rightwards, the U-shaped box 1 also moves rightwards, the inward concave handle 12 is held by a hand, the movable door 11 moves leftwards, the construction position is isolated, meanwhile, pedestrians or vehicles can normally pass through the U-shaped box 1 moving, the flexible use is also realized, grooves 13 are respectively arranged in the two fixing plates 3, the grooves 13 are positioned under the first sliding grooves 9, the side surfaces of the connecting rods are movably connected with the inner parts of the grooves 13, the top parts of the two fixing plates 3 are respectively provided with a second sliding groove 14, the inner parts of the two second sliding grooves 14 are respectively movably connected with four second rollers 15, the number of the second rollers 15 is four, the U-shaped box 1 can move more flexibly by arranging the second rollers 15 and the second sliding grooves 14, the weight of the U-shaped box 1 is shared, the gravity borne by the sleeve plate 7 is reduced, the number of the second rollers 15 is four, every two second rollers 15 are in one group, one end of each second roller 15, which is close to the spiral rod 6, is respectively fixedly connected with the front surface and the back surface of the U-shaped box 1, one side, which is opposite to the supporting plate 2 and the U-shaped plate 4, a spring 16 is fixedly connected with a buffer plate 17 at, the quantity of spring 16 and buffer board 17 is four, through setting up spring 16 and buffer board 17, prevent the collision between U-shaped case 1 and U-shaped plate 4 and the backup pad 2, the practicality of this bridge maintenance construction facility has been strengthened, the interior roof fixedly connected with street lamp 18 of U-shaped case 1, street lamp 18 can be used for the illumination at night, make things convenient for the pedestrian to walk and the current of vehicle, the quantity of street lamp 18 is ten, and per five street lamps 18 are a set of, the distance between two adjacent street lamps 18 in every group equals, two equal fixedly connected with warning light 19 in one side that fixed plate 3 carried on the back mutually, when the construction at night, warning light 19 can remind pedestrian or vehicle to notice safety, the draw-in groove has been seted up at the top of U-shaped plate 4, draw-in groove bottom fixedly connected with bearing frame 20, the inside of bearing frame 20 rotates with the right-hand.
When using, through setting up U-shaped case 1, pedestrian or vehicle can be current in U-shaped case 1, set up floating gate 11, can keep apart the construction position, the current safety of pedestrian or vehicle has been ensured, when the construction operation completion of bridge right is about to carry out the construction operation to the left side, starter motor 5, make hob 6 rotate, drive lagging 7 and remove right, make U-shaped case 1 also remove right, hold concave type handle 12, make floating gate 11 remove left, make the construction position kept apart, pedestrian or vehicle can normally pass through in the U-shaped case 1 that moves to the right simultaneously.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a bridge maintenance construction facility, includes U-shaped case (1) and backup pad (2), its characterized in that: the top of the right side of the supporting plate (2) is fixedly connected with two fixing plates (3), one end, far away from the supporting plate (2), of each fixing plate (3) is fixedly connected with a U-shaped plate (4), the top of the left side of the supporting plate (2) is fixedly provided with a motor (5) through an extending plate, the right side of the supporting plate (2) is in threaded connection with a spiral rod (6), the top of the U-shaped box (1) is fixedly connected with a sleeve plate (7), the sleeve plate (7) is in threaded connection with the surface of the spiral rod (6) through a threaded hole (8), first sliding grooves (9) are formed in the two fixing plates (3), first rollers (10) are movably connected in the two first sliding grooves (9), the bottom of each first roller (10) is fixedly connected with a movable door (11) through a connecting rod, and concave handles (12) are fixedly connected to the front side and the back side of, two second spout (14), two have all been seted up at the top of fixed plate (3) the equal swing joint in inside of second spout (14) has second gyro wheel (15), the equal fixedly connected with spring (16) in one side that backup pad (2) and U-shaped board (4) are relative, the other end fixedly connected with buffer board (17) of spring (16).
2. A bridge servicing construction installation according to claim 1, wherein: the left end of the screw rod (6) penetrates through the right side of the support plate (2), extends to the outside of the support plate (2), and is rotatably connected with an output shaft of the motor (5).
3. A bridge servicing construction installation according to claim 1, wherein: the number of the second rollers (15) is four, every two second rollers (15) form a group, and one end, close to the spiral rod (6), of each second roller (15) is fixedly connected with the front face and the back face of the U-shaped box (1) respectively.
4. A bridge servicing construction installation according to claim 1, wherein: grooves (13) are formed in the two fixing plates (3), the grooves (13) are located right below the first sliding grooves (9), and the side surfaces of the connecting rods are movably connected with the insides of the grooves (13).
5. A bridge servicing construction installation according to claim 1, wherein: the street lamps (18) are fixedly connected to the inner top wall of the U-shaped box (1), the number of the street lamps (18) is ten, every five street lamps (18) form a group, and the distance between every two adjacent street lamps (18) in each group is equal.
6. A bridge servicing construction installation according to claim 1, wherein: two the equal fixedly connected with warning light (19) in one side that fixed plate (3) carried on the back mutually.
7. A bridge servicing construction installation according to claim 1, wherein: the top of U-shaped plate (4) has seted up the draw-in groove, draw-in groove bottom fixedly connected with bearing frame (20), the inside of bearing frame (20) is rotated with the right-hand member of hob (6) and is connected.
CN201922241525.5U 2019-12-15 2019-12-15 Bridge maintenance construction facility Expired - Fee Related CN211689968U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922241525.5U CN211689968U (en) 2019-12-15 2019-12-15 Bridge maintenance construction facility

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922241525.5U CN211689968U (en) 2019-12-15 2019-12-15 Bridge maintenance construction facility

Publications (1)

Publication Number Publication Date
CN211689968U true CN211689968U (en) 2020-10-16

Family

ID=72791265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922241525.5U Expired - Fee Related CN211689968U (en) 2019-12-15 2019-12-15 Bridge maintenance construction facility

Country Status (1)

Country Link
CN (1) CN211689968U (en)

Similar Documents

Publication Publication Date Title
CN211689968U (en) Bridge maintenance construction facility
CN108777451B (en) Convenient cable installation alignment jig for electric power engineering construction who adjusts
CN103818504B (en) The electro-tricycle that vehicle frame can stretch
CN211395504U (en) Automatic roadblock device of traffic management
CN216596539U (en) Signal indicating device for smart urban road traffic
CN112185142B (en) Wisdom traffic signal pilot lamp
CN210341750U (en) Traffic guide guardrail for city planning
CN209593349U (en) A kind of portable photovoltaic apparatus in field
CN211815787U (en) District entrance guard is banister for vehicle management
CN108166411A (en) A kind of berth lock
CN214737578U (en) Height limiting device for highway bridge
CN210416434U (en) Automatic drive sightseeing vehicle roof equipment fixing device
CN215254980U (en) Rainproof device for stereo garage
CN215052425U (en) Parking area is with intelligent banister
CN220579786U (en) Bridge anti-overturning device
CN213869230U (en) Interim guardrail of hydraulic engineering construction usefulness
CN211142849U (en) Bridge maintenance hoist device
CN214091334U (en) Protection device is used in railway work operation construction
CN210013143U (en) Rail guard is used in public road bridge roof beam construction
CN218843950U (en) Municipal administration public works rail guard
CN213987659U (en) New retail device with voice function and convenient to transport and move
CN214565440U (en) Tricycle skeleton reinforcing box
CN216551681U (en) Roadblock is used in road engineering construction
CN215164893U (en) Traffic facilities sign convenient to installation
CN215254973U (en) Sideslip device for stereo garage

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220804

Address after: No. 2, 3, 4, 10th Floor, Unit 1, Building 1, No. 11, Yuren North Road, Jinniu District, Chengdu, Sichuan 610000

Patentee after: Sichuan SANZU road and Bridge Engineering Co.,Ltd.

Address before: 510515 No. a14093, Guangzhou new Baijia Commodity City, east side of jingxiqiao, Baiyun District, Guangzhou City, Guangdong Province

Patentee before: Guangzhou Shenxue Construction Engineering Co.,Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201016

CF01 Termination of patent right due to non-payment of annual fee