CN211472489U - Building combined pile convenient to move and used for civil engineering - Google Patents

Building combined pile convenient to move and used for civil engineering Download PDF

Info

Publication number
CN211472489U
CN211472489U CN201821023584.4U CN201821023584U CN211472489U CN 211472489 U CN211472489 U CN 211472489U CN 201821023584 U CN201821023584 U CN 201821023584U CN 211472489 U CN211472489 U CN 211472489U
Authority
CN
China
Prior art keywords
base
civil engineering
motor
cross beam
hydraulic telescopic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821023584.4U
Other languages
Chinese (zh)
Inventor
白新亮
王毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821023584.4U priority Critical patent/CN211472489U/en
Application granted granted Critical
Publication of CN211472489U publication Critical patent/CN211472489U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a building composite pile for civil engineering convenient to move in the technical field of civil engineering, which comprises a base, universal wheels are arranged at four corners of the bottom of the base, an energy accumulator is embedded at the middle end of the bottom of the base, a control switch is arranged at the right side of the base, a fixed frame is connected at the left side of the top of the base, motors are arranged at the left side and the right side of the fixed frame, a hydraulic telescopic rod and a push rod are connected at the right side of the top of the base, the hydraulic telescopic rod is arranged at the left side of the push rod, a cross beam is connected at the top of the hydraulic telescopic rod, a vibrating motor is connected at the left side of the bottom of the cross beam, a solar photovoltaic component is arranged at the top of the cross beam, and the solar photovoltaic component is connected with the energy accumulator through a wire, convenient to use utilizes the push pedal to adjust the diameter size of stake, has effectively improved work efficiency.

Description

Building combined pile convenient to move and used for civil engineering
Technical Field
The utility model relates to a civil engineering technical field specifically is a building combined pile for civil engineering who conveniently removes.
Background
Civil engineering refers to the planning, construction and maintenance of all water, soil and culture related infrastructures. Current general civil work projects include: road, water conservancy, canal affairs, disaster prevention engineering, traffic and the like. In the past, all civil engineering projects for non-military use are classified into this category, but with the increasingly wide engineering science, many contents originally belonging to the civil engineering range are already independent and independent. The construction of an engineering facility generally needs three stages of investigation, design and construction, and subjects such as engineering geological investigation, hydrogeological investigation, engineering measurement, soil mechanics, engineering design, building materials, building equipment, engineering machinery, building economy and the like, knowledge in the fields of construction technology, construction organization and the like, and technologies such as electronic computer and mechanical test and the like need to be applied. Therefore, civil engineering is a comprehensive subject with a wide range. With the progress of science and technology and the development of engineering practice, the discipline of civil engineering has also developed into a comprehensive system with wide connotation, numerous categories and complex structure. For example, as for the use functions of the construction facilities constructed by civil engineering, there are those for living and living, or as a "safe-to-earth" tomb; some as production activity sites; some are used for land, sea and air transportation; some are used for water conservancy projects; some tools are used for information transmission; some as a means of energy transmission, etc. This requires the civil engineering work to use various material conditions in combination to meet various demands. Civil engineering has developed many branches, such as housing engineering, railway engineering, road engineering, airport engineering, bridge engineering, tunnel and underground engineering, special engineering structures, water supply and drainage engineering, city heat and gas supply engineering, port engineering, hydraulic engineering and other disciplines. Some of the branches, such as hydraulic engineering, have been separated from civil engineering into independent subject systems due to the increasing number of self-engineering objects and the development of special scientific techniques, but they still have the commonality of civil engineering to a large extent. The existing civil engineering composite pile is inconvenient to adjust, inconvenient to use, time-wasting, low in working efficiency and inconvenient to operate.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building composite pile for civil engineering who conveniently removes to solve the current civil engineering composite pile that proposes in the above-mentioned background art and be not convenient for adjust, inconvenient when using, the waste time, work efficiency is low moreover, operates inconvenient problem.
In order to achieve the above object, the utility model provides a following technical scheme: a building combined pile convenient to move for civil engineering comprises a base, universal wheels are mounted at four corners of the bottom of the base, an energy accumulator is inlaid at the middle end of the bottom of the base, a control switch is mounted at the right side of the base, a fixing frame is connected to the left side of the top of the base, motors are mounted on the left side and the right side of the fixing frame, a hydraulic telescopic rod and a push rod are connected to the right side of the top of the base, the hydraulic telescopic rod is arranged on the left side of the push rod, a cross beam is connected to the top of the hydraulic telescopic rod, a vibrating motor is connected to the left side of the bottom of the cross beam, a solar photovoltaic assembly is mounted at the top of the cross beam and connected with the energy accumulator through a wire, outer sleeves are connected to the left side and the right side of an inner cavity of the fixing, the inner side of the nut is connected with the outer side of the inner sleeve, the nut and the inner sleeve are both arranged in the inner cavity of the outer sleeve, the inner side of the inner sleeve is connected with the push plate, the control switch, the motor, the hydraulic telescopic rod and the vibrating motor are connected with the energy accumulator through wires, and the motor, the hydraulic telescopic rod and the vibrating motor are all electrically connected with the control switch.
Preferably, a reinforcing rib is arranged at the joint of the hydraulic telescopic rod and the cross beam.
Preferably, the motor is connected with the fixing frame through a bracket.
Preferably, the push rod is a stainless steel push rod.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses a building composite pile for civil engineering simple structure, the transport of being convenient for, the convenient removal, convenient to use utilizes the push pedal to adjust the diameter size of stake, has effectively improved work efficiency.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a sectional view of the fixing frame of the present invention.
In the figure: the solar energy-saving device comprises a base 1, universal wheels 2, an energy accumulator 3, a control switch 4, a fixing frame 5, a motor 6, a hydraulic telescopic rod 7, a cross beam 8, a vibration motor 9, a solar photovoltaic module 10, a push rod 11, an outer sleeve 12, a lead screw 13, a nut 14, an inner sleeve 15 and a push plate 16.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-2, the present invention provides a technical solution: a building combined pile convenient to move for civil engineering comprises a base 1, universal wheels 2 are mounted at four corners of the bottom of the base 1, an energy accumulator 3 is inlaid at the middle end of the bottom of the base 1, a control switch 4 is mounted at the right side of the base 1, a fixing frame 5 is connected at the left side of the top of the base 1, motors 6 are mounted at the left side and the right side of the fixing frame 5, a hydraulic telescopic rod 7 and a push rod 11 are connected at the right side of the top of the base 1, the hydraulic telescopic rod 7 is arranged at the left side of the push rod 11, a cross beam 8 is connected at the top of the hydraulic telescopic rod 7, a vibrating motor 9 is connected at the left side of the bottom of the cross beam 8, a solar photovoltaic module 10 is mounted at the top of the cross beam 8, the solar photovoltaic module 10 is connected with the energy accumulator 3 through a wire, outer sleeves 12 are connected at the left side, the inboard of two sets of nuts 14 is connected with interior sleeve pipe 15's the outside, and two sets of nuts 14 and interior sleeve pipe 15 all are at outer sleeve pipe 12's inner chamber, and two sets of interior sleeve pipe 15's inboard all is connected with push pedal 16, and control switch 4, motor 6, hydraulic telescoping rod 7 and vibrating motor 9 all are connected with accumulator 3 through the wire, and motor 6, hydraulic telescoping rod 7 and vibrating motor 9 all with control switch 4 electric connection.
Wherein, the strengthening rib is installed to the junction of hydraulic telescoping rod 7 and crossbeam 8, and motor 6 passes through the support to be connected with fixed frame 5, and push rod 11 is the stainless steel push rod.
The working principle is as follows: when in use, the push rod 11 is pushed by hand, the utility model is pushed to a designated place, the control switch 4 is utilized to control the motor 6 to start, the output shaft of the motor 6 rotates to drive the lead screw 13 to rotate, the lead screw 13 drives the nut 14 to move in the nut 12, the nut 14 drives the inner sleeve 15 to move, the inner sleeve 15 drives the push plates 16 to move, the distance between the two groups of push plates 16 is adjusted, the distance between the two groups of push plates 16 is in accordance with the size of the pile, after the distance between the two groups of push plates 16 is adjusted, the concrete is guided between the two groups of push plates 16, the hydraulic telescopic rod 7 is started, the hydraulic telescopic rod 7 drives the cross beam 8 to vertically extend and retract, the cross beam 8 drives the vibration motor 9 to vertically extend and retract, the vibration motor 9 is lowered into the fixing frame 5, the vibration motor 9 is in contact with the concrete, the vibration motor 9, the operation is simple and convenient, the time is saved, the working efficiency is high, after the tamping is carried out, the control switch 4 controls the vibration motor 9 to stop, and the hydraulic telescopic rod 7 is started to take the vibration motor 9 out of the inner cavity of the fixed frame 5, so that the vibration motor 9 is lifted to the original position.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. The utility model provides a convenient building composite pile for civil engineering who removes, includes base (1), its characterized in that: the solar photovoltaic energy storage device is characterized in that universal wheels (2) are installed at four corners of the bottom of the base (1), an energy storage device (3) is inlaid at the middle end of the bottom of the base (1), a control switch (4) is installed on the right side of the base (1), a fixed frame (5) is connected to the left side of the top of the base (1), a motor (6) is installed on each of the left side and the right side of the fixed frame (5), a hydraulic telescopic rod (7) and a push rod (11) are connected to the right side of the top of the base (1), the hydraulic telescopic rod (7) is arranged on the left side of the push rod (11), a cross beam (8) is connected to the top of the hydraulic telescopic rod (7), a vibrating motor (9) is connected to the left side of the bottom of the cross beam (8), a solar photovoltaic assembly (10) is installed at the top of the cross beam (8), the solar photovoltaic assembly (, two sets of the inboard output shaft of motor (6) all is connected with lead screw (13), and nut (14) and interior sleeve pipe (15), two sets of have been cup jointed to the outer wall of two sets of lead screw (13) the inboard of nut (14) is connected with the outside of interior sleeve pipe (15), and is two sets of nut (14) and interior sleeve pipe (15) are all outside the inner chamber of sleeve pipe (12), and are two sets of the inboard of interior sleeve pipe (15) all is connected with push pedal (16), control switch (4), motor (6), hydraulic telescoping rod (7) and vibrating motor (9) all are connected with accumulator (3) through the wire, motor (6), hydraulic telescoping rod (7) and vibrating motor (9) all with control switch (4) electric connection.
2. A portable construction composite pile for civil engineering works according to claim 1, characterized in that: and reinforcing ribs are arranged at the joint of the hydraulic telescopic rod (7) and the cross beam (8).
3. A portable construction composite pile for civil engineering works according to claim 1, characterized in that: the motor (6) is connected with the fixing frame (5) through a support.
4. A portable construction composite pile for civil engineering works according to claim 1, characterized in that: the push rod (11) is a stainless steel push rod.
CN201821023584.4U 2018-06-29 2018-06-29 Building combined pile convenient to move and used for civil engineering Expired - Fee Related CN211472489U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821023584.4U CN211472489U (en) 2018-06-29 2018-06-29 Building combined pile convenient to move and used for civil engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821023584.4U CN211472489U (en) 2018-06-29 2018-06-29 Building combined pile convenient to move and used for civil engineering

Publications (1)

Publication Number Publication Date
CN211472489U true CN211472489U (en) 2020-09-11

Family

ID=72376441

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821023584.4U Expired - Fee Related CN211472489U (en) 2018-06-29 2018-06-29 Building combined pile convenient to move and used for civil engineering

Country Status (1)

Country Link
CN (1) CN211472489U (en)

Similar Documents

Publication Publication Date Title
CN211472489U (en) Building combined pile convenient to move and used for civil engineering
CN209225261U (en) A kind of self-propelled surveying device of the road and bridge of civil engineering
CN217620541U (en) Pipe fitting storage rack for civil engineering
CN107831032B (en) Roadbed sampler with anti-deviation structure for construction engineering
CN212026569U (en) Dredging device for municipal underground pipeline
CN211472075U (en) Road and bridge bituminous pavement crack detection device
CN204475842U (en) Packaged type single side formwork for building
CN210834256U (en) Civil engineering detects uses concrete sampling device
CN212689030U (en) Single-pile bearing capacity experimental device for civil engineering
CN212865489U (en) Civil engineering road drainage device
CN206786232U (en) A kind of hydraulic pressure push-pull device at fixed
CN206987070U (en) Steel construction assembled architecture wallboard node
CN207525802U (en) A kind of water conservancy automatic desilting device
CN207501023U (en) A kind of mobile solar street lamp
CN212509827U (en) Support arrangement for municipal construction pipeline
CN213897068U (en) Municipal works soil sampling pore-filling device
CN210305523U (en) Steel bar cutting device for constructional engineering
CN216369142U (en) Civil engineering is construction waste recovery processing equipment for site operation night
CN214462914U (en) Crossbeam support frame is used in civil engineering construction
CN214113315U (en) Civil engineering pipeline placer
CN217840096U (en) Town road prevents subsiding inspection shaft construction equipment
CN216580649U (en) Municipal administration water supply and drainage pipeline construction equipment
CN214832262U (en) Municipal administration construction equipment with protection pipeline function
CN203687994U (en) Deep displacement and underground water monitor
CN215854861U (en) Be used for civil engineering construction strutting arrangement convenient to remove

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200911

Termination date: 20210629

CF01 Termination of patent right due to non-payment of annual fee