CN211500680U - Hydraulic support of pin installation double insurance - Google Patents

Hydraulic support of pin installation double insurance Download PDF

Info

Publication number
CN211500680U
CN211500680U CN201921674621.2U CN201921674621U CN211500680U CN 211500680 U CN211500680 U CN 211500680U CN 201921674621 U CN201921674621 U CN 201921674621U CN 211500680 U CN211500680 U CN 211500680U
Authority
CN
China
Prior art keywords
back timber
articulated
base
roof beam
stand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921674621.2U
Other languages
Chinese (zh)
Inventor
丁雁
鞠亚航
裴广州
赵光明
张鹏飞
李向兵
原媛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jincheng Jinfei Electromechanical Co ltd
Original Assignee
Jincheng Jinfei Electromechanical Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jincheng Jinfei Electromechanical Co ltd filed Critical Jincheng Jinfei Electromechanical Co ltd
Priority to CN201921674621.2U priority Critical patent/CN211500680U/en
Application granted granted Critical
Publication of CN211500680U publication Critical patent/CN211500680U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model provides a hydraulic support of post apex pin installation dual fail-safe, belongs to hydraulic support technical field, and the support post nest ear part spoilage that can solve current hydraulic support is high, changes the problem that the repair degree of difficulty is high, including back timber, shield roof beam, tail-boom and base, the one end of back timber is articulated with the one end of shield roof beam, and the other end of shield roof beam is articulated with the one end of tail-boom, is equipped with the stand between back timber and the base, and the one end of stand is articulated with the post nest ear of back timber bottom, and the other end is articulated with the base, the upper end of the bottom of back timber, base and the bottom of shield roof beam are equipped with the sensor respectively, are equipped with the drilling that corresponds with the column cap pore pair of stand on the major rib board. The utility model discloses the most probably damage of avoiding takes place, if damage, can use simple convenient mode to remedy the change.

Description

Hydraulic support of pin installation double insurance
Technical Field
The utility model belongs to the technical field of hydraulic support, concretely relates to hydraulic support of capital pin installation double insurance.
Background
Hydraulic support is in the working face use, roof pressure distributes unevenly, lead to the back timber atress inequality to have become the normality, carry out three machines according to the working face particular case and form a complete set, the anterior supporting size of general support is great, when guaranteeing hydraulic support overall stability, it arranges by the back timber front end to tend to the support front stall, still it is big apart from coal wall accuse apical area, consequently, row's stand working resistance inequality around often appearing, lead to the unstable condition of support low-head "pull out the back post", if there is not timely discovery of operating personnel, cause the probability of support post nest ear part damage to be high. The damage of the column nest lug directly affects the use of the column, the column cannot be fixed to affect the normal lowering, the underground environment is severe, the space is limited, the replacement and repair difficulty is high, and the propelling speed of the working face is greatly affected.
Disclosure of Invention
The utility model discloses support post nest ear part spoilage to current hydraulic support is high, changes the high problem of the repair degree of difficulty, provides a hydraulic support of capital pin installation dual fail-safe.
The utility model adopts the following technical scheme:
the utility model provides a hydraulic support of post apex pin installation dual fail-safe, includes back timber, shield roof beam, tail-boom and base, and the one end of back timber is articulated with the one end of shielding the roof beam, and the other end of shielding the roof beam is articulated with the one end of tail-boom, is equipped with the stand between back timber and the base, and the one end of stand is articulated with the post nest ear of back timber bottom, and the other end is articulated with the base, the bottom of back timber, the upper end of base and the bottom of shield roof beam are equipped with the sensor respectively, are equipped with the drilling that corresponds with the column cap pore pair of stand on the main rib board of post.
And a pin shaft corresponding to the drilled hole is arranged in the drilled hole.
And a stop pin block for connection is arranged on the outer side of the pin shaft.
The utility model has the advantages as follows:
1. the utility model discloses a control back timber pivot angle at back timber, base, shield roof beam installation sensor, carries out alarm control when approaching extreme position to the support is excessively low, plays the prevention guard action, reduces and avoids the emergence number of times of this problem.
2. The utility model discloses a reserve pinhole design is just to drilling stand connecting pin department on the major rib board of post nest ear both sides, can use reserve pinhole installation round pin axle fixed stand after the ear damages, and the round pin axle is connected with the shelves block pin in the outside, guarantees the stand and normally connects the use.
Through the setting, the damage can be avoided to the greatest extent, and if the damage happens, the replacement can be remedied by using a simple and convenient mode.
Drawings
Fig. 1 is a schematic view of the structure of the present invention;
fig. 2 is a schematic top view of the present invention;
wherein: 1-top beam; 2-a shield beam; 3-tail beam; 4-a base; 5-upright column; 6-a sensor; 7-drilling.
Detailed Description
The present invention will be further explained with reference to the accompanying drawings.
As shown in the figure, a hydraulic support of post apex pin installation dual fail-safe, including back timber 1, shield roof beam 2, tail-boom 3 and base 4, the one end of back timber 1 is articulated with the one end of shield roof beam 2, and the other end of shield roof beam 2 is articulated with the one end of tail-boom 3, is equipped with stand 5 between back timber 1 and the base 4, and the one end of stand 5 is articulated with the post nest ear of back timber 1 bottom, and the other end is articulated with base 4, the upper end of the bottom of back timber 1, base 4 and the bottom of shield roof beam 2 are equipped with sensor 6 respectively, are equipped with the drilling that corresponds with the column cap pore pair of stand 5 on the major rib board of post nest ear both sides.
And a pin shaft corresponding to the drilled hole is arranged in the drilled hole.
And a stop pin block for connection is arranged on the outer side of the pin shaft.
The principle of the utility model is as follows:
the first step is as follows: the hydraulic support adopts an electro-hydraulic system, a sensor is installed on the top beam, the base and the shield beam, the posture of the support is controlled through the sensor, the angle of the support top beam relative to the base is limited, the support is prevented from excessively lowering, the rear upright post is enabled to be transited and pulled up, and the damage to the top beam and the column nest is avoided.
The second step is that: and designing a spare pin hole and installing a spare pin shaft. After the lug of the column nest is broken, the standby pin hole is started to be matched with the column head hole of the column, and the standby pin shaft is installed.
The hydraulic support adopts an electro-hydraulic control system, wherein sensors are arranged at a plurality of positions, the control is carried out aiming at the swing angle of the top beam, and an alarm is given when the support excessively lowers the head. The installation of sensors and the electro-hydraulic control system of the hydraulic support are well known to those skilled in the art.

Claims (3)

1. The utility model provides a hydraulic support of capital pin installation dual fail-safe, including back timber (1), cover roof beam (2), tail boom (3) and base (4), the one end of back timber (1) is articulated with the one end that covers roof beam (2), the other end that covers roof beam (2) is articulated with the one end of tail boom (3), be equipped with stand (5) between back timber (1) and base (4), the one end of stand (5) is articulated with the post nest ear of back timber (1) bottom, the other end is articulated with base (4), its characterized in that: sensors (6) are respectively arranged at the bottom of the top beam (1), the upper end of the base (4) and the bottom of the shield beam (2), and drill holes corresponding to column head holes of the stand columns (5) are formed in the main rib plates on the two sides of the column nest lugs.
2. A pin-mounted double safety hydraulic mount as claimed in claim 1, wherein: and a pin shaft corresponding to the drilled hole is arranged in the drilled hole.
3. A pin-mounted double safety hydraulic mount as claimed in claim 2, wherein: and a stop pin block for connection is arranged on the outer side of the pin shaft.
CN201921674621.2U 2019-10-09 2019-10-09 Hydraulic support of pin installation double insurance Active CN211500680U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921674621.2U CN211500680U (en) 2019-10-09 2019-10-09 Hydraulic support of pin installation double insurance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921674621.2U CN211500680U (en) 2019-10-09 2019-10-09 Hydraulic support of pin installation double insurance

Publications (1)

Publication Number Publication Date
CN211500680U true CN211500680U (en) 2020-09-15

Family

ID=72406223

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921674621.2U Active CN211500680U (en) 2019-10-09 2019-10-09 Hydraulic support of pin installation double insurance

Country Status (1)

Country Link
CN (1) CN211500680U (en)

Similar Documents

Publication Publication Date Title
CN200985799Y (en) Alley way advanced support bracket
CN101592035A (en) Big mining height shield type low caving coal hydraulic support
CN211500680U (en) Hydraulic support of pin installation double insurance
JPH01207592A (en) Mining machinery
CN201025051Y (en) Cover type hydraulic supporter
CN204199338U (en) Movable arm cylinder of excavator bearing pin fixed mechanism
CN102213251A (en) Hydraulic cylinder with locking mechanism
CN1821545B (en) Attachment support of mining device
CN201310370Y (en) Large mining height shield hydraulic support
CN210977546U (en) Top pillar pit protection and standby device
CN207277414U (en) A kind of loading machine lip abrasion-proof structure
CN214997754U (en) Heightening top beam transition hydraulic support suitable for roadway and working face with unequal heights
CN207863007U (en) Integral type rock drilling arm
CN213116362U (en) Steep roadside hydraulic support group
CN210686023U (en) Large mining height hydraulic support top and side protection mechanism
CN207554094U (en) A kind of new type hydraulic bearer balance jack protective device
CN208106471U (en) Convenient for discharging the single pendulum beam hydraulic support of top coal
CN202766161U (en) Crane telescopic arm, crane knuckle arm and crane
CN201620899U (en) Upper beam of hydraulic support
CN111042711A (en) Entrance guard with protection function
CN207934922U (en) Low caving coal hydraulic support
CN216788443U (en) Stand column assembly for advanced hydraulic support and advanced hydraulic support
CN218882185U (en) Anti-toppling device for hydraulic support
CN209228395U (en) A kind of underground coal mine removes the shielding apparatus of hydraulic support
CN216342259U (en) Safety support device for coal mine tunneling support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant