CN210369315U - Building system adopting steel construction column-steel ring beam - Google Patents

Building system adopting steel construction column-steel ring beam Download PDF

Info

Publication number
CN210369315U
CN210369315U CN201920842396.2U CN201920842396U CN210369315U CN 210369315 U CN210369315 U CN 210369315U CN 201920842396 U CN201920842396 U CN 201920842396U CN 210369315 U CN210369315 U CN 210369315U
Authority
CN
China
Prior art keywords
steel
steel ring
column
construction
steel construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920842396.2U
Other languages
Chinese (zh)
Inventor
杨俊�
徐国军
田宇治
王振颖
习友冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Green Building Integration Technology Co Ltd
Original Assignee
Zhejiang Green Building Integration Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Green Building Integration Technology Co Ltd filed Critical Zhejiang Green Building Integration Technology Co Ltd
Priority to CN201920842396.2U priority Critical patent/CN210369315U/en
Application granted granted Critical
Publication of CN210369315U publication Critical patent/CN210369315U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model relates to a building system adopting steel construction columns and steel ring beams, which comprises a main beam, the steel construction columns, the steel ring beams, a filler wall and a hanging net plastering; wherein the main beam is welded with a connecting plate; the steel construction columns are connected to the connecting plates through bolts, so that the steel construction columns are vertically connected between the main beams; the steel ring beam is vertically connected to the steel construction column; the filler wall is arranged between the main beams; the steel construction column is coated at the end part of the filler wall; the steel ring beams are arranged between the filler walls; the net hanging plastering is arranged on the surfaces of the filler wall, the steel construction column and the steel ring beam. The steel construction column and the ring beam of the construction system adopting the steel construction column-steel ring beam adopt hot rolled channel steel, and the purchase is convenient; the steel construction column is connected with the main beam by bolts; the steel ring beam and the steel construction column are connected in a welding mode, so that construction is convenient and simple, wet operation and templates are reduced on site, construction efficiency of a building is greatly improved, and the steel ring beam and the steel construction column are safe and environment-friendly.

Description

Building system adopting steel construction column-steel ring beam
[ technical field ] A method for producing a semiconductor device
The utility model relates to a building element, concretely relates to adopt steel construction post-steel loop beam's building system belongs to building engineering technical field.
[ background of the invention ]
China vigorously pushes the traditional building to be transformed into an industrialized building. In the traditional building, most constructional columns need to be completed on a construction site, and the problems of long construction period, more wet operation, serious environmental pollution, more template materials, shortage of constructors and the like become barriers for inhibiting the progress of the building industry.
The steel structural body and the steel structural column are representative of prefabricated and assembled building products. The steel structure has the advantages of high construction speed, good earthquake resistance and recyclable materials. The steel structure column has the advantages of fast construction, convenient connection, no wet operation and no template. If the two can be combined, the advantages of the assembled building can be better embodied.
Therefore, in order to solve the above technical problems, it is necessary to provide an innovative construction system using steel construction columns-steel ring beams to overcome the above-mentioned drawbacks of the prior art.
[ Utility model ] content
In order to solve the above problems, an object of the present invention is to provide a construction system using steel construction columns-steel ring beams, which can reduce wet work and forms on site, is convenient to construct, and is safe and environment-friendly.
In order to achieve the above purpose, the utility model adopts the following technical scheme: a building system adopting steel construction columns and steel ring beams comprises a main beam, the steel construction columns, the steel ring beams, a filler wall and a hanging net plastering; wherein the main beam is welded with a connecting plate; the steel construction columns are connected to the connecting plates through bolts, so that the steel construction columns are vertically connected between the main beams; the steel ring beam is vertically connected to the steel construction column; the filler wall is arranged between the main beams; the steel construction column is coated at the end part of the filler wall; the steel ring beams are arranged between the filler walls; the net hanging plastering is arranged on the surfaces of the filler wall, the steel construction column and the steel ring beam.
The utility model discloses an adopt building system of steel structure post-steel ring roof beam further sets up to: the steel constructional column and the steel ring beam are hot rolled channel steel; the tip of steel ring roof beam inserts in the steel structure post, and both are in the same place through fillet weld welding.
The utility model discloses an adopt building system of steel structure post-steel ring roof beam further sets up to: the connecting plate is provided with a long round hole, and the bolt can be adjusted in the long round hole.
The utility model discloses an adopt steel structure post-steel ring roof beam's building system still sets up to: the main beam is specifically H-shaped steel.
Compared with the prior art, the utility model discloses following beneficial effect has: the steel construction column and the ring beam of the construction system adopting the steel construction column-steel ring beam adopt hot rolled channel steel, and the purchase is convenient; the steel construction column is connected with the main beam by bolts; the steel ring beam and the steel construction column are connected in a welding mode, so that construction is convenient and simple, wet operation and templates are reduced on site, construction efficiency of a building is greatly improved, and the steel ring beam and the steel construction column are safe and environment-friendly.
[ description of the drawings ]
Fig. 1 is an elevation view of the steel column-steel ring beam building system of the present invention.
Fig. 2 is a cross-sectional view taken along a-a in fig. 1.
Fig. 3 is a cross-sectional view taken along B-B in fig. 1.
Fig. 4 is a schematic view of the connection of the main beam and steel structural columns of fig. 1.
Fig. 5 is a schematic view of the connection of fig. 4 from another perspective.
Fig. 6 is a schematic view of the connection of the steel ring beam and the steel structural column of fig. 1.
[ detailed description ] embodiments
Referring to the attached drawings 1 to 6 in the specification, the utility model relates to a building system using steel construction column-steel ring beam, which comprises a main beam 1, a steel construction column 2, a steel ring beam 3, a filler wall 4 and a hanging net plastering 5.
The main beam 1 is specifically H-shaped steel, and a connecting plate 6 is welded on the main beam. The connecting plate 6 is provided with a long round hole 61.
The steel structural column 2 is connected to the connecting plate 6 by bolts 7, so that the steel structural column 2 is vertically connected between the main beams 1. The bolt 7 can be adjusted in the oblong hole 6 to adjust the installation position of the steel structural column 2, so that the steel structural column 2 is installed. In the present embodiment, the steel structural column 2 is specifically a hot-rolled steel channel.
The steel ring beam 3 is vertically connected to the steel construction column 2, and is also made of hot rolled channel steel. Specifically, the end of the steel ring beam 3 is inserted into the steel structural column 2, and the two are welded together by fillet welding.
The infilled walls 4 are arranged between the main beams 1. The steel constructional column 2 is coated at the end part of the filler wall 1. The steel ring beams 3 are arranged between the infill walls 4. The strength of the infilled wall 4 is enhanced by the steel structural columns 2 and steel ring beams 3.
The hanging net plastering 5 is arranged on the surfaces of the filler wall 4, the steel construction column 2 and the steel ring beam 3.
The steel construction column 2 and the steel ring beam 3 in the construction system adopting the steel construction column-steel ring beam have the advantages of high construction speed, good earthquake resistance and recyclable materials; the steel construction column 2 is connected with the main beam 1 through bolts; the steel ring beam 3 and the steel construction column 2 are connected in a welding mode, so that construction is convenient and simple, wet operation and templates are reduced on site, construction efficiency of buildings is greatly improved, and the steel ring beam is safe and environment-friendly.
The above embodiments are merely preferred embodiments of the present disclosure, which are not intended to limit the present disclosure, and any modifications, equivalents, improvements and the like, which are within the spirit and principle of the present disclosure, should be included in the scope of the present disclosure.

Claims (4)

1. The utility model provides an adopt steel construction post-steel ring roof beam's building system which characterized in that: the steel ring beam is connected with the main beam through a steel ring beam; wherein the main beam is welded with a connecting plate; the steel construction columns are connected to the connecting plates through bolts, so that the steel construction columns are vertically connected between the main beams; the steel ring beam is vertically connected to the steel construction column; the filler wall is arranged between the main beams; the steel construction column is coated at the end part of the filler wall; the steel ring beams are arranged between the filler walls; the net hanging plastering is arranged on the surfaces of the filler wall, the steel construction column and the steel ring beam.
2. The building system using steel structure column-steel ring beam of claim 1, wherein: the steel constructional column and the steel ring beam are hot rolled channel steel; the tip of steel ring roof beam inserts in the steel structure post, and both are in the same place through fillet weld welding.
3. The building system using steel structure column-steel ring beam of claim 1, wherein: the connecting plate is provided with a long round hole, and the bolt can be adjusted in the long round hole.
4. The building system using steel structure column-steel ring beam of claim 1, wherein: the main beam is specifically H-shaped steel.
CN201920842396.2U 2019-06-05 2019-06-05 Building system adopting steel construction column-steel ring beam Active CN210369315U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920842396.2U CN210369315U (en) 2019-06-05 2019-06-05 Building system adopting steel construction column-steel ring beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920842396.2U CN210369315U (en) 2019-06-05 2019-06-05 Building system adopting steel construction column-steel ring beam

Publications (1)

Publication Number Publication Date
CN210369315U true CN210369315U (en) 2020-04-21

Family

ID=70263521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920842396.2U Active CN210369315U (en) 2019-06-05 2019-06-05 Building system adopting steel construction column-steel ring beam

Country Status (1)

Country Link
CN (1) CN210369315U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115354778A (en) * 2022-07-13 2022-11-18 中建科工集团有限公司 Assembled wall structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115354778A (en) * 2022-07-13 2022-11-18 中建科工集团有限公司 Assembled wall structure

Similar Documents

Publication Publication Date Title
CN204023778U (en) The connected node of prefabricated assembled concrete beam column
CN201738458U (en) Novel assembly type end-plate connecting node of cold-bending rectangular steel pipe column and H type steel beam
CN102359180B (en) Truss combined beam and upper and layer connected light steel structure and construction method thereof
CN202248251U (en) Lightweight steel construction for connecting truss combination beams, upper layer and lower layer
CN208934197U (en) The plug-in filling wall construction system of steel frame and assembled filled-in panel
CN204475846U (en) A kind of conversion support system for socket joint dish button steel tube frame
CN105275087A (en) A prefabricated assembled type concrete beam-column connecting structure
CN202430876U (en) Floor system with structure of steel and concrete precast slabs
CN210369315U (en) Building system adopting steel construction column-steel ring beam
CN103437493A (en) Connecting node of prefabricated reinforced concrete beam and construction method of connecting node
CN210530135U (en) Vertical concatenation node structure of partial cladding shaped steel concrete column
CN207144181U (en) The attachment structure of assembly concrete-filled steel tube post and girder steel
CN214739017U (en) Steel tube bundle combined shear wall and steel beam connecting device
CN202055413U (en) Huge column shaped like double Chinese character YA
CN213539882U (en) Middle node of steel pipe concrete column H-shaped steel beam support pi-shaped connecting side column
CN213773849U (en) L-shaped concrete filled steel tube column and steel beam bolted welding connection node structure
CN211257025U (en) Steel sheet pile cofferdam with slip casting platform
CN113944309A (en) Cold-formed steel support beam framework and construction method thereof
CN210767970U (en) Assembled foundation pit ladder
CN210562620U (en) Inserting-mortise connection prefabricated assembly type steel frame structure
CN211622006U (en) H-shaped steel beam and square tube steel column strong shaft rigid connection node using vertical stiffening plate
CN211622007U (en) H-shaped steel beam and square tube steel column weak axis rigid connection node using vertical stiffening plate
CN207633583U (en) A kind of connection structure of prefabricated post and prefabricated partition wall
CN111962953A (en) Steel tube concrete column-H-shaped steel beam-steel support-pi-shaped connecting piece combined side column middle node and manufacturing method
CN205894389U (en) Novel external wallboard node

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Anhui Zhihong Precision Construction Technology Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2023990000037

Denomination of utility model: A building system with steel structure column-steel ring beam

Granted publication date: 20200421

License type: Common License

Record date: 20230113

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Jiangxi Huahong Jinggong Steel Structure Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2023980034645

Denomination of utility model: A building system using steel columns and steel ring beams

Granted publication date: 20200421

License type: Common License

Record date: 20230413

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Jiangsu Lvjian Jinggong Technology Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2023980034833

Denomination of utility model: A building system using steel columns and steel ring beams

Granted publication date: 20200421

License type: Common License

Record date: 20230421

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Weinan Guokong Jinggong Green Building Technology Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2024980009941

Denomination of utility model: A building system using steel columns and steel ring beams

Granted publication date: 20200421

License type: Common License

Record date: 20240717

EE01 Entry into force of recordation of patent licensing contract

Assignee: Chongqing Kunda Precision Integrated Technology Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2024980014873

Denomination of utility model: A building system using steel columns and steel ring beams

Granted publication date: 20200421

License type: Common License

Record date: 20240914

EE01 Entry into force of recordation of patent licensing contract

Assignee: Anhui Huiyu Construction Engineering Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2024980016463

Denomination of utility model: A building system using steel columns and steel ring beams

Granted publication date: 20200421

License type: Common License

Record date: 20240926