CN211473351U - Be applied to high strength pole setting of climbing frame - Google Patents

Be applied to high strength pole setting of climbing frame Download PDF

Info

Publication number
CN211473351U
CN211473351U CN201922446640.6U CN201922446640U CN211473351U CN 211473351 U CN211473351 U CN 211473351U CN 201922446640 U CN201922446640 U CN 201922446640U CN 211473351 U CN211473351 U CN 211473351U
Authority
CN
China
Prior art keywords
pole setting
mounting hole
row
recess
setting body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922446640.6U
Other languages
Chinese (zh)
Inventor
胡奇斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dongguan Sansi De Warehousing Equipment Co ltd
Original Assignee
Dongguan Sansi De Warehousing Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongguan Sansi De Warehousing Equipment Co ltd filed Critical Dongguan Sansi De Warehousing Equipment Co ltd
Priority to CN201922446640.6U priority Critical patent/CN211473351U/en
Application granted granted Critical
Publication of CN211473351U publication Critical patent/CN211473351U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a pole setting field especially relates to a be applied to high strength pole setting of climbing frame, including the pole setting body, first recess has been seted up to the relative both sides of pole setting body, one row of first mounting hole has been seted up in the first recess, one row of first mounting hole is followed the length direction of pole setting body is a style of calligraphy and arranges, the second recess has been seted up at pole setting body top, one row of second mounting hole has been seted up in the second recess, one row of second mounting hole is followed the length direction of pole setting body is a style of calligraphy and arranges, pole setting body surface is provided with chromium-plated layer. The utility model provides a high strength pole setting of climbing frame is applied to with low costs of use, installation convenient and reliable.

Description

Be applied to high strength pole setting of climbing frame
Technical Field
The utility model relates to a pole setting field especially relates to a be applied to high strength pole setting of climbing frame.
Background
The climbing frame is also called a lifting frame, and can be classified into hydraulic, electric, manual and hand-pulling types according to its power source. The scaffold is a novel scaffold system developed in recent years and is mainly applied to high-rise shear wall type floors. It can climb up or down along the building. This system makes the scaffold technology completely improved: firstly, the frame does not need to be turned over; and secondly, the scaffold is free from the dismounting and mounting procedures (the scaffold is used until the construction is finished after one-time assembly), and is not limited by the height of a building, so that the manpower and the materials are greatly saved. And also has a great improvement on the traditional scaffold in the safety angle. Has great development advantages in high-rise buildings.
The pole setting intensity that climbs the frame and use at present is low, and weight is big, leads to use cost to improve, is unfavorable for promoting, and the installation is also very inconvenient simultaneously, has reduced workman's installation effectiveness, and the reliability is low.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides a low in use cost, install convenient reliable be applied to the high strength pole setting of climbing the frame.
The utility model adopts the following technical scheme:
the utility model provides a be applied to high strength pole setting of climbing frame, includes the pole setting body, first recess has been seted up to the relative both sides of pole setting body, one row of first mounting hole has been seted up in the first recess, one row of first mounting hole is followed the length direction of pole setting body is a style of calligraphy and arranges, the second recess has been seted up at pole setting body top, one row of second mounting hole has been seted up in the second recess, one row of second mounting hole is followed the length direction of pole setting body is a style of calligraphy and arranges, pole setting body surface is provided with chromium-plated layer.
The further improvement on the technical scheme is that the first groove is an arc-shaped groove, and the diameter of the first mounting hole is 16-18 mm.
The further improvement to above-mentioned technical scheme does, one row of first mounting hole and one row of second mounting hole are the equidistance and evenly arrange, the second mounting hole diameter is 16 ~ 18 mm.
The further improvement of the technical scheme is that a plurality of fixing holes are respectively formed in the two sides of the second groove and above the vertical rod body, the fixing holes are through holes, and the diameters of the fixing holes are 13-14 mm.
The technical scheme is further improved in that the thickness of the chromium plating layer is 0.5-1.5 mm.
The utility model has the advantages that:
1. the utility model discloses a pole setting body, first recess has been seted up to the relative both sides of pole setting body, one row of first mounting hole has been seted up in the first recess, one row of first mounting hole is a style of calligraphy along the length direction of pole setting body and arranges, the second recess has been seted up at pole setting body top, one row of second mounting hole has been seted up in the second recess, one row of second mounting hole is a style of calligraphy along the length direction of pole setting body and arranges, pole setting body surface is provided with chromium-plated layer, through setting up two first recesses and second recess, further improve the utility model discloses an intensity has reduced weight when satisfying intensity, has also reduced the cost, sets up first mounting hole simultaneously, the second mounting hole, lets the creeper installation, scaffold board installation, net piece installation are more swift, and is more reliable, further reduce cost, and high strength effectively improves production and installation effectiveness.
2. First recess sets up to the arc recess, effectively improves the service strength of pole setting, and the diameter of first mounting hole is 16 ~ 18mm, can select the aperture according to actual need, effectively reduces use cost, and the practicality is strong.
3. One row of first mounting hole and one row of second mounting hole are the equidistance and evenly arrange, and the second mounting hole diameter is 16 ~ 18mm, makes to climb frame installation, scaffold board installation, net piece installation more swift, and is more reliable, further reduce cost, improvement production and installation effectiveness.
4. A plurality of fixed orificess have been seted up respectively to second recess both sides lie in pole setting body top, and the fixed orifices is the through-hole, and the fixed orifices diameter is 13 ~ 14mm, and the fixed flute net frame when climbing the installation of being convenient for further improves the installation intensity, makes the installation more swift simultaneously, and is more reliable, further reduce cost, and the practicality is strong.
5. The thickness of the chromium plating layer is 0.5-1.5 mm, the chromium plating thickness can be selected according to actual needs, the use cost is effectively reduced, the service life is further prolonged, meanwhile, the chromium plating layer effectively enhances the wear resistance and the rust resistance, and the practicability is high.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a cross-sectional view of the present invention.
Detailed Description
The technical solution in the embodiment of the present invention will be clearly and completely described below with reference to the drawings in the embodiment of the present invention.
As shown in fig. 1-2, a high-strength vertical rod applied to a climbing frame comprises a vertical rod body 110, first grooves 120 are formed in two opposite sides of the vertical rod body 110, a row of first mounting holes 121 are formed in the first grooves 120, a row of first mounting holes 121 are arranged along the length direction of the vertical rod body 110 in a straight line shape, a second groove 130 is formed in the top of the vertical rod body 110, a row of second mounting holes 131 are formed in the second groove 130, the row of second mounting holes 131 are arranged along the length direction of the vertical rod body 110 in a straight line shape, and a chromium-plated layer is arranged on the outer surface of the vertical rod body 110.
First recess 120 sets up to the arc recess, effectively improves the service strength of pole setting, and the diameter of first mounting hole 121 is 16 ~ 18mm, can select the aperture according to actual need, effectively reduces use cost, and the practicality is strong.
One row of first mounting hole 121 and one row of second mounting hole 131 are the equidistance and evenly arrange, and second mounting hole 131 diameter is 16 ~ 18mm, makes and climbs the installation, scaffold board installation, net piece installation more swift, and is more reliable, and further reduce cost improves production and installation effectiveness.
A plurality of fixed orificess have been seted up respectively to second recess 130 both sides lie in pole setting body 110 top, and the fixed orifices is the through-hole, and the fixed orifices diameter is 13 ~ 14mm, and the fixed flute net frame when climbing the installation of being convenient for further improves installation strength, makes the installation more swift simultaneously, and is more reliable, further reduce cost, and the practicality is strong.
The thickness of the chromium plating layer is 0.5-1.5 mm, the chromium plating thickness can be selected according to actual needs, the use cost is effectively reduced, the service life is further prolonged, meanwhile, the chromium plating layer effectively enhances the wear resistance and the rust resistance, and the practicability is high.
The utility model comprises a pole setting body 110, wherein two opposite sides of the pole setting body 110 are provided with first grooves 120, a row of first mounting holes 121 are arranged in the first grooves 120, a row of first mounting holes 121 are arranged in a straight line along the length direction of the pole setting body 110, a second groove 130 is arranged at the top of the pole setting body 110, a row of second mounting holes 131 is arranged in the second groove 130, a row of second mounting holes 131 are arranged in a straight line along the length direction of the pole setting body 110, the outer surface of the pole setting body 110 is provided with a chromium coating, by arranging the two first grooves 120 and the second grooves 130, the strength of the utility model is further improved, the weight is reduced while the strength is satisfied, the cost is also reduced, the first mounting holes 121 and the second mounting holes 131 are arranged simultaneously, the climbing frame installation, the scaffold board installation and the net sheet installation are more rapid and reliable, the cost is further reduced, the strength is improved, production and installation efficiency are effectively improved.
The above-mentioned embodiments only represent one embodiment of the present invention, and the description thereof is specific and detailed, but not construed as limiting the invention. It should be noted that those skilled in the art will recognize that the invention may be practiced without departing from its spirit or scope. Therefore, the protection scope of the present invention should be subject to the appended claims.

Claims (5)

1. The utility model provides a be applied to and climb high strength pole setting of frame which characterized in that: including the pole setting body, first recess has been seted up to the relative both sides of pole setting body, one row of first mounting hole has been seted up in the first recess, one row of first mounting hole is followed the length direction of pole setting body is a style of calligraphy and arranges, the second recess has been seted up at pole setting body top, one row of second mounting hole has been seted up in the second recess, one row of second mounting hole is followed the length direction of pole setting body is a style of calligraphy and arranges, pole setting body surface is provided with chromium-plated layer.
2. A high-strength upright for a climbing frame according to claim 1, which is characterized in that: the first groove is an arc-shaped groove, and the diameter of the first mounting hole is 16-18 mm.
3. A high-strength upright for a climbing frame according to claim 1, which is characterized in that: one row of first mounting hole and one row of second mounting hole are the equidistance and evenly arrange, the second mounting hole diameter is 16 ~ 18 mm.
4. A high-strength upright for a climbing frame according to claim 1, which is characterized in that: a plurality of fixing holes are formed in the two sides of the second groove and located above the vertical rod body respectively, the fixing holes are through holes, and the diameter of each fixing hole is 13-14 mm.
5. A high-strength upright for a climbing frame according to claim 1, which is characterized in that: the thickness of the chromium plating layer is 0.5-1.5 mm.
CN201922446640.6U 2019-12-27 2019-12-27 Be applied to high strength pole setting of climbing frame Active CN211473351U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922446640.6U CN211473351U (en) 2019-12-27 2019-12-27 Be applied to high strength pole setting of climbing frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922446640.6U CN211473351U (en) 2019-12-27 2019-12-27 Be applied to high strength pole setting of climbing frame

Publications (1)

Publication Number Publication Date
CN211473351U true CN211473351U (en) 2020-09-11

Family

ID=72372005

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922446640.6U Active CN211473351U (en) 2019-12-27 2019-12-27 Be applied to high strength pole setting of climbing frame

Country Status (1)

Country Link
CN (1) CN211473351U (en)

Similar Documents

Publication Publication Date Title
CN211473351U (en) Be applied to high strength pole setting of climbing frame
CN207365244U (en) A kind of supporting structure for building
CN209780196U (en) aluminum alloy climbs frame and uses track
CN210032264U (en) Aluminum honeycomb curtain wall convenient to pull installation
CN208251085U (en) A kind of building engineering construction prestress pulling resistant pilework
CN202170585U (en) Steel and aluminum combination fireproof section bar for curtain wall
CN211622564U (en) Connect stable pole setting connecting piece
CN206513398U (en) Between a kind of cable tunnel escape arranged suitable for cable bilateral
CN205840138U (en) A kind of assembled wide span steel roof frame structure
CN205804999U (en) The attachment structure of prefabrication tower crane
CN213174736U (en) High-rise building climbing frame falling prevention device
CN109629818B (en) Track for aluminum alloy climbing frame
CN205558032U (en) Modular honeycomb roof beam
CN205604281U (en) Double entry rock long anchor rod formula foundation structure
CN205153126U (en) Fixed steel construction
CN211524036U (en) Corrugated net sheet for climbing frame
CN208152915U (en) A kind of dual-purpose screen window
CN211948921U (en) Pre-tightening connecting device for steel structure building
CN220058308U (en) Quick-assembling steel structure steel frame
CN215368336U (en) Light-duty prefabricated sunshading board installation node structure
CN209016616U (en) A kind of I-shaped threeway gantry
CN217206124U (en) Ventilation energy-saving aluminum alloy door and window
CN217537452U (en) Energy-saving waterproof curtain wall
CN210508949U (en) Energy-saving light aluminum alloy profile
CN208594691U (en) Microlite wood section can be recycled in a kind of novel environment friendly for pushing up watt

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant