CN211421520U - Stone dry-hanging structure - Google Patents
Stone dry-hanging structure Download PDFInfo
- Publication number
- CN211421520U CN211421520U CN201922048275.3U CN201922048275U CN211421520U CN 211421520 U CN211421520 U CN 211421520U CN 201922048275 U CN201922048275 U CN 201922048275U CN 211421520 U CN211421520 U CN 211421520U
- Authority
- CN
- China
- Prior art keywords
- dry
- card
- hanging
- stone
- connecting plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model discloses a stone material hangs structure futilely relates to interior decoration technical field. The technical key points are as follows: the utility model provides a stone material hangs structure futilely, includes along vertical direction install the main joist on the wall body, with the perpendicular and vice fossil fragments of being connected of main joist, install the dry link plate of a plurality of on the vice fossil fragments and by the slabstone of the dry link plate cooperation centre gripping on two adjacent vice fossil fragments, the one end of dry link plate is articulated with the vice fossil fragments, and is provided with the torsional spring between dry link plate and the vice fossil fragments, the one end that the vice fossil fragments were kept away from to dry link plate is provided with the gib block with the slabstone gomphosis, works as when the torsional spring is in natural state, the. The utility model has the advantages of high installation efficiency.
Description
Technical Field
The utility model relates to an interior decoration technical field, more specifically say, it relates to a stone material hangs structure futilely.
Background
The dry hanging method of stone is also called empty hanging method. Is a novel construction process in the prior wall decoration. The method uses the metal hanging piece to directly hang the facing stone on the wall surface or hang the facing stone on the steel frame in the air, and grouting and pasting are not needed. The principle is that main stress points are arranged on a main body structure, and stone is fixed on a building through a metal hanging piece to form the stone decorative curtain wall.
Chinese utility model patent that bulletin number is CN204571176U discloses marble hangs structure futilely, and it includes wall body (1) and marble plane materiel (2) of locating the wall body, the wall body surface is provided with waterproof layer (3), M12 chemical bolt (4) are installed to the wall body, hot-galvanize angle steel (5) are installed to M12 chemical bolt, stainless steel hangs (7) futilely through stainless steel bolt (6) are installed to hot-galvanize angle steel, and this stainless steel hangs the arch that has the hanging seam that stretches into the marble surface course and establish, protruding and the clearance that articulates between the seam are provided with foam rod structure (8), and the gap between the adjacent concatenation unit of marble plane materiel is provided with marble cement structure (9), the cross-section of stainless steel hangs futilely is the T shape.
The above prior art solution has the following drawbacks: during construction, the workman need install the stainless steel of lower extreme dry pendant on hot-galvanize angle steel earlier, insert the hang joint seam of marble plane materiel lower extreme with the arch of stainless steel dry pendant again, need the workman to hold the marble plane materiel with the hand and prevent to drop this moment, then install the stainless steel dry pendant above the marble plane materiel, stretch into the hang joint seam of marble plane materiel upper end with the arch of the stainless steel dry pendant of top, thereby accomplish the installation of a marble plane materiel, because the workman will hold the marble plane materiel and still install the stainless steel dry pendant yet, the operation is inconvenient, waste time and energy, the installation effectiveness is low.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art exists, the utility model aims to provide a stone material hangs structure futilely, it has the advantage that the installation effectiveness is high.
The above object of the present invention can be achieved by the following technical solutions:
the utility model provides a stone material hangs structure futilely, includes along vertical direction install the main joist on the wall body, with the perpendicular and vice fossil fragments of being connected of main joist, install the dry link plate of a plurality of on the vice fossil fragments and by the slabstone of the dry link plate cooperation centre gripping on two adjacent vice fossil fragments, the one end of dry link plate is articulated with the vice fossil fragments, and is provided with the torsional spring between dry link plate and the vice fossil fragments, the one end that the vice fossil fragments were kept away from to dry link plate is provided with the gib block with the slabstone gomphosis, works as when the torsional spring is in natural state, the.
Through adopting above-mentioned technical scheme, during the construction, all dry link plates are all installed on the false keel, earlier with the lower extreme of slabstone and the card strip gomphosis of the dry link plate of below, upwards rotate the dry link plate of top, move the upper end of slabstone to the below of the card strip of the dry link plate of top, loosen dry link plate, the torsional spring drives dry link plate and rotates, and then makes the card strip of top and the upper end gomphosis of slabstone to accomplish the installation, convenient operation, the installation effectiveness is high.
The utility model discloses further set up to: the lateral wall that the slabstone is close to the card strip seted up with card strip complex recess, the card strip includes that the interval sets up have elastic interior card and outer card, the one end and the dry link plate of interior card and outer card are connected.
Through adopting above-mentioned technical scheme, because interior card and outer card piece have elasticity, after the card strip got into the recess, interior card and outer card were by compressive deformation, and interior card and outer card support the inner wall of tight recess to make card strip and slabstone zonulae occludens, avoid the slabstone to rock.
The utility model discloses further set up to: the one end that interior card and outer card kept away from the board of doing hanging all inwards extends and is provided with the guide part, two be equipped with the clearance between the guide part.
Through adopting above-mentioned technical scheme, the guide part plays the guide effect for the card strip gets into the recess of slabstone more easily.
The utility model discloses further set up to: and a rubber block is arranged between the inner card and the outer card.
Through adopting above-mentioned technical scheme, card and outer card excessively warp in can avoiding by the block rubber, but also can assist in card and outer card and support tight recess inner wall.
The utility model discloses further set up to: the auxiliary keel is an angle steel, a connecting plate is arranged between the dry hanging plate and the auxiliary keel, the dry hanging plate is hinged to the connecting plate through a hinge shaft, a connecting bolt which sequentially penetrates through the auxiliary keel and the connecting plate is arranged on the auxiliary keel, and one end, penetrating through the connecting plate, of the connecting bolt is connected with a connecting nut in a threaded mode.
Through adopting above-mentioned technical scheme, the board that hangs futilely passes through connecting plate, connecting bolt and is connected with the false keel, simple to operate, can also used repeatedly after the later stage is dismantled.
The utility model discloses further set up to: rectangular adjusting holes are formed in the connecting plate and located around the connecting bolt, and the length direction of the adjusting holes is parallel to the length direction of the auxiliary keel.
Through adopting above-mentioned technical scheme, can finely tune the position of connecting plate through the regulation hole to the card strip that makes the board of hanging futilely cooperates with the recess accuracy of slabstone.
The utility model discloses further set up to: the auxiliary keel is horizontally provided with a supporting part towards one side of the clamping strip, and the supporting part is attached to the lower surface of the dry hanging plate.
Through adopting above-mentioned technical scheme, the supporting part plays the supporting role to the cladding panel futilely, avoids the cladding panel futilely to receive the gravity continuation downwardly rotating of slabstone, improves stability.
The utility model discloses further set up to: the runner has been seted up towards one side of connecting plate to the false keel, the length direction of the length direction false keel of spout is parallel, the connecting plate is located the spout and with spout sliding connection.
Through adopting above-mentioned technical scheme, when the position of connecting plate is finely tuned to needs, can make it slide along the spout, avoid the connecting plate skew, improve the installation effectiveness.
To sum up, the utility model discloses a beneficial technological effect does:
(1) through setting up with the articulated board of hanging futilely of false keel, the torsional spring, the card strip, during the construction, all dry link boards are installed on the false keel, earlier with the lower extreme of slabstone and the card strip gomphosis of the dry link board of below, upwards rotate the dry link board of top, move the upper end of slabstone to the below of the card strip of the dry link board of top, loosen dry link board, the torsional spring drives dry link board and rotates, and then makes the card strip of top and the upper end gomphosis of slabstone, thereby accomplish the installation, high operation, high installation efficiency.
(2) Through setting up interior card and outer card, because interior card and outer card have an elasticity, after the card strip got into the recess, interior card and outer card were by compressive deformation, and interior card and outer card support the inner wall of tight recess to make card strip and slabstone zonulae occludens, avoid the slabstone to rock.
(3) Through setting up the supporting part, the supporting part plays the supporting role to the cladding panel futilely, avoids the cladding panel futilely to receive the gravity continuation downwardly rotating of slabstone, improves stability.
Drawings
FIG. 1 is a schematic structural diagram of a stone dry-hanging structure;
FIG. 2 is an enlarged partial schematic view of portion A of FIG. 1;
FIG. 3 is a partial cross-sectional view of a stone dry-hang structure;
fig. 4 is a connection structure view of the dry hanging plate, the clamping strip and the connecting plate.
Reference numerals: 1. a wall body; 2. a main keel; 3. a false keel; 4. hanging the board dry; 5. a stone slab; 6. a torsion spring; 7. hinging a shaft; 8. clamping the strip; 81. an inner card; 82. an outer card; 9. a groove; 10. a guide portion; 11. a gap; 12. a rubber block; 13. a connecting plate; 14. a connecting bolt; 15. a connecting nut; 16. an adjustment hole; 17. a support portion; 18. a chute.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1 and 2, for the utility model discloses a stone material hangs structure futilely, include and install main joist 2 on wall body 1 along vertical direction, main joist 2 passes through chemical bolt fastening on wall body 1, and one side that wall body 1 was kept away from to main joist 2 is provided with main joist 2 vertically false keel 3, and false keel 3 is connected with main joist 2 through bolt and nut, installs a plurality of dry link plate 4 along its length direction on the false keel 3, presss from both sides between the dry link plate 4 on two adjacent false keels 3 and holds slabstone 5. One end of the dry hanging plate 4 is hinged to the auxiliary keel 3, a torsion spring 6 is arranged between the dry hanging plate 4 and the auxiliary keel 3, one end, far away from the auxiliary keel 3, of the dry hanging plate 4 is provided with a clamping strip 8 embedded with the stone slab 5, a groove 9 matched with the clamping strip 8 is formed in the side wall, close to the clamping strip 8, of the stone slab 5, and when the torsion spring 6 is in a natural state, the dry hanging plate 4 is horizontally placed.
During the construction, all install on false keel 3 all dry link plate 4, earlier with the lower extreme of slabstone 5 and the 8 gomphosis of the dry link plate 4 of below, upwards rotate the dry link plate 4 of top, move the upper end of slabstone 5 to the below of the card strip 8 of the dry link plate 4 of top, loosen dry link plate 4, torsional spring 6 drives dry link plate 4 and rotates, and then make the card strip 8 of top and the upper end gomphosis of slabstone 5, thereby accomplish the installation, and convenient for operation, the installation effectiveness is high.
Referring to fig. 3 and 4, in order to fix slate 5 more stably, the fastening strip 8 comprises an inner fastening piece 81 and an outer fastening piece 82 which are arranged at intervals and have elasticity, the inner fastening piece 81 and the outer fastening piece 82 can be made of stainless steel material, one end of the inner fastening piece 81 and one end of the outer fastening piece 82 are integrally formed with the cladding panel 4, and the distance between the outer side walls of the other ends of the inner fastening piece 81 and the outer fastening piece 82 is slightly larger than the width of the groove 9. Card strip 8 gets into recess 9 after, interior card 81 and outer card 82 are by compression deformation, and interior card 81 and outer card 82 support the inner wall of tight recess 9 to make card strip 8 and 5 zonulae occludens of slabstone, avoid slabstone 5 to rock.
The one end that interior card 81 and outer card 82 kept away from dry-hanging board 4 all inwards extends and is provided with guide part 10, guide part 10 and interior card 81 and outer card 82 integrated into one piece, and be equipped with clearance 11 between two guide parts 10, the opening edge of recess 9 be provided with guide part 10 complex chamfer. The guiding portion 10 and the chamfer serve as a guide for the snap strip 8 to enter the recess 9 of the slate 5 more easily. Be provided with the block rubber 12 between interior card 81 and the outer card 82, the block rubber 12 can avoid interior card 81 and outer card 82 excessive deformation, but also can assist interior card 81 and outer card 82 to support tight recess 9 inner wall.
The false keel 3 is the angle steel, is equipped with connecting plate 13 between cladding panel 4 and the false keel 3 futilely, and cladding panel 4 is articulated through articulated shaft 7 with connecting plate 13 futilely, and 6 covers of torsional spring are located around articulated shaft 7. The auxiliary keel 3 is provided with a connecting bolt 14 which sequentially penetrates through the auxiliary keel 3 and the connecting plate 13, and one end of the connecting bolt 14 penetrating through the connecting plate 13 is connected with a connecting nut 15 through threads. Rectangular adjusting holes 16 are formed in the connecting plate 13 around the connecting bolts 14, and the length direction of the adjusting holes 16 is parallel to the length direction of the auxiliary keel 3. The position of the connecting plate 13 can be finely adjusted by adjusting the holes 16, so that the clamping strips 8 of the dry hanging plate 4 are accurately matched with the grooves 9 of the stone slab 5.
The auxiliary keel 3 is provided with a sliding groove 18 towards one side of the connecting plate 13, the length direction of the auxiliary keel 3 in the length direction of the sliding groove 18 is parallel, the connecting plate 13 is positioned in the sliding groove 18 and is in sliding connection with the sliding groove 18, and the upper surface of the connecting plate 13 and the upper surface of the horizontal section of the auxiliary keel 3 are on the same horizontal plane. When the position of connecting plate 13 needs to finely tune, can make it slide along spout 18, avoid connecting plate 13 skew, improve the installation effectiveness.
The one side level of false keel 3 orientation card strip 8 is provided with supporting part 17, supporting part 17 and false keel 3 integrated into one piece, and supporting part 17 is laminated with the lower surface of hanging plate 4 futilely. The supporting part 17 plays a supporting role for the dry hanging plate 4, the dry hanging plate 4 is prevented from continuously rotating downwards due to the gravity of the stone plate 5, and the stability is improved.
The implementation principle of the embodiment is as follows: during construction, fix main joist 2 on wall body 1 through chemical bolt, rethread bolt and nut fixes false keel 3 on main joist 2, put all connecting plate 13 of dry link plate 4 in spout 18, install on false keel 3 through connecting bolt 14 and connecting nut 15, earlier with recess 9 of the lower extreme of slabstone 5 and the card strip 8 gomphosis of the dry link plate 4 of below, upwards rotate the dry link plate 4 of top, move the upper end of slabstone 5 to the below of the card strip 8 of the dry link plate 4 of top, loosen dry link plate 4, torsional spring 6 drives dry link plate 4 and rotates, and then make the card strip 8 of top and the recess 9 gomphosis of the upper end of slabstone 5, thereby accomplish the installation, and convenient for operation, and the installation effectiveness is high.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.
Claims (8)
1. The utility model provides a stone material hangs structure futilely, includes along vertical direction install main joist (2) on wall body (1), with main joist (2) perpendicular and the false keel (3) of being connected, install a plurality of on false keel (3) hang board (4) futilely and by slabstone (5) of hanging board (4) cooperation centre gripping on two adjacent false keels (3), its characterized in that, the one end of doing link board (4) is articulated with false keel (3), and is provided with torsional spring (6) between hang board (4) and false keel (3), the one end that vice keel (3) were kept away from in hang board (4) is provided with gib (8) with slabstone (5) gomphosis, works as torsional spring (6) are in when natural state, hang board (4) level is placed futilely.
2. The stone dry-hanging structure as claimed in claim 1, wherein the side wall of the stone slab (5) close to the card strip (8) is provided with a groove (9) matching with the card strip (8), the card strip (8) comprises an inner card (81) and an outer card (82) which are arranged at intervals and have elasticity, and one end of the inner card (81) and one end of the outer card (82) are connected with the dry-hanging plate (4).
3. The stone dry-hang structure as claimed in claim 2, wherein the ends of the inner clamping pieces (81) and the outer clamping pieces (82) far away from the dry-hang plate (4) are provided with guide parts (10) extending inwards, and a gap (11) is arranged between the two guide parts (10).
4. A stone dry-hang structure as claimed in claim 3, wherein a rubber block (12) is arranged between the inner clamping sheet (81) and the outer clamping sheet (82).
5. The stone dry-hanging structure according to claim 4, characterized in that the furring channel (3) is an angle steel, a connecting plate (13) is arranged between the dry-hanging plate (4) and the furring channel (3), the dry-hanging plate (4) is hinged to the connecting plate (13) through a hinge shaft (7), a connecting bolt (14) sequentially passing through the furring channel (3) and the connecting plate (13) is arranged on the furring channel (3), and one end of the connecting bolt (14) passing through the connecting plate (13) is in threaded connection with a connecting nut (15).
6. The stone dry-hanging structure as claimed in claim 5, characterized in that the connecting plate (13) is provided with rectangular adjusting holes (16) around the connecting bolts (14), and the length direction of the adjusting holes (16) is parallel to the length direction of the furring channel (3).
7. The stone dry-hanging structure as claimed in claim 5, characterized in that a support portion (17) is horizontally arranged on one side of the furring channel (3) facing the clamping strip (8), and the support portion (17) is attached to the lower surface of the dry-hanging plate (4).
8. The stone dry-hanging structure as claimed in claim 5, characterized in that a sliding groove (18) is opened on one side of the furring channel (3) facing the connecting plate (13), the length direction of the furring channel (3) in the length direction of the sliding groove (18) is parallel, and the connecting plate (13) is located in the sliding groove (18) and is connected with the sliding groove (18) in a sliding manner.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922048275.3U CN211421520U (en) | 2019-11-22 | 2019-11-22 | Stone dry-hanging structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922048275.3U CN211421520U (en) | 2019-11-22 | 2019-11-22 | Stone dry-hanging structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211421520U true CN211421520U (en) | 2020-09-04 |
Family
ID=72254266
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201922048275.3U Active CN211421520U (en) | 2019-11-22 | 2019-11-22 | Stone dry-hanging structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211421520U (en) |
-
2019
- 2019-11-22 CN CN201922048275.3U patent/CN211421520U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212358964U (en) | Mounting structure for rapid leveling of assembled wall and pipeline separation | |
CN211421520U (en) | Stone dry-hanging structure | |
CN108265872A (en) | A kind of furred ceiling conversion layer main joist integrative installation technology method | |
CN201901964U (en) | Three-dimensional adjustable and disconnectable curtain wall | |
CN213477314U (en) | Hang stone material formula curtain mounting structure futilely | |
CN102677858A (en) | Back hanging piece for installing decorative inorganic tetrafluoromethane veneer and construction method of back hanging piece | |
CN102787709A (en) | Construction method of decorating plate dry hanging system and decorating plate dry hanging system manufactured by same | |
CN202359714U (en) | Installing structure for concealed frame glass curtain wall | |
CN210797998U (en) | Dry hanging type stone curtain wall structure | |
CN210342532U (en) | Indoor stone dry-hanging mounting structure | |
CN209891509U (en) | Hanging rack for fixing stone curtain wall | |
CN202144644U (en) | Transitional structure for suspended ceilings of different horizontal height | |
CN101886453B (en) | Method for fixing thermal insulation decorative board and X-type and J-type fixing devices | |
CN216840341U (en) | Prevent to construct accessory device of caulking strip dislocation | |
CN218623075U (en) | Stone dry-hanging structure | |
CN217129071U (en) | Multi-angle auxiliary supporting assembly for steel structure connection | |
CN205876040U (en) | Indoor light gauge steel partition wall door frame reinforced structure | |
CN213418194U (en) | Suspended ceiling structure at access hole part | |
CN210798000U (en) | Inner corridor stone cornice structure | |
CN214615190U (en) | Porcelain steel plate dry-hanging device | |
CN217326241U (en) | Novel wallboard keel system | |
CN205172387U (en) | Apron flashing | |
CN220414681U (en) | Ultralight steel connecting piece for building roof color steel tile | |
CN113062491B (en) | Construction method of glass magnesium rock wool color steel wallboard | |
CN216810500U (en) | Energy-saving stone curtain wall with good sealing performance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |