CN211665588U - Shearing-resistant corbel structure at top of steel pipe pile - Google Patents

Shearing-resistant corbel structure at top of steel pipe pile Download PDF

Info

Publication number
CN211665588U
CN211665588U CN201922376476.6U CN201922376476U CN211665588U CN 211665588 U CN211665588 U CN 211665588U CN 201922376476 U CN201922376476 U CN 201922376476U CN 211665588 U CN211665588 U CN 211665588U
Authority
CN
China
Prior art keywords
pipe pile
bracket
top plate
steel pipe
slots
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922376476.6U
Other languages
Chinese (zh)
Inventor
周先念
祝长春
朱正伟
吴筱文
赵航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201922376476.6U priority Critical patent/CN211665588U/en
Application granted granted Critical
Publication of CN211665588U publication Critical patent/CN211665588U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a shearing-resistant bracket structure at the top of a steel pipe pile, wherein a bracket comprises a horizontally arranged rectangular top plate, two vertical plates are welded on the bottom surface of the top plate, bracket mounting ports with the width equal to that of the top plate are arranged on two opposite sides of the top of the steel pipe pile, two vertical slots are arranged on the bottom edge of the bracket mounting ports, the distance between the two slots is equal to the distance between the two vertical plates of the bracket, and the depth of the slot is equal to the height of the vertical plates; the two vertical plates of the bracket are respectively inserted into the two slots and welded with the two sides of the slots, and the lengths of the two ends of the top plate extending to the outer side of the steel pipe pile are equal. The utility model changes the on-site overhead welding process of the traditional bracket into the flat welding process in the processing yard, which can improve the welding quality; shear-resistant conversion of conventional steel-pipe pile is bracket tensile and bending resistance, can effectively improve shear-resistant and whole compressive capacity at steel-pipe pile top.

Description

Shearing-resistant corbel structure at top of steel pipe pile
Technical Field
The utility model relates to a bearing structure of bridge construction field large steel construction, concretely relates to install bracket structure that shears at steel-pipe pile top.
Background
Often adopt the steel-pipe pile as the bearing structure of support or platform in road bridge engineering, set up the corbel at the steel pipe top and regard as superstructure's strong point, all loads of superstructure all transmit the steel-pipe pile through the corbel on. The conventional bracket adopts two triangular or trapezoidal steel plates (shear plates) to weld the outer side of the steel pipe, the panel is welded at the top of the shear plate to form the steel bracket, the vertical welding and overhead welding are involved in the bracket welding process, the welding quality of the overhead welding is difficult to guarantee under the influence of the field construction environment, and the steel pipe opening is easily torn by the bracket when bearing large load, so that safety accidents are caused.
Disclosure of Invention
The utility model aims at the defect that current steel-pipe pile top bracket structure exists, provide one kind and install the bracket structure that shears at steel-pipe pile top, with difficult welded position by the scene to the processing field in prefabricated, then transport to the field installation to reduce the construction degree of difficulty, improve construction quality, optimize the bracket structure simultaneously, increase the steel-pipe pile ability of shearing, improve structural security.
The technical scheme of the utility model as follows:
the utility model provides a corbel structure that shears at steel-pipe pile top, includes bracket and steel-pipe pile, its characterized in that: the bracket comprises a horizontally arranged rectangular top plate, the width of the top plate is smaller than the diameter of the steel pipe pile, the length of the top plate is larger than the diameter of the steel pipe pile, and two vertical plates which are perpendicular to the top plate and have a certain distance are welded on the bottom surface of the top plate in parallel along the longitudinal direction of the top plate; two opposite sides of the top of the steel pipe pile are provided with bracket mounting openings with the same width as the top plate, the bottom edge of each bracket mounting opening is provided with two vertical slots extending downwards, the distance between the two slots is equal to the distance between two vertical plates of a bracket, and the depth of each slot is equal to the height of the vertical plate; the two vertical plates of the bracket are respectively inserted into the two slots and welded with the two sides of the slots, and the lengths of the two ends of the top plate extending to the outer side of the steel pipe pile are equal.
The utility model sets the corbels at both sides of the conventional steel pipe pile into an integral structure, converts the shearing resistance of the conventional steel pipe pile into the tensile and bending resistance of the corbel, can effectively improve the shearing resistance and the integral compression resistance of the top of the steel pipe pile, and greatly improves the bearing capacity of the top of the steel pipe pile; because the prefabricated assembly technology is adopted, the on-site overhead welding technology is changed into the flat welding technology in a processing field, the blanking and cutting quality of steel can be ensured, the length of a welding seam of on-site welding is reduced, and the construction quality is improved.
Drawings
Fig. 1 is a schematic side view of the present invention;
fig. 2 is a schematic front view of the present invention;
fig. 3 is a schematic top view of the present invention;
fig. 4 is a schematic structural view of the steel pipe pile.
Detailed Description
As shown in fig. 1, 2 and 3, the utility model comprises a bracket and a steel pipe pile, wherein the bracket comprises a horizontally arranged rectangular top plate 1, the width of the top plate 1 is smaller than the diameter of the steel pipe pile 3, the length of the top plate is larger than the diameter of the steel pipe pile, and two vertical plates 2 which are vertical to the top plate and have a certain distance are welded on the bottom surface of the top plate 1 in parallel along the longitudinal direction of the top plate; the structure of the steel pipe pile 3 is shown in fig. 4, two opposite sides of the top of the steel pipe pile are provided with bracket mounting openings 31 with the same width as the top plate, the bottom edge of each bracket mounting opening 31 is provided with two vertical slots 32 extending downwards, the distance between the two slots 32 is equal to the distance between the two vertical plates 2 of the bracket, and the depth of each slot 32 is equal to the height of the vertical plate 2; the two vertical plates 2 of the bracket are respectively inserted into the two slots 32 and welded with the two sides of the slots, and the lengths of the two ends of the top plate 1 extending to the outer side of the steel pipe pile 3 are equal.
The utility model discloses during the concrete implementation, riser 2 is the isosceles trapezoid structure that topside length is greater than base length, and the length on 2 bases of riser is greater than or equal to steel-pipe pile 3's diameter.
The bracket top plate 1 and the two vertical plates 2 of the utility model can be welded in a processing field in advance, the field overhead welding of the common bracket is changed into the flat welding of the processing field, the construction difficulty is greatly reduced, and the welding quality can be ensured; a bracket mounting opening 31 and a slot 32 are formed in the top of the steel pipe pile 3 in advance; after the steel pipe pile is inserted and driven in a construction site, the two vertical plates 2 of the bracket are inserted into the slots 32 of the steel pipe pile and are welded with the slots, and then bracket installation is completed. The installation site only has a vertical welding process, so that the installation quality can be ensured; meanwhile, the load at the top of the steel pipe pile mainly depends on the tensile strength and the bending resistance of the bracket, the shearing force borne by the pipe wall of the steel pipe pile is reduced, and the bearing capacity of the steel pipe pile can be improved.

Claims (2)

1. The utility model provides a corbel structure that shears at steel-pipe pile top, includes bracket and steel-pipe pile, its characterized in that: the bracket comprises a horizontally arranged rectangular top plate, the width of the top plate is smaller than the diameter of the steel pipe pile, the length of the top plate is larger than the diameter of the steel pipe pile, and two vertical plates which are perpendicular to the top plate and have a certain distance are welded on the bottom surface of the top plate in parallel along the longitudinal direction of the top plate; two opposite sides of the top of the steel pipe pile are provided with bracket mounting openings with the same width as the top plate, the bottom edge of each bracket mounting opening is provided with two vertical slots extending downwards, the distance between the two slots is equal to the distance between two vertical plates of a bracket, and the depth of each slot is equal to the height of the vertical plate; the two vertical plates of the bracket are respectively inserted into the two slots and welded with the two sides of the slots, and the lengths of the two ends of the top plate extending to the outer side of the steel pipe pile are equal.
2. The shear-resistant corbel structure at the top of the steel pipe pile according to claim 1, wherein: the vertical plate is of an isosceles trapezoid structure, the length of the top edge of the isosceles trapezoid structure is larger than that of the bottom edge of the isosceles trapezoid structure, and the length of the bottom edge of the vertical plate is larger than or equal to the diameter of the steel pipe pile.
CN201922376476.6U 2019-12-25 2019-12-25 Shearing-resistant corbel structure at top of steel pipe pile Active CN211665588U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922376476.6U CN211665588U (en) 2019-12-25 2019-12-25 Shearing-resistant corbel structure at top of steel pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922376476.6U CN211665588U (en) 2019-12-25 2019-12-25 Shearing-resistant corbel structure at top of steel pipe pile

Publications (1)

Publication Number Publication Date
CN211665588U true CN211665588U (en) 2020-10-13

Family

ID=72734861

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922376476.6U Active CN211665588U (en) 2019-12-25 2019-12-25 Shearing-resistant corbel structure at top of steel pipe pile

Country Status (1)

Country Link
CN (1) CN211665588U (en)

Similar Documents

Publication Publication Date Title
CN108049633A (en) A kind of precast concrete concrete frame joint construction method
CN107338873B (en) Unilateral buckling restrained steel beam and column connecting node and steel structure building
CN102926504B (en) Construction method of steel and concrete overlapped beam combined part
CN114855594B (en) Shearing-resistant connecting piece of steel-concrete composite girder bridge and construction method thereof
CN202954464U (en) Steel bar truss template
CN102493553A (en) Member for connection node of reinforced beam and steel beam and construction method thereof
CN202227283U (en) Reinforcement structure for T beam truss
CN110965479A (en) Detachable lifting lug for vertical lifting of assembled bridge pier stud and bracket-free mounting of cover beam and bracket-free mounting platform of cover beam
CN211665588U (en) Shearing-resistant corbel structure at top of steel pipe pile
CN203514528U (en) Composite connection structure of concrete filled steel tubular column and thin steel plate shear wall
CN205954478U (en) Assembled concrete barrier and adopt its bridge
CN110130485B (en) Prefabricated assembly type beam column node with toothed plates and assembly method thereof
CN104032862B (en) Assembled girder steel seam line L shape mixing coupled wall and construction method thereof
CN209907689U (en) Prefabricated member of floor member unit assembly
CN203361170U (en) Supporting upright column pile for building foundation pit support
CN206143927U (en) Node of beam manufacturing and prefabricated plate in advance
CN215164796U (en) A nose girder mounting structure for steel box girder top pushes away construction
CN106088437A (en) A kind of superimposed sheet strengthening two-way transmission force property
CN105350447A (en) Bottom plate connecting structure for precast segmental concrete bridge and construction method thereof
CN215104604U (en) Connecting device for prefabricated bridge pier and bearing platform
CN202347665U (en) Connection node constructional member of reinforced concrete beam and steel beam
CN210369315U (en) Building system adopting steel construction column-steel ring beam
CN212956103U (en) Assembled multi-pier column and bent cap assembling structure
CN210013109U (en) Combined beam pier and bridge consolidation structure and bridge
CN212000620U (en) Connecting structure of prefabricated concrete anti-collision guardrail and bridge deck

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant