CN211647202U - Combined building construction scaffold - Google Patents

Combined building construction scaffold Download PDF

Info

Publication number
CN211647202U
CN211647202U CN201921795701.3U CN201921795701U CN211647202U CN 211647202 U CN211647202 U CN 211647202U CN 201921795701 U CN201921795701 U CN 201921795701U CN 211647202 U CN211647202 U CN 211647202U
Authority
CN
China
Prior art keywords
block
rod
spring
working plate
opposite
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921795701.3U
Other languages
Chinese (zh)
Inventor
丁超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921795701.3U priority Critical patent/CN211647202U/en
Application granted granted Critical
Publication of CN211647202U publication Critical patent/CN211647202U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model relates to a building technical field just discloses a modular construction scaffold frame, be four support, the left and right sides including quantity the equal movable mounting in top and the bottom of the relative one side of support has the sliding block. This modular construction scaffold frame, through pressing the briquetting and making according to the briquetting because the effort retraction spring inslot portion of first spring, the pulling movable rod gets into inside the dead lever, make the movable rod break away from with the working plate, then the flexible piece of pulling makes it break away from with the joint block, when the one side pulling pull ring towards the dead lever, the carriage release lever, block and the whole dead lever direction motion towards of second spring, then fix the block on the connecting block, thereby make the grafting block break away from the insertion block, realize the dismantlement of scaffold frame middle part connecting piece, then take two upper and lower working plates out through the slip sliding block, wholly realize scaffold frame dismantlement's purpose, greatly reduced the time of installation.

Description

Combined building construction scaffold
Technical Field
The utility model relates to a building technical field specifically is a modular construction scaffold frame.
Background
The scaffold is a working platform which is erected for ensuring that each construction process is smoothly carried out, and is divided into an outer scaffold and an inner scaffold according to the erected position, and the scaffold can be divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials.
The scaffold has that the load variability that receives is great, fastener connected node belong to semi-rigid and great etc. of the restrictive variation of tie point to scaffold with the wall, scaffold on the existing market has the inconvenient shortcoming of dismouting, lead to the workman to use the installation of external instrument when the scaffold need be used in the construction to greatly increased the time of installation scaffold, reduced work efficiency, so proposed a modular construction scaffold in order to solve above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The utility model provides a not enough to prior art, the utility model provides a modular construction scaffold possesses advantages such as the dismouting of being convenient for, has solved the scaffold frame on the current market and has had the inconvenient shortcoming of dismouting, leads to the workman to install with external tool when the scaffold frame need be used in the construction to greatly increased the time of installation scaffold frame, reduced work efficiency's problem.
(II) technical scheme
In order to realize the purpose of convenient disassembly and assembly, the utility model provides a following technical scheme: a combined scaffold for building construction comprises four brackets, sliding blocks are movably mounted at the top and the bottom of the opposite sides of the brackets at the left and right sides, a working plate is fixedly mounted between the opposite sides of the sliding blocks, a movable rod is movably mounted at the opposite side of the working plate, a spring groove is formed in the movable rod, a first spring is fixedly connected with the rear side wall of the spring groove, one end of the front side of the first spring is fixedly connected with a pressing block which sequentially penetrates through the spring groove and the working plate and extends to the outer side of the working plate, the opposite end of the movable rod penetrates through and extends to the inside of the fixed rod and is movably connected with the fixed rod, connecting rods are fixedly connected with the left and right sides of the fixed rod, connecting blocks are fixedly mounted at the tops of the connecting rods, and second springs are fixedly connected with the opposite sides of the, the utility model discloses a connecting rod, including the first spring, the second spring is back of the body all fixed mounting have one end to run through and extend to the outside grafting piece of connecting rod, the top fixedly connected with carriage release lever of grafting piece, the top fixedly connected with pull ring of carriage release lever, one side that the carriage release lever is relative all articulates through the pivot has the block, one side that the grafting piece was back of the body all runs through and extends to the inside and swing joint of grafting piece and have the block of inserting, block and support swing joint insert, the bottom fixedly connected with installation pole of connecting rod, one side fixed mounting that the connecting rod was kept away from to the installation pole has flexible piece, the equal joint in one side that flexible piece was back of the body mutually has the joint piece, joint piece and support fixed connection, the bottom swing joint of support has.
Preferably, the sliding groove is formed in one side, opposite to the support, of the support, the volume of the sliding groove is matched with the volume of the sliding block, the matching groove is formed in one side, opposite to the inserting block, of the inserting block, and the matching groove is matched with the inserting block.
Preferably, the quantity of working plate is two, two the working plate is the symmetry equidistance and distributes, and two working plate volumes inequality, the activity hole has been seted up in the front of working plate, the activity hole with press a briquetting looks adaptation.
Preferably, the telescopic block consists of a fixed block and a movable sleeve, and one end of the inner side of the movable sleeve is movably connected with the fixed block, penetrates through the fixed block and extends to the outside of the movable sleeve.
Preferably, the quantity of connecting rod is two, two the connecting rod is the equidistance of symmetry and distributes, the quantity of rubber sleeve is four, four the rubber sleeve is the equidistance of symmetry and distributes.
Preferably, the connecting groove has all been seted up to the opposite one side of working plate, the volume of connecting groove and the volume looks adaptation of movable rod.
(III) advantageous effects
Compared with the prior art, the utility model provides a modular construction scaffold frame possesses following beneficial effect:
1. this modular construction scaffold frame, through pressing the briquetting and making according to the briquetting because the effort retraction spring inslot portion of first spring, the pulling movable rod gets into inside the dead lever, make the movable rod break away from with the working plate, then the flexible piece of pulling makes it break away from with the joint block, when the one side pulling pull ring towards the dead lever, the carriage release lever, block and the whole dead lever direction motion towards of second spring, then fix the block on the connecting block, thereby make the grafting block break away from the insertion block, realize the dismantlement of scaffold frame middle part connecting piece, then take two upper and lower working plates out through the slip sliding block, wholly realize scaffold frame dismantlement's purpose, greatly reduced installation time.
2. This modular construction scaffold frame, push and install on the support two upper and lower working plates through the slip sliding block, promote the movable rod, can be because the effort retraction spring inslot of first spring when the movable rod is inside according to briquetting contact working plate, can pop out fixedly when contacting according to the briquetting and seting up at the positive movable orifice of working plate, then promote flexible piece and make its and joint block joint, deviate from one side pulling of dead lever with the pull ring, the carriage release lever, block and the whole lateral motion to deviating from the dead lever of second spring, thereby make the grafting piece peg graft in the grafting piece, the function of quick installation has been realized, the purpose of the dismouting of being convenient for has been reached, greatly reduced installation time.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the internal structure of the movable rod of the present invention;
FIG. 3 is a schematic view of the connection structure of the connecting rod and the second spring according to the present invention;
fig. 4 is an enlarged view of a portion a in fig. 1 according to the present invention.
In the figure: the device comprises a support 1, a sliding block 2, a working plate 3, a movable rod 4, a spring groove 5, a first spring 6, a pressing block 7, a fixed rod 8, a connecting rod 9, a connecting block 10, a second spring 11, an inserting block 12, a pull ring 13, a movable rod 14, a clamping block 15, an inserting block 16, an installing rod 17, an expansion block 18, a joint block 19 and a rubber sleeve 20.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, rather than all embodiments, and all other embodiments obtained by a person of ordinary skill in the art without creative work belong to the protection scope of the present invention based on the embodiments of the present invention.
Referring to fig. 1-4, the present invention provides the following technical solutions: a combined scaffold for building construction comprises four brackets 1, sliding blocks 2 are movably mounted at the top and the bottom of one side of each of the left and right brackets 1 opposite to each other, an upper working plate 3 and a lower working plate 3 are pushed in and mounted on the brackets 1 through the sliding blocks 2 to push a movable rod 4, when a pressing block 7 inside the movable rod 4 contacts the working plates 3, the pressing block 7 retracts into a spring groove 5 due to the acting force of a first spring 6, when the pressing block 7 contacts a movable hole formed in the front of the working plates 3, the pressing block pops out and is fixed, then a telescopic block 18 is pushed to be clamped with a joint block 19, one side of a pull ring 13 departing from a fixed rod 8 is pulled, a movable rod 14, a clamping block 15 and a second spring 11 integrally move towards one side away from the fixed rod 8, so that an inserting block 12 is inserted into an inserting block 16, the function of quick mounting is realized, and the purpose of convenient dismounting is achieved, greatly reducing the installation time, a working plate 3 is fixedly arranged between one opposite sides of the sliding block 2, a movable rod 4 is movably arranged at one opposite side of the working plate 3, a connecting groove is formed at one opposite side of the working plate 3, the volume of the connecting groove is matched with the volume of the movable rod 4, a spring groove 5 is formed inside the movable rod 4, a first spring 6 is fixedly connected with the rear side wall of the spring groove 5, one end of the front surface of the first spring 6 is fixedly connected with a pressing block 7, one end of the pressing block extends through the spring groove 5 and the working plate 3 in sequence and extends to the outer side of the working plate 3, the number of the working plates 3 is two, the two working plates 3 are distributed in a symmetrical and equidistant mode, the volumes of the two working plates 3 are unequal, a movable hole is formed in the front surface of the working plate 3 and is matched with the pressing block 7, one end of the movable rod 4 extends through, the left side and the right side of a fixed rod 8 are both fixedly connected with a connecting rod 9, the top of the connecting rod 9 is fixedly provided with a connecting block 10, one side of the connecting rod 9 opposite to each other is fixedly connected with a second spring 11, one side of the second spring 11 opposite to each other is fixedly provided with an inserting block 12, one end of the inserting block extends to the outside of the connecting rod 9, the top of the inserting block 12 is fixedly connected with a moving rod 14, the top of the moving rod 14 is fixedly connected with a pull ring 13, one side of the moving rod 14 opposite to each other is hinged with a clamping block 15 through a rotating shaft, one side of the inserting block 12 opposite to each other is both penetrated and extends to the inside of the inserting block 16 and is movably connected with the inserting block 16, the pressing block 7 is pressed to be retracted into the spring groove 5 due to the acting force of a first spring 6, the moving rod 4 is pulled to enter the fixed rod 8 to be, when the pull ring 13 is pulled towards one side of the fixed rod 8, the movable rod 14, the clamping block 15 and the second spring 11 integrally move towards the direction of the fixed rod 8, then the clamping block 15 is fixed on the connecting block 10, so that the inserting block 12 is separated from the inserting block 16, the connecting piece at the middle part of the scaffold is disassembled, then the upper working plate 3 and the lower working plate 3 are pulled out through the sliding block 2, the aim of disassembling the scaffold is integrally realized, the installation time is greatly reduced, sliding grooves are formed in the opposite sides of the support 1, the volumes of the sliding grooves are matched with the volumes of the sliding blocks 2, matching grooves are formed in the opposite sides of the inserting block 16, the matching grooves are matched with the inserting blocks 12, the inserting block 16 is movably connected with the support 1, an installation rod 17 is fixedly connected to the bottom of the connecting rod 9, a telescopic block 18 is fixedly installed on the side, away from the installation rod 17, far, the inboard swing joint of movable sleeve has one end to run through and extend to the outside fixed block of movable sleeve, and the equal joint in one side that flexible piece 18 carried on the back mutually has joint block 19, joint block 19 and 1 fixed connection of support, and the bottom swing joint of support 1 has rubber sleeve 20, and the quantity of connecting rod 9 is two, and two connecting rods 9 are the symmetry equidistance and distribute, and the quantity of rubber sleeve 20 is four, and four rubber sleeves 20 are the symmetry equidistance and distribute.
When using, install working plate 3 on support 1 through sliding block 2, through pressing the briquetting 7 with the joint of movable rod 4 on working plate 3, peg graft connecting rod 9 on inserting piece 16 through structures such as second spring 11 and grafting piece 12, realized the function of whole quick installation.
To sum up, the combined scaffold for building construction has the advantages that the pressing block 7 is pressed to be retracted into the spring groove 5 due to the acting force of the first spring 6, the movable rod 4 is pulled to enter the fixed rod 8, the movable rod 4 is separated from the working plate 3, the telescopic block 18 is pulled to be separated from the joint block 19, when the pull ring 13 is pulled to one side of the fixed rod 8, the movable rod 14, the clamping block 15 and the second spring 11 integrally move towards the fixed rod 8, then the clamping block 15 is fixed on the connecting block 10, so that the inserting block 12 is separated from the inserting block 16, the connecting piece at the middle part of the scaffold is disassembled, then the upper working plate 3 and the lower working plate 3 are pulled out through the sliding block 2, the aim of disassembling the scaffold is integrally realized, the installation time is greatly reduced, the upper working plate 3 and the lower working plate 3 are pushed into and installed on the bracket 1 through the sliding block 2, when the movable rod 4 is pushed, the pressing block 7 in the movable rod 4 is retracted into the spring groove 5 due to the acting force of the first spring 6 when contacting the working plate 3, and is ejected and fixed when contacting the movable hole arranged on the front surface of the working plate 3, then the telescopic block 18 is pushed to be clamped with the joint block 19, the pull ring 13 is pulled at the side away from the fixed rod 8, the movable rod 14, the clamping block 15 and the second spring 11 move integrally to the side away from the fixed rod 8, thereby make the grafting piece 12 peg graft in the piece 16 that closes of inserting, realized the function of quick installation, reached the purpose of the dismouting of being convenient for, greatly reduced installation time has solved the scaffold frame on the current market and has had the inconvenient shortcoming of dismouting, leads to the workman to use the installation of external instrument when the scaffold frame need be used in the construction to greatly increased the time of installation scaffold frame, reduced work efficiency's problem.
It is to be noted that, in this document, relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action, without necessarily requiring or implying any such actual relationship or order between such entities or operations, furthermore, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements, but also includes other elements not expressly listed or inherent to such process, method, article, or apparatus, without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a modular construction scaffold, is support (1) that quantity is four, its characterized in that: the spring fixing device comprises a support (1), sliding blocks (2) are movably mounted at the top and the bottom of one side, opposite to the support, of the left side and the right side, a working plate (3) is fixedly mounted between one sides, opposite to the sliding blocks (2), a movable rod (4) is movably mounted at one side, opposite to the working plate (3), a spring groove (5) is formed in the movable rod (4), a first spring (6) is fixedly connected to the rear side wall of the spring groove (5), one end of the front of the first spring (6) is fixedly connected with a pressing block (7) which sequentially penetrates through the spring groove (5) and the working plate (3) and extends to the outer side of the working plate (3), one end, opposite to the movable rod (4), of the movable rod sequentially penetrates through the fixing rod (8) and extends to the inner part of the fixing rod (8), a connecting rod (9) is fixedly connected to the left side and the right side of the fixing, one side of the connecting rod (9) opposite to the other side is fixedly connected with a second spring (11), one side of the second spring (11) opposite to the other side is fixedly provided with an inserting block (12) with one end penetrating and extending to the outside of the connecting rod (9), the top of the inserting block (12) is fixedly connected with a moving rod (14), the top of the moving rod (14) is fixedly connected with a pull ring (13), one side of the moving rod (14) opposite to the other side is hinged with a clamping block (15) through a rotating shaft, one side of the inserting block (12) opposite to the other side penetrates and extends to the inside of the inserting block (16) and is movably connected with the inserting block (16), the inserting block (16) is movably connected with the support (1), the bottom of the connecting rod (9) is fixedly connected with a mounting rod (17), one side of the mounting rod (17) far away from the connecting rod (9) is fixedly provided with a telescopic, the telescopic joint is characterized in that a joint block (19) is clamped on one side of the telescopic block (18) opposite to the other side, the joint block (19) is fixedly connected with the support (1), and a rubber sleeve (20) is movably connected to the bottom of the support (1).
2. A modular construction scaffold according to claim 1, wherein: the support (1) relative one side has all seted up the spout, the volume of spout and the volume looks adaptation of sliding block (2), the adaptation groove has all been seted up to the relative one side of piece (16) that closes of inserting, the adaptation groove with plug block (12) looks adaptation.
3. A modular construction scaffold according to claim 1, wherein: the quantity of working plate (3) is two, two working plate (3) are the symmetry equidistance and distribute, and two working plate (3) volume inequalities, the activity hole has been seted up in the front of working plate (3), the activity hole with press piece (7) looks adaptation.
4. A modular construction scaffold according to claim 1, wherein: the telescopic block (18) is composed of a fixed block and a movable sleeve, and one end of the inner side of the movable sleeve is movably connected with the fixed block, penetrates through the fixed block and extends to the outside of the movable sleeve.
5. A modular construction scaffold according to claim 1, wherein: the quantity of connecting rod (9) is two, two connecting rod (9) are the equidistance distribution of symmetry, the quantity of rubber sleeve (20) is four, four rubber sleeve (20) are the equidistance distribution of symmetry.
6. A modular construction scaffold according to claim 1, wherein: the connecting groove has all been seted up to one side that working plate (3) is relative, the volume of connecting groove and the volume looks adaptation of movable rod (4).
CN201921795701.3U 2019-10-24 2019-10-24 Combined building construction scaffold Active CN211647202U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921795701.3U CN211647202U (en) 2019-10-24 2019-10-24 Combined building construction scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921795701.3U CN211647202U (en) 2019-10-24 2019-10-24 Combined building construction scaffold

Publications (1)

Publication Number Publication Date
CN211647202U true CN211647202U (en) 2020-10-09

Family

ID=72690841

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921795701.3U Active CN211647202U (en) 2019-10-24 2019-10-24 Combined building construction scaffold

Country Status (1)

Country Link
CN (1) CN211647202U (en)

Similar Documents

Publication Publication Date Title
CN211647202U (en) Combined building construction scaffold
CN212317262U (en) Detachable temporary supporting structure of steel bar truss floor bearing plate
CN211572472U (en) Scaffold for building construction
CN216787444U (en) Steel construction building crossbeam connecting piece
CN211193608U (en) Clamping structure for tooling plate of wallboard production line
CN215949233U (en) Window square tube is with reinforcing stand of being convenient for installation
CN113622516A (en) Cross-shaped connecting assembly for assembly type concrete building
CN218493962U (en) Glass magnesium board convenient to installation
CN212557693U (en) Energy-saving discharging machine for producing hydroxyl acrylic resin coating adhesive
CN215329922U (en) Easy dismouting formula underground structure
CN220954099U (en) Assembled aluminium veneer curtain connection structure
CN211623661U (en) Sheet metal part connecting structure for air compressor
CN221160015U (en) Auxiliary connecting device for tap water supply pipe
CN221143686U (en) Concrete crack reinforcement structure
CN213537034U (en) Linkage hoisting device for wind tower high cylindrical section
CN215670496U (en) Building wallboard that can assemble
CN216616451U (en) Improved fast-connection type indoor light decorative curtain wall structure
CN217558342U (en) Tunnel lining polymer end cap board subassembly of convenient equipment
CN213926761U (en) C-shaped steel connecting assembly
CN216239160U (en) Partition wall convenient to disassemble and assemble
CN213477270U (en) Connecting mechanism of building wallboard
CN215907242U (en) Interior decoration and finishing wallboard
CN215720072U (en) Adjustable quick fixed comprehensive hanger
CN220014296U (en) Novel steel wall for building decoration
CN214463429U (en) Trunk left hinge cover convenient for ash removal

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant